ML17179A459

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/92-19 & 50-249/92-19 on 920610-0806. Violations Noted.Major Areas Inspected:Training, Qualifications,External & Internal Exposure Control, Including ALARA Considerations & Contamination Control
ML17179A459
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 09/14/1992
From: Michael Kunowski, Markley A, Schumacher M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17179A457 List:
References
50-237-92-19, 50-249-92-19, NUDOCS 9209290017
Download: ML17179A459 (10)


See also: IR 05000237/1992019

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION I II

Reports No. 50-237/92019(DRSS); 50-249/92019(DRSS)

Docket Nos. 50-237; 50-249

Licenses No. DPR-19; DPR-25

Licensee:

Commonwea 1th Edi son Company

1400 Opus Place

Downers Grove, IL 60515

Facility Nam~: Dresden Nuclear Generating Station, Units 2 and 3

Inspection and Meeting At:

Dresden.Site, Morris, Illinois

Inspection Conducted:

June 10 through August 6, 1992

Meeting Conducted:

J~~Y~~~~:_2A;~/l_./

Inspectors:

.~ifno':S-k~~

.*.b~

A.*w. M~~

/n~

Approved By:

M. C. Schumacher, Chief

Radiological Controls Section 1

Inspection Summary

9-/LJ ~Cf'Z

Date

Inspection on June 10 through August 6, 1992. and Meeting oh July 17, 1992

(Report Nos. 50-237/92019(DRSS); 50-249/92019CDRSS))

. A~eas Inspected and Discussed at the Meeting:

Special, an~ounced inspection

of the radiation protection program (Inspection Procedure (IP) 83750),

including staffing, training, and qualifications; external and internal

exposure control, including ALARA considerations; and contamination control.

The inspectors alsb reviewed the program for transportation of radioac~ive ,

materials (IP 86750) and the ventilation system for several radioactive waste

. (radwaste) buildings (IP 84750).

In addition, a special meeting was held at

the request of the NRC to discuss actions on several radwaste issues.

Results:

The inspection identified weaknesses in radiological controls that

sugg~sted worker indifference to good radiological control~ and the need for

improved management oversight at the job site. Violations were jdentified for

failures to follow procedures, absence of radiation area postings, and

inadequate surveys (Sections 4 and 5).

The inspectors also observed .

. ventilation system problems in the radwaste and max recycle buildings that

reflected system design problems.

The licensee has made good progress toward

resolving sev~ral longstanding radwaste p~oblems (Section 7) and the

inspectors observed good radi ol ogi ca 1 controls. by radiation protection

technicians on several jobs (Section 5).

9209290017

PDR

ADOCK

A

920918

05000237

PDR

1.

DETAILS

Persons Contacted

@R. E. Aker, Performance Assessment

@*D. F. Ambler, Health Physics .Services Supervisor

  • S. J. Bell, Chemistry and Radwaste Services, Corporate
  • @*l. Bennett, Radwaste Coordinator
  • W. Causer, Engineering Assistant

@*E. W. Carro 11, Regulatory Assurance

@F. Dundek,' Auxiliary Systems Group Leader

M. Gagnon, Health Physicist

@*L. F. Gerner, Technical Superintendent

  • K. W. Heinrich, Chemistry and Radwaste Services, Corporate
  • C. Herzog, Chemistry and Radwaste Services, Corporate
  • S. Horvat.h, Health Physicist, Corporate

@M. Korchynsky, Unit 3 Operating Engineer

  • T. Murphy, Radwaste System Engineer, Technical Staff

T. J. O'Connor, Assistant Superintendent of Maintenance

@*L. L. Oshier, Lead Health Physicist-Operations

@R. Radtke, Regulatory Assurance Supervisor

  • R. Raguse, Health Physicist, Corporate

@W. Rakes, Radiation Protection Supervisor

  • P. Roth, Chemistry and Radwaste Services, Corporate

@*D. Saccomando, Nuclear Licensing

@*C. W. Schroeder, Station Manager

  • G. L. Smith, Assistant Superintendent of Operations

@D. S. Southcomb, Auditor, Nuclear Quality Programs

  • R. W. Stobert, Operating Engineer

M. Strait, Technical Staff Supervisor

. @R. C. Winslow, Lead Health Physicist-Technical

  • R. Hand, Supervisor, Environmental Services, Illinois Department of

Nuclear Safety (IONS)

  • W. L. Axelson, Deputy Director, Division of R.adiation Safety and

Safeguards, NRC

@*M. C. Schumachei, Chief, Radiological Controls Section 1, NRC

The inspectors also contacted other licensee and contractor personnel.

  • Denotes those present on July 17, 1992, at t~e meeting to.discuss

radwaste issues.

@Denotes those present at the exit meeting on August 6, 1992.

2.

General

This concluded a three-month special inspection of the Dresden radiation

protection (RP) program by two senior radiation specialists in an

attempt to understand the reasons for persistent performance weaknesses.

It emphasized observation of ongoing work in the radiologically

controlled area (RCA), interviews with both workers and managers,.

independent dose rate measurements, and the station program for

. 2

3.

maintaining exposures as-low-as-rea*sonably-achievable (ALARA).

The

inspectors also made extensive tours inside and outside of the RCA,

including both well travelled and infrequently travelled areas, to

observe radiological controls.

Nuclear General Employee Training (IP 83750)

The Nuclear* General Employee Training (NGET) for contractors.and new

station radiation workers (radworkers) is one and a half days of

instruction on RP and such topics. as security, industrial safety, and

fitness for duty.

Students in this initial training must show they can

properly don and doff protective clothing. Annually thereafter,

radworkers are required to take a half-day of refresher (requalifi-

c~tion) training. Written tests are given for both.

In an initfal NGET session attended by the inspector, the instructor, a

former RP and chemistry technician, was conscie~nt i ous and competent.

However, the session had little discussion of pra~tical radiological

problems such as those documented in station Radiological Occurrence

Reports (RORs) and no audible demonstration of electronic dosimeter (ED)

alarms.

Proper worker response to ED alarms has been a problem over the

past two years at the station.

An alarm training tape that was being

developed by the licensee was put into use following the inspection.

In

addition, the licensee was planning to incorporate more discussion of

RORs into future NGET sessions.

Both efforts will be reviewed during

future inspections.

The inspectors learned from licensee representatives that. NGET was to be

enhanced in September 1992 with advanced radworker topics after being.

twice postponed from earlier target dates of December 1991 and June

1992.

A more detailed training course involving advanced radworker.

t6pics w~s also being de~eloped for late 1992.

The inspectors. also.

learned from other plant personnel that NGET ~redibility sometimes

suffered from use of instructors with little recent plant experience.

Licensee management was aware of and dealing with this problem.

No violations of NRC requifements were identified.

.

.

.

4.

Material Conditions and Radiological Controls CIPs 83750 and 86750))

The inspectors reviewed material conditions, radiolrigical controls, and

radiation protection technician (RPT) performance during several plant

tours.

a.

Outside Areas

The inspectors identified unpasted, accessible radiation areas

(where dose rates could result in a wh6le body dose greater than

5 millirem in one hour or greater than 100 millirems in 5

consecutive days) on the Unit 2/3 radwaste building roof on

June 20, 1992, and around a seavan adjacent to the Unit 2/3 truck

bay on July 15-20, 1992.

These conditions, which were contrary to

the .requirements .of 10 CFR 20.203(b), were confirmed by licensee

surveys of the _roof on June 17 (10 millirem per hour) and June 22

(60-65 millirem per hour) and of the seavan on July 20 (4 millirem

3

per hour) (Violation No. 237/92019-0la(ORSS) and -Olb(ORSS);

249/92019-0la(ORSS) and -Olb(DRSS)).

The significant variation on.

the roof resulted from changing conditions in the radwaste rooms

below.

The inspectors also identified in both areas the failure of the

licensee to make surveys required by 10 CFR 20.20l(b) to evaluate

the potential radiation hazards. Specifically: licensee

representatives stated that the roof area had not been surveyed

since radwaste storage in the rooms below was discontinued in 1990

despite the fact that storage was resumed in 1991, and the seavan

had not been survey~d during the period from July 15 until July 20

(Violation No. 237/92019-02a(DRSS) and -02b(DRSS); 249/92019-02a

(DRSS) and -02b(ORSS)).

Both areas w~re posted as radiation area~

and added to the surveillance schedule.

Long term corrective

action included re-assignment of area posting responsibilities

from the station laborer group to the RP department and ~ssignment

  • of specific plant areas for RP managers to tour daily and weekly.

The short and long term corrective actions to the two violations

appeared adequate.

Although not posted as a radiation area on Jun~ 16, the roof area

was posted as a radioactive materials area .. However, the posting

was well weathered, indicating it was irifrequently visited, and -

the area delineation was incomplete.

Additional evidence of

neglect were seen in nearby roof areas.

In one location, the

inspectors saw a high radiation area (HRA) sign fac~ down on the

floor and a radiation area sign taped over.

They apparently had

been used when high radiation area controls were temporarily

imposed and not removed afterwards.

Also neafby, the inspectors

saw a considerable accumulation of dirt on the roof from.which two

small trees were growing, cable trays containing debris, a

discarded empty radioactive material bag, and a chain fall painted

purple (later identified as having fixed contamination).

Conditions in both of the above areas* appeared to reflect

.

insufficient concern by workers as well as insufficient management

oversight to ensure good working conditions;

These matters were

discussed at the exit interview.

b.

Inside Areas

The inspectors made numerous entries into the reactor, turbine and

radwaste buildings during the inspection.

Housekeeping and

material conditions were generally good,

alt~ough the Unit l

radwaste control room and the adjacent outdoor storage were messy.

There were also examples of inconsistent postings of contaminated

areas of the kind noted in previous reports.

Two violations were identified.

5.

Maintaining Occupational Exposures ALARA (IP 83750)

The inspector reviewed the licensee's program for maintaining_

occupational exposures ALARA.

Overall, the program was adequate.

4

I

Details of the review are discussed below.

a..

Implementation of ALARA in Design Activities-

On Ju~e 19, 1992, the inspector attended an Installers ~alkdown

Meeting for Minor Modification Pl2~3-92-699. This involved

installing a modified spool piece and upgrading associated

restraints on the fuel *pool cooling bypass line to alleviate

cavitation-caused vibration.

An orifice on this line was a crud

  • trap and a significant source of radiation exposure.

The meeti~g

was .attended by representatives from various corporate and pl ant

tech~ical groups and the licensee's architect-engineer (AE)

consultant.

Several weaknesses were noted at the meeting by station ALARA and

maintenance personne 1 and by the inspector including 1 ack of

'

certainty that the modification would eliminate the vibration,

engineering decisions made without adequate ALARA co'ns iderat ions

  • (e.g., no hydrolazing ports or shielding supports), and lack of

ALARA training for two of the three engineers. irivolved.

Installation of the spool piece was p6stponed until station

concerns could be resolved.

A similar problem with the lack of ALARA considerations in a

modification was identified by the station in May 1.991 after.

unexpectedly high dose rates were identified around a hydrogen

water chemistry system skid ..

  • b.

Unit 3 Incore Detector Replacement

On July 2, 1992, the inspector observed a portion of the pre-j.ob

briefing for a transversing incore probe (TIP) replacement and

reviewed the ALARA evaluations and radiation work permit.

The

briefing was conducted in the instrument maintenance (IM) shop by

an IM superviso_r, the assigned RPT, and an ALARA representative.

Later that day~ the inspector watched the job. Several

observations from the meeting and the job are described below.

A special planning meeting (a "Heightened Level of

Awareness" (HLA) meeting) was conducted on July 1, 1992, and

resulted in the reduction of the number of workers involved

in the job.

Distractions from non-participant IM personnel affected the

quality -0f the briefing.

Specific information about TIP decay time was not known by

personnel involved in the job, although it was known that a

minimum of three weeks had elapsed.

Exposure control by ttie RPT was good with dose (0. 089 p*erson

rem) was about half the prejob estimate although dose rates

(150 mrem/hour contact) were similar to prev1ous TIP work

  • and the duration (39 person-hours) five times the pre-job

estimate.

5

Contamination lev~ls of 1-1~5 million dpm/100 centimeters

squared.were expected and found.

Appropriate contamination*

control measures were taken.

The TIP cable was cranked too far into the drive machine and

the detector fell into the machine.

E~tra time was required

to retrieve the detector.

Cable cutters were dull and required extra time to sever the

TIP from the cable.

The spool for winding used cable was too small causing cable

to unwind and contaminate the floor.

'

Overall, the exposure for the job was low, but the pre-job

briefing distractions and the equipment problems listed *above

highlighted the need for improved recognition of ALARA principles

by work groups other than RP.-

c.

Heater Bav Entry

On June 17, 1992, the inspector accompanied a work group into the

Unit 3 turbine heater bay while the reactor power *was 450 MWe. *

The pre-jrib briefing by RP personnel was well done ~nd a reduction

in the number of workers was successfully negotiated.

During the

job, exposure cont ro 1 by the RPT was exce 11 ent.

Exiting personnel adequately removed protective clothing and

frisked themselves; however, hand-carried items such as

flashlights and papers were not surveyed prior to being handled on

the clean side of the step off pad and the RPT held contamination.

smears in his bare hands while surveying them and did not survey a

canvas bag used to remove equipment and the smears from the heater

bay.

Although contamination levels in the heater bay were low

(500-5,000 dpm/100 centimeters squared) and no workers were

contaminated, the contamination control practices ~xhibited were

poor and not unique as ~imilar occurrences were*noted during

previous inspections.

d.

RWP and ALARA Procedural Requirements

On June 17,

1992~ the inspector reviewed the following RWPs to _

determine if pre-job ALARA checklists and briefings were completed

in accordance with OAP 12-09, "ALARA Action Reviews;

11

RWP Number

  • 20011A.

20290A

20323A

20334A

20336A

20349A

20355A

Job Description

Radioactive Waste Processing and Shipping

Hydrolaze Floor Drains in 2/3 Reactor Building -

General Access Areas

Remove and Replace Refuel Grapples

Replace 2B RWCU Post St~ainer/Cap Drain Line

Mechanically Overhaul RWCU MOV 3-1201-12

Cut Out and Replace V-36 AO Valve in Unit 1

Waste Surge Tank Cleanqut

6

20370A

Remove and Replace Unit 3 E TIP Detector

The review indicated that all the questions in the checklists had

  • been addressed during RWP preparatfon, but a rationale or basis

for the answers was not always provided.

This is considered a

weakness.

The inspector's review also identified several instances where

required briefings were not given before work was performed on the

RWPs:

on May 12, 18, and 19, two workers and three RPTs on RWP

20290A; on May 28 and 29, and June 8; 10, and 15, 1992, ten

workers on RWP 20323A; and.on June 15 and 16, 1992, three workers

and two RPTs on RWP 20355A.

OAP 12-09 required briefings for

these jobs because they involved exposure estimates in excess of 1

person-rem or smearable contamination levels in excess of 250,000

disintegrations per minute (dpm) per lOO centimeters squared.

Workers and RPTs were subsequently given the req~ired briefings,

and RP personnel and job supervtsors we~e counselled on the need

to ensure that briefings are given.

The failure to follow the

briefing requirement of OAP 12-09 is an example of a violation of

Technical Specification (T/S) 6~2.8., which requires adherence to

radiation control procedures (237/92019-03a(DRSS); 249/92019-

03~(DRSS)).

Also during the RWP review, the inspector identified references to

three diffe~ent procedures for extremity dosimeter requirements

(DRP 1210~02, DRP 1210-04, and DRP 1210-05) which contained mutual *

inconsistencies.

No regulatory limits were approached during the

work but the need for better attention to detail was indicated.

Similar procedure inconsistencies wer~ identified in an earlie~

inspection (Inspection R~ports No. 237/90026(DRSS); 249/90025

(DRSS)).

.

On June 19, 1992, an NRC inspector observed a station maintenance

worker remove his dosimeters and begin work in the Unit 2 High

Pressure Coolant Injection pump room, a po~ted radiation area.

He

worker put them ~~ again when approached by the inspector.

According to a licen~ee followup, the worker r~moved the dosi-

meters because he was concerned about them falling through .the

grating he was working from.

The worker was counseled and given

one day off without pay.

The failure to follow the require~ent of

the RWP (No. 20356A) to wear the dosimeters is contrary to OAP 12-

25, "Radiation Work Permit Program," and is another example of a

violation of T/S 6.2,B. (237/92019-03b(ORSS); 249/92019-03b

(DRSS)).

.

e.

High Radiation Area Door Controls

The inspector reviewed a recent ROR written for a high radiation

area door found unlocked on July 6, 1992.

Although dose rates in

the area at the time did not require the door to be locked, this

problem and other recent similar problems with areas controlled as

high radiation areas, indicated a need for greater management

attention.

7

...

6.

One violation was identified.

Radwaste Ventilation Problems (IP 84750)

On July 6, 1992, during a tour of the ~adwaste and max recycle (floor

drai~ ~recessing) buildings, the inspector observed three doors leading

to the outside that were blocked fully open, contrary to a sign posted

on each door that read "Door to remain closed at all .times to maintain

ventilation flow except for ac~ess." Air flowed noticeably into the

buildings through two of the doors, but not through the third door,

located on the roof of the max recycle building .. This door offered a

potentially unmonitored release path although probably of limited

.radiological significance owing to the low level of contamination and

absence of recent airborne radioactivity problems in the area. This was

later corroborated by .a licensee survey of the adjacent roof area which

found no contamination.

Nevertheless, it was of concern because of the *

apparent disregard by plant personnel of the instructions posted on the

doors and management's apparent tolerance of.this attitude.

The short term corrective actions for.these problems included closing

the doors, initiating a work request to repair or replace the radwaste

building door which was in disrepair, and emphasizing py memoranda to

each plant employee that outside doors to all three buildings ~ere* to be

maintain~d closed, in accordance with posted instructions.

The open doors also prompted inspector concerns regarding adequacy of

radwaste ventilation systems.

Licensee tests on July 10, 1992,.found

that inside pressures were negative with respect to the outside except

for the max recycle building which was slightly positive with outside

doors open.

With doors closed the radwaste building met its design

specification of -0.25" while the max recycle building was about -0.05"

compared with its design specification range of -0.105" to -0.145".

However, neither building .could be shown to meet the Final Safety

Analysis Report (FSAR) design basis of -0.25" water pressure

differential between clean areas and those with the gre.atest

contamination potential.

The radwaste building measured -0.125" with

doors c;losed and -0.10" to ,...0.18" with doors open .. The differential was

not measured in the max recycle building because of the lack of

installed pressure instrumentation.

The licensee was able to bring max recycle differential pressure to -

0.18" to -0.20"

by shutting off the one ventilation supply fan

previously used, with intention to operate this way until new_exhaust

fans with higher capacity were installed.

The need to maintain outside doors closed and the problem with the ~ax

recycle building meeting the design specification were identified during

modification and review of the ventilation sy~tem which took place from

1986-1989. After the modification was completed in April 1989, signs

were posted on the doqrs and workers were informed of the need to keep

them shut, and work requests were issued to replace the max recycle

ventilation exhaust fans, which had been found to be undersized;

ho~ever, the requests were canceled in May 1~90 owing to l~ck ~f funds.

Problems with low level contamination of personnel attributa~le to the.

8

ventilation system occurred in 1990 and 1991, and replacement fans were

again requested.

They are expected to be installed by 1993.

In summary, management actions to correct the max recycle building

ventilation problem identified in. 1986-1989 were inadequate and the

.. ventilation system was operated in a generally degraded manner since

then.

Of additi~nal concern were the apparent tolerance of radwaste

doors being left open and a two-year lapse between completion of the

ventilation system modification and declaration of the system operable.

These weaknesses were discussed at the exit interview and licensee

corrective actions will be reviewed during a future inspection

(Inspection Follow-up Item 237/92019-04(DRSS); 249/92019-04(DRSS)).

No violations were identified.*

7.

Meeting to Discuss Radwaste Issues

The licensee reported significant progress on a number of outstanding

. radwaste issues at a July 17, 1992, meeting was at Dresden attended by

licensee, state, and NRC representatives. A similar meeting was held in

June 1991 (Inspection Reports No. 010/91001; 237/91018; 249/91017).

a.

Radwaste Upgrade--The project was 63% completed with full

completion expected in 1993.

The final dose total estimate is 500

person-rem, compared to an original estimate of 1958 person-rem.

Dose savings were attributed to aggressive source term reduction,

use of automated equipment, and ALARA training classes: *

b.

Contaminated Soil--Fences have been erected around two piles of

soil and a vegetation ground cover is planned.

A 10 CFR 20.302-

type petition has been filed with the IONS for one of the piles

and is planned for the other pile. Contaminated soil in four

other areas is expected to be left inplace until decommissioning,

c.

Radwaste Backlog~-A backlog of about 60000 cubic feet of radwaste

on hand in July 1989 was reduced to less than 8000 cubic feet in

June 1992.

It included already solidified drums needing

characterization, liquid decontamination solution from the unit

one cleanup and other solid wastes.

The work was achieved with

low dose expenditure and 660 shipments were made.with no

regulatory problems.

d.

Radwaste Ventilation--The licensee has recently begun to address

radwaste ventilation problems including those discussed in Section

6.

Among actions taken were plugging of holes in the ceiling of

the spent resin and sludge tank rooms and installing an exhaust

duct from the spent resin tank room to improve air flow and

replacing two supply fans to improve reliability.

e.

Contaminated Area Reduction--A station goal was established to

reduce the amount of contaminated floor from the current.27% to

5%.

Implementation plans, which are still being developed, will

concentrate on the torus basements, the turbine floor, and floors

of the reactor building equipment drain tank rooms.

The licensee

9

~

has also adopted a commonly used contaminated area definition of

1000 dpm/100 square centimeters.

f.

Recent Unplanned Exposure Event--The 1icensee briefly described

the June 3, 1992, unplanned exposure of a contract radwaste

technician during the installation of a lid on a liner of

. radwaste.

The technician received approximately 197 millirem

compared to a 100-mi'llirem administrative limit. This event is

discussed in .Inspection Reports No. 237/92016; 249/92016.

g.

Clean-up of the Spent Resin Tank and Sludge Tank*Rooms--The

licensee stated that the approximately one barrel of resin that

spilled in the spent resin tank room on March 1, 1992 {Inspection

Reports No. 010/92002; 237/92007; 249/92007), would be cleaned up.

by the end of 1992.

In addition, with the clean-up of the sludge

tank room about 95% completed~. the cost-benefit of further clean-

up was being evaluated.

The licensee agreed to inform the NRC in

writing of the results of the evaluation.

NRC representatives acknowledged good licensee performance overall in

this area.

8.

Exit Meeting

The scope and findings of the inspection were discussed with licensee

representatives {denoted in Section 1) on August 6, 1992.

Specifically,

the inspector discussed the.NGET program weaknesses and early

improvements made by new personnel {Section 3); material condition,

posting, and survey problems {Section 4); ALARA program problems and

good job coverage provided by RPTs {Section 5); and radwaste ventilation

problems {Section 6).

The relative ease with which these problems were

identified was emphasized and the need for increased management presence

in the plant was highlighted.

The licensee acknowledged the comments

and did not identify any likely inspection report material as

proprietary.

10