|
---|
Category:2.206 Petition
MONTHYEARML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter ML23066A0892023-02-24024 February 2023 OEDO-22-00419 - Email Dated 02/24/2023 to Petitioner on Seabrook Unit 1 ASR Petition ML22349A1062022-12-14014 December 2022 OEDO-22-00419 - Lochbaum Comments on C-10 ASR 2.206 Petition for Seabrook ML23009B1362022-12-14014 December 2022 Transcript - Meeting with the Petition Review Board and C-10 Research & Education Foundation Regarding a 2.206 Petition Submitted on October 4, 2022 ML22333A7452022-11-22022 November 2022 OEDO-22-00419 - Email: C-10 Response on PRB Initial Assessment - C-10 Petition on Seabrook ASR Concrete Degradation ML22287A1472022-10-13013 October 2022 2.026 Petition Screen-in Email ML17227A5382017-05-12012 May 2017 OEDO-17-00529- Letter from Research & Education Foundation 10 CFR 2.204 Demand for Information (DFI) ML16169A1722016-07-0606 July 2016 OEDO-16-00007 - Letter to S. Gavutis, C-10 Research & Education Foundation, Final Decision 2.206 Petition from C-10 Research & Education Foundation Regarding Seabrook Station, Unit No. 1 ML16006A0022015-12-22022 December 2015 OEDO-16-00007 - 2.206 - Seabrook Immediate Implementation and Enforcement of Aci 349.3R & ASTM C 856-11 Code Standards Requiring Core Sampling and Petrographic Testing for the Mechanical Properties of Tensile ML0829005822008-10-0505 October 2008 G20080695/EDATS: OEDO-2008-0770 - Thomas Saporito Ltr. Request for Enforcement Action Against the Florida Power and Light Company (Fpl), and FPL Group, and FPL Energy Point Beach LLC and FPL Energy Seabrook LLC and Individuals 2023-03-03
[Table view] Category:Letter
MONTHYEARIR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 05000443/LER-2024-001, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-038, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-037, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) 2024-09-25
[Table view] |
Text
May 12, 2017 Via electronic submission: OPA.resource@NRC.gov
Subject:
10 CFR 2.204 Demand For Information (DFI)
Mr. Victor McCree Execu ve Director for Opera ons United States Nuclear Regulatory Commission Washington, D.C. 205550001
Dear Mr. McCree:
On behalf of the C10 Research and Educa on Founda on (hereina er C10), 44 Merrimac Street, Newburyport, Massachuses, 01950, I submit this pe on pursuant to Ch. 2.206, Title 10, of the Code of Federal Regula ons (herea er 10 CFR).
Demand for Information requested C10 pe ons the NRC to issue demands for informa on pursuant to 10 CFR 2.204, and to then issue an order under 10 CFR 2.202 to licensee NextEra, owner of Seabrook Sta on who is the en ty seeking approval of its LAR 1603 License Amendment Request (Seabrook Sta on License Amendment Request 1603; Revise Current Licensing Basis to Adopt a Methodology for the Analysis of Seismic Category 1 Structures with Concrete Aected by AlkaliSilica Reac on, August 1, 2016, 10 CFR 50.90, Docket No. 5443, SBKL16071.). This DFI applies to the August 1, 2016, LAR 1603 and any and all amendments, aachments and revisions.
Justification for Enforcement Action Requested In its response to C10s "led conten ons to this LAR, NextEra (Docket No. 50443LA2, May 5, 2017, before the Atomic Safety and Licensing Board of the Nuclear Regulatory Commission), Next Era makes a number of statements that purport to demonstrate that the LAR 1603 should be approved by the NRC and that the conten ons submied by C10 should be rejected. A signi"cant number of their statements in support of those posi ons refer to the technical data submied in LAR 1603.
However, because virtually all of the sta s cs in the technical data are redacted, it is impossible for C10 to assess the validity of NextEras statements.
Therefore, C10 herewith requests the NRC to approve via this Demand For Informa on that the LAR 1603 documents be released to C10 with no por ons redacted.
C10 Founda on 44 Merrimac Street, Newburyport Mass. 01950 www.c10.org (978) 4656646
C10 Founda on 10 CFR 2.204 DFI, 5/12/2017 page 2 C10 understands that at least some of this informa on it is seeking is proprietary, and C10 is willing to sign a con"den ality agreement. C10 maintains regular, secure oce space in which these documents would be keep in a locked "ling closet and would be available only to C10s sta and members of the Board of Directors, to be accessed and used only on the premises.
Examples of sections of NextEras response to C10s contentions that cannot be adequately assessed due to the extensive redaction in LAR 1603
- 1. para. 1, page 4: ASRinduced expansion in reinforced concrete has an eect, similar in some ways to prestressing, that mi gates the loss of structural capacity that would be assumed based on the change in material proper es, up to a point. Without the redacted data to support this asser on, it is not possible for C10 to assess its validity.
- 2. para. 2, page 7: The overall conclusion from analyses of structural limit states is that limit state capacity is not degraded when small amounts of ASR expansion are present in structures. Presently, the ASR expansion levels in Seabrook structures are below the levels at which limit state capaci es are reduced. (LAR evalua on Sec on 3.2.1.)
Without having access to what small amounts numbers are and the levels at which limit state capaci es are reduced, C10 cannot assess the validity of the claims of LAR 1603.
- 3. para. 2, page 16: The LAR explicitly calls for core sample tes ng as an integral part of its ASR monitoring methodology, and the results of the "rst campaign of tests are included in a technical document submied as part of the LAR. The sta s cal results of the tes ng are redacted; therefore, again, C10 is prevented from being able to actually review and assess the results.
- 4. para. 2, page 17: As explained throughout the technical documents underlying the LAR, the mechanical eect of ASR does not necessarily result in an adverse impact to structural capacity, at least up to the point of expansion that was observed in the program. Because the sta s cal data is redacted, C10 cannot review or asses it; therefore, C10 cannot know up to what point expansion due to ASR was tested. Since the point of LAR 1603 is to establish a valid tes ng methodology for the eect of ASR on the structures at Seabrook Sta on, having these sta s cs is vital for adequate review of the LAR.
- 5. para. 2, page 22: MPR4153 even provides the results of those tests. These results, which state the outcome of tests on the material proper es of concrete tested in the University of Texas FSEL by the company MPR are redacted.
(MPR4153 Sec on 4.1; Id. At Appx D (Throughthickness expansion ToDate for the First Campaign of Extensometers).
- 6. para. 1, page 36: The "rst campaign to examine outofplane expansion has been completed and involved tes ng of cores. The results of those tests are available in the LAR. The results are redacted.
- 7. para 1, page 43: This tes ng examines the current elas c modulus of the concrete, which in turn requires compressive strength tes ng. The "rst campaign to examine outofplane expansion involved tes ng of cores. The results of those tests are available in the LAR. Pe oner neither references nor challenges the tests conducted to date. The Pe oner (C10) cannot reference nor challenge the test results, because they are redacted. This is a classical circular argument advanced by Seabrook Sta ons owner NextEra.
C10 Founda on 44 Merrimac Street, Newburyport Mass. 01950 www.c10.org (978) 4656646
C10 Founda on 10 CFR 2.204 DFI, 5/12/2017 page 3 Petition Logistics C10 is willing to sign and commit fully to a con"den ality agreement. C10 requests via this DFI that such an agreement be prepared and communicated to C10 and that following its execu on LAR 1603 with all its amendments, aachments and revisions be released to C10 for review and assessment.
Sincerely, Patricia Lang Skibbee President of the Board of Directors C10 Research & Educa on Founda on 44 Merrimac Street Newburyport, MA 01950 Ph: 978 465 6646 Email: Patricia.skibbee@verizon.net Natalie Hildt Treat Execu ve Director C10 Research & Educa on Founda on 44 Merrimac Street, Newburyport, MA 01950 Ph: (978) 4656646 Email: natalie@c10.org C10 Founda on 44 Merrimac Street, Newburyport Mass. 01950 www.c10.org (978) 4656646