ML17195B022

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/85-33 & 50-249/85-29 on 850930-1021. Violation Noted:Failure to Adhere to Program Staffing Requirements & Failure to Install Automatic Fire Detection Sys in Reactor Bldg Refueling Floor Area
ML17195B022
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/13/1985
From: Guldemond W, Holmes J, Ramsey C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17195B021 List:
References
50-237-85-33, 50-249-85-29, NUDOCS 8511190084
Download: ML17195B022 (17)


See also: IR 05000237/1985033

Text

..

. U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-237/85033(DRS); 50-249/85029(DRS)

Docket Nos. 50-237; 50-249

Licenses No. DPR-19; DPR-25

Licensee:

Commonwealth Edison Company

P. 0. Box 767

Chicago, IL 60690

Facility Name:

Dresden Nuclear Power Station, Units 2 and* 3

Inspection At:

Morris, IL

Inspection Conducted:

September 30 through October 21, 1985

C\\J)J ~

Inspectors:

~Holmes

Approved By:

W. G.

ul

mond, Chief

Operational Programs Section

Inspection Summary

Inspection on Settember 30 through October 21, 1985 (Reports

No. 50-237/85033 DRS); 50-249/85 29(DRS))

II- f 3-85°

Date

ti - 1*-B~

Date

Areas Inspected:

Routine, unannounced safety inspection conducted to verify

the adequacy of the facility's fire.protection program implementation and to

determine the status of LERs and previous open items.

The inspection involved

71 inspector-hours by two NRC inspectors including 2 inspector-hours onsite

during off-shifts and 11 inspector-hours conducting in-office review at the

Region III off,ice.

Results:

Of the 6 areas inspected, no violations or deviations were identified

in four areas.

Two violations were identified in the remaining two areas

(failure to adhere to program staffing requirements - Paragraph 3; failure to

comply with a license condition to install an automatic fire detection system

in the Reactor Building refueling floor ar~a - Paragraph 7a).

9511190084 e§!ll.~7

PDR

ADOCK O~oR

-<-

0

1.

DETAILS-

D. Adam, Compliance Administrator

  • J. Brunner, Assistant Superintendent, Technical Services

T. Ciesla, Assistant Superintendent, Operations

  • M. Dillon, Fire Marshall
  • R. Flissner, Service Superintendent
  • T. Hausheer, Nuclear Services, Technical
  • P. Lau, QA Supervisor
  • J. McDonald, Station Nuclear Engineering
  • B. Rybak, Station Nuclear Engineering
  • D. Scott, Station Manager
  • R. Whalen, Technical Staff

J. Wujciga, Production Superintendent

US NRC

E. Hare, Resident Inspector

  • L. McGregor, Senior Resident Inspector

S. Stasek, Resident Inspector

  • Denotes those in attendance at the exit meeting of October 4, 1985.

2.

Licensee Actions on Previous Inspection Findings

a.

(Open) LER (237/85029) and Violation (237/85028-01):

Auxiliary

electric equipment room halon system declared inoperable due to

ventilation dampers failing to close.

Fire watch was not established

per Technical Specification No. 3.12.H.2.

Region III 1s followup of this event is documented in Inspection

Report No. 50-237/85028(DRS).

As a result of this followup violation

No. 237/85028-01 was issued.

No response to this violation was

required because the licensee 1s interim and long term corrective

actions were determined satisfactory.

The interim corrective actions

were implemented.prior to or during the followup inspection.

The

proposed long term corrective actions have not been implemented.

Therefore, this event report remains open.

b.

(Closed) LER (249/85014):

Wet pipe sprinkler system in Unit 3

turbine trackway had to be rerouted to allow for overhead clearance

for new turbine rotors.

The sprinkler system was out of service

5 1/2 hours beyond the 14 day limit permitted by Technical

Specification 3.12.C.3 .

2

c.

The event report is closed based on the licensee's corrective

actions* taken. which included restoration of the system to service

and~functiona*l testing prior to declaring the system operable .

. '((:fii:&~df LER (237/85010):

Fire door for the Unit 2 125V DC battery

room found open.

A fire watch was not established within one hour

per Technical Specification 3.12.F.2.

This event report is closed based on the licensee's corrective

actions taken which included immediate closure of the fire door and

training/instruction of plant operators on the requirements to keep

fire doors closed at all times when not in use.

d.

(Open) LER (237/84-20):

Two of seven root valves that were installed

on fire hose stations were found to be in the closed position

rendering the fire hose stations inoperable.

e.

Although the licensee's corrective actions for this event included

prompt opening of the closed root valves, the inspectors determined

that the licensee's program for administratively controlling valves

that are not electrically supervised using wire seals to secure these

valves _in the open position and performing monthly inspections to

~

verify valve positions does not appear to be .working.

During the

-~

inspection the inspectors observed several non-electrically supervised

valves in the fire protection system with missing or damaged wire

seals .

To correct this problem, the licensee stated that the program for

administratively controlling these valves is being upgraded to

include locking these valves (chain and lock) in the open position

in addition to monthly inspections to verify each valve position in

accordance with NFPA Standard 26.

This event report remains open

pending Region III verification of the licensee's upgraded corrective

actions.

(Open) LER (237/84-17; 237/84-05):

Failure to establish continuous

or'-hourly fire watch patrols due to inoperability of all or portions

of fire detection and sprinkler alarm systems in the control room.

During these events and at the present time, the fire detection and

sprinkler alarm system printer indications are interlocked (dependent)

into the plant security system computer.

Indication of fire detection

and sprinkler alarms in the control room was lost in two events either

because of a loss of power to the plant security system computer or

because of modifications being made to upgrade the plant security

system computer.

Apparently, any failure of the plant security

system computer can cause the loss of all or portions of fire

detection and sprinkler alarm annunciation in the control room.

This installation does not comply with the licensee's commitment to

NFPA 720 as stated in the licensee's April 1977 response (point-by-

point comparison) to Appendix A to NRC Branch Technical Position

3

f.

(BTP) APCSB 9.5-1.

The licensee

1s scheduled plant modification

No .. ;~12-2/3-84-109 identifies corrective action for this problem as

the-:A*nstallation of independent circuits for fire detection and

spr'.fhkler system alarms which alarm and annunciate in the control

room'~n accordance with NFPA 720.

This modification is scheduled to

be completed in December 1985.

These LERs will remain open pending

Region III verification of the licensee

1s corrective actions.

(Closed) LER (237/84-11):

Fire wall penetrations to.Unit 2/3

diesel generator rooms were not sealed.

This event report is closed based on the licensee 1 s corrective

actions taken, which include establishment of a fire watch within

one hour per Technical Specification No. 3.12.F.2 and sealing the

penetrations per drawing No. 12E-6058.

g.

(Closed) LER (237/84-08):

NRC inspection of the licensee 1s

compliance with fire protection Technical Specification surveillance

requirements identified that a cardox system master valve was not

being tested in the automatic mode.

The master valve test procedure

was written to test the valve in the manual mode.

This event report is closed based on the licensee 1s corrective

actions taken which included prompt removal of the master valve

from service, revision of the surveillance test procedure, and

satisfactory testing o~ the valve in the automatic mode.

h.

(Closed) LER (249/83-34/03L):

Unit 3 trackway sprinkler system out

of service due to damage by mobile crane boom.

This event is closed based on the licensee 1 s corrective actions

taken, which included making the necessary system repairs, prompt

restoration of the system to service and instructions to plant

personnel regarding the movement of mobile cranes and the fragility

of systems and components in their path.

i.

(C)-0sed) LER (249/83-17/03L):

HPCI deluge system solenoid valve

taken out of service because the valve would not reset.

j.

This event report is closed based on the licensee 1 s corrective

actions taken, which included prompt removal of the deluge system

froni-service, making the necessary repairs to the solenoid valve and

restoration of the system to service.

(Closed) LER (237/81-15/03L):

Unit 2/3 diesel generator room C02

system heat detector surveillances not performed per Technical

Specification 4.12.A.1.

This event report is closed based on the licensee 1s corrective

actions taken, which included instruction to plant personnel to

perform the required heat detector surveillances and satisfactory

performance of the surveillance .

4

k.

(Closed) Violations (237/81-09-01; 249/81-06-01):

Four penetration

seals identified as being defective were inoperable for an excessive

per_t~rj;.* of time.

Neither prompt nor timely corrective action was taken.

This~ item is closed based on the licensee's June 29, 1981 response

to Region III which discussed the licensee's corrective actions

taken to avoid future violations in this area.

The inspector's

review of Procedure No. DFPP-4175-2, Revision 4, indicated that

appropriate instructions are provided to plant personnel which

refer to detail drawings for proper installation of penetration

fire seals.

1.

(Open) Violations (237/81-09-03; 249/81-06-03):

(a) Fifty percent

of fire extinguishers sampled did not have 1981 monthly inspection

tags attached; (b) 5 year hydrostatic test for portable C02

extinguisher cylinders were overdue; and (c) numerous compressed

gas cylinders were improperly stored.

m.

The licensee's corrective actions identified in their June 29, 1981

response to items (a) and (b) of this violation were ineffective.

Subsequent QA audits and surveillance by the licensee's onsite QA

department have revealed that these deficiencies are continuing.

For example, deficiencies identified in QA surveillance No. QAS

j

12-85-236 for the period September 23 through 29, 1985 include the

following:

wrong date on extinguisher tags; extinguishers past due*

for 5 year hydro testing; no service date on extinguisher tags; no

seal on extinguisher plill pin; partially discharged extinguisher.

During plant tours by the inspectors, identical deficiencies were

observed.

In one instance, a C02 portable extinguisher hose was

damaged to the extent that the webbing in the hose was exposed.

A hole existed in the webbing that may have allowed the extinguishing

agent to escape through the hose prior to reaching the C02 discharge

nozzle.

This extinguisher was located on fire cart No. 2.

In

addition, the inspectors observed that wheeled dry chemical

extinguishing units*Nos. PK 21 and PK 22 had tags which indicated

th~t surveillances were missed the months of May and September 1985.

The continuing existence of this type of deficiency is indicative of

a lack of management attention in this area.

Management attention

and staffing is the subject of a violation documented in paragraph

3 of this report.

Your response to that violation should address

your corrective actions for failing to properly maintain fire

extinguishers.

These items will remain open pending the further

review of the licensee's corrective actions by Region III.

Item (c) of this violation is closed based on the licensee's

corrective action taken which included the installation of metal

storage racks for compressed gas cylinders, securing the cylinders

with metal chain~ and revision of Procedure No. OAP 3-11.

I

(Open) Unresolved Item (237/81-09-06; 249/81-06-06):

Fire brigade

drills and training do not appear to meet the intent of NRC

requirements.

5

"Section 6.0 of the original fire protection SER, dated March 1978,

  • recommended. that the licensee's administrative controls follow the

.... gµ.(~e)!Jnes set forth in the NRC Guidance Document entitled 11 Nuclear

  • .* Plai\\t;.Fire Protection Functional Responsibilities, Administrative

Controls* and Quality Assurance.

11

A supplement to the original SER

was issued December 2, 1980.

Section 3.1 of this supplemental SER

closes out the issue of administrative controls with the NRC staff's

acceptance of the licensee's discussion of administrative controls

provided in letters dated January 24, February 24, March 20 and

July 27, 1978, January 31, and April 30, 1979.

Therefore, Section

III.1.3.b of Appendix R is not applicable to administrative controls

for fire protection at Dresden.

Based on the licensee's submittals discussed above, the NRC staff

concluded that the licensee's administrative controls for fire

protection met NRC guidelines and, the applicable regulatory

requirement for fire protection administrative controls at Dresden

is the Commission 1s guidance issued on the implementation of General

Design Criterion 3 of Appendix A to 10 CFR Part 50 for existing

power plants.

Section 2.0 and 3.0 of Attachment No. 2 to NRC Guidance Document

~

..

11 Nuclear Plant Fire Protection Functional Responsibilities,

Administrative Controls and Quality Assurance

11 requires practice

sessions be held for fire brigade members to provide each brigade

member wi.th experience in actual fire extinguishment and the use of

emergency breathing apparatus under strenuous conditions.

Fire

brigade dri 11 s are required to be performed so that th*e fire brigade

can practice as a team.

The drills are to be performed at regular

intervals but not to exceed three months for each fire brigade.

The

drills are required to be critiqued to assess each brigade member's

knowledge of his role in fire fighting strategy.

The licensee is not meeting these requirements for the following

reasons:

(1)

By attempting to meet the requirements contained in

Section III.1.3.b of Appendix R to 10 CFR 50, the licensee

has been conducting one fire drill per month with the intent

of getting all designated fire brigade members involved in

at least two drills per year.

(2)-* Practice sessions that provide each brigade member with actual

fire extinguishment experience and the use of emergency

breathing apparatus under strenuous conditions (full fire

fighting gear) have not been conducted due to a breakdown in

contractual arrangements with an independent firm.

(3) Fire brigade drills have not been critiqued at three year

intervals by qualified individuals independent of the

licensee's staff .

6

3.

To resolve this concern, the licensee is requested to make available

a detailed assessment of fire brigade drills, practice sessions and

thrf!,~_year. audits of fire brigade drills by qualified individuals

_.- -. indeRendent of the licensee* s staff. This assessment should

  • establi.sh whether the licensee is in compliance with commitments

made to the NRC which resulted in the NRC staff conclusions that

the licensee 1s administrative controls for fire protection were

acceptable.

This item remains open pending region review of the licensee*s

assessment.

n.

(Open) Unresolved Item (237/81-09-07; 249/81-06-07):

Specific

pre-fire fighting plans or strategies for all safety-related areas

and areas presenting a hazard to safety-related equipment were not

developed and implemented.

As discussed in item 237/81-09-06; 249/81-06-06 above, the

requirements of 10 CFR 50, Appendix R (Sections III.K.11 and 12)

are not applicable in this case.

The applicable requirements are

contained in Attachment No. 5 of NRC Guidance Document

11Nuclear

Plant Fire Protection Functional Responsibilities, Administrative

Controls and Quality Assurance.

11

During the inspection, the licensee provided the inspectors with

a copy of pre-fire plans that contained specific fire fighting

strategies for fighting fires in all safety-related areas and

areas that present a hazard to safety-related equipment.

The

pre-fire plans appear to provide adequate fire fighting procedures

and instructions.

However, these plans have not been implemented.

According to the licensee, the plans will be implemented and

incorporated into fire*brigade training lesson plans by the end

of the first quarter of 1986.

This item will remain open pending

said implementation.

o.

(Open) Unresolved Item (237/81-09-08; 249/81-06-08):

Fire brigade

practice sessions have not been conducted in accordance with

commitments made to the NRC.

A hands-on practice session was held

in 1979 with full brigade attendance, but no practice session was

held in 1980.

This item will remain open pending Region III review of the

licensee's response to Item b of Unresolved Item No. 237/81-09-06;

249/81-06-06 as discussed in this report.

Fire Protection Program Organization and Personnel Staffing

.;,

f;

c

10 CFR 50.48 requires that each operating nuclear power plant have a fire

protection plan that satisfies Criterion 3 of Appendix A to 10 CFR 50.

Except for the requirements of Section III.G, III.J, and III.O of

Appendix R to 10 CFR 50, the approved fire protection plan that satisfies

Criterion 3 of Appendix A to 10 CFR 50 is discussed in the original fire

protecti'on SER. dated March 1978, a fire protection SER Supplement, dated

December 2, 1980, and the licensee 1s Fire Hazard Analysis submittals entitled

7

11 InformaU.on .Relevant to Fire Protection. Systems and Programs" dated

Octobe~ l976,.January 1977, and April 1977.

Furthermore, the licensee

committe:d\\'.t,o~ follow certain NRC Supplemental Gui dance Documents as

discusse,~;';{6. letters to the NRC, dated January 24, February 24, March 20

and July*:?;2T, 1978; January 31 and April 30, 1979.

The requirements for overall responsibility for the Fire Protection

Program are discussed in Sections IV.A and 3.1.A.1 of Parts 1 and 3 of

the licensee

1s Fire Hazard Analysis submittal, dated October 1, 1976

and April 1977.

The NRC

1s position, as restated stated in Section 3.1.A.l

of this document establishes guidance on implementation of basic criteria

for fire protection program organization and personnel staffing.

In response to the NRC

1s position discussed in Section A.l of Appendix A

to NRC Branch Technical Position APCSB 9.5-1 concerning the qualification

requirements for the Fire Protection Engineer who will assist in various

aspects of fire protection program development for the operating plant,

the licensee states

11comply

11 in Section 3.1.A.l of the Fire Hazard

Analysis submittal.

The licensee further states, in part,

11 CEC0 has a

Fire Protection Coordinator who reports to the Supervisor of Safety ..

Responsibilities of the Fire Protection Coordinator are:

coordination

of activities; procurement of equipment, resolve questions on standards f

and technical issues; make recommendations for improvements; coordinate,~

plan, and conduct inspections (make inspections of Dresden, Units 2 and ~~

once a month); ensure that adequate fire fighting equipment is provided -

and that such equipment is maintained in good operating condition,

coordinate with offsite fire department; conduct normal and preoperational

testing; provide forms and instructions for reporting fires; issue

publications outlining employee policy and procedures in fire protection;

assist and supervise training of personnel; assist and advise departments

concerned with established rules and standards; coordinate with the staff

all matters of mutual concern and make final recommendations for specific

actions to be taken on fire protection issues.

11

The inspectors identified the following examples of the licensee

1s

failure:to consistently and effectively comply with the staffing

requirements for fire protection program implementation:

a.

Fire Protection Engineer

A qualified Fire Protection Engineer was not involved in the

deve.1 opment of certain aspects of the fire protection program

for the operating pl ant as required by Sect ion 3. 1. A. 1 of the

licensee 1s Fire Hazard Analysis submittal.

The qualifications for

this individual were not stated in any document.

The resume of the

individual performing the original Fire Hazard Analysis is contained

in Attachment 2A of the Fire Hazard Analysis submittal, but this

individual is no longer employed by the licensee.

According to the licensee, there was a contract with M&M Protection

Consultants which included services that would satisfy some of the

responsibilities of the Fire Protection Engineer, but this contract

expired in December 1984.

8

Although the licensee has employed another qualified Fire Protection

Cons*4aant- firm to do some specific fire protection work relative to

upgJtc;1dHJg the fire protection program, this firm was not retained to*

ful.fj~lyall of the responsibilities of the Fire Protection Engineer.

b.

Fire Protection Coordinator

The Fire Protection Coordinator was not performing all the duties

at the site that are delineated in Section 3.1.A.l of the licensee's

Fire Hazard Analysis. submittal.

According to the licensee's staff,

the individual that was originally assigned these duties was trans-

ferred to Corporate Quality Assurance some time ago.

Once vacated,

this position was not filled.

The duties and responsibilities of

the position were delegated to the Fire Marshal and other individuals

within the CECo organization.

Through Amendment No. 86 to Facility Operating License No. DPR-19

(Unit 2) and Amendment No. 79 to Facility Operating License No. DPR-25

(Unit 3), the NRC accepted a proposed licensee staffing change.

Figure 6.1-1 (Corporate and Station Organization Chart) shows a Fire

Protection Inspector reporting to the Corporate Director of Quality

Assurance Operations.

The inspectors requested, but the licensee di~

not provide the inspectors with documentatio~ to verify that the NR~

was aware that the same individual who was the site Fire Protection-~

Coor.dinator was filling the position entitled "Fire Protection

Inspector" for Corporate Quality Assurance.

The licensee's failure to adhere to the staffing requirements

discussed above resulted in programmatic breakdowns that have

decreased the level of fire protection that was intended to

satisfy Criterion 3 of Appendix A to 10 CFR 50.

For example:

(1) A fire detection system was not installed on the refueling

floor as required by Amendment No. 33 to Facility Operating

License No. DPR-25.

(This is discussed in Paragraph 7.a of

, the report. )

(2) Installed fire protection hardware and equipment was not

being properly maintained.

(This is discussed in Paragraphs

2.d, 2.e, 4, 5, and 7 of the report.)

(3) Technical specification surveillance procedures did not

incorporate appropriate testing of quality affecting parameters *

in accordance with design and governing code requirements.

(This is discussed in Paragraph 4 of the report.)

(4) Administrative controls did not adequately control fire

protection features.

(This is discussed in Paragraph 5 of

the report.)

(5)

Many deficiencies that were identified in LERs, NRC inspections,

QA audits, and QA surveillances did not receive prompt or effec-

tive.corrective action.

(This is discussed in Paragraph 2 and 6

of the report.)

9

(6)

W~C!knesses in the scheduling of fire drills were identified.

~L(This is discussed in Paragraphs 2.m, and 2.o of this report).

Fafl\\ife- to; comply with the staffing requirements for development and

implerilentatiori of the fire protection program is considered a

violation of 10 CFR 50.48 and Criterion 3 of Appendix A to 10 CFR 50

(237/85033-01; 249/85029-0l(DRS)).

The Station Fire Marshal

1s qualifications include 58 junior college

credits in fire science; an associates degree in electronics

engineering and 15 years experience as a volunteer firefighter.

He

has held the position of station fire marshal for seven years.

At

the present time, the fire marshal is assigned the following

responsibilities:

a.

Coordinate and assist in fire systems periodic testing.

b.

Plan, coordinate, conduct, and critique fire drills.

c.

Fire Brigade classroom training.

d.

Review, revise, and write new administrative procedures.

e.

Review, revise and write new surveillance procedures.

Make

work requests to repair deficiencies, verify surveillances

are completed as required and maintain files on completed

surveillances.

,

f.

Review plant modifications, assist in training, testing, and

development of procedures.

g.

Maintain fire equipment, verify availability of spare parts and

procurement of parts.

h.

Participates in insurance inspections, Technical Specification

Reviews, QA, INPO, and NRC audits.

i.

Assure Technical Specification compliance.

j.

Review work requests.

k.

Verify fire watch and insurance notification.

1.

Coordinate activities with the offsite fire department.

m.

Make reports on deviations and fire damage experiences.

n.

Perform plant cleanliness inspections.

o.

Correspond with other agencies on fire protection issues.

p .

Assure that the fire protection program meets NRC and other

requirements.

10

q *. Explain fire protection* requirements to the licensee's staff

when required.

Accorcfing to the licensee's staff and Station Nuclear Engineering

Depa:rtment (SNED) procedure number PE Q.44, a qualified corporate

fire protection engineer reviews new plant modifications prior to

implementation by the Architect-Engineering firm. *This appears to

be the extent of the corporate fire protection engineer's involvement.

The qualifications of the Station Fire Marshal do not appear to be

commensurate with the list of responsibilities assigned to that

position. This lengthy list of responsibilities constitute a workload that

may not be achievable by a single individual, regardless of the

individual's qualification and experience.

To resolve this concern, the licensee is requested to provide at

the site, a written evaluation (complete work study) of the responsi-

bilities assigned to the station fire marshal. This evaluation

should make a determination of the fire marshal's ability to

effectively achieve each delegated responsibility based on his

qualifications and time constraints.

This is considered an Unresolved Item (237/85033-02; 249/85029-02{DRS))

pending Region Ill's review of this evaluation.

..

4.

Technical Specification Surveillance Review

Technical Specification 6.2.A.11 requires that detailed written procedures

be developed, approved and adhered to for implementation of the Fire

Protection Program.

The inspector's review of the licensee's surveillance

procedures and test results for fire protection Technical Specification *

surveillance requirements resulted in identification of the following

discrepancies:

a.

Testing of Diesel Fire Pump at Least Once Per Operating Cycle

Section 4.12.B.1.(e) of Technical Specification No. 3.12.B requires

that the station diesel fire pumps be demonstrated operable by per-

forming a system functional test which includes simulated automatic

actuation of the pumps throughout their operating sequence.

The

licensee's commitment in Section 3.5.E.2 of the Fire*Hazard Analysis

Report dated April, 1977, requires the fire pump installations to

conform to NFPA standard No. 20. This commitment states that a

plant modification would provide an adequate flow gage for full flow

testing of the pumps in accordance with NFPA standard 20.

The

licensee's surveillance procedure Nos. DFPP 4124-3 and DFPP 4124-4

were deficient in that:

(1)

The procedure required manual throttling of the pumps to achieve

the specific flows contained in Technical Specification 3.12.B.

and did not address automatic activation.

(2)

The procedures required testing the pumps to the specific head

and flow contained in the Technical Specification No. 3.12.B,

11

.. but failed to require testing for head and flow as specified in

-: :NFPI\\.- 20.:.. * .

{3')~~i~~e~~tir~~~!nt of quality affecting parameters such as pump

  • *,t,;v.i'.bratioff under full flow conditions were not included in
  • the test procedure or the test results.

(4) The test results were not compared to the origin.al manufacturer's

shop test curve or field acceptance test for the pumps because

neither of these curves were available to the licensee's staff.

b.

Testing of Water Suppression Systems at least Once Per Operating

Cycle

Section 4.12.B.1.(e) of Technical Specification No. 3.12.B requires

that fire suppression water systems be demonstrated operable by

performing a system functional test which includes simulated automatic

actuation of the systems throughout their operating sequence.

The

licensee's commitment in Section 3.5.E.3 of the Fire Hazard Analysis

Report requires that automatic sprinkler systems conform to NFPA

Standard No. 13.

The licensee's surveillance procedure No.

SP~4-6-39 failed to

incorporate appropriate test requirements to demonstrate the

sprinkler system is operable in accordance with NFPA 13 in that:

(1) The procedure didrnot require flow from the inspector's test

valve of wet sprinkler systems.

Instead, the alarm bypass

valve was used for this test.

(2) The procedure did not require flow from the two inch drain

valve of wet or dry systems.

Instead, the alarm bypass

valve was used for this test.

c.

Semiannual Testing of Fire Detectors

Section 4.12.A of Technical Specification No. 3.12.A requires that

the fire detection system be demonstrated operable by performing a

channel functional test every six months.

The licensee commitment

in Section 3.5.E.l of the Fire Hazard Analysis Report requires that

the fire detectQr system conform to the requirements of NFPA

Standard 720.

The licensee's surveillance procedure No. OFPP 4185-2 (Revision 4)

failed to incorporate the following quality affecting parameters as

required by NFPA 720:

(1) Periodic cleaning of detector units.

(2) Periodic adjustment for sensitivity (Section 3.1.2 of the

original SER required this test to be conducted).

12

  • ~,.

.O*.

Accordjng_to.,:tb~,_.licensee

1 s staff, an independent fire protection

consu.}:t~n~;r-h.~s~;,'.been;-employed to review all technical specification

pro~ed~f~s;;:~tjc;t<t!!$t results to evaluate their adequacy in accordance

wi th;~Nf P~:f;s~~6cf~r.$1$;, and design requirements.

This assessment was in

progress;{~~:;~ttr~>tirne of the inspection and is expected to be comp 1 eted

by the end c>°f 1985.

Accardi ng to the 1 i censee, where necessary, the

procedures will be revised to coincide with the governing code and

design requirements.

This is considered an Open Item (237/85033-03; 249/85-029-03(DRS))

pending Region III 1s review of the licensee's actions.

No violations or deviations were identified.

5.

Administrative Controls - Control of Welding, Cutting, and Ignition

Sources

Licensee procedure No. OAP 3-11 (Revision 4) contained what appears

to be acceptable instructions for controlling storage of flammable and

combustible liquids, storage of compressed gas cylinders, and accumulation

of rubbish and transient combustibles such as wood scaffolding, etc. The.

procedure specifies housekeeping and cleaning responsibilities to be>

,r;f

followed by all employees and contractors.

'f

. ~~:: ..

No violations or deviations were identified in this area, however; the

inspectors cautioned the licensee on a proposed revision to welding and

cutting procedure No. DMP 41-00-1 that would include a provision to

facilitate ALARA concerns in high radiation areas.

The inspectors

informed the licensee that any relief from the requirements for a

firewatch to remain in the immediate area thirty minutes after cutting

and welding has been completed would have to be discussed with NRR.

6.

Quality Assurance Program

The licensee's commitment to Quality Assurance for fire protection is

documented in Section 3.3 of

11 Information Relevant to Fire Protection

Systems<<and Programs

11 and in letters to the NRC on this subject dated

January *24, February 24, March 20, and March 27, 1978, January 31 and

April 30, 1979.

The insp.ectors review of the licensee's Quality Assurance Program for

Fire Prot.ectfon. focluded review of the following:

a.

Eleven criteria applicable to fire protection that satisfy

Appendix A to Branch Technical Position 9.5-1 and supplement

guidance

11Nuclear Plant Functional Responsibilities, Administrative

Controls and Quality Assurance.

11

<.;

~*

b.

Quality Assurance Surveillance Reports dated September 3-6, 1985,

September 5-9, 1985, September 9-13, 1985, and September 16-30, 1985.

c.

Annual Quality Assurance Audits Nos. QAA 12-84-I dated April 17,

1984, and .. QAA 12-83-I dated April 15, 1983.

13

d.

Triennial. Audit by M&M Protection_ Consultants dated December 4, 1984.

No viOla~tiio:rfa or deviations were identified; however, the inspectors

suggest~d~t~(>. the licensee that for clarification, the statements made in

Section 3'~~3.-of the

11 Information Relevant to Fire Protection Systems and

Programs

11 should be modified to indicate their specific commitment to a

QA program to fire protection.

As written, this statement can be

interpreted to mean that the licensee committed to apply all of the

criteria of Appendix B in 10 CFR 50 to fire protection.

The inspectors determined that the licensee's practice of considering

fire protection as reliability-related is acceptable because this practice

ensures that all of the eleven criteria contained in the NRC's Guidance

are included in the program.

In addition, this practice allows for the

normal QA program for safety-related systems to be applied to fire

protection in it's entirety. Only one QA manual exists for reliability-

related systems and fire protection systems.

Although the licensee's Quality Assurance Program appears to be

.

effectively identifying issues that are contributing to hardware and

programmatic weaknesses, the licensee does not appear to be taking prompt

and effective corrective actions. This is exemplified by the remaining :t:

open items that have been identified in QA audits-and surveillances,

~

LERs, and NRC inspections. (This is further discussed in 3.b.(5) of thel

report.).

~

7.

Plant Tours

During tours of the plant, the inspectors observed the following

deficient conditions:

a.

Failure to Comply with* License Condition No. 2.B. of Amendment

No. 33 to Facility Operating License No. DPR-25 and Amendment

No. 36 to Provisional Operating License No. DPR-19.

Se~tion 5.1.6.6 of the original Fire Protection SER for Dresden Units

2(3 dated March 22, 1978 states that the licensee proposed the

installation of an automatic fire detection system to provide early

warning of a fire in the Refueling Floor Area in order to satisfy the

objectives of Criterion 3 of Appendix A to 10 CRF 50.

Amendment

No. 36 to Provisional Operating License No. DPR-19 (Unit 2) and

Amendment No. 33 to Facility Operating License No. DPR-25 (Unit 3)

da~ed October 1, 1980, require that the early warning automatic fire

detection system for the refueling floor area be installed by start

up following the 1979 Unit 3 refueling outage.

As of the date of this inspection (approximately six years after

start up following the Unit 3 1979 refueling outage) the licensee

has failed to comply with the provisions of Amendment No. 36 to

Provisional Operating License No. DPR-19 and Amendment No. 33 to

Facility Operating License No. DPR-25.

An early warning automatic

fire detection system fire detection system h~s not been installed

14

in, the .. Refueling Floor Area and no compensatory measures have been

. taken.'.;_a:s:* a* result of this decreased effectiveness of the plant's

.Jfr~1£ptcitection features.

  • ~*~.--**~ <~.~~~:.-:~~=~-:~---~-~-* _:.**. -- -:(_

system in the refueling floor area was not discussed in any of the

licensee's correspondence to the NRC that requested amendments to

modify the plant's fire protection Technical Specifications to

incorporate Limiting Conditions for Operation and Surveillance

Requirements for the fire protection modifications required by the

original SER for Dresden Units 2/3.

None of the proposed Tables

3.12.1 to Technical Specification 3.12 listed fire detection

instruments in the refueling floor area. However, sufficient

information- existed which should have alerted the licensee that

he was in violation of a license condition.

For example:

(1)

By letter dated February 25, 1980 (R. F. Janecek-CECO to

T. A. Ippolito-NRG) the licensee noted that they did not

believe installation of an automatic early warning fire

detection system in the refueling floor area was warranted

based on low fire loading and the ability to make up water

_

and cool the spent fuel pools in the event of a loss of either!

Unit's spent Fuel pool cooling equipment due to fire. This l:

letter did not request relief from the installation of a

~-

refueling floor fire detection system.

No official NRC

~

response was

issu~d for this letter.

(2)

By letter dated March 18, 1980 (L. Derderian-NRG to

M. Antonetti - Gage Babcock and Associates - Consultants

to the Licensee) the NRC referenced a March 17, 1980 telecon

record with T. Pickens (CECO) in which the following was agreed

to concerning Rea~tor Building Refueling floor fire detection

systems for Dresden Units 2/3 and Quads Cities Units 1 and 2:

(a)

The license was to confirm to the NRC that in the most

heavy fire loading situations (i.e. refueling periods),

the loading would not exceed that necessary to cause

structural failures.

(b)

The licensee was to confirm that structural concrete

protection extends from the floor to some specified

height, lessening the likelihood of structural failure.

(c) The licensee was to recalculate average combustible

loading subtracting out the pool areas.

The licensee could not provide the inspectors with documented

evidence that these issues were addressed.

This failure to followup on implementation of a license condition

is indicative of a programmatic breakdown which has resulted in

a reduced level of fire protection than was intended to satisfy

15

criterion 3 of Appendix A to 10 CFR 50 and is considered a

vioJatHm of Amendment No. 36 to Provisional Operating License

  • No~~;iDEf~~19, Amendment No. 33 to Facility Operating License

No;;'.Jl,P,R;;.25,.10 CFR 50 (237/85-033-04; 249/85-029-04)(DRS).

'_-l, .... :::;' .~: -~

-.:...::-~~ **. -;.

b.

Preparations for the Upcoming Extended Unit 3 Outage Separation of

Unit 1 from Units 2/3

c.

During plant tours and in meetings with the licensee during the

inspection, the licensee agreed to update their response to the NRC

and describe the administrative* controls and the actions that will

be necessary to isolate Unit 1 trom Units 2 and 3 since Unit 1 is

no longer operational but shares co1T111on areas with Units 2 and 3.

The inspectors also requested that the licensee describe those

administrative controls and actions that will be necessary to

separate common areas in Units 2/3 while Unit 2 is operating and

Unit 3 is in an extended outage.

This is considered an Open Item (237/85-033-05; 249/85-029-05)(DRS)

pending further review by Region II I. .

Self Contained Breathing Air Supply for the Fire Brigade

"-E

~

Section 3.4.D.4(h) of the document entitled

11 Information Relevant

~--*

to Fire Protection Systems and Programs

11

, requires that breathing

apparatus using full face piece positive pressure masks that are

approved by NIOSH be provided for the fire brigade.

)

The inspectors examined the fire brigade Scott Air Pak breathing air

cylinders that were provided on Fire Chart No. 2.

Four out of four

of these cylinders contained 1800 pounds of air pressure. According

to the licensee's staff, a minimum of 2200 pounds of air pressure

should be contained in each cylinder.

2400 pounds of air pressure

would indicate the cylinder is full and may provide a 30 minute air

supply for the average fire brigade member.

The cylinder gauges have

a_!ange of up to 3000 pounds of air pressure.

A December 1984 three year audit recommended that a set of written

instructions be provided at the breathing air cylinder filling

station to assure that the cylinders are filled properly. Filling

of the cylinders is the responsibility of Health Physics.

Due to

tirrie constraints, the inspectors were unable to contact Health

Physics to follow up this concern. Therefore, the licensee is

requested to provide at the site the appropriate acceptance criteria

for filling breathing air supply cylinders. This is considered an

Open Item (237/85-033-06; 249/85-049-06)(DRS) pending Region III

review of the licensee's breathing air cylinder filling procedures.

d.

300 Pound Fixed Cardox System Supply Tank First Floor, Turbine

Building

During plant tours, the inspectors observed the following

deficienc~es on the main C~ system storage tank located on

the first floor of the turbine buildings.

16

(1) The access door to the tank compressor motor was missing.

. '~'a');~:~Th_~:fglas-s' cover to the tank 1 s mercoid switch located inside

  • --~'**~::t~?i};,:'.:t~~:;:;¥fg~~s door was missing.
--:TR~:;~1\\:fdk*ii~ee ti-ad no explanation for these deficiencies, but agreed

to take immediate corrective actions.

This is considered an Open Item (237/85-033-07; 249/83-029-07)(DRS)

pending further verification of the licensee

1s corrective actions

by Region III.

8.

Open Items

Open items are matters which have been discussed with the licensee, which

will be reviewed further by the inspector, and which involve some action

on the part of the NRC of licensee of both.

Open items disclosed during

the inspection are discussed in Paragraphs 4.c, 5.a, 7.b, 7.c, 7.d.

9.

Unresolved Items

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable _items, items of

noncompliance, or deviations.

An unresolved item disclosed during

the insp~ction is discussed in Paragraph 3.c.

10.

Exit Interview

The inspectors met with the licensee representatives at the conclusion

of the inspection on October 4, 1985, and summarized the scope and

findings of the inspection.

The licensee acknowledged the statements

made by the inspectors.

The inspectors also discussed the likely

informational content of the inspection report with regard to documents

reviewed by the inspector during the inspection.

The licensee did not

identify any such documents as proprietary.

On October 21, 1985, in a

telephone conversation with the licensee additional concerns regarding

the lack of fire detectors on the refueling floor were discussed with the

1 icensee.

  • ... *

17