Letter Sequence RAI |
---|
|
|
MONTHYEARML17090A4292017-03-27027 March 2017 ASME Section XI Inservice Inspection Program Proposed - Inservice Inspection Alternative N1-14-NDE-010 and N2-14-NDE-005 Project stage: Request ML17160A2632017-06-0505 June 2017 ASME Section XI Inservice Inspection Program PRA Information to Support Proposed Inservice Inspection Alternatives N1-14-NDE-010 and N2-14-NDE-005 Project stage: Request ML17163A0052017-06-0808 June 2017 NRR E-mail Capture - North Anna Power Station, Units 1 and 2 - Acceptance of Relief Requests N1-I4-NDE-010 and N2-I4-NDE-005 Project stage: Acceptance Review ML17235A9972017-07-21021 July 2017 NRR E-mail Capture - North Anna Power Station, Units 1 and 2 - Request for Additional Information, Regarding Proposed Inservice Inspection Alternatives N1-I4-NDE-010 and N2-I4-NDE-005 Project stage: RAI ML17241A0452017-08-24024 August 2017 Proposed ISI Alternatives NI-14-NDE-010 and N2-14-NDE-005 Reactor Pressure Vessel Nozzle Weld Inspections Response to Request for Additional Information Project stage: Response to RAI ML18029A1842018-02-0202 February 2018 Proposed Inservice Inspection Alternatives N1-I4-NDE-010 and N2-I4-NDE-005 (CAC Nos. MF9534 and MF9535; EPID L-2017-LLR-0029) Project stage: Other 2017-06-08
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24107A9112024-04-15015 April 2024 NRC to Fws, Follow-up on Request for Concurrence for North Anna SLR ML24107A9122024-04-11011 April 2024 Fws to NRC, Follow-up on Request for Concurrence for North Anna SLR ML24087A0102024-03-26026 March 2024 NRR E-mail Capture - Verbal Relief for North Anna Unit 1 - (ASME Code), Section XI, Subsection IWB-2430 ML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML24107B1562024-02-20020 February 2024 Cherokee Nation E.Toombs Na Removal Request ML24044A2462024-02-0606 February 2024 001 Radiation Safety Baseline Inspection Information Request ML23320A1122024-01-18018 January 2024 NRC to Fws, Concurrence with Endangered Species Act Determinations for North Anna Power Station, Units 1 and 2, Subsequent License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML23355A2722023-12-21021 December 2023 NRR E-mail Capture - Schedule Revision for Emergency Preparedness Staff Augmentation Times License Amendment Request ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML23039A1712023-02-0808 February 2023 NRR E-mail Capture - Acceptance Review for Technical Support Center (TSC) Relocation (L-2023-LLA-0006) ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22342B1472022-12-0808 December 2022 NRR E-mail Capture - Acceptance Review for LAR Re NAPS Post LOCA Buffer Change (L-2022-LLA-0162) ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22104A0252022-04-14014 April 2022 NRR E-mail Capture - Dominion Presentation Slides for April 21, 2022 Public Meeting on Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML22032A0962022-02-0101 February 2022 002 Radiation Safety Baseline Inspection Information Request ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22007A2672022-01-0707 January 2022 NRR E-mail Capture - North Anna, Unit 2, ASME Section XI Inservice Inspection Program Relief Request N2-14-LMT-003 Fourth Interval Third Period Limited Examinations (L-2021-LLR-0088) ML21335A0812021-12-0101 December 2021 NRR E-mail Capture - Acceptance Review for OMN-28 Request Alternative to ISTC-3700, Position Verification Testing (L-2021-LLR-0086) ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21312A0082021-11-0404 November 2021 Enclosure 2 - NAPS Draft SER Table A.1-1 Markup ML21312A0012021-11-0404 November 2021 Comments on North Anna Draft SER ML21312A0112021-11-0404 November 2021 Enclosure 3 - NAPS Draft SER Section 3 Comments ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21274A0022021-09-30030 September 2021 NRR E-mail Capture - Acceptance Review for TSTF-577 LAR (L-2021-LLA-0158) ML21312A0072021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure B - NAPS SER App a - Dominion Comments 9-21-2021 ML21312A0032021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure a - Dominion Table A4.4-1 Clean Version ML21312A0022021-09-21021 September 2021 Enclosure 1 - E-mail - NAPS SLR SER Appendix a for Dominion Review ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21152A1722021-09-0707 September 2021 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for North Anna Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21154A0152021-06-0101 June 2021 NRR E-mail Capture - Acceptance Review for Primary Grade Water LAR (L-2021-LLA-0082) ML21140A3682021-05-20020 May 2021 Response to North Anna Hardship (Temporary Staff Guidance Additional Guidance for FOF Inspections During the PHE) 2024-04-15
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23081A5282023-04-26026 April 2023 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21322A0992021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21256A0692021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Request for Confirmation of Information ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure ML21049A0212021-02-17017 February 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000338/2021012 and 05000339/2021012) and Request for Information (RFI) ML21028A3902021-01-29029 January 2021 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21012A3412021-01-22022 January 2021 Requests for Confirmation of Information for the Environmental Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information ML20316A0422020-11-10010 November 2020 NRR E-mail Capture - FW: Draft RAI for North Anna Unit 2 Steam Generator Tube Inspection Report (ML19179A075) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20125A0762020-05-0101 May 2020 NRR E-mail Capture - Draft RAI Related to Revised Reactor Vessel Material Surveillance Capsule Withdrawal Schedule Dominion Energy Virginia North Anna Power Station Units 1 and 2 (L-2020-LLL-0038) ML20113A5792020-04-21021 April 2020 NRR E-mail Capture - Draft RAI North Anna Fifth 10-year Interval Relief Request (L-2020-LLR-0023) ML19354B6142019-12-20020 December 2019 NRR E-mail Capture - Draft RAI for North Anna Relief Request P-9 ML19317F1042019-11-0707 November 2019 NRR E-mail Capture - Draft RAIs for SB LOCA LAR (Non Prop) ML19191A2512019-07-10010 July 2019 NRR E-mail Capture - Request for Additional Information Open Phase Condition LAR ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19108A1902019-04-18018 April 2019 Emergency Preparedness Program Inspection Request for Information ML19060A2432019-03-0101 March 2019 Related to License Amendment Request to Address Open Phase Conditions 2024-03-23
[Table view] |
Text
NRR-PMDAPEm Resource From: Hall, Randy Sent: Friday, July 21, 2017 4:58 PM To: Craig D Sly (Generation - 6)
Cc: Diane Aitken (Generation - 6) (diane.aitken@dominionenergy.com);
Tom.Huber@dom.com
Subject:
North Anna Power Station, Units 1 and 2 - Request for Additional Information, Regarding Proposed Inservice Inspection Alternatives N1-I4-NDE-010 and N2-I4-NDE-005 (CAC Nos. MF9534 and MF9535)
Attachments: REQUEST FOR ADDITIONAL INFORMATION RR N1-I4-NDE-010 and N2-I4-NDE-005.docx July 21, 2017 Mr. Craig Sly Manager, Nuclear Regulatory Affairs Virginia Electric and Power Company
Dear Mr. Sly,
By letter dated March 27, 2017 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML17090A429), as supplemented by letter dated June 5, 2017 (ADAMS Accession No. ML17160A263), Virginia Electric and Power Company (Dominion, the licensee) requested relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI regarding the inspection program for the fourth 10-year inspection interval at North Anna Power Station (NAPS), Units 1 and 2. Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z), the licensee proposed in Alternatives N1-I4-NDE-010 and N2-I4-NDE-005, revision of the inspection requirements in the inspection program for ASME Code,Section XI, Category B-F, Pressure Retaining Dissimilar Metal Welds in Vessel Nozzle, from 10 years to 20 years based on Topical Report (TR)
WCAP-17236-NP-A, Risk-Informed Extension of the Reactor Vessel Nozzle Inservice Inspection [ISI] Interval (ADAMS Accession No. ML12215A043).
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided by the licensee regarding the subject requests for alternative, and has determined that additional information is needed to complete its evaluation, as stated in the attached Request for Additional Information (RAI).
Please let me know if you would like a clarification call regarding the attached RAI. The goal of a call would be to ensure that the RAI questions are understandable, the regulatory basis for the questions is clear, and to determine whether any of the information requested was previously docketed. Following a clarification call, or your confirmation that a call is not necessary, the staffs RAI will be documented as an Official Agency Record in ADAMS. Dominion is requested to provide a written response to the RAI within 30 days of the date of the clarification call, or your confirmation that a call is not needed.
Sincerely, Randy Hall, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation USNRC (301) 415-4032 1
Randy.Hall@nrc.gov 2
Hearing Identifier: NRR_PMDA Email Number: 3683 Mail Envelope Properties (Randy.Hall@nrc.gov20170721165800)
Subject:
North Anna Power Station, Units 1 and 2 - Request for Additional Information, Regarding Proposed Inservice Inspection Alternatives N1-I4-NDE-010 and N2-I4-NDE-005 (CAC Nos.
MF9534 and MF9535)
Sent Date: 7/21/2017 4:58:21 PM Received Date: 7/21/2017 4:58:00 PM From: Hall, Randy Created By: Randy.Hall@nrc.gov Recipients:
"Diane Aitken (Generation - 6) (diane.aitken@dominionenergy.com)"
<diane.aitken@dominionenergy.com>
Tracking Status: None "Tom.Huber@dom.com" <Tom.Huber@dom.com>
Tracking Status: None "Craig D Sly (Generation - 6)" <craig.d.sly@dominionenergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2335 7/21/2017 4:58:00 PM REQUEST FOR ADDITIONAL INFORMATION RR N1-I4-NDE-010 and N2-I4-NDE-005.docx 26390 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR ALTERNATIVE NOS. N1-I4-NDE-010 AND N2- I4-NDE-005 REACTOR PRESSURE VESSEL NOZZLE WELD INSPECTIONS FOURTH 10-YEAR INSERVICE INSPECTION INTERVAL NORTH ANNA POWER STATION, UNITS 1 AND 2 VIRGINIA ELECTRIC AND POWER COMPANY DOCKET NOS. 50-338 AND 50-339 CAC NOS. MF9298 AND MF9299 By letter dated March 27, 2017 (ADAMS Accession No. ML17090A429), as supplemented by letter dated June 5, 2017 (ADAMS Accession No. ML17160A263), Virginia Electric and Power Company (the licensee or Dominion) requested relief from the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI regarding the inspection program for the fourth 10-year inspection interval for North Anna Power Station (NAPS), Units 1 and 2.
Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z),
Dominion proposed in alternatives N1-I4-NDE-010 and N2-I4-NDE-005 revision of the inspection requirements in the inspection program for ASME Code,Section XI, Category B-F, Pressure Retaining Dissimilar Metal Welds in Vessel Nozzle, from 10 years to 20 years, based on Topical Report (TR) WCAP-17236-NP-A, Risk-Informed Extension of the Reactor Vessel Nozzle Inservice Inspection [ISI] Interval (the TR; ADAMS Accession No. ML12215A043).
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided by Dominion regarding the subject requests for alternative, and has determined that the additional information requested below is needed to complete its evaluation.
RAI-APLB 1 Section 4, Limitations and Conditions for Acceptance, of TR WCAP-17236-NP-A specifies conditions and limitations that must be addressed by licensees proposing to use its methodology to justify extension of the ISI interval from 10 to 20 years for the ASME Code,Section XI, Category B-F, and B-J RPV nozzle welds that do not contain Alloy 82/182 material.
The third bullet on page 4-3 of the TR requires licensees to address probabilistic risk assessment (PRA) quality in their relief request. The licensees supplement dated June 5, 2017, provided some of the information needed to address PRA quality for the purposes of the proposed ISI alternatives N1-I4-NDE-010 and N2-I4-NDE-005. Based on the information provided, it appears that PRA quality is being demonstrated without relying on the previously Attachment
approved RI-ISI program, because a more current full-scope peer review is available. However, the information provided was insufficient to determine whether the PRA quality requirements were met.
Please clarify which method is proposed for demonstrating PRA quality and provide the necessary additional information as indicated. Either approach (a or b) may be used to demonstrate PRA quality.
a) If Dominion elects to rely on the approved RI-ISI program to demonstrate PRA quality:
Please provide any updated information appropriate for the application since the approved RI-ISI application.
b) Alternatively, Dominion may describe the technical adequacy of the PRA used in the relief request, by addressing the following questions:
- i. Provide additional information on the resolution of the peer review findings in light of this application by:
- 1. Specifying how each finding was resolved for those findings which were not documentation-only issues (summarize the changes that were made to address the finding), or
- 2. Comparing the peer review results to the acceptance criteria established in Electric Power Research Institute (EPRI) Report 1021467, Nondestructive Evaluation: Probabilistic Risk Assessment Technical Adequacy Guidance for Risk-Informed In-Service Inspection Programs, (ADAMS Accession No. ML12171A450), as modified by the limitations and conditions of the associated NRC Safety Evaluation (ADAMS Accession No. ML11262A206). Indicate how the peer review findings were resolved if they were not documentation-only issues.
ii. Indicate whether any updates, other than those described in the response to (i) above, were made to the PRA which are relevant to this application since the peer review described in the supplemental submittal dated June 5, 2017.