Text
- '
Cornmo.alth Edison 1400 Opus Place,
Downers Grove, Illinois 60515 Dr. Thomas Murley, Director
-U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention:
Document Control Desk October 22, 1993
Subject:
Dresden Nuclear Power Station Units 2 and 3
Reference:
Dr. Murley, Quad Cities Nuclear Power Station Units 1 and 2 Generic Letter 92-01, Revision 1 "Reactor Vessel Structural Integrity," dated March 6,1992.'
NRC Docket Numbers 50-237/249 and 50-254/265 GL 92~01 submittal of additional information *from M. A. Jackson to the USNRC, Dr. Thomas Murley dated November 30, 1992.
In the referenced letter Commonwealth Edison provided additional information pertaining to GL 92-01, Revision 1 "Reactor Vessel Structural Integrity," dated March 6,1992.
Reference 1 was inadvertently submitted without the referenced attachments.
This letter provides those attachments.
Commonwealth Edison sincerely apologizes for any inconvenience this may have caused.
Please direct any questions you may have to this office.
Respectfull,
~in J. Vonk 0400 /17 Attachments: 1)
- 2)
- 3)
- 4)
- 5)
Generic Issues Administrator Nuclear Regulatory Services Quad Cities Unit 1 Capsule Report Quad Cities Unit 2 Capsule Report Dresden Unit 1 and 2 Surveillance Properties Dresden Unit,3 Capsule Report Dresden Unit 3. Capsule Report cc:
J. Martin, Regional Administrator, RIII, w/attachment J. Dyer, Project Director, NRR J. Stang, PM NRR, w/attachment C. Patel, PM NRR, w/attachment M: Leach, Dresden SRI T. Taylor, Quad Cities SRI
\\