ML17177A645

From kanterella
Jump to navigation Jump to search
Responds to Re Insp Rept 50-237/91-36.Concludes That Root Cause of LPCI Inoperability Was Vendor Supplied Training Inadequacies on motor-operated Valve Testing Sys
ML17177A645
Person / Time
Site: Dresden Constellation icon.png
Issue date: 09/15/1992
From: Beverly Clayton
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hubbard R
MHB TECHNICAL ASSOCIATES
References
NUDOCS 9209220253
Download: ML17177A645 (6)


See also: IR 05000237/1991036

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

Docket No.

50-237

License No. DPR-19

MHB Technical Associates

ATIN:

Mr. Richard Hubbard

Vice President

1723 Hamilton Avenue, Suite K

San Jose, CA, 95125

REGION Ill

7H AOOSEVEL T ROAD

GLEN ELLYN, ILLINOIS 50137

SEP 1 5 1992

References: 1)

Letter from MHB Technical Associates to NRC Region III dated

February 18, 1992, Concerning NRC Inspection Report

50-237/91036(DRP)

2)

3)

Dear Mr. Hubbard:

Letter from NRC Region III to MHB Technical Associates dated

March 13, 1992, Providing Interim R~sponse

Letter from MHB Technical Associates to NRC Region III dated

September 3, 1992, .Concerning Final Response to MHB's Letter

of February 18,1992

In Reference 2 we advised you that we would provide our complete response to

your co11111ents once we had completed our review. This letter provides our

response.

Our Inspection Report (50-237/91036),*and its cover letter, should have more

clearly reflected that some of the issues discussed in the report were stHl

being pursued. At the time of your letter, we were continuing inspection *

effort to address the issues in the unresolved item mentioned in the

. inspection report. The issues requiring 110re review were (1) Co11111onwealth

Edison Company's (the licensee's) completion of a 10 CFR Part 21 review, and

subsequent NRC review, (2) NRC review of the licensee's corrective actions

program, and (3) NRC review of the licensee's calculational controls program.

These issues encompassed two of your conments.

Ve also performed a more

intensive review of the other weaknesses identified in the inspection report

to determine if violations of quality assurance requirements existed. The

results of our further review were discussed in Inspection Report

50-237/92009(DRP); 50-249/92009(DRP) (Enclosure 2).

The three issues mentioned above were left as an unresolved item because more

information was.needed in order to determine whether or.not they were

.. violations. Therefore, it would have been premature to issue violations with

Inspection Report 50-237/91036. However, as previously stated, clearer

wordingc should have ,been used~ -in_Jnspection_ Repo.rt 59::-?17 /~lO~~ ~n-~. its cover

letter to--indicate that the NRC was not finished with its review: * - *

9209220253 920915. -- -- .

PDR . ADOCK 05000237

.

G

PDR

  • .

..

MHB Technical Associates

2

SEP.1 5 1992 *

Inspection Report 50-237/92009(DRP); 50-249/92009(DRP) stated that portions of

  • the unresolved item involved apparent violations of NRC requirements. Those

concerns, and others, were discussed with the licensee in an enforcement

conference held June 4, 1992. Following the enforcement conference, NRC

evaluated the safety significance and characterization of the apparent

. violations,* including those referenced in your letter. The results of our

deliberations are contained .in our letter to the licensee transmitting a

Notice of Violation dated September 2, 1992. A copy of that letter is also

enclosed (Enclosure 3).

The remainder of your conments were again reviewed to determine if we had

overlooked any issue.

We found that they all were addressed, as documented in

Enclosure 1 to this letter. Finally we reviewed the issues raised by your

conments as contributors to the low pressure coolant injection (LPCI) system

inoperabil ity. Our final determinat.ion was that, even 1f these issues had not

occurred, the reactor recirculation valve VOTES trace would have been

misinterpreted, resulting in the LPCI 1noperability. The root cause of the

LPCI tnoperability was vendor-supplied training inadequacies on the motor-

operated-valve (MOY) testing system being used, due to the emergent nature of

MOY testing methodology. This resulted in misinterpretation of the reactor

recirc_ulation valve's unusual diagnostic test data. Therefor,, none of the . . .

. issues discussed in your letter were considered to be contributors to the LPCI

inoperability.

If you have additional questions, please do not hesitate to call.

Enclosures:

1. Detailed Discussion

of MHB Technical

Associates Conments

2. Inspection Report

50-237/92009(DRP);

50-249/92009(DRP)

3. Cover Letter Transmitting

a Notice of Violation

See Attach~d D1str1but1on

Sincerely,

µ(hi._

Brent Clayton, Chief

Reactor Projects Branch 1

-*

. .

  • ' *

MHB Technical Associates

cc w/enclosures:

C. Reed, Senior Vice President

D. Galle, Vice President, BWR

Operations

T. Kovach, Nuclear Licensing

Manager

C. Schroeder, Station Manager

R. Radtke, Regulatory Assurance

Supervisor

DCD/DBC (RIDS)

OC/LFDCB

Resident Inspectors, Dresden-

LaSalle, Quad Cities

J. Mccaffrey, Chief, Public

Utilities Division

R. Newmann, Office of Public

tounsel, State of Illinois Center

Licensing Project Man~ger~ NRR

State Liaison Officer

C. J. Paperiello, Rill

SEP 1 5 1992

3

  • '.

.*.

Enclosure 1

Detailed Discussion of 1118 Technical Associates CClllllents

(a)

failure of the licensee to maintain records documentirig statipn *and-

corporate personnel qualification to NOD-MA.I nquirements.

.

(b)

  • As discussed in Inspection Report 237(249)/92009, section lO~A. records

documenting station personnel qualification to NOD-MA.I requirements

. were available, and satisfied the requirements of the C011111onwealth

Edison quality assurance program. Similar records were not available

for corporate personnel, as identified in the licensee's internal audit.

Criterion II *Quality Assurance Program* to 10 CFR Part 50, Appendix B,

requires that the quality assurance program provide for indoctrination

and training of personnel performing activities affecting quality, as

necessary to assure that suitable proficiency ts achieved and

maintained. The failure of the corporate office to maintain records of

motor-operated valve training to assure that suitable proficiency was

achieved and maintained was in violation of Criterion II requirements.

"owever the violation met the requirements specified in Section Y.6.1 of

the 1991 Enforcement Policy, in that it was identified by the licensee,

was of minor safety significance because the personnel were adequately

trained, was isolated, an~ actions were taken to correct the violation *

Therefore, the violation was not cited.

Use of a non-safety-related consulting service to perform safety-related*

work.

As discussed in Inspection Reports 237/91036 and 237(249)/92009; the

contract to procure engineering services of a motor operated valve

industry expert was let as a non-safety-related contract. Criterion IV

in part that measures.be established to assure applicable requirements

necessary to assure adequate quality are suitably included or referenced

in documents for procurement of services. The procurement of

engineering services via a non-safety-related contract fi11ed to assure

that the applicable requirements necessary to assure quality were

included in the procurement document, and was in violation of the

requirements of Criterion IV.

.

  • The inspectors concluded.that the actual procurement of the contract as*

non-safety-related did not affect the quality of the engineering

services in regard to the reactor recirculation valve. This was because

the contractor involved was a recognized industry expert and the *

contract was treated in accordance with the contractor's approved

Quality Assurance Program. Therefore, the violation met the

requirements specified in Section Y.A of the 1991 Enforcement Policy, in

that the violation was of minor safety significance, was isolated, and

the contract was reissued as safety-related prior to the end of the

inspection. Therefore, the violation was not-c1-ted.

  • ' *

Enclosure 1

(c)

Neither the work package nor the testing procedure delineated anv

quantitative or gualttatiye acceptance criteria related to the YOTES

diagnostic. the as-foynd or as-left torque switch settings. pr the yalye

thrust windows.

.

(d)

As part of the review documented in Inspection Report 237(24)/92009, the

inspectors looked into how motor-operated-valve torque switch settings

were set. The inspectors determined that no value for torque switch

settings ts normally provided, rather the torque switches were adjusted

to obtain a desired thrust value. This desired thrust value was

obtained as output from the VOTES traces, which used calculated target

thrust values, obtained from the corporate engineering office. The work

package contained target thrust values to be used, along with a letter

from the corporate engineering office stating that use of thrust values

outside the target values required corporate approval. *Additionally, *

the test package contained qualitative testing criteria that the valve

was to be stroked to the full open and full closed positions *.

Therefore, the inspectors concluded that quantitative acceptance

criteria, in the form of target thrust values, and qualitative

acceptance criteria, in the fonn of valve. stroking, were contained in

the work package, and that Inspection Report 237/91036 overstated the

lack of acceptance criteria. Criterion V *Instructions, Procedures, and

Drawings* to 10 CFR Part 50, Appendix B, requires in part that

instructions,. procedures, or drawings include appropriate quantitative

or qualitative acceptance criteria. This requirement was met in this

case, and no violation occurred.

The MOY coordinator's concerns about select1nq the zero point on the

yalve and use of industry expert seryices were not documented.

As discussed in Inspection Report 237(249)/92009, the test engineer

failed to follow the requirements of a Dresden administrative procedure

which could have been interpreted to require documentation of the valve

anomalies and the use of a consultant in determining the final thrust *

values to be used.

Criterion V *Instructions, Procedures, and Drawings* to 10 CFR Part 50,

Appendix B, requires in part that activities affecting quality be

documented in instructions, procedures, or drawings, and accomplished in

accordance with these instructions, procedures, or drawings. The

administrative procedure required that the engineer document any

discrepancies encountered during the VOTES test. Although the engineer

bad trouble reading the VOTES trace, and enlisted the aid of an outside

consultant, this was not documented as required by the procedure. 'This

was in violation of the requi.rements of Criterion V.

2


-~~- --- _ .......... -- --=----~

Enclosure 1

The failure to document the problems encountered during the VOTES test

occurred in December 1990, a time when Connonwealth Edison recognized

that there was a problem with adherence to administrative procedures,

because of previous NRC violations, and was taking steps to correct

them.

For this reason, and because the actual failure was of *inor

safety significance, this item met the requirements of Section V.G.2 of

the 1991 Enforcement Poltcy, and no violation was cited.

(e) Failure to document reanalysis of YOTES tests by the corporate Nuclear

Engineering Deoartment and failure to coQ1Dunicate to the station that

discrepancies were identified and bow they were resolved.

(f)

As discussed in Inspection Report 237(249)/92009, several deficiencies

were identified in the method that the corporate Nuclear Engineering *

depart~nt handled nonconfonning conditions on the motor operated valve

program. This item, and the following one, were considered for

escalated enforcement and were discussed in an enforcement conference

with the licensee on June 4, 1992.

Following.the enforcement conference, NRC deliberated on the.safety

significance of the items'and.determined that the root cause of the

violations was the lack of a procedure addressing the motor-operated

valve program. Therefore the NRC determined that the requirements of

10 CFR Part 50, Appendix 8, Criterion V, *instructions, Procedures, and

Drawings* were not met, .and a violation was issued accordingly.* This

conclusion was documented in a letter to the ltcensee dated September 2,

1992; which transmitted a Notice of Violation (Enclosure 2).

. ..

NED failed to document torqyi switch adtystment calculations for safetv~

related yalyes.

As stated above, this issue was considered for escalated enforcement and

was discussed with the licensee in the June 4, 1992, enforcement

conference. Following the conference, NRC determined .that the root

cause of the failure to document the adjustment calculations was again a

procedural deficiency. Therefore, this item was included in the

violation.of 10 CFR Part 50, Appendix 8, Criterion Y described above.

Finally, your letter stated that these violations contributed to the

. tnoperability of the low pressure coolant injection (LPCI) system for $even

110nths. Our final determinatton was that, even tf the minor violations had

not occurred, the reactor recirculation valve VOTES trace would have been

misinterpreted, resulting tn the LPCI tnoperability. The root cause of .the

LPCI tnoperability was vendor-supplied training inadequacies on the motor-

operated-valve (MOV) testing system being used, due to the emergent nature of

MOV testing technology. This resulted in misinterpretation of the reactor

recirculation valve's unusual diagnostic test data. Therefore, none of the

issues discussed to your Jetter were considered to be contributors to the. LPCI

tnoperability.

3