Forwards Insp Repts 50-387/93-09 & 50-388/93-09 on 930511- 0628.One non-cited Violation Identified
ML17157C413
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 07/23/1993
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Byram R
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17157C414 List:
References
NUDOCS 9308020001
Download: ML17157C413 (5)


See also: IR 05000387/1993009

Text

JUL 23 893

Docket Nos.

50-387

50-388

Mr. Robert G. Byram

Senior Vice President - Nuclear

Pennsylvania Power & Light Company

2 North Ninth Street

Allentown, Pennsylvania

18101

Dear Mr. Byram:

SUBJECT:

NRC REGION I COMBINED INSPECTION 50-387/93-09; 50-388/93-09

The enclosed report documents a resident safety inspection conducted by Messrs.

G. S.

Barber and D. J. Mannai, and others from May 11, 1993 through June 28, 1993, at the

Susquehanna

Steam Electric Station (SSES), Salem Township, Pennsylvania.

The inspection

covered plant operations,

surveillance, and maintenance for both units. At the conclusion of

the inspection, Mr. G. S. Barber, Senior Resident Inspector, summarized the inspection

findings with Mr. H. G. Stanley and other members of your staff.

Areas examined during the inspection are important to public health and safety and are

identified in the report.

Within these areas,

the inspection consisted of selective

examinations of procedures

and representative

records, interviews with personnel,

and

observation of activities in progress.

The purpose of the inspection was to determine

whether NRC licensed activities were being conducted safety and in accordance with

regulatory requirements.

Although you failed to provide adequate inspection of fire doors at

both units, your staff's identification and corrective actions in this regard were considered

a

strength.

Consequently,

we have exercised discretion in accordance with 10 CFR 2,

Appendix C,Section VII.Band have not cited this as a violation.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and

its enclosures willbe placed in the NRC Public Document Room.

Your cooperation with us in this matter is appreciated.

Sincerely,

ORIGINALSIGNED BY+

Edward C. Wenzinger, Chief,

Reactor Projects Branch 2

Enclosure:

1.

Combined NRC Inspection Report 50-387/93-09; 50-388/93-09

93p8p2pppi

5ppp387

gy3p7Q3

PDR

ADOCK p

6

cc w/encl:

H. G. Stanley, Vice President - Nuclear Operations

J. M. Kenny, Nuclear Licensing

M. M. Urioste, Nuclear Services Manager

D. F. McGann, Supervisor, Nuclear Compliance

H. D. Woodeshick, Special Office of the President

J. C. Tilton, III, Allegheny Electric Cooperative, Inc.

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

K. Abraham, PAO (2) Inspection Reports (20) SALP

NRC Resident Inspector

Commonwealth of Pennsylvania

bcc w/encl:

Region I Docket Room (with concurrences)

JUL 23 Igcg

bcc w/encl via E-Mail:

D. Wheeler, OEDO

R, Clark, NRR, Project Manager

M. Boyle, Acting PDI-2, NRR

RI:DRP

07/08/9

RI:DRP

07/+93

enzinger

07 '/93

OFFICIALRECORD COPY