Notification of 920409 Meeting W/Util in Rockville,Md to Discuss Individual Plant Evaluation Methodology & Approach in Effort to Facilitate NRC Review Process of Util 911213 Submittal
ML17157B121
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 03/26/1992
From: Raleigh J
Office of Nuclear Reactor Regulation
To: Chris Miller
Office of Nuclear Reactor Regulation
References
NUDOCS 9203310175
Download: ML17157B121 (4)


Text

March 26, 1992 Docket Nos.

50-387 and 50-388 MEMORANDUM FOR:

,FROM:

SUBJECT:

DATE 5 TIME:

LOCATION:

Charles L. Miller, Director Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation James J. Raleigh, Project Manager Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

, INDIVIDUALPLANT EVALUATION (IPE)

REVIEW, SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1

AND 2

,April 9, 1992 9:30 a.m.

One White Flint North Room 6B-13 Rockville, Maryland i

F PURPOSE:

Pennsylvania Power and Light Company (PPKL) is presenting their IPE methodology and approach in an effort to facilitate the NRC staff review process of PPEL's December 13, 1991 IPE submittal.

PARTIC IPANTS*:

NRC W. Hilstead C. Ader J.

Flack E. Lois A. Ramey-Smith cc:

See next page PECo J.

Kenny R. Sgarro et.

al D. Wheeler R. Hernan E. Rodrick C. Ryder J.

Raleigh

/S/

James J. Raleigh, Project Manager Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

  • Heetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Re ister 28058, 6 28 78.

OFFICE I / J ien PDI-2 P

JRalei h:rb PD D

DATE 92 d

92 5 74'/92 OFFICIAL RECORD COPY DOCUMENT NAME:

SU.HTG 9203310175.920326:

PDR ADOCK 05000387 P

'DR, I

NiiL 4M lsaidiwh U~eri'0

~

)

~

~

4

~g flEcg c,"

0 Cy 0O IVl

/y gO

+**++

Docket Nos.

50-387 and 50-388 UNITEDSTATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 March 26, 1992 MEMORANDUM FOR:

Charles L. Miller, Director Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation FROM:

SUBJECT:

DATE & TIME:

LOCATION:

PURPOSE:

James J. Raleigh, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation INDIVIDUALPLANT EVALUATION-(IPE)

REVIEW, SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1

AND 2 April 9, 1992 9:30 a.m.

One White Flint North Room 6B-13 Rockville, Maryland Pennsylvania Power and Light Company (PP&L) is presenting their IPE methodology and approach in an effort to facilitate the NRC staff review process of PP&L's December 13, 1991 IPE submittal.

PARTICIPANTS*:

NRC W. Milstead C. Ader J.

Flack E. Lois A. Ramey-Smith D. Wheeler R. Hernan E. Rodrick C. Ryder J. Raleigh PECo J.

Kenny R. Sgarro et.

al cc:

See next page ames J. Raleigh, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Re ister 28058, 6/28/78.

Pennsylvania Power L Light Company Susquehanna Steam Electric Station, Units 1

5. 2 CC:

Jay Silberg, Esq.

Shaw, Pittman, Potts E Trowbridge 2300 N Street N.W.

Washington, D.C.

20037 Bryan A. Snapp, Esq.

Assistant Corporate Counsel Pennsylvania Power L Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. J.

M. Kenny Licensing Group Supervisor Pennsylvania Power 8 Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. Scott Barber Senior Resident Inspector U. S. Nuclear Regulatory Commission P.O.

Box 35 Berwick, Pennsylvania 18603-0035 Mr. Thomas M. Gerusky, Director Bureau of Radiation Protection Resources Commonwealth of Pennsylvania P. 0.

Box 2063 Harrisburg, Pennsylvania 17120 Mr. Jesse C. Tilton, III Allegheny Elec. Cooperative, Inc.

212 Locust Street P.O.

Box 1266 Harrisburg, Pennsylvania 17108-1266 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 Mr. Harold G. Stanley Superintendent of Plant Susquehanna Steam Electric Station Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. Herbert D. Woodeshick Special Office of the President Pennsylvania Power and Light Company 1009 Fowles Avenue Berwick, Pennsylvania 18603 Mr. Robert G.

Byram Vice President-Nuclear Operations Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Mr. Harold W. Keiser Senior Vice President-Nuclear Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsylvania 19101

ISTRIBllTION - Routine Heetin Notice Docket -Fil NRC ocal PDRs PDI-2 Reading T. Hurley, 12G-18 F. Hiragl i a, 12G-18 J. Partlow, 12G-18 S.

Varga J.

Calvo C. Hiller J. Raleigh H. O'rien(2)

A. Chaffee, EAB OGC E. Jordan, 3701 B. Grimes, 9A-2 Receptionist (OWFN)

W. Milstead, NLS007 C. Ader, NLS324 J.

Flack, 6H3 E. Lois, NLN372 A. Ramey-Smith, NLS372 D. Wheeler, 12D-22 R. Hernan, 14C-7 E. Rodrick, NLS324 C. Ryder, NLS372 ACRS (10)

OPA E. Tana, PHAS P. O'Dell, PHAS L. Plisco, 10A-19 R. Lobel, EDO 17G-21 R. Blough, RGN-I J. White, RGN-I K. Abraham, RGN-I cc:

Licensee

& Service List