Discusses Semiannual Plant Performance Review (PPR) of SSES Completed on 971021.PPR Involved Participation of All Divs in Evaluating Insp Results & Safety Performance Info from April to Sept 1997.Advises of Planned Insp Effort
ML17159A084
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/24/1997
From: Anderson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Byram R
PENNSYLVANIA POWER & LIGHT CO.
References
NUDOCS 9712170086
Download: ML17159A084 (4)


Text

CATEGORY 2 REGULATORY INFORMATION DISTRXBUTION SYSTEM (RIDS)

II ACCESSION NBR:9712170086 DOC.DATE: 97/11/24 NOTARIZED: NO DOCKET ¹ FACIL:50-387 Susquehanna Steam Electric Station, Unit 1, Pennsylva 05000387 50-388 Susquehanna Steam Electric Station, Unit 2, Pennsylva 05000388 AUTH.NAME AUTHOR AFFILIATION ANDERSON,C.J.

Region 1 (Post 820201)

RECIP.NAME RECIPIENT AFFILIATION BYRAM,R.G.

Pennsylvania Power

& Light Co.

SUBJECT:

Discusses semiannual Plant Performance Review (PPR) of SSES completed on 971021.PPR involved participation of all diys in evaluating insp results

&. safety performance info from April to Sept 1997.Advises of planned insp effort.

DISTRIBUTION CODE:

IEOID COPIES RECEIVED: LTR 1

ENCL g SIZE:

3 TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES:

RECIPIENT ID CODE/NAME PD1-2 PD COPIES LTTR ENCL 1

1 RECIPIENT ID CODE/NAME NERSES,V COPIES LTTR ENCL 1

1 05000387G 0

INTERNAL: ACRS ILE NTE NRR/DRPM/PERB OE DIR RGN1 FXLE 01 EXTERNAL: LITCO BRYCE, J H NRC PDR NOTES:

2 2

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

AEOD/SPD/RAB DEDRO NRR/DXSP/PXPB NRR/DRPM/PECB NUDOCS-ABSTRACT OGC/HDS2 NOAC NUDOCS FULLTEXT 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 0 (-

C NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COP1ES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)

ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 21 ENCL 21

November'4, 1997 Mr. Robert G. Byram Senior Vice President - Nuclear Pennsylvania Power 5 Light Company 2 North Ninth Street Allentown, Pennsylvania 18101

SUBJECT:

PLANT PERFORMANCE REVIEW (PPR) - SUSQUEHANNA STEAM ELECTRIC STATION

Dear Mr. Byram:

On October 21, 1997, the NRC staff completed the semiannual Plant Performance Review.

(PPR) of the Susquehanna Steam Electric Station.

The staff conducts these reviews for all operating nuclear power plants to develop anintegrated understanding of safety performance.

The results are used by NRC management to facilitate planning and allocation of inspection resources.

The PPR for Susquehanna involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period April 1997 through September 1997. PPRs provide NRC management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance and Senior Management Meeting reviews.

This letter advises you of our planned inspection effort resulting from the Susquehanna PPR review.

It is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnelavailability to be resolved in advance of inspector arrival onsite. The enclosure details our inspection plan for the next 6 months.

Resident inspections are not listed due to their ongoing and continuous nature.

We willinform you of any changes to the inspection plan. Ifyou have any questions, please contact Clifford J. Anderson at 610-337-5227.

Clifford J. Anderson, Chief Project Branch No. 4 Division of Reactor Projects Docket Nos. 50-387; 50-388

Enclosure:

Inspection Plan

~~r G l 1 c',",) f'33.

97i2i70086 9'7ii24 PDR ADOCK 05000387 8

PDR

~4 IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII

Mr. D. M. Smith cc w/encl:

G. T. Jones, Vice President - Nuclear Operations G. Kuczynski, General Manager J. M. Kenny, Supervisor, Nuclear Licensing G. D. Miller, General Manager - Nuclear Engineering R. R. Wehry, Nuclear Licensing M. M. Urioste, Nuclear Services Manager, General Electric C. D. Lopes, Manager - Nuclear Security A. Male, Manager, Nuclear Assessment Services H. D. Woodeshick, Special Assistant to the President J. C. Tilton, III, Allegheny Electric Cooperative, Inc.

Commonwealth of Pennsylvania Distribution w/encl:

Region I Docket Room (with concurrences)

Nuclear Safety Information Center (NSIC)

H. Miller, RA P. Swetland, DRP A. Linde, DRP NRC Resident Inspector PUBLIC Distribution w/encl: (Via E-Mail)

W. Dean, OEDO C. Poslusny, Project Manager, NRR J. Stolz, PDI-2, NRR Inspection Program Branch, NRR (IPAS)

R. Correia, NRR F. Talbot, NRR DOCDESK DOCUMENT NAME: G:IIBRANCH4iPPRLTR,SUS To receive a copy of this document, Indicate In the bosn C

~ Copy without attachment/enclosure E

Copy with attachment/enclosure N

~ No copy OFFICE I/DRP WANE nder DATE 11/19/

7 11/

/97 11/

/97 11/

/97 11/

/97 OFFI IAL RECORD COPY

SUSQUEHANNA INSPECTION PLAN IP NUMBER IP 83750-CO IP 83750-CO IP 84750-CO IP 62706-CO IP 37550-CO IP 40500

<P 37001 TITLE Occupational Radiation Exposure Occupational Radiation Exposure.- Outage Radioactive Waste Treatment and Effluent and Environmental Monitoring Maintenance RuIe Team Inspection Engineering Team Inspection DATE 12/1/97 03/09/98 4/13/98 5/18/98 09/14/98 IP - NRC Inspection Procedure CO - Core Inspection (NRC Program Requirement)

Rl - Regional Initiative