ML17158B885

From kanterella
Jump to navigation Jump to search
Summary of 961030 Meeting W/Pp&L Re Installation of Onsite Storage Facility for Spent Fuel at Plant,Units 1 & 2.List of Attendees & Licensee Handouts Encl
ML17158B885
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 12/02/1996
From: Poslusny C
NRC (Affiliation Not Assigned)
To:
NRC (Affiliation Not Assigned)
References
NUDOCS 9612040178
Download: ML17158B885 (36)


Text

f,AR REou fl O

I O

~O

+**++

LICENSEE:

FACILITY:

SUBJECT:

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 2, 1996 Pennsylvania Power and Light Company Susquehanna Steam Electric Station (SSES),

Units I and 2

SUMMARY

OF OCTOBER 30, 1996 MEETING TO DISCUSS INSTALLATION OF ON-SITE STORAGE FACILITY FOR SPENT FUEL AT SSES, UNITS I AND 2 On October 30, 1996 a management meeting was held between members of the Office of Nuclear Reactor Regulation (NRR), Office of Nuclear Material Safety and Safeguards (NESS),

and Pennsylvania Power

& Light Company (PP&L or the licensee) to discuss the licensee's plans for design and installation of a new on-site storage facility for spent fuel at the Susquehanna Steam Electric Station located in Berwick, Pennsylvania.

Enclosure I is a list of the meeting attendees.

The first part of the meeting was a presentation by PP&L staff about PP&L's design control process, a discussion of the spent fuel storage

design, public involvement and quality assurance oversite of the design process, plans for implementation, project organization, and the strategy for implementation.

Enclosure 2 is a set of the slides outlining the details of.the discussions.

Other key items discussed were that 13 procedures are in draft form now with the remainder expected to be completed in draft by the end of the year.

The approved procedures would then be "dry runned" and also evaluated at the Davis Besse site when its procedures are being implemented.

PP&L also emphasized that it will maintain its vigilance over the project and considers the work to be as important as a safety-related modification to the plant.

Also, it was stated that the licensee was developing detailed design basis documentation which would be developed for the project.

During the second part of the meeting, the NNSS staff provided a discussion of the status of pending regulatory guidance regarding Part 72 licensing.

Specifically new inspection procedures are being issued, a draft Standard Review Plan (SRP) section is to be issued in January for general license

reviews, a site-specific license SRP is expected to be issued in draft for comments soon and transportation and dual purpose license SRP sections are also under development.

Other industry issues were mentioned for consideration including the quality of concrete aggregate in the storage

modules, the use of thermal heat shield paint in the casks, and American Society of Mechanical Engineers Code and testing requirement development.

040043 9bf2040i78 'Phi202 PDR ADOCX OSOOOS87 Y

PDR

A J

N 4

\\

'articipants istatLed that the exchange of information was valuable for both the licensee and regulator and the staff noted that it felt that PP8IL was doing a

'good job in its oversite and control of the quality of the project.

/s/

Chester

Poslusny, Senior Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation Docket Nos.

50-387/388

Enclosures:

1.

Meeting Attendees List 2.

Licensee's Handouts cc w/encls:

See next page DISTRIBUTION: *w/Enclosures 1 and 2

HARD COPY

  • Docket File
  • PUBLIC
  • WPasciak, RGN-I E-NAIL WRussell/FMiraglia RZimmerman SVarga JZwolinski JStolz
  • CPoslusny MO'Brien EJordan (JKR)

WReckley FSturz ELeeds JMcGinty PEng PRay GMarcus JSpets CHaughney WDean OFFICE PDI-2/PM Y

PD PDI 2D NAME DATE CPoslusny":rb S 96,'.,

MO Y

JSto

/

96 OFFICIAL RECORD

COPY, Dl)CUMENT RANE:

SU10-30.NTS U

Ih

tf

'I t

I ~

I

!I (I

H l'

H t

l

~f I

'(

I I

f II'I I(

f I'"

II r

ill I

Participants stated that the exchange of information was valuable for both the licensee and regulator and the staff noted that it felt that PP&L was doing a

good job in its-oversite and control of the quality of the project.

Chester

Poslusny, Senior Project Hanager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation Docket Nos.

50-387/388

Enclosures:

I.

Meeting Attendees List 2.

Licensee's Handouts cc w/encls:

See next page

f ennsylvania Power

& Light Company Susquehanna Steam Electric Station, Units 1

& 2 CC:

Jay Silberg, Esq.

Shaw, Pittman, Potts

& Trowbridge 2300 N Street N.W.

Washington, D.C.

20037 Bryan A. Snapp, Esq.

Assistant Corporate Counsel Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. J.

M. Kenny Licensing Group Supervisor Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. K. Jenison Senior Resident Inspector U. S. Nuclear Regulatory Commission P.O.

Box 35 Berwick, Pennsylvania 18603-0035 Mr. William P. Dornsife, Director Bureau of Radiation Protection Pennsylvania Department of Environmental Resources P. 0.

Box 8469 Harrisburg, Pennsylvania 17105-8469 Mr. Jesse C. Tilton, III Allegheny Elec. Cooperative, Inc.

212 Locust Street P.O.

Box 1266 Harrisburg, Pennsylvania 17108-1266 Chairman Board of Supervisors 738 East Third Street

Berwick, PA 18603 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 Mr. Harold G. Stanley Superintendent of Plant Susquehanna Steam Electric Station Pennsylvania Power and Light Company Box 467 Berwick, Pennsylvania 18603 Mr. Herbert D. Woodeshick Special Office of the President Pennsylvania Power and Light Company Rural Route 1,

Box 1797 Berwick, Pennsylvania 18603 George T. Jones Manager-Engineering Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. Robert G.

Byram Senior Vice President-Nuclear Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803

HEETING ATTENDEES LIST INSTALLATION OF ON-SITE STORAGE FACILITY FOR SPENT FUEL OCTOBER 30 1996 NAME ORGANIZATION S.

W.

C.

F.

E.

T.

P.

P.

G.

J.

C.

J.

W.

R.

G.

G.

D.

R.

R.

K.

H.

D.

V.

A.

B.

A.

Varga Reckley Poslusny Sturz Leeds McGinty Eng Ray Marcus Spets Haughney Kenny Burchill Saccone Hiller Jones Haron Matthews Sgarro Kelenski Woodeshick Larkin Franceschi Nelson Maiers Panogos NRC/NRR NRC/NRR NRC/NRR NRC/NHSS NRC/NHSS NRC/NMSS NRC/NMSS NRC/NRR NRC/NRR NRC/NMSS NRC/NMSS PP&L PP&L PP&L PP&L PP&L PP&L PP&L PP&L PP&L PP&L WPPSS Vectra NEI PADEP-BRP ComEd ENCLOSURE 1

SPENT FUEL STORAGE SR%OR hhQCAGEMENY G

gag iO

~are S~"

U.S. Nuchar Regulatory Comm@sion Rocleilh, MD OCTOBER 30, 19SS

SPENT FUEL S TORAGE AT SUS UEHANNAS TEAM ELECTRIC STATION SENIOR MANAGEMENTMEETING U.S. NRC October 30, 1996 Rockville, MD

PP&L's Plans for Spent Fuel Storage at Susquehanna Steam Electric Station

+ Introducbon.......................................................

G. T. Jones Vice President - Nuclear Operations

+ Management Perspective................................

G. D. Miller Manager-Nuclear Engineering

+ PProspect Overview...............................................

R. A.Saccone Manager-Nuclear Modifications g ~

riT m n L11 Quahty Assurance Vv'. E. BurciuH Manager-Nuclear Assessment Services

PP &LMANAGEMENTPERSPECTIVE

+ PP &L'sDesign Control Process

+ SSES ISFSI Attributes

~ Pad Design

~ Public Involvement

~ QA Oversight

PP&L MANAGEMENTPERSPECTIVE

+ Specific Standards Applied to this Project Include:

Regulatory Compliance Industry Experience Good Public Involvement Proactive Approach

~ Strong Management Involvement and Commitment of Resources Engineering Accountability Strong Quality Assurance Plan

BACKGROUND

+ Susqueharma Steam Electric Station - 2 UnitSite, each consisting of a General Electric BoilingWater Reactor, BWR/4 with a 1150 MWe nominal rating.

+ Unit 1 original fuel load - July 27, 1982; commercial operation June 8, 1983.

+ Unit 2 original fuel load - March 28, 1984; commercial operation February 12, 1985.

+ Common Refuel Floor and Maintain a Single Failure Proof Crane

BACKGROUND(coNTINUED)

+ Each Unit has its own spent fuel storage pool

+ Project Objective/Schedule is predicated on maintaining Dual Core Offload Capabilities

+ Project Plan calls for the firstfuel moves to the Independent Facility to begin in September 1997

J

SPENT FUEL STORAGE PROJECT PROJECT ORGANIZATION SR V.P. Nudear R. G. Byram V. P. Nudear G.T. Jones Manager Nudear Engineering G. D. Miller Manager Nudear Modifications R. Saccone High Level Waste Team Public I Internal Communication Q

Q \\ \\

% \\ '0 Q

Q Q

Project Manager K. Kelenski Vectra Technologies Design rocure ment Licensing System Eng Training QAI QC Nudear Fuel ENuent HP Operation Rx Eng Security

PRO ECT EVALUATIONS

+ Siting Report September, 1992

+ Phase I Technical Assessment - February, 1993"

+ Performance Specification Developed for Reracking and Dry Cask Storage June, 1993"

+ Final Technical Assessment Completed October, 1994"

+ Awarded Contract January.1995"

CO UNICATIONS

+ A Public Involvement Program was initiated to ensure Public awareness and to solicit input into decision making process

+ Various methods of presenting PP8zL's plans were implemented:

Presentations to the Susquehanna Citizens Committee Personal Notification of Area Officials Media Day Presentations to Volunteer Orgamuzations which support the Susqueharma Emergency Response Organization Articles in the Susqueharma Newsletter which is distributed to the surrounding communities

RY STORAGE TECHNOLOGY ATSSES

+ VECTRA"NUHOMS" Horizontal Storage Technology

+ Implementing under General License

+ Certificate of Compliance Certificate Number 72-1004

NUHOMS KEYSYSTEM COMPONENTS

+ Dry Shielded Canister DSC's

+ Horizontal Storage Modules HSM's

+ Transfer Cask

r

~

SHIELD PLUG OUTER COVER.

PLA'lE IIRKR CotER PLATE ORAIH AHO FILL PORT C

CAIRSTER SHE LL C

C O4 OUTER COVER tLATE tOISOII tlATE RASIIET ASSE~y (u PLCS)

SIPHON TWE 0

Figure 2.2-2 O

C

~,c 4

,, I gUHpMst tv spynt Fwl Manig Syaten tlannino Guhfe VECTRA MKT94-01J ROOF MOUNTED HEAT SHIELD ROOF SIAQ AIR OUTLET VENT REMOVABLE

'UFTING EYEBOLT SHIELDEO ACCESS DOOR REMOVABLE CASK RESTRAINT EYEBOLT AIR INLET VENT BASE UNIT SIDE WAlL MOUNTED HEAT'HIELD CANISTER SUPPORT STRUCTURE

'Figure 2.3-1 2-52

HOMS~ Dry $

RNI Mt S stem Ptannino Qigdy VKCTAAMKT941 TOP COVER ASSCVSLY UffER UfTIHO TRUHHIOH LCAO OAVVA SHIELD IHHER LIHER

. STRUCTURAL 5HCLL RA@

ACCESS fEHCTRATIOH HCUTROH

~ 5HIELO LOWER 5UffORT TRUHHIOH RAV ACCC55 fCHCTRATIOH SOTTOV COVER ASSSCVSLY

~OTTOil CHO A55CllSLY CASX CAVITY ORAIH fORT 2-63

00000

S TRATEGYFOR IMPLEMENTATION

+ Design PP8zL's Project Management and Design Control Process Other utilities experience factored into SSES design

+ Construction SSES ISFSI is being constructed inside the protected area and is encompassed by the existing Security and Emergency Plans Spent Fuel Storage Pad Fencing Lighting

. ~

Temperature Monitoring

S TRATEGYFOR IMPLEMENTATION (CONTINUED)

+ Fabr'ication of Components

~ Horizontal Storage Modules -Bayshore, Cape Charles VA.

~ Dry Shielded Canisters - Ranor, Westminster MA.

~ Transfer Cask-Leased from VECTRA Technologies (Fabricated by Ranor)

STRATEGY FOR IMPLEMENTATION (CONTINUED)

+ Operation - tasks to support operation have been defined and willfactor in Industry Experiences

~ Procedures Development

~ TMlnlng

.. Movement of Spent Fuel

S TRATEGY FOR IMPLEMENTATION (CONTINUED)

+ Extensive Preplanning

+ Certified Horizontal Design

+ Public Involved in Decision

+ PP&L 's Design Control Program

UALITYASSURANCE

+ PP&L has put together a comprehensive Quality Assurance Plan for this Project

~ Special Integrated Quality Assurance Plan

~ PPkL Initiatives

UALITYASS URANCE (CONTINUED)

+Integrated uali Assurance Plan

~ Design Review/Technical Evaluations

'rocurement/Fabrication Oversight

~ On Site Construction Oversight

~ Operations/Maintenance Oversight

QUALITYASS URANCE (CONTINUED)

PP&L Vendor Oversight Activitiy PPSL Structural Reinforcement Pad Reinforcement Sulvey 96478 Source VefNcatfons:

96425, 96-United Inspect.

Servtces Independent Conc. Testing Survey 96454 Source VerNcations:

96435 (7 day) 96439 (28 day)

Surveiiiances: 96464, 96-Vectra Central Builders Audit 96401 Pad Concrete NUHOMS Joint (Independent Testing)

Audit-PP&L Lead Ranor Hi-Tech Bayshore Allied QSGs DSCs/Leased MisceNanso us Equipment Steel (HSM)

Audit96483 Source NUHOMS Joint VerNcations:

PP&L Lead 96443, 96-Leased HSM Survey'6-138 Source Verifications:

96-Readiness Review (10/28/96)

Nuts/Boils (HSM)

Independent PC-ASQL Vendor Rebar Tesbng (HSM)

PL-ASQL Vendor Readiness Review (1/97)

Source VerNcations:

97-Source Verifications:

Cask 95412 95413 95425

- 95427 95436 95443 95448 Hook/Yoke 95442 95444 95447 Hall-Hodges Rebar Cut/Bend (HSM)

Source VerNcations: 96442, 96-Birmingham Steel Rebar Mfg (HSM)

Source Verification 96438

ee'v C'

UALITYASS URANCE (CONTINUED)

+ PP8zL Initiatives

~ VECTRA Project Instruction FS-PPL-96-01

~ NUHOMS Owners'roup QA Subcorrumittee

~ NUHOMS Owners'roup AuditTeam Leader VECTRA, San Jose, CA Ranor, Westminster, MA

~ Leased Equipment Control

~ Reactor Water Chemistry

~ Load Test Calibration

+

PP&L OWNS and is ACCOUNTABLEfor a11 activities associated with the Design, Construction, and Operation of the ISFSI at SSES.

Ownership and Accountability demonstrated through:

~

Strong Management Commitment.

Integrated Project Team.

Comprehensive Quality Assurance Compliance to applicable Regulatory requirements Continued Lessons Learned, both Others &PP&L

+

The SSES ISFSI is being Designed, Constructed, and Operated to PP&L's Standards and the NRC's Expectations.

0 l

~

1

~ sq

~,

rI +Ac

/*

~ 3'