CATEGORY 1 REGULATO INFORMATION DISTRIBUTION TEM (RIDS)
ACCESSIOM NBR:9702070219 DOC.DATE: 97/01/30 NOTARIZED: NO FABIL:50-335 St. Lucie Plant, Unit 1, Florida Power 6 Light Co.
AUTH.NAME AUTHOR AFFILIATION STALL,J.A.
Florida Power a Light Co.
RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
DOCKET ¹ 05000335
SUBJECT:
Submits rev to schedule for periodic containment anomaly inspections re interim relief request 20.
DISTRIBUTION CODE:
A047D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: OR Submittal: Inservice/Testing/Relief from ASME Code GL-89-04 NOTES:
RECIPIENT ID CODE/NAME PD2-3 LA WIENS,L.
INTERNAL:
A~C
~IIE~CEN E~R...
01 NUDOCN'ABSTRACT RES/DET/EIB EXTERNAL: LITCO ANDERSON NRC PDR COPIES LTTR ENCL 1
1 1
1 RECIPIENT ID CODE/NAME PD2-3 PD AEOD/SPD/RAB NRR/DE/EMEB OGC/HDS3 RES/DET/EMMEB NOAC COPIES LTTR ENCL NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE!
CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN SD-5(EXT. 415-2083)
TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 14 ENCL
/1
Florida Power 5 Light Company, P.O. Box128, Fort Pierce, FL34954-0128 Zanuary 30, 1997 L-97-3 10 CFR 50.4 10 CFR 50.55a U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.
20555 RE:
St. Lucie Unit 1 Docket No. 50-335 In-Service-Inspection Plan Second Ten-Year Interval On October 4,
- 1996, pursuant, to 10 CFR 50.55a (a)(3), Florida Power and Light Company (FPL) requested approval of Interim Relief Request 20.
Interim Relief Request 20 was submitted by FPL letter, L-96-246.
The interim relief requested approval of a temporary non-code repair of the ASME Class 3 containment cooling unit coil, HVS-1B.
In Attachment B of our letter, the discussion of the augmented inspection stated that the structural integrity of the temporary repair would be assessed periodically during the normally scheduled containment anomaly inspections; and that the containment anomaly inspections were typically performed once every two weeks.
FPL has revised the schedule for the periodic containment anomaly inspections to, nominally, once per month.
The containment anomaly inspection interval change was made primarily in the interest of maintaining personnel radiation exposure ALARA.
The associated'ncrease in the augmented inspection interval for containment cooling unit coil HVS-1B has been evaluated and determined acceptable for the following reasons:
1)
No leakage has been identified since the temporary non-code repair was implemented approximately three months
- ago, and
- 2) the integrated component cooling water surge tank makeup and the containment sump level are periodically monitored and recorded by Operations personnel.
Therefore, the augmented inspection interval change will have no impact on fulfilling the purpose of the augmented inspections described in the relief request.
9702070219 970130
~ PDR
'ADQCK 05000335 8
~7
(,
an FPL Group company
St. Lucie Unit 1 Docket No. 50-335 L-97-3 Page 2
This letter contains no new regulatory commitments.
It only provides notification to the NRC of a periodicity change for the routine containment anomalies inspection which was mentioned in the subject relief request.
Please contact us if there are any questions about this submittal.
Very truly yours, J.
A. Stall Vice President St. Lucie Plant JAS/GRM cc:
Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, St. Lucie Plant