Submits Info Re Steam Generator Insp Program in Response to NRC 800708 Request.Multifrequency Eddy Current Exam Will Be Performed on 100% of Inlet Tubes Including First Support Plate Intersection in a & B Steam Generators by 801101
ML17250A595
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/12/1980
From: White L
ROCHESTER GAS & ELECTRIC CORP.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8009170311
Download: ML17250A595 (2)


Text

-, t gzssrzz g (trzzzznl ROCHESTER GAS AND ELECTRIC CORPORATION o

89 EAST AVENUE, ROCHESTER, N.Y. 14649 LEON D. WHITE, JR.

VICE PRESIDENT TELEPHONE AREA CODE Tld 546-2700 September 12, 1980 Director of Nuclear Reactor Regulation ATTN: Mr. Dennis M. Crutchfield, Chief Operating Reactors Branch 45 U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Subject:

Steam Generator Mid-Cycle Inspection, Pall 1980 R. E. Ginna Nuclear Power Plant, Unit No.

1 Docket No. 50-244

Dear Mr. Crutchfield:

1 In'accordance with your request of 7uly 8, 1980 to inform your staff of our planned inspection program for the Ginna plant's steam generators forty (40) days prior to the rnid-cycle inspection, we submit the following.

A multifrequency eddy current examination willbe performed on 100% of the inlet (hot leg) tubes up to and including the first support plate intersection in both the A and B steam generators.

Particular attention willbe paid to the tube sheet crevice areas in both steam generators; however, to date, we have only seen crevice indications in the B steam generator as reported to you in our April 29, 1980 letter.

Our present schedule calls for this inspection to be performed around November 1, 1980.

Very truly yours, L. D. White, Jr.