ML17180A762

From kanterella
Jump to navigation Jump to search
Revised Pages 2 & 20 to Insp Repts 50-237/94-03 & 50-249/94-03
ML17180A762
Person / Time
Site: Dresden  
Issue date: 05/20/1994
From: Langstaff R, Vanderniet C, Walker H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17180A760 List:
References
50-237-94-03, 50-237-94-3, 50-249-94-03, 50-249-94-3, NUDOCS 9405240107
Download: ML17180A762 (2)


See also: IR 05000237/1994003

Text

utilizing portions of inspection procedures 37700, 92701, 92702, and 92720 and

draft inspection procedure 37550 to ascertain whether engineering and

technical support was effectively accomplished and assessed by the licensee.

Results:

Based on the items inspected, overall performance in engineering and

technical support was considered acceptable. The level, quality, and

timeliness of engineering and technical support for the plant appeared to be

acceptable.

Most of the individuals contacted were knowledgeable and

motivated and displayed a strong sense of ownership in their areas of

responsibility, however, there were some exceptions as noted in this report.

Significant improvements were noted in the Site Engineering and Construction

Organization, however, there were several findings where engineering

activities had not been thorough and the necessary attention to detail was

lacking. Little improvement was evident in the Systems Engineering

Organization.

The most significant weakness appeared to be in the control of temporary

alterations and lack of compliance to plant procedures.

The most significant

strength appeared to be the Site Engineering and Construction Organization

management's motivation and commitment to improvement.

Two violations, one with three examples, were identified. Violations included*

weaknesses in design control and a lack of compliance to procedures.

9405240107 940520

r.

PDR

ADOCK 05000237

G

PDR

2

time delay was 2-seconds rather than the required 7-seconds.

The

replaced relay was still indicated as an instantaneous relay,

rather than the installed time delay relay, as called for in the

TA documentation.

Procedure DAP 02-09, "Control of Critical Drawings," requir~d that

control room drawings be revised or updated to reflect the.correct

plant configuration. The failure to implement the requirements of

this procedure and correctly update the control room drawing with

the plant configuration for this temporary alteration is

considered an example of a violation of Criterion V of 10 CFR 50,

Appendix B (249/94003-02C(DRS)).

A ~iolation example was identified in this area.

4.3.2.4 Review of Safety Evaluations and Screenings

The inspectors reviewed the methods used- to perform 10 CFR 50.59 safety

screenings and evaluations.

Records of the screenings and evaluations

were reviewed for the selected modification, exempt change and temporary

alteration (TA) packages to verify completeness, accuracy, and

compliance with regulatory requirements.

Procedure DAP 10-02, "10CFR50.59 Review Screenings and Safety

  • Evaluations," Revision 8, was reviewed and found to be well .written and

concise. Several minor weaknesses were noted and discussed with

licensee personnel for possible procedural improvements.

Licensee

personnel acknowledged these weaknesses and indicated that the procedure

would be revised.

During the review of modifications Ml2-2(3)-93-004, the inspectors noted

that an unreviewed safety question was identified during the original

10 CFR 50.59 safety evaluation performed for the modifications.

Due to

discussions with the Office of Nuclear Reactor Regulation regarding the

issue, the modification was subsequently redesigned to eliminate the

unreviewed safety question.

As a result of the identification of this

problem, Information Notice 93-89, "Potential Problems with BWR Level

Instrumentation Backfill Modifications," was issued.

The inspectors

considered the identification and resolution of this issue to be a

positive application of the 10 CFR 50.59 safety evaluation process.

Safety evaluations or screenings were usually performed and were

acceptable.

The modification and TA packages reviewed contained the

required 10 CFR 50.59 safety screenings or evaluations and they appeared

to be well documented.

Some of the packages contained additional

supporting information.

Procedure OAP 10-02, if properly implemented,

provided sufficient controls.to ensure that proper 10 CFR 50.59

screenings and safety evaluations were performed and documented as

required.

Based on the review,of records and subsequent discussions

with licensee personnel, the inspectors concluded that the safety

  • screenings and evaluations were acceptable.

4.3.2.5 Review of Calculations

In order to complete the assessment of the design change and

modification process, the inspectors reviewed portions of selected

20