ML17223A946

From kanterella
Jump to navigation Jump to search
Insp Repts 50-335/90-19 & 50-389/90-19 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected: Licensee Actions in Response to NRC Bulletin 88-004 Re Potential safety-related Pump Loss
ML17223A946
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 08/22/1990
From: Belisle G, Hallstrom G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17223A945 List:
References
50-335-90-19, 50-389-90-19, IEB-88-004, IEB-88-4, NUDOCS 9009240303
Download: ML17223A946 (9)


See also: IR 05000335/1990019

Text

~R RECIA

A0

ss

~t

O

0

+sb*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report Nos. 50-335/90-19

and 50-389/90-19

Licensee:

Florida Power and Light

9250 West Flagler Street

Miami, Fl 33102

Docket Nos.:

50-335

and 50-389

Facility Name: St. Lucie Units I and

2

Inspection

Conducted:

August 6-10,

1990

Inspector:

.

G.

.

a

strom

Approved by:

y~G..

e

s e,

se

Test

Programs

Section

Engineering

Branch

Division of Reactor Safety

License

NoseI

DPR-67 and NPF-16

ate

sgne

2 -gz-

0

ate

)gne

SUMMARY

Scope:

This routine,

unannounced

inspection

examined

licensee

actions

in response

to

NRC Inspection

and Enforcement Bulletin (IEB) 88-04 "Potential

Safety-Related

Pump Loss."

The bulletin requested

the licensees

to determine if the operation

of

any safety-related

systems

would result

in dead-heading,

to, evaluate

safety-related

systems

for flow division,

and to evaluate

the

minimum flow

bypass

lines for safety-related

pumps with respect

to

damage

resulting

from

operations

and testing in the minimum flow mode.

Results:

All actions

in response

to the bulletin were stated

to

be completed

by the

licensee

prior to this inspection.

Most licensee

responses

and actions

were

verified to be satisfactory during this inspection.

However, the inspector

was

unable

to independently

verify three

items while

on site

due to lack of

necessary

data.

Additional satisfactory clarifications for the items involved

were

received

by telecopy

on August

16,

1990

and in

a followup telephone

conference

with licensee

personnel

on that date

the inspector

informed the

licensee that Bulletin 88-04 was closed for Plant St. Lucie Units

1 and 2.

Licensee

engineers

and operations

personnel

provided knowledgeable

responses

to

technical

issues

raised

by the inspector during this inspection.

No violations or deviations

were identified.

9009240303

900823

PDR

ADQCK 05000335

6

PNU

REPORT

DETAILS

Persons

Contacted

Licensee

Employees

  • G. Boissy, Plant Manager
  • J. Barrow, Operations

Superintendent

  • D. Culpepper,

Site Engineering Supervisor

  • J. Dyer, guality Control Supervisor
  • R. Englmeier, guality Assurance

Superintendent

J. Hallem, Plant Systems

Engineer

  • L. Mc Laughlin, Plant Licensing Superintendent
  • G. Madden, Plant Compliance

Engineer

  • A. Menocal, Nuclear Engineering

Group Supervisor

  • G. Pustover,

Senior Project Nuclear Engineer

D. Stuart,

Systems

Engineering Supervisor

  • J. West, Mechanical

Maintenance

Supervisor

  • D. West, Technical Staff Supervisor

Other

licensee

employees

contacted

during this

inspection

included

engineers,

technicians,

operators,

and office personnel.

NRC Resident

Inspectors

S. Elrod, Senior Resident

Inspector

(SRI)

M. Scott,

Resident

Inspector

(RI)

"Attended exit interview on August 10,

1990.

Acronyms

and initialisms

used

throughout this report are listed in the

last paragraph.

TI 2515/105,

IEB 88-04,

Potential for Safety-Related

Pump Loss

IEB 88-04

was

issued

May 5,

1988,

due to the potential for damage

of

safety-related

centrifugal

pumps

when operated

in parallel at low flow.

When

one of the

pumps is "stronger"

than the other (i.e.,

has

a higher

developed

head for the

same

flow) it may cause

"dead

heading" of the

weaker

pump; i.e.,

pump impeller operation without fluid flow. This can

lead to pump damage

due to cavitation

and heat buildup.

The inspector

examined the licensee's

responses

to IEB 88-04 dated

July ll and

December

19,

1988;

and

May 26,

1989 to determine

whether

actions

taken were satisfactory.

The July 11,

1988, letter identified the

following safety-related

pumps:

II

SYSTEM

Motor Driven Auxiliary

Feedwater

(MDAFW)

Turbine Driven Auxiliary

Feedwater

(TDAFW)

Low Pressure

Safety

Injection (LPSI)

High Pressure

Safety

Injection (HPSI)

Containment

Spray

(CS)

Boric Acid Makeup

(BAMU)

PUMPS

1A 5

1B

2A 5

2B

1C

2C

1A 5

1B

2A 5

2B

1A, 1B,

5

1C

2A

8( 2B

1A 5

1B

2A 5 2B

lA 5

1B

2A

8( 28

MANUFACTURER

Byron-Jackson

Ingersoll-Rand

Byron-Jackson

Ingersoll-Rand

Ingersoll-Rand

Ingersoll-Rand

Bingham-Willamette

Bingham-Willamette

Byron-Jackson

Ingersoll-Rand

Goulds

Goulds

The

inspector

reviewed

the following additional

documents

to verify

licensee

commitments

contained

in their response:

Documents

associated

with latest

pump vendor

recommendations

for pumps

listed above included;

( 1) licensee

PO PB88636-90081

and October 25,

1988,

letter from Sulzer-Bingham for HPSI

pumps,

(2) licensee

PO PB88636-90080

and October

18,

1988 letter from Ingersoll-Rand for Unit 2

AFW and

CS,

and

Units

1

5

2 LPSI

pumps,

(3) licensee

PO PB88633-90084

and

September

22,

1988 letter from Byron-Jackson for Unit

1

AFW and

CS

pumps,

and (4) July

25,

1988 letter

from Goulds for BAMU pumps.

These

documents

together

with system

design

drawings

established

that

installed miniflow line capacities

are greater

than or equal

to latest

manufacturers's

recommendations

for all

pumps

except Unit

1

CS

(50

gpm

installed versus

150

gpm recommended).

Documents

reviewed to establish

adequacy

of original design

bypass

flow

capacities

included

pump vendor data,

A-E specifications

(e.g.

Combustion

Engineering Specifications

No. 19367-487-401

and

No. 13172-PE-401 for HPSI

pumps),

and calculations

(e.g.

No.

NSSS-038A,

Revision

0,

AFW Pumps

Miniflow Recirculation,

and

No. PSL-O-J-M-90-0019,

Revision 0, Temperature

Rise

During

Minimum Recirculation

Flow Operation).

Calculation

No.

PSL-0-J-M-90-0019 established

the adequacy of a 50

gpm minimum bypass

flow

for unit

1

CS

pumps but did not establish

that the installed orifices were

as per original design.

Documents

reviewed to establish

confidence that

no

damage

to the

above

pumps

has occurred

due to hydraulic instability or inadequate

minimum flow

bypass line capacity included;

1989

and

1990

LERs (both units),

summaries

of Plant

Work Orders

(PWOs) written against

the

above

pumps

from 1987 to

date,

and

summaries

of ASME Section

XI quarterly

pump tests

from 1989 to

date.

The inspector also reviewed

a February

14,

1990 consultant's

report

providing results of a specific inspection of the

1A HPSI

pump to assess

any

damage

which might have occurred

due to inadequate

miniflow or dead

heading of the

pump.

No damage

was identified by the inspection.

After examination 'of the

above

documentation

and field verification the

inspector

concluded that licensee

actions

in response

to

IEB 88-04 were

satisfactory

provided satisfactory

clarification could

be obtained

on

three

items which the inspector

was unable to verify while on site

due to

lack of data.

These included:

( I)

Proper installation of "unidirectional"

minimum flow orifices for

all auxiliary feedwater

pumps

(both units).

The pertinent

design

drawings

indicated

flow direction for these

50

gpm

(HDAFWP) and,70

gpm

(TDAFWP) orifices.

However the installed orifices

were

not

marked to indicate flow direction

and neither pertinent installation

quality data, clarification of design

drawing,

nor actual

minimum

flow test data

was readily available.

(2)

Adequate

installation

of flow orifices for Unit

2

containment

spray

pumps.

The design

drawings require these non-directional

3 inch

OD

150

gpm flow orifices to be installed within the

2 inch

OD bypass

miniflow lines

using

socket

welds.

Piping insulation

prevented

adequate

field verification of the installed orifices

and neither

installation quality data

nor actual

gpm minimum flow test data

was

readily available.

(3)

Adequate

minimum flow orifices for Unit I containment

spray

pumps.

Design drawings for the

50 gpm non-directional orifices were

not available.

The pertinent

pump purchase

specifications

indicated

that they were to have

been

designed

and manufactured

by the

pump

vendor.

However

the installed orifices

appeared

to

have

been

fabricated

in the field and consisted

of threaded

stainless

steel

pipe fittings (two 3/4 inch by 6 inch pipe nipples separated

by a 3/4

inch

coupling)

which

had

been

welded

into the

bypass

lines.

Clarification that the presently installed orifices were the original

design or were adequate for 50

gpm minimum flow was required.

Additional clarification

received

by

telecopy

on

August

16,

1990

established;

( I) vendor confirmation that

AFW miniflow orifices

were

designed

to

be non-directional,

(2) pre-operational

miniflow tests

for

'unit 2

CS

pumps verified a minimum flow of 151

and

155

gpm,

and

(3) the

original design bill of materials for Unit

1

CS orifices specified 3/4

inch

OD threaded fittings (3/8 inch diameter orifice).

3.

Exit Interview

The in'spection

scope

and findings were summarized

on August 10,

1990, with

those

persons

indicated in paragraph I above.

The inspector described

the

areas

inspected

and

discussed

in detail

the

inspection

findings.

No

dissenting

comments

were

received

from

the

licensee.

Proprietary

information

was

reviewed

in the course of this inspection,

but is not

included in this report.

The inspector

completed

review of additional

satisfactory clarifications

on August

16,

1990,

and informed the licensee

that bulletin 88-04

was closed for Plant St. Lucie Units I and 2.

4.

Acronyms

and Initialisms Used in This Report

A-E

AFW

ASME

BAMU

CS

gpm

HPSI

IEB

LER

LPSI

NSSS

MDAFW

OD

PSL

PWO

TDAFW

Architect-Engineer

Auxiliary Feedwater

System

American Society of Mechanical

Engineers

Boric Acid Makeup System

Containment

Spray System

gallons

per minute

High Pressure

Safety Injection System

Inspection

and Enforcement Bulletin

Licensee

Event Report

Low Pressure

Safety Injection System

Nuclear Steam Supply System

Motor Driven Auxiliary Feedwater

System

outside diameter

Plant St. Lucie

Plant

Work Order

Turbine Driver Auxiliary Feedwater

System