Forwards Insp Repts 50-387/95-25 & 50-388/95-25 on 951219-960205.No Violations Noted
ML17158B128
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 03/04/1996
From: Pasciak W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Byram R
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17158B129 List:
References
NUDOCS 9603130286
Download: ML17158B128 (3)


See also: IR 05000387/1995025

Text

March 4,

1996

Mr. Robert

G.

Byram

Senior Vice President

Nuclear

Pennsylvania

Power

& Light Company

2 North Ninth Street

Allentown, Pennsylvania

18101

SUBJECT:

NRC COMBINED INSPECTION

REPORT

NOS. 50-387/95-25;

50-388/95-25

Dear Mr. Byram:

The enclosed

report documents

a resident

inspection

conducted

by Ms.

M.

Banerjee,

Mr. B. J.

McDermott,

and others

from December

19,

1995 through

February

5,

1996, at the Susquehanna

Steam Electric Station

(SSES),

Salem

Township, Pennsylvania.

Areas relevant to the health

and safety of the public

examined during the inspection

are described

in the enclosed report.

At the

conclusion of the inspection,

the inspectors

summarized their preliminary

findings with Mr. G. J.

Kuczynski

and other members of your staff.

We consider the recent operations

management's

effort to reduce the number of

lit annunciators

in the control

room,

and the monthly status

review meeting to

ensure

appropriate prioritization of corrective actions to reduce the operator

work around

items are considered

as very positive initiatives.

It appears

to us that you are taking aggressive

actions to resolve the

recently identified health physics

issues

related to inadequate

surveys,

postings,

and contaminated

items found outside the radiologically controlled

areas.

These

issues

are of concern to us,

and

we will continue to follow your

progress

in these

areas.

Ih accordance

with 10 CFR 2.'790 of the

NRC's "Rules of Practice,"

a copy of

this letter and its enc'losures will be placed in the

NRC Public Document

Room..

Your cooper ation with us in this matter is appreciated.

Sincerely,

ORIGINAL SIGNED BY:

Walter J.

Pasciak,

Chief

Reactor Projects

Branch

4

Division of Reactor Projects

Docket Nos. 50-387;50-388

Enclosures:

1.

Combined

NRC Inspection

Report 50-387/95-25;

50-388/95-25

2. Attachment

1:

PP8L's

Enforcement

Conference

Handout

>20O63

9b03i3028b

9b0304

PDR

ADOCK 05000387

8

PDR

Mr. Robert

G.

Byram

cc

w encl:

/

H.

G. Stanley,

Vice President

Nuclear Operations

J.

M. Kenny, Nuclear Licensing

G. T. Jones,

Vice President - Nuclear Engineering

G. Kuczynski, Plant Manager

R.

R. Wehry, Nuclear Licensing

M. M. Urioste, Nuclear Services

Manager,

General

Electric

C.

D. Lopes,

Manager

Nuclear Security

W. Burchill, Manager,

Assessment

Services

H.

D. Woodeshick,

Special Office of the President

J.

C. Tilton, III, Allegheny Electric Cooperative,

Inc.

Nuclear Safety Information Center

(NSIC)

.

Commonwealth of Pennsylvania

Hr. Robert

G.

Byram

Distribution w/encl:

Region I Docket

Room (with concurrences)

K. Gallagher,

DRP

D. Screnci

NRC Resident

Inspector

PUBLIC

Distribution w/encl: (Via E-Hail)

W. Dean,

OEDO

C. Poslusny,

Project Manager,

NRR

J. Stolz,

PDI-2,

NRR

Inspection

Program Branch,

NRR (IPAS)

DOCUMENT NAME: A:9525.SUS

To receive a copy of this docume,

dicate

the box:

C" ~ Copy without attachment/enclosure

E'

Copy with

attachment/enclosure

M'

o co y

OFFICE

NAME

DATE

RI:0

WPas

a

3/,

6

RI:DRS-EP

JLaughlin

Section

5.

3/

/96

0 FICIAL RECORD

COPY