ML17179A763

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-237/93-02 & 50-249/93-02 on 930111-15 & 0218-22.No Violations Noted
ML17179A763
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/02/1993
From: Wright G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Delgeorge L
COMMONWEALTH EDISON CO.
Shared Package
ML17179A764 List:
References
NUDOCS 9303090409
Download: ML17179A763 (7)


See also: IR 05000237/1993002

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No:

50-237/93002(DRS); No. 50-249/93002(DRS)

Docket Nos:

50-237; 50-249

Licenses No:

DPR-19; DPR-25

Licensee:

Commonwealth Edison Company

Executive Towers West III

1400 Opus Place-Suite 300

Downers Grove, IL

60515

Facility Name:

Dresden Nuclear Power Station

Units 2 and 3

Inspection At:

Morris, Illinois

Inspection Conducted:

January 11-15 and February 18-22, 1993

3-2-'13

Date

~- 2- Cf's

Date

Section

Inspection Summary

Inspection on January 11-15 and February 18-22. 1993 (Reports No.

50-237/93002CDRS), No. 50-249/93002CDRS))

Areas Inspected: Routine fire protection inspection of

surveillances, equipment, fire brigade training and drills, zebra

mussel problems, and fire protection audits.

The inspector

utilized selected portions of NRC inspection procedures 64704 and

92702.

Results: Steady improvements continued in the fire _protection

program.

Overall, the fire protection program was considered

good.

The staff was knowledgeable and had taken appropriate

actions to correct issues and problems.

Strengths included

correcting hardware deficiencies, performing surveillances, and

training of fire brigade members.

Fire doors and transient

combustibles were well controlled.

Critiques of fire brigade

drills were performed well.

Control of fire protection concerns

was adequate in the area of plant modifications.

Reliability and

material condition of the diesel driven fire pumps was poor.

Preventive maintenance was being increased and the pump/engines

were being considered for replacement.

Concerns were identified

with the reliability of the Unit 1 loop fire main and the overuse

--*- - of repetitive checklists-during audits.

1.

2.

DETAILS

Persons Contacted

Commonwealth Edison Company (CECo)

  • R. Black, Assistant Fire Marshal

E. Carroll, Regulatory Assurance

  • L. Cartwright, Assistant Technical Staff Supervisor
  • A. D'Antonio, Supervisor Quality Verification
  • M. Dillion, Fire Marshal
  • R. Flahive, Technical Superintendent
  • B. Gurley, Regulatory Assurance
  • K. Housh, Technical Staff Fire System Engineer
  • J. Kotowski, Operations Manager
  • D. Mershon, Technical Staff Fire Protection Engineer

M. Nagle, Fire Brigade Instructor

  • D. Roberts, Corporate Fire Protection Engineer

R. Stachniak, Operating Engineer

D. Winchester, Internal Audit Group Superintendent

u. s. Nuclear Regulatory Commission CNRC)

M. Leach, Senior Resident Inspector

M. Peck, Resident Inspector

  • Denotes those individuals attending the exit meeting on

February 22, 1993.

Routine Fire Protection Program Review (64704)

This inspection consisted of observations of plant areas and

reviews of fire protection surveillances, maintenance on fire

protection equipment, fire brigade training and drills, fire

reports, deviation reports, work requests, safety evaluations,

controls to prevent bio-fouling by zebra mussels, and audits of

fire protection activities.

2.1

Observation of Plant Areas

The inspector observed several areas of the reactor building and

turbine building.

The observation included hose stations,

extinguishers, sprinkler valves, emergency lights, and

housekeeping.

The inspector determined that the equipment was

being maintained in good condition. Housekeeping was excellent

prior to the outage, although housekeeping could have been

improved during outage activities.

For example, rags were left

in work areas and large quantities of anti-contamination clothing

were allowed to accumulate.

The majority of the wood used during

outage activities was treated to make it fire resistant.

Fire

resistant plastic was also being used.

Lubricants and oils were

properly stored in fire resistant cabinets or in steel

2

containers.

Equipment areas were mostly free of oil as the

result of equipment leaks.

Appropriate controls for cutting and

welding operations were being enforced.

No discrepancies were

noted with sprinklers or with fire main valves or headers.

Halon

bottles were at appropriate pressures and fire extinguishers had

been inspected and had a current inspection date.

No areas were

noted where sprinklers should have been installed but were not

already in place.

Controls were being maintained for transient

combustibles and fire doors.

All fire doors were functional and

temporary outage cables had been routed to ensure that the fire

doors were operable.

2.2

Surveillances

The inspector reviewed completed surveillance procedures for

1992.

The surveillances were performed accurately and on time.

The observations and discrepancies were corrected with the

exception of the Unit 2/3 diesel fire pump.

Numerous engine and

pump problems were noted in surveillances DFPP 4123-5, "Unit 2/3

Diesel Fire Pump Weekly Operability."

The licensee was making

efforts to better utilize surveillance resources based on risk

and failure rate of equipment, which helped make resources

available for other efforts.

2.3

Maintenance on Fire Protection Equipment

2~3.1

Diesel Fire Pumps

The diesel fire pumps (DFP) were poorly maintained.

Very little

preventive maintenance (PM) was done.

Maintenance history showed

that the DFPs had a large number of failures during the 1990 to

1993 time period.

The repair data indicated that the DFPs went

from failure to failure without any overall corrective actions to

correct the situation.

The failures were caused by years of

neglect when PM efforts were not appropriate for the importance

of the DFPs, that is, for fire protection and refilling the

condenser following a station blackout.

PM activities did not include replacing parts that deteriorated

with age, such as hoses and gaskets, and checking strainers.

For

example, when one of the DFP engine coolant hoses burst because

of age and pressure, the licensee did not replace the other

hoses.

The hoses were also not put on a PM schedule to be

replaced.

Other failures included gaskets, radiator caps,

packing, and seals.

The engine coolant strainer was not on the

PM schedule for periodic cleaning.

Strainers were only cleaned

in the fire main system following a problem.

Other system

strainers had been cleaned and checked for the first time since

their installation more than 20 years ago.

3

..

DFPl engine failed in 1991.

The licensee could not pinpoint the

exact cause, but the engine had overheated several times in the

six months prior to this problem.

The engine was replaced but

the pump is in poor condition with very little margin to meet its

flow requirement.

Maintenance history indicated that the

reliability of DFP 1 increased after the engine replacement.

The

pump and engine are scheduled for replacement in 1993.

A

modification package was approved and the licensee is pursuing an

equipment supplier.

Repair data indicated that DFP 2/3 was in poor condition.

The

reliability was low.

The failure rate was high and occurred even

though the pump was only operated 40-50 hours per year.

As a

result of an engine hose failure, DFP 2/3 failed the same time

DFPl failed.

The licensee was able to make repairs within 24

hours otherwise the reactors were required to be shut down.

The

licensee purchased a third OFP that can be temporarily connected

until one of the two main pumps are repaired.

The problem of

shutting down the plants is solved, but the reliability has not

been increased much for the two main fire pumps in the event of a

fire.

Both DFPs will be replaced in the 1993/1994 time frame. In

addition, improved PM procedures are in the concurrence cycle for

the existing pumps.

Also, The PM schedule now includes checking

and cleaning strainers.

The technical superintendent stated

during the exit that the DFPs would be put on the Technical

Issues List, which assures that adequate resources will be

devoted for improving the material condition of the DFPs.

2.3.2

Batteries

Surveillance reports indicated that maintenance of the DFP

batteries had been a problem including water levels, possible

overcharging, and maintaining specific gravity.

The licensee had

taken action to turn over the maintenance of the batteries to the

electrical group during 1992.

Following this change the

surveillance reports indicated that the condition of the

batteries had improved.

2.3.3

Unit 1 Yard Fire Main Loop

The Unit 1 yard fire main loop appeared to be in poor condition.

The 1992 fire protection insurance log indicated that the fire

loop was inoperable several times in 1991 and 1992.

The problems

were believed to have occurred because of being disturbed during

the installation of the sewage system, and not as a result of the

asbestos cement piping being made brittle because of pressure

4

1*

cycling and aging.

Maintaining reliability of the loop is

important because both main fire loops are required to meet the

requirements of 10 CFR 50, Appendix R.

Current low reliability

makes it questionable whether this system will be available

during a fire.

2.4

Fire Brigade, Fire Reports, and Fire Drills

Fire brigade members received extensive training, which included

classroom and offsite fire fighting.

The onsite fire drill

requirements had been met by all brigade members who were listed

as qualified.

All appropriate drill and training records were

properly maintained.

A review of the fire records indicated that the fire brigade was

only required to respond twice in 1992.

The two events were for

a motor fire and a power transformer fire.

The small number of

responses was indicative of good control of combustibles,

cutting/welding activities, and housekeeping.

Recent efforts at improvements for fire fighting include

purchasing more equipment to better outfit the fire brigade

members, with plans to locate the equipment at strategic

locations in the plant.

This will allow a faster response to

fires.

2.5

Deviation Reports and Work Requests Review

The inspector reviewed open nuclear work requests (NWRs) for fire

protection.

The backlog was low considering the high number of

NWRs that had been performed during the year.

The NWRs had been

properly prioritized and none of the outstanding work items

appeared to be highly safety significant.

The backlog had been

reduced from 175 to 139 during 1992.

In addition, the fire

protection Nuclear Tracking System (NTS) backlog had been reduced

from 65 to 32 in 1992.

There have been numerous tamper switch maintenance problems on

fire protection valves.

Many of the problems resulted from old

tamper switches and the difficulty in purchasing replacement

parts.

A contributing factor was that the switches were an add-

on feature, which was easily knocked out of calibration.

These

problems were being corrected by including valves on the locked

valve program with valves being maintained in position by chains

and locks.

Specific locks and keys will be maintained for fire

protection valves.

The licensee reviewed the valves to assure

that those important to safety were included in this effort.

Some valves had been added to or deleted from the list based on

the review.

5

2.6

10 CFR 50.59 Safety Evaluations

The majority of the fire protection program has been removed from

the Technical Specification.

This allows changes to be made to

the fire protection program by performing a 10 CFR 50.59 safety

evaluation.

The inspector reviewed 10 CFR 50.59 safety

evaluations issued for program changes for 1992.

All of the

changes were appropriate and were not detrimental to fire

protection safety.

Some surveillance cycles had been extended

based on industry data and failure rates.

The safety evaluations

that delayed performing full flow testing of the fire main system

for six months were based on preventing zebra mussels from

entering the fire protection systems, and to give the licensee

adequate time to make corrective actions.

The plant is currently dealing with a bio-fouling problem, zebra

mussel infestation, in its intake water.

Zebra mussels were

found last summer on screens in the intake structure.

Notable

efforts were being made to prevent zebra mussels from entering

the fire main systems and potentially making the fire protection

systems inoperable.

Full flow surveillances of the fire

protection system were suspended for six months to permit

modifications to the systems.

Hypochlorite is being injected

into the service water system, which connects to the keep fill

line of the main system.

In addition, thermal shock treatment is

also being used to kill the mussels.

A modification is planned

for an injection system into the fire main system.

Strainer

checks indicate that the zebra mussels have not entered the fire

main system.

The licensee has increased the surveillance

frequency for strainers.

The concentration of chemicals will be

monitored in the fire main system following the full flow tests

to ensure that the system is maintained zebra mussel free.

2.7

Audits of Fire Protection Abtivities

The inspector reviewed the following audits of fire protection

activities:

Quality Assurance/Nuclear Safety Audit Report Number

12-91-I, January 17 through 30, 1991; Quality Assurance/Nuclear

Safety Audit Report Number 12-92-I, January 27 through 31, 1992;

and Offsite Quality Verification Audit Report Number 12-93-I,

December 14 through 18, 1992.

Preparation for the audits was good.

The audit reports were

brief and did not indicate the amount of reviews that had been

performed in the fire protection area.

The audits had adequate

detail to detect most program problems.

The licensee had taken

timely corrective actions for those fire protection deficiencies

that were identified during the audits.

The audits met

regulatory requirements.

6

q.;

In general, the audits were more compliance based rather than

being performance based.

The licensee utilized a repetitive

check list approach to auditing.

The check lists indicated that

activities listed had been reviewed in detail; however, this

continued approach could contribute to missing deficiencies year

after year.

For example, problems with the DFP and Unit 1 yard

loop reliability, which are discussed in Paragraph 2.3, were not

discussed in the audits.

3.

Exit Interview

The inspector met with licensee representatives (denoted in

Paragraph 1) on February 22, 1993, and summarized the scope and

findings of the inspection. The informational content of the

inspection report was discussed with regard to documents reviewed

during the inspection.

The licensee did not identify any of the

documents as proprietary.

7