ML17179A726

From kanterella
Jump to navigation Jump to search
Forwards Safety Insp Repts 50-237/92-34 & 50-249/92-34 on 921214-930129.Violations Identified & Being Considered for Ea.Enforcement Conference Scheduled for 930222
ML17179A726
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/12/1993
From: Greenman E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Delgeorge L
COMMONWEALTH EDISON CO.
Shared Package
ML17179A727 List:
References
EA-93-019, EA-93-19, NUDOCS 9302230124
Download: ML17179A726 (3)


See also: IR 05000237/1992034

Text

.. '*

  • Docket No.

50-237;-50-249.

EA Numbei 93~019

Commonwealth Edison Company

ATTN:

Mr. L. 0 .. DelGeorge

rEB 1 2. 1993 .. *

Vice President, Nuclear Oversight

and Regulatory Services

Executive Towers West III

1400 Opus Place, Suite 300

Downers Grove,

IL

60515

Dear M~. D~lGeorge:

This ieferi io the special safety inspection tonducted by Mt. Michael S. Peck

and others of this office from December 14, 1992, to January* 29, 1993. * The

inspection included a review of activiti~s authbrized for your Dresden Nuclear

Power Station, Units 2 and 3; At the conclusion of the inspection, th~

findi~gs wer~ discussed with those ~ember~ of your staff identified in the

e~closed report (Encl~sure 1).

Areas ~xamined during the ~nspection ~re identified in the report. *This

special inspection focused on the containment heat removal system with

particular emphasis on containment cooling service water.

Within these areas,

.the inspection consisted of selective examinations of procedures and

representative rec6rds, interviews with person~el, ~nd observation of

activities and tests in progress.

Based o~ the results of this inspection,* several apparent violations were

identified and are being considered for escalated enforc~ment actidh in

accordance with the "Gen~ral Statement *of Policy and Protedure for NRC

Enforcement Actions" (Enforcement Policy}, 10 CFR Part 2, Append~x c,

The

apparent viol~tions concern the degraded condition of the containment cooling

service water ~ystem and potential weaknesses with your engine~ring design

function, potential inadequacies in safety evaluations performed on changes to

the facility,* and apparent misunderstandings of NRC reporting requirements.

Atcordingly, no Notice of Violation is ~resently being issued for these *

inspection fin_dings.

In addition, please be advised that the number and

~haracterizatibn of apparent violations described in the enclosed inspection

report may change as a result of further NRC r~view.

An enforcement conference to discuss these apparent violations has been

scheduled for Febru~ry 22, 1993.

This enforcement conference will be operi to

public observatioh in accordance with the Commission's trial program as

discussed in the enclosed Federal Register notice (Enclosure*2.)

The purposes

of th i's 'conference are to dis.cuss the -apparent violati*ons; their root causes

9302230124 09350002012237

PDR.

ADOCK

G

.. *--* ________ PPR

,-

FEB 1 Z. 1993

Commonwealth Edison Company

2

and their safety signific~nce; to provide you the oppoftunity to point out any

errors in our inspectio~ report; and to provid~ an opportunity for you to

pr~sent.your proposed corrective actions.

In additio~, this i~ an opportunity

for you to provide any information concerning your perspective on the seveiity

of the issue, the factors that the NRC consider~ when _it determines the amo~nt

of a civil penalty that may be assessed in accordance with Section VI.B.2 of

the Enforcement Policy, and the possible basis for exercising discretion in.

accbrdance with Section VII &f the Enforcement Policy.

You will be advised by

separate corr~spondence of the results of our deliberations in this matter.

No response regarding these .apparent violations is required at this time.

In accordance with 10 CFR 2,790 of the :commission's regulations, ~ copy of

this letter and its enclosures will be placed in th~ NRt P~blic Document Room._-

We will gladly dis~~ss any question~ you have concerning this inspection.

Enclosures~

1.

Inspection Report

50-237/249-92034 -

2.

Federal Register Notice

dated July 22, 1992

See Attached Distribution

Riii

Riii

- Riii

PJ.\\},_1,./~~

PJ.-l},/11ln

(!.£

r .Peck- -

Hiland

-- Clayton-- --

-

-

~111/!3

Sincerely,

  • - OriB1nal signed by 11::. C. Crsanman

-

-

.

  • Edward G. Gieenman, Director

Division of Reactor Projects

~

RII I

RII I

RI II

~

-(JJ~

Grit~~

DeFayette

Forney

J//ttff v ->f ,, r~"

Commonwe~lth Edison Co~p~~y *

cc w/enclosures:

.

M. Lyster, Site Vice President,

t. Schroeder, Station Manager

J. Shields, Regulatory Assurance

Supervisor

D. Farrar, Nuclear Regulatory.Services

_ ~anager

~D/OBC t.('RlOS) .

OC/LFDCB

Resident Inspectors, Dresden

LaSalle, Quad Cities, Clinton

R. Hubbard *

J, Mc Caffrey, Ch.i ef, Pub l iC

Utilities Division

R. Newmann, Office of Public

Counsel, State of Illinois Center

J. Stang, Licensing Project Manager, NRR

State Liaison Officer

H. J. Miller, Riii

T. 0. Martin, Rill

J. * E. Dyer, NRR

E. J .. Leeds, NRR

M. L. Jordan, Riii

C. D. Pederson, Riii

S. Stasek, SRI,

D~vis Besse

3

rEB 1 2 139~