ML17157B008

From kanterella
Jump to navigation Jump to search
Rev 7 to ISI-T-100.0, Sses,Unit 1,ISI Program Plan for Pump & Valve Operational Testing, Per Generic Ltr 89-04
ML17157B008
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 12/31/1991
From:
PENNSYLVANIA POWER & LIGHT CO.
To:
Shared Package
ML17157B009 List:
References
GL-89-04, GL-89-4, ISI-T-100.0, NUDOCS 9201140168
Download: ML17157B008 (295)


Text

'l t

ISI-T-100.0 SUSQUEHANNA STEAM ELECTRIC STATION UNIT 1 1

PUMP AND VALVEINSERVICE INSPECTION TESTING PROGR4M The pump and valve ISI testing program at the Susquehanna SES Unit 1 will be conducted in accordance with the 1980 Edition of Section XI of the ASME Boiler and Pressure Vessel Code incorporating through the Winter 1980 Addenda. Specific exceptions from these requirements are included here as Relief Requests. The inservice portion of the program commences at the receipt of the Operating License. Requirements for specific components commence concurrent with Technical Specification operability requirements.

For valves so equipped, remote position indicators will be utilized to demonstrate valve operability. Proper functioning of these position indicators will be demonstrated at least once every 24 months. Pressure relief valve testing will be conducted using test procedures which incorporate the testing methods of Section 4.09 of ANSI/ASMEPTC 25.3-1976. The provisions of Paragraph IWV-3511 shall begin at the receipt of the operating license. Thermal relief devices are excluded from the program. With the exception of valves providing a high pressure to low pressure boundary (pressure isolation function), valve leakage rate testing and acceptance criteria will be based on 10CFR50 Appendix J requirements as discussed in FSAR Subsection 6.2.6 and Susquehanna SES Technical Specification 3/4.6.1.2. Pressure isolation function testing is discussed below.

Excess flow check valves are installed on instrument lines penetrating containment in accordance with Regulatory Guide 1.11. As such, the lines are sized and/or orificed such that off-site doses will be substantially below 10CFR100 limits in the event of a rupture. Therefore, individual leak rate testing of these valves is not required for conformance with 10CFR50, Appendix J requirements. Functional testing of valves to verify closure can be accomplished by the process of venting the instrument side of the valve while the process side is under pressure. Such testing is required by Technical Specification 4.6.3.4 at least once per 18 months. Testing on a more frequent basis is not feasible for several reasons. Instruments serviced by these valves frequently have interlock or actuation functions that would be interfered with should testing be performed during plant operation. Also, process liquid will be contaminated to some degree, requiring special measures to collect flow from the vented instrument side. Functional testing with verification that flow is checked will be performed at least once per 18 months per Technical Specification 4.6.3 via SI-199-206, 207, 208, 209, 210, and 211. A listing of excess flow check valves can be found in Technical Specification Table 3.6.3-1.

Check valves whose safety function is to open will be full-stroke tested. Since disc position is not always observable, verification of the safety analysis design flowrate through the valve is considered an adequate demonstration of the full-stroke requirement. This convention is in agreement with NRC Generic Letter 89-04, Position 1.

Rev. 7 1D-1 12/91

ISI-T-100.0 Limit stroke times for power operated valves are provided and controlled in a general plant procedure in accordance with the NRC guidance provided by "Minutes of the Public Meetings on Generic Letter 89-04" (NRC Response to Question 38).

Where devices monitoring appropriate parameters exist permanently installed instrumentation will be used during pump performance testing. Both permanent plant instrumentation and measuring and test equipment will be maintained by the Instrumentation and Controls Section in accordance with their administrative procedures.

Rev. 7 1D-2 12/91

'L 0

ISI-T-100.0 E END F R VAL TABL Valve Number: Unique system designated valve identification HV - hand switch-operated valve SV - solenoid-operated valve PSV - pressure safety/relief valve XV- excess flow check valve FV - flow control valve PSE - rupture disks ASME Class'SME Code Classes 1, 2, and 3 S - non-code valve which performs a safety-related function P&ID Coordinates: Location of valve on P&ID drawing Section XI Valve Category: A - valves with specified maximum leakage rate B- valves with no specified maximum leakage rate C - self-actuating (check, relief valves)

D- actuated by energy source capable of only one operation (rupture disks, explosive valves)

Active: Valves required to change position to accomplish specified safety function Passive: Valves not required to change position to accomplish specified safety function Size: Nominal valve size in inches Valve Type: C- Check valve B- Butterfly valve G- Gate valve GL- Globe valve RV- Pressure relief valve XFC- Excess Flow Check valve RD- Rupture Disk BA- Ball valve X- Shear (explosive valve)

SC- Stop Check valve Rev. 7 1LV-1 12/91

D D

I D 1 )t I

D D 11

ISI-T-100.0 Actuator Type: M - Motor A- Air S - Solenoid H - Hand (manual)

- None (self-actuated)

E/H - Electro-hydraulic Remote Position Indicator: X - valve is equipped with an RPI (RPI) - - valve is not equipped with an RPI Normal Position: C- closed 0- open Test Requirements: Q - quarterly exercise test MT - stroke time measurement concurrent with quarterly exercise test

,LT -,,, leakage rate test once per 24 months CV -'uarterly check valveexercise, test',

SRV - safety/relief valve liftsetpoint test in accordance, with ASME PTC 25.3-1976, Section 4.09 (testing schedule per Table IWV-3S10-1)

DT - category D test requirement Relief Request: Yes/No and number(s) of applicable relief request(s)

Testing Alternative: CS - Testing shall commence no later than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after the plant enters Cold Shutdown (Operational Condition 4) from Power Operation. Valves in this category are subject to testing if they have not been tested in the previous 92 days. Testing shall continue until all subject valves are tested or the plant begins startup. Testing at subsequent cold shutdowns willcommence with those valves having the longest interval (if greater than 92 days) since previous tests. This definition applies to all relief requests with cold shutdown alternative testing.

RR - every 18 or 24 months as specified in relief request See relief request - specific guidance in individual relief request Remarks: Notes on any special methods of testing. If identified as a pressure isolation valve, additional leak rate testing will be performed (water as test medium) at 1000 J10 psig with an acceptance criterion of 1 gpm. Valve testing configurations will be similar to that utilized for containment local leak rate testing.

Rev. 7 1LV-2 12/91

'll 4 ill p

T.

J,

.1 '( 01

ISI-T-100.0 F. END F R PUMP TABLE Pump Number: Unique designated pump identification number Pump Name: Commonly recognized pump name ASME Class: ASME Code Classes 1, 2, and 3 S - non-code pump which performs a safety-related function

'equired Parameters Measured:

Subsection IWP test measurements in accordance with Section XI, X - Parameter will be required to be measured t

Specific code exemptions listed

~I C

tc I Jk Test Frequency: 'Schedule'd test implementation frequency Relief Request Number: Reference to individual relief requests from code requirements Remarks: Notes on methods of testing.

Rev. 7 1LP-1 12/91

ISI-T-100.0 Rev. 7 12/91

J 1/

0

SERVICE WATER M-109 Sheet 2

.,';':;:i<,",'N'umbct':.;::.;':::;"; (((:'AItc'in'attv5.:"".": :,"':,,:';:;-:.",:,:'.::i.Rciiia'iki9 '.':"'>gj

?::j'

';:'::A':.:.::'::i'.':,"::,::B;::::-",.:::::,'-:,:Cg~',:,"'!':,'-.':9:'.'

HV-10943 A2 3 C-8 B A X 0 Q,MT No HV-10943 B2 3 C-8 X 4 B A X 0 Q,MT No

, tt I It I

SERVICE WATER M-110

.Rchef;:":'-.

".;":;j'":':>",Valve.'".'..:;',.:;i",";;

,":Rcjiics't":,'-:Rej'd.".'-.":;;:;:

';,"Number':::,::.~i:

':::-"A':-'::"'::.:;B"'i'..':;,:C':;:::;:;'.;';.-,'D;;;.

HV-11024A1 3 B-5 X X 10 B X Q,MT No HV-11024A2 3 A4 X X 10 B, A X Q,MT No HV-11024B1 3 C-5 X X 10 B A X Q,MT No HV-11024B2 . 3 C-5 X X 10 B .A X Q,MT No M

C)

CO o

I EMERGENCY SERVICE WATER M-111 Silcct 1

'.';;::.<i:0~ .v.;::.',,",':

%7 .N.Y

%. '.@yy,,

,::,Relief."":".'.

.:Request:.

r, Rcq (l~i<g

.". A',;,'-'.:4B';":;:;,"::,;:i',i,'C;::",'j~ij~D.l '. 'v>ÃN .4< " gy>g+g@s".: :,:4" cg": ~

0-11~1 3 G-3 X 18 C CV Yes 51 Sce Relief Request.

0-11-002 3 G-3 X X 18 C CV Ycs 51 Sce Rclicf Request.

0-11-003 3 GW X X 18 C CV Ycs 51 Sce Relief Request.

0-11-004 3 G-7 X X 18 C CV Ycs 51 Sce Relief Request.

0-11%33 3 C-1 X X 8 C CV 27 Sce Rclicf 64 Request.

0-11%34 3 C-1 X X 8 C CV 27 Sce Rclicf 64 Request.

0-11%35 3 C4 X X 8 C CV 27 See Relief 64 Request.

0-11M 6 3 CC X X 8 C CV 27 Sec Relief 64 Rcqu est.

I Q n

t l

fg

EMERGENCY SERVICE WATER M-111 Shcct 1 (Continued) p"'"'-"-'::.:'-'-"

',R'elIef,.'
::.;','.:::

jRequest::  ;;:i~j)Testtng g;:;:g':

':":.":",Num&'eij'!";. "'Rc'q'd.',i', Alteii'iaItve',:,.

5~+a+A~A'~~)~x(~

0-11M 7 X X CV 27 Scc Rclicf 64 Request.

0-11438 X X CV 27 See Relief 64 Request.

0-11M 9 X X CV 27 Scc Rclicf 64 Rcqu est.

0-11440 3 C-9 X CV 27 Sce Rclicf 64 Request.

TV-01124A 3 C-2 X GL E/H 0 No TV%1124B 3 C-7 X GL E/H 0 No TV%1 124C 3 C-5 X X GL E/H 0 No TV%1124D 3 C-9 X X GL E/H 0 No

EMERGENCY SERVICE WATER M-111 Sjlcct 2

.iN.;;:,<N

.'.s<:."?:.";";;<'",.';(,":;,",

.K'
";,

wg "%': . "':.:.? '::.

,:<<. <<<...,Y.,

xO>>

'nl '"";.

g t Relief,::::.:,-:i

'i':.",::-;;,Valv'c',::";,':, <tg,'," s 'equest:." i:;i<:,'cstlIlg,'".'<;;.
.: <<< pj i;;.2Nuinbcr,.'.,: .'";
Rcq,'d,,;: SAItetnative:t<< "- i'<"':RelIlalkt"-"
.~a<.>. m
< A g .;
yg4

%:: 'a<:

kc':.

HV-11143A 3 A-2 X X B A X C Q,MT No HV-11143B 'k 3 X B A X C Q,MT No 1-11-144 3 A-8 X X C CV 40 Sce Rclicf Open Test 64 Request. Only.

1-11-145 3 A-1 X X C CV 40 See Relief Open Test 64 Request. Only.

IC

'l

EMERGENCY SERVICE WATER M-111 Sheet 3

" Relic f,
;:i::.;:i;

~:Rcqumt'.erI'd""

".,'"."'Alter'n'atrv~i$

eCMRe 0-11-513 X X 10 CV 27 Sce Relief 64 Request.

0-11-514 X '10 CV 27 Sce Relief 64 Request.

HVW1110E 3 B-3 X X B M Q,MT No Closure Test 10'0 Only HV-01112E 3 B-4 X B X Q,MT No Closure Test Only HV-01120E 3 B-7 X B M X Q,MT No Closure Test 10'0 Only HV%1122E 3 B4 X B 'M X Q,MT No Closure Test Only TVW1124E F-8 X GL E/H 0 No

RHR SERVICE WATER M-112 Sheet 1

,"",;
A":;::>"",:';::B':."::""::,i:::,C-;::;,.i::,i;,:D.i 1-12401 3 C-2 X X 20 C C CV No 1-12-003 3 G-2 X 20 C C CV No HV-11210A 3 C-5 X X 20 B C QMT No HV-11210B 3 G-5 X 20 B C Q,MT No PS V-11212A 3 C-7 X X 4 RV C SRV No PS V-11212B 3 G-7 X X 4 RV .C SRV No HV-11215A 3 C-8 X 20 B M X C Q,MT No HV-11215B 3 G-8 X 20 B X C Q,MT No HV-112F073A 3 A-3 X X 6 G M X C Q,MT No HV-112F073B 3 C-5 6 G C Q,MT No HV-112F074A S A-5 X I GL 0 Q,MT Yes 38 HV-112F074B S G-5 X X 1 GL 0 Q,MT Yes 38 HV-112F075A 2 A-5 X X 6 G M X C Q,MT No

EMERGENCY SERVICE WATER M-112 Sheet 1 (Continued)

>Cg,

~Ski.".,.;

.,'c".,'.g~c:.

A'A'C.:  ;.?gi

.V,,i:

.yP~

.Rc1ief:;:"."'::.'.

",:,"!~?.'i,':.:"sValve::'::::,:;.g,':"::-'.".

tn '."; ,:';6"::,p'.

';:.;-:'.Te'stin j"""-.';--::;:

Yg;.,

"<<w<'y%Numb'cl": 'i)$ < sAltefnattve s ;;:;:,:Rem'aikido vs>>

HV-112F075B 2 E-5 X X M X Q,MT No 112F078A 2 A-5 X CV No Open test only 112F078B 2 E-5 X X CV No Open test only

RHR SERVICE WATER M-112 Sheet 2

@?'.:'.p'.:  :;:,%'%C '?

YC?;.

':,'"YC."CC C

'C '

'C, 'C',

, CY% ..C YY,'C%'V)

?I

~, '4  ?.::::

.Y,'?,

-'
:Rclicf';:"::,-";::;:: :.:..'::Yy?

N;

$ C)'Y.c. .'.?: .;. NC YC. Y.," Y.":";.C?,".C?~~;;.;?

.C, ."..:C'YPTjgtgjg'a~;.',,",

Xg@

,C& 'C Ol Y Rcq',dg":':

""  ::  ::.",:, Aite'iiiatiiie"..:i '.:j'iRcmi'res'.,':.".';

,:;:;; .".? 'v'.",'" "::. Y

'4

..:; .:,CC.;?:

I.",'A"!,.'4:':;B.':.': .g Yc,'~',". D';. ";"':Y?C HVW1201 A1 3 B4 X Plug M X Q,MT No HV41201A2 3 D-3 X Plug M X Q,MT No HV-01201B1 3 D-7 X 3 Plug M X Q,MT No HV<1201B2 3 D-8 X X Plug M X Q,MT No HV%1222A 3 B-5 X X 36 B M X Q,MT No HVW1222B 3 A-9 X X 36 M X Q,MT No HV41224AI 3 B-5 X 30' B -

M X Q,MT No HV<1224A2 3 B-3 X X 24 B M X Q,MT No HV<1224B1 3 A-7 X X 30 M X Q,MT No HV1224B2 3 A-9 X X 24 B M X Q,MT No

Jr II V K

l

'I 1'

REACTOR BUILDING CLOSED COOLING WATER M-113

'R pND

'V:::.'a:m

.
";;
:::'~;.Valve;:pi',~:

':.;:.::.".-.;,:,N'i'iinbc'r"-:.'::.:':,

.,Xy (4 ..'. '
.;:,;w.,g
A".;,ki:";B..;-:j~<.',C"j:,'::::::!.":D.':;

K HV-11313 C-1 X X M X HV-11314 . '2'-3 X X 4 G M X HV-11345 X X 4 G M X HV-11346 C -X 4 G M X

DIESEL OIL STORAGE AND TRANSFER M-120 Sheet 1

'.gi

'lief);,;,.Req',d',-,':~

":,":::;"';"A'Iteiative-',;'.':.

X X 2 C C CV Ycs 47 See Relief Request D4 X 2 C C CV Ycs 47 See Rclicf Request 0-20412 X 2 C C CV Ycs 47 Scc Rclicf Request 0-20415 X X 2 C C CV Ycs 47 Sce Rclicf Rcqucst

I, II II II

DIESEL OIL STORAGE AND TRANSFER M-120 Sheet 2

Rcllcfi'~;.

~~";;,, "jigjjlye.':."";':,:,'. i:Request,", g:~..'.".",Testtllg",'"p"',

",,".;,': N'uiiibcr';:"'"'.-:.i.  !'Rce'q'd:":.::;", ';~.'.A'Itciiistiv'e'::-",'-;:.'.';; :::;;::::,:';.,"':.;:""Reni'a'rki::i:,:.; -";:.:

s:'i"c: .'..'N 0-20-300 F-5 2 C C CV Yes 47 See Relief Request CO C) p CO

CONTAINMENTINSTRUMENT GAS M-126 Sjlcct 1

',:?:<:SN',

w., '.@

Q

.j4?C ..?

.:.; Oy,.': 'gpss?.",'?'(g;;.'.;::.,';?

':.':. 0 +v'.": ":w gI)?p'"':.; ~R'clief::,:;-,::i

,'g  ;':;RcclUest;;;: QR.::::.::;:::, ~::Ycstglg'.:: .? g?

CO' 'i::Rcq'd:::':-::.?'-'.";

":;:. jet';:":;:,:;,"'i;;'Alt'er'naive;-',: ~"-"'Retnarks'. ---""
lg',".,

.?.'. -: '.:? ": ..;,.;: ~

'A"'-':,:.:;:::,:B.'::-,';-".,'::::.;C"'4":::::::,D'::

1-26418 2 AW X X 0 CV Closure test only.

1-26429 2 C-5 X X 0 CV Closure test only.

1-26472 2 G-7 X X X C CV,LT Closure test only, verify operation during leak test.

1-26474 2 E8 X C CV,LT Closure test only, verify operation during leak test.

1-26-152 2 B-8 X X X C CV,LT Verify operation during leak test.

1-26-154 2 A-8 X X C CV,LT Verify operation during leak test.

1-26-164 2 H4 X C CV,LT Closure test only, verify operation during leak test.

PS V-12643 2 B4 X X RV C SRV No SV-12643 3 B4 X X GL S X C Q,MT 38 See Relief Rapid acting 58 Request. valve.

M C?

CO CO

CONTAINMENTINSTRUMENT GAS M-126 Sheet 1 (Continued)

+C' Ms s

i Rch'cf;..'".;
.',:;;R'cjuest':.,

.",':";+Valv'c)P-::+'..'

"Re'q',d '..i';.  ;'.:";::,.:;::.:;i:.:i:;Reinaiks.,':',-;:,':";,',

.': ,:;:: N SV-12644 2. A4 X X 1 GL S 0 Q,MT 38 Sce Relief Rapid acting 58 Rcqucst. valve.

PS V-12648 3 C-5 X X 1 RV SRV No SV-12648 3 DP X X 1 GL S X Q,MT 38 Sec Relief Rapid acting 58 Request. valve.

SV-12649 X X 1. GL S 0 Q,MT 38 Sec Rclicf Rapid acting 58 Request. valve.

SV-12651 2 E-7 X X 3 ,GL S X 0 Q,MT, 3 Rapid acting LT 38 valve.

58 SV-12654A 2 A-7 X 1 GL S 0 Q,MT, 4 Rapid acting LT 38 valve.

58

CONTAINMENTINSTRUMENT GAS M-126 Shcct 1 (Continued)

?" ?W W. N

Nc'%"":N

'~* 'C.',N;C 'r;

?~~

.N:a 'C,"

M;.N ..'C.,', ....'

h%s

.?NC ..

"C.,

XP'?WC

':,'C:,R,':.'"::,".,':,'.;

N?:  ?: ":" .:::

YW'NCAA:Caa"

'?N;c

U:," R'clicf;..',":;:"

q j)';.p 'O.;,

,:;;.;:t.'?'. '::Red'est"';

.5!:,."-;

Q,,  ? .'~CIl,':,", ,".:R'cq'd.','";

'",,:p,:::: ':;"',"',"":":.:;'.";',Ren'tarki':.:;i;;"::'.;:;:.

.C;%CAN '; C;" '?C 0

'.C;? ?Nc  ? N'?.'?

@,g N.';:N

%Xi?N PW%X" N%< ..  %:cs SV-12654B G-7 X X 1 GL X 0 Q,MT, 4 Rapid acting LT 38 valve. ~

58 C??

SV-12661 X 1 GL X 0 Q,MT, 38 Sec Rclicf Rapid acting LT 58 Rcqu est. valve.

SV-12671 H4 X 1 GL X Q,MT, 38 Sce Rclicf Rapid acting LT 58 Rcqu est. valve.

CONTAINMENTINSTRUMENT GAS M-126 Sheet 2

."Relief:: ..',

Reqiieat";.

.:i,'.:~~':N'umbcrgj~'.:;:;;:,: ,.':Ri)',d.:',:,-",:.;:::. '".";:':;::";::,, ternary'c;!.'..

-HV-12603 2 D-9 X X GL M X 0 Q,MT, No LT SV-12605 2 D4 X GL X 0 Q,MT, 38 See Relief Rapid acting LT 58 Request. valve.

MSIV LEAKAGE CONTROL SYSTEM M-139 f i"';;-,';Ropcst.'(

';j:;:

i?:'.;'.,"";'.",':Rch'c:":Rej',cl:::-:,':.~ '.,".,:A1teriiatriie',".':,",

HV-139F001B 1 D-3 X 'X G M X C Q,MT,LT Rcduccd Pressure Leak Test.

HV-139F001F 1 G-3 X X G M X C Q,MT,LT Rcduccd Pressure Leak Test.

HV-139F001K 1 G-3 X G M X C Q,MT,LT Reduced Pressure Leak Test.

HV-139F001P 1 H-3 X G M X C Q,MT,LT Rcduccd Pressure Leak Test.

HV-139F002B 2 E-3 X G M X C Q,MT HV-139FSQF G-3 G M X C Q,MT HV-139F002K 2 G-3 G M X C QMT HV-139 F002P 2 H-3 G M X C Q,MT HV-139F003B 2 E-5 X G M X C Q,MT No

l1 A 1

l1 )

t

MSIV LEAKAGE CONTROL SYSTEM M-139 (Continued)

Rchcf j'
.':
."RCIIUcst>:
,'A'".
i;
:;i::i;::B,:"';':;"::.i.:;:::C:;:'::;:-D';i HV-139F003F 2 G-3 X G M X C Q,MT No HV-139F003K 2 G-3 X G M X C Q,MT >No HV-139F003P 2 H-3 X X G M X C Q,MT No HV-139F006 2 D-8 X X G M X C Q,MT ' Ycs HV-139F007 2 E-8 X X G M X C Q,MT HV-139F008 2 D-8 X X G M X C Q,MT HV-139F009 2 D-8 X G M X C Q,MT

N I

(<<=

NUCLEAR BOILER M-141 Sheet 1

,. X>.

w

'V:: XW:;:;

5c%F

..'X:

!:::Rclicf::.:':.',':.,

y,:,'g>:;.g

': >N:i: %Request

Rcq',8',
:::.:i'::
CC; ..'.;M>X

',':C ';.;:;P PS V-14137A 3 HX X RV SRV =-

See Rclicf Rcqucst.

PSV-14137B 3 HP X RV SRV Sce Rclicf Rcquest.-

o PS V-14137C 3 H4 X RV SRV Sce Relief Request. =

PS V-14137D 3 H4 X RV SRV 8 See Rclicf .

Rcqu est.

PS V-14137E 3 H4 X X RV SRV 8 .-

See Rclicf Request.

PS V-14137F 3 H4 X RV SRV Scc Relicf-Rcquest.

PS V-14137G 3 H4 X RV SRV Sce Rclicf Request.-:- ~

PS V-14137H 3 H4 X X RV SRV Scc Relief Request.

PS V-14137J 3 H4 X X RV SRV Scc Relief Request.

Q pV

l H

I'

NUCLEAR BOILER M-141 Sheet 1 (Continued)

";Relief::.i." .

Re'jucst;

-:Ret'I'd:,"-.'. '.'~;:Reiiiaiks';jj PSV-14137K 3 H4 X X 6 RV SRV Sce Rclicf Rcqu est.

PSV-14137L 3 H4 X 6 RV SRV Scc Relief Rcqu est.

PS V-14137M 3 H4 X X 6 RV SRV Sce Relief Rcqu est.

PS V-14137N 3 HP X 6 RV SRV Sce Relief Request.

PSV-14137P 3 H4 X 6 RV SRV See Relief Request.

PS V-14137R 3 H4 X 6 RV SRV See Relief Request.

PS V-1413 7S 3 H4 X X 6 RV SRV Sce Relief Request.

PS V-141 F013 A C-3 X 6 RV SRV No

NUCLEAR BOILER M-141 Sheet 1 (Continued)

".gag<
:<;;; .g;PC; <

Gl '%.%<'A.G g:,':":,:  :, %;: ..C

8'c<.','
;.",.<;i;$i;;:

N,

"'@5 <

j< '..gG: .:C,.~y<

,'Reef..';ReIIu'est;:

."~."'%%8tnJ'-":yt.

';:"-',".'"Nu'niber",': ',",;; .".,'.  :-.-:Alt'ernative'> t:;Rcnlarks .;;I

., C:<<

wypC ',%.,'

',::..Reij'd:,.',:.'::<:<".:.:y:.."

N: <C;:

':. Y:.'C,,'GG',

'.C y<G.:'yea '.<g< 4G'( yG yy,,

PS V-141 F013B 1 C-3 X RV SRV No PSV-141F013C 1 C-3 X X RV SRV No PS V-141F013D 1 C-3 = X X RV SRV No PSV-141F013E 1 C-3 X RV SRV No PSV-141F013F 1 -X RV SRV No PSV-141F013G 1 X X X RV SRV,Q 10 RR ADS Valve.

PSV-141F013H 1 C-3 X X RV SRV No PSV-141F013J 1 C-3. X X X RV SRV,Q 10 RR ADS Valve.

PSV-141F013K 1 X X X RV A SRV,Q 10 RR ADS Valve.

PSV-141F013L 1 C-3 X X X RV SRV,Q 10 RR ADS Valve.

ED CO CO

f NUCLEAR BOlLER M-141 Sheet 1 (Continued)

' @N>:>

':C,',.';:;Rchcf-,"

'y%e:.;/'..

'44" "...

Rcqucat,"',

%,>X@';,';

.',y',~Tcating .'g
;"
Re'i':d:,:,::;:,"':,':  :.':Alt'ct'nativ'ci! ;:.,;;.,Ren'ta'iki '"

'".;m: A'!.',';:::;:',: B~:';: C:'"':'";-:;:~9'j:

PSV-141F013M 1 C-3 X X X RV A SRV,Q 10 RR ADS Valve.

PS V-141F013N C-3 X X RV A SRV,Q 10 RR ADS Valve.

PSV-141F013P 1 C-3 X RV SRV No PSV-141F013R C-3 X X RV SRV No PSV-141F013S C-3 X X RV SRV No HV-141F016 1 EA X X G M X 0 Q,MT, No LT HV-141F019 1 EA X X G M X 0 Q,MT, No LT HV-141F020 2 E-7 X GL M X 0 Q,MT No

0 I

1 v tl

NUCLEAR BOILER M-141 Sheet 1 (Continued)

y,'

,ycy:

Nc.:

): gs.'",, .5

' (Q'"',:-;'Pg;':-",'.

(@'y:.';'";; x.<<'~4 ~

~P

. N4;:,S ye:,."i ', 5g:.y:

Yh('m;yyca 044:

.";Rcgucst:;l ,.'.Test@:::i.,".'.

.';,.:.,"Numbe'i",:: ".,~,

""0 ':::;:Rcg',8 ';::,:"":;

',%',',y,?,:,y

",'i'Alt'cr'n'ativc:,', ':,"O'Remarks" ""

" "P. ""::

".ayyy.'A'yy:

.+wM.

A

~';.;:;:QCQXC ..',,', g>b c ya. A HV-141F022A I C-5 X GL A X 0 Q,MT, Scc Rclicf Reduced LT Request. pres sUIc leak test in ICVCISC

'direction.

HV-141F022B I C-5 X 26 GL A X 0 Q,MT, Sce Rclicf Rcduccd LT Request. pIessulo leak test in ICVCISC direction.

HV-141F022C I C-5 X X GL A X 0 Q,MT, See Rclicf Reduced LT R~u est. PICSSUIC leak test in ICVCISC direction.

I f

l

NUCLEAR BOILER M-141 Sheet 1 (Continued) lpga,

~ .P; '"Rchef:.~

'-'Request'j "'~Tcsttng "'

>'
.'ej!N'umber',','",'::..";p.-",,
'Roij',d.-,":  :.:.-"'A'Itc~jristiyi-;',,:

)~4@::.!:l::;::..

"';."'";A'
~"'!,:B'imp.:,".'C,.'Sg(,j9":

HV-141 F022D 1 C-5 X X 26 GL A X 0 Q,MT, Sce Relief Rcduccd LT Request. pressure leak test in 1cvcrse direction.

141F024A 3 A-5 X 0 CV Closure test only.

141F024B 3 A-5 X X 0 CV Closure test only.

141F024C 3 A-5 X X 0 CV Closure test only.

141F024D 3 A-5 X X 0 CV Closure test only.

HV-141F028A 1 ~ X X GL A X 0 Q,MT, LT See Relief Request.

Rcduccd pressure leak test.

NUCLEAR BOILER M-141 Sheet 1 (Continued)

'a

<vv a.<vv'::

tg 4".:; .  :;:Rehe, f;::::.'.',':.

Rcque'st!; v'a.':"."..'Tcs tlAg.;::: ':
.Rcq',d:,".::.:  :':;"Alt'er'n'ative",', ;"i;Reiriarki"'-.'."'.

v:.'c..a ".

HV-141F028B 1 C4 X 26 GL A X 0 Q,MT, Sce Relief Rcduccd LT Rcqu cat. prcssure leak test.

HV-141F028C 1 C4 X 26 GL A X 0 Q,MT, See Relief Rcduccd LT Rcqucst. prcssure leak test.

HV-141F028D 1 X X 26 GL A X 0 Q,MT, Sce Rclicf Rcduccd LT Rcqu cat. prcssure leak test.

141F029A A-7 X X 0 CV Closure test only.

141 F029B A-7 X X 0 CV Closure test only.

141F029C A-7 X 0 CV Closure test only.

141F029D A-7 X X 0 CV Closure test only.

NUCLEAR BOILER M-141 Sheet 1 (Continued)

,, /gh...

p+gc:

c'...Cvpy, iRcllef,;.";--'..'"

A,,.",", !Q .:: Re'qiicst:., . Testing:: ';;i

':::;,.',":j:,:;;,Nuiiibet.,:.'.".".,.".?, "AP x'C k 'Sr,v 'l'Alt'eaistiv'e",'" ~j::;Rcntslks.: ",;

'~?'N A~~

.Xg  :;.";.)xo>M+oxc Ri%

PSV-141 F037A 3 G4 X X RV SRV Yes Sce Relief Rcqu est.

. PSV-141F037B 3 G-4 X RV SRV Ycs Scc Relief Request.

PS V-141F037C 3 G4 X X RV SRV Sce Rclicf Rcqu est.

PS V-141F037D 3 G4 X X RV SRV Sce Rclicf Request.

PSV-141F037E 3 X X RV SRV Sce Rclicf Request.

PS V-141F037F 3 GX X X RV SRV Sce Relief Request.

PS V-141F037G 3 G-4 X RV SRV 8 '- See Relief Request.

PSV-141F037H 3 G-4 X X RV SRV Sce Relief Request.

E'

\(

U

'I h

NUCLEAR BOILER M-141 Sheet 1 (Continued)

',>:N4 Mx&

@y 'yg

<::,'",,:gg;:.::;:,:t>;

'.:::.N

Rchef
,"."

"'-'Rcequcst';.

PS V-141 F037J 3 X X RV SRV Scc Rclicf Request.

PSV-141F037K 3 RV SRV Sce Relief Request.

PS V-141F037L 3 X X RV SRV Scc Rclicf Request.

PS V-141F037M 3 X RV SRV Sce Rclicf Rcqucst.

PS V-141 F037N 3 X X RV SRV Sce Relief Rcqucst.

PSV-141F037P 3 X X RV SRV Scc Rclicf Request.

PSV-141F037R 3 X X RV SRV See Relief Request.

PSV-141F037S 3 X X RV SRV Sce Rclicf Request.

Cll C)

l E I 1

I' l

NUCLEAR BOILER M-141 Shcct 2

?N'?

',~'.

Rc11cfpg

+:;j.';.  :: Rajiicst.

Rc~g.d-.-.::,::.'-:

@:;.?::0::.

1<1%17 2 F-3 X 1 GL H LT No 1%1-018 2 F-3 X 1 GL H LT No HV-14107B E-3 X X 0 CV No Open check only.

HV-14182A 2 C-2 X X 3 G M X 0 Q,MT,LT No HV-14182B 2 E-2 X 3 G M X 0 Q,MT,LT No 141 F010A X X X 0 CV,LT Sce Rclicf Closure Rcqu est. check only.

141F010B E-3 X 0 CV,LT Sce Rclicf Request.

HV-141F032A 2 C-2 X X 24 SC M X 0 Q,MT, 12 Closure test LT only.

HV-141F032B 2 E-2 X X 24 SC M X 0 Q,CV, 12 Closure test MT,LT only.

REACTOR RECIRCULATION M-143 Sheet 1

'Rehcf~

';::Request:"; P>!." '7estmg.g'

R~ d~~~.:  ::;"AlteJnatiye',., ::,""-~R'e'm'arki:";",;.:;:";j HV-143F019 X 3/4 GL Q,MT, 38 Sce Rclicf Rapid acting LT Rcqu est. valve.

HV-143F020 X X 1 GL A X Q,MT, 38 Sce Relief Rapid acting LT Request. valve.

HV-143F031A F-8 X X 28 G M X 0 Q,MT Ycs 16 HV-143 F03 1B F-8 X 28 G M X 0 Q,MT Ycs 16 HV-143 F032A F-8 4 G M X 0 Q,MT No HV-143F032B F-8 X 4 G M X 0 Q,MT No

1 II

REACTOR RECIRCULATION M-143 Sheet 2

'eh'e f,::i'.,';:,',i

~-.';Alte'rnative:.:-:

143F013A 2 E-5 X X 0 CV,LT Ycs 15 Closure test only.

143F013B 2 E-5 X X 0 CV,LT Ycs 15 Closure test only.

XV-143F017A 2. F-3 X X XFC X 0 CV,LT Ycs 14, Closure test only.

XV-143F017B 2 H-2 X X X X 0 CV,LT Yes 14 Closure test only.

I REACTOR WATER CLEANUP M-144

ttt&"';
:,Rclie'f'll,";':.:R~'ct";.":::::

HV-144F001 1 B-2 X G M X 0 Q,MT, 62 CS LT-HV-144 F004 1 B-2 X X G M X 0 Q,MT, 62 CS LT

>1 I li t

CONTROL ROD DRIVE M-147 Sheet 1

',:,';; C;Vh

.::: N(  ;: %'g"...%':

g@:;:,: ';:,

ajar<<>

i?~NÃ::

C.'.

(Rclicf:.';":;.'jR+uest

(' . .> gy?,g

',;:R'g",di~y",Fj j dj ':5',; Tcstutg:FaÃ":'.

,;:,; 'Alternatiy'e';",'",.i.:

g XV-147F010 2 X X 1 GL A X 0 Q,MT Ycs 61 Sec Relief Rcqu est.

XV-147F180 2 A-5 X 1 GL A X 0 Q,MT Ycs 61 Sec Relief Request.

XV-147F011 2 X 2 GL A X 0 Q,MT Ycs 61 See Rclicf Rarest.

XV-147F181 2 X X 2 GL A X 0 Q,MT Ycs 61 See Relief Request.

CO CO po

CONTROL ROD DRIVE M-147 Sheet 2

,: 'Relic f,:,':.'.,',

', Rajucst',

.,:";'.-;".':i.;::Nu'mber',.';i:;:;.'.,-:,';; ,':Rej.d:  ;.,"::,'..."Aiternst'iirc, '.",, ::,:.',.Reiiia'ilts'.;;,",.

147114* A-8 X- 3/4 C CV 17 Sce Rclicf Open test R~u est. only.

147115* D-8 X 1/2 C CV 17 Sce Relief Closure test Request. only.

XV-14726* X 1/2 GL A 17 Sce Rclicf Open test Request. only.

XV-14727* X 1/2 GL A 17 Sce Rclicf Open test Request. only.

147138* D4 X X 1/2 C 0 CV 17 Scc Rclicf Closure test Rarest. only.

~ There valves, one for each are a total of 185 sets of these of the 185 CRD Hydraulic Control Units.

)I

STANDBY LIQUID CONTROL M-148 148 F004A D-7 X X X DT No Explosive Valve.

148F004B D-7 X X DT No Explosive Valve.

HV-148 F006 1 D-8 X X SC M X Q,MT, 18 Closure test LT,CV with motor operator, open test during reactor vcsscl injection test.

148F007 X X X CV,LT 19 Closure test during leak test, open test during reactor vessel injection test.

PS V-148 F029A 2 D-5 X RV SRV No PS V-148 F029B 2 F-5 X X RV SRV No 148 F033A D-6 X CV No

Eg I'

STANDBY LIQUID CONTROL M-148 (Continued)

,Rehef "'
i

'::;;:;::::,:;:Vjivci:::,:,-':;:,::::~ Rajucsi;-,  :~~j; )'TC$ 4flg:,;~.',.

R~'.d:.:,:::.',:

'::;,"Altetnattv'e".'48F033B X X 1Vi C CV No M

CO CO

REACTOR CORE ISOLATION COOLING M-149

'..Rclicf.";; ".;.

!;;,.:j':,':.,Valve!i';"',:: ,', Raju'e'st':;

149420 2 E-5 X X 1 GL H LT No HV-149F007 1 C-3 X X 4 G M X 0 Q,MT, 20 Sce Relief Leak test in LT Request. reverse direction.

HV-149F008 2 C-3 X ~ X M X 0 Q,MT, No LT HV-149F013 2 E-5 X X M X Q,MT, No LT FV-149 F019 2 F-3 X 2 GL M X 0 Q,MT, 38 Sce Relief Leak test in LT Request. revcrsc direction.

Rapid acting valve.

149F021 2 F-7 X X X =2 CV,LT Ycs 21 Closure test only.

65 149 F028 2 G-5 X X X '2 CV,LT Ycs 21 Closure test only.

HV-149F031 2 H-2 X X 6 G M X Q,MT, 20 Sce Relief Leak test in LT Rcqu est. reverse direction.

CD C)

CO o

0 fI k,'I J't' v,

lr gI 0

K h

REACTOR CORE ISOLATION COOLING M-149 (Continued)

F.:,::,;'.':. ';::: ."i;;:,:;.

,.OP!:  : Rehcf.;,
R'cc'jucst'-".
~
",'."Niimber'>,:,"';.:.

~g AItcrnative.';,." ',:,'::-.::::;::-:,::Rcmark,',,:-':,.-:.,

ssN~HPP:.:.'b:<:::::.:."

.i"i';:

149 F040 G-5 X X X 10 CV,LT 21 Closure test only.

HV-149F059 2 G-3 X 10 G M 0; Q,MT, Sce Relief Leak test in LT Request. reverse direction.

HV-149F060 2 G-3 X X GL M X '0 Q,MT, . No Leak test in LT reverse direction.

HV-149F062 2 X X G M X 0 Q,MT, No LT 149 F063 X X CV Ycs Open test only.

149F064 X X CV Ycs 22 Open test only.

64 HV-149F084 2 F-3 X G M X Q,MT, Yes 20 See Relief Leak test in LT R~u est. revcrsc direction.

0 4

4 l 1 S

REACTOR CORE ISOLATION COOLING M-149 (Continued)

.';;;i 4xcjx:,v.:4

~pg

~;: lgNg." ;o.'~g,:. r'<0:r,.

r C.Nh48

o4~~ '.m.g<'v .'S:,zr
.'Rchef):;:,;":
,,
-.+Valve'~<.-"-.'...',;. '-.;glj
;."Rahu'est,':;:

Q';9:CC i';R'e'cj',d:::':':

,g?;>ii k(:c Y:W"84~

,';;;.'A~4"'"':B':y.':.,;,'C:;:i':!,",i'.:'D,'. .g@.Mr, HV-149FOSS C-3, . X GL A X C Q,MT, 3$ Scc Relief Leak test in LT Request. rcvcrse direction.

Rapid acting valve.

RESIDUAL HEAT REMOVAL M-151 Sheet 1

%:CC C PXC j

.Relief,,<<<<'i;

',;.,",-"...jj,":Valv'e,

".;"ii';:.; '-.'i:;;"'Testing!:;.::4

,,
,;::";Alter'native:l"':,'"."""i'd%?:wiN?:;.,'.",,?
.'
::,';;.;.g(y, HV-151F004A 2 F-8 X G M X 0 Q,MT, 20 Sce Relief Leak test in LT Request. reverse direction.

HV-151F004C 2 F-9 X X G M X 0 Q,MT, 20 Sce Relief Leak test in LT Request. reverse direction.

HV-151F006A 2 G-7 X 20 G M X Q,MT No HV-151F006C 2 H-8 20 G M X Q,MT No HV-151F007A 2 F-7 X X G M X 0 Q,MT, Yes - 20 Sce Relief Leak test in LT Request. reverse direction.

HV-151F015A 1 D-7 M X C Q,MT, 26 Pressure LT isolation valve.

HV-151F016A 2 B-5 12 GL M X Q,MT, No LT HV-151 F017A 2 D3 X GL M X 0 Q,MT No HV-151F021A 2 B-7 12 G M X Q,MT No C/I C)

C)

CO

I

RESIDUAL HEAT REMOVAL M-151 Sheet 1 (Continued)

..'~j>>'." 'Rclicfj:;:"";:.":;.

o:R~Ucst:

il".'-':.".":";:,::Nu'inbcr",.:"",::i:"  :,"':.:Rej d'::"':!'":.';:;,"Alter'native ". :;::;:;":'R'eiii'arka;:,';;

HV-151F022 1 B-8 X X G M X Q,MT, 20, Leak test in LT 26 zcYersc direction.

HV-151F023 1 B-8 X X G M X Q,MT, 26 LT HV-151F024A 2 E-7 X X 18 GL M X Q,MT No HV-151 F027A 2 E-7 X X GL M X Q,MT No HV-151F028A 2 E-5 X 18 G M X Q,MT, No LT 151F031A 2 G-3 20 CV No 151F031C 2 H-2 X 20 CV No 151 F046A 2 F-3 X X CV See Relief Open test Request. only.

151F046C 2 F-2 CV Sce Relief Open test Request. only.

1f RESIDUAL HEAT REMOVAL M-151 Sheet 1 (Continued)

'%? 'rY.;>'c, SYS

p;Y.

"";. C?X;.

~:<.:? Y. X S

'?~(8

@~?

a< YY. '?

.
. YX ' .Q..YY

~" o,::;::;:,.

f;":,; '.

'A,;~ax;:l

~ Y.%'.

c< la<  : 0;";;:

XC':,:Relic<

';.".~'h.';:;

~o':,'::Q" ',. Rejucs't:.  ::;:,.;.:Teshng::;::,:::,

'?Y,' Cll

".;."'<j:;;.;Nuinhcr',.::.':"..""-:

CYC<": ~

.g:', i: Rcq.'d.";;;i.. ';'- Aitei'na?tive;:;:,:: '::,;."'Rcii'tailts:"":,",:I

a;",<YX>;. ~,'Y,x  :
.,",'?)X?X a<,

,C " ~pap<?:.jgye.pp<?..

HV-151F048A G-1 X X GL-. M X 0 Q,MT No HV-151FOSOA D-8 X X X C C CV,LT 26 Pressure isohtion valve.

15IF090A X C 0 CV Sce Relief Closure test Request. only.

HV-151F122A E-8 X GL A X Q,MT, 26, Prcssure LT 38 isolation valve.

Rapid acting valve.

6(

1 ~

H Eg r

RESIDUAL HEAT REMOVAL M-151 Sheet 2

?:o"-',

'"'"",~,';Test tng:;;,",

. >>>':.N

.'.;:'".',::Ajtcr'i'iattvc;:;:",

HV-151F003A 2 F-5 X 20 G M X 0 Q,MT No HV-151F011A 2 H4 X 4 G H X C LT No Disabled HV-151F047A 2 C-8 X 20 G M X 0 Q,MT No PS V-151F055A 2 A-5 X X X 8 RV C LT No SV-151F079A X X 1 GL S X C QMT 38 Scc Relief Rapid Rarest. acting vave.

HV-151F103A C-3 X X 1 GL M X C LT No Leak test in reverse direction.

PS V-15106A 2 F-3 X X 1 RV C LT No

RESIDUAL HEAT REMOVAL M-151 Sheet 3

,'@C .'NQ N:~y~y<,  ;:;"C'..;:.:

yyg<~ymPC i,,'.

~g'.:C.".C CC

" 'C.""

Z o,',.",':;c:. Q lgP; ..CC QtA g ~y: ':

~'R'c1icf,:";.""l';.';

,,:,bluest;:,  ;;.'; Tcstlngg~:

.g;:"",:":::j::

,g(:::cc ~jRcq,d'-'. ':.: .':;:::::::::Rcn'tarki:,':.'c

'.:Altcrnattvc);

i
~'m mC 4 ..,
;.,i..':";".y

@'/

.;:::;;y',:,yC Y.,:

<<cyc;. yy w y '.M'yCC'y: 4'."yXC HV-151F004B 2 F-3 X 24 G X 0 Q,MT, Sce Relief Leak test in:

LT Request. -, rcvcrse direction.

HV-151F004D 2 F-1 X X 0 Q,MT, Scc Rclicf Leak test in LT Rcqu cat. reverse direction.

HV-151F006B 2 G-3 X X 20 X C Q,MT No HV-151F006D 2 H-2 X X 20 G X C QMT No HV-151 F007B 2 F-3 X X 6 G X 0 Q,MT, Sce Relief . Leak test in LT Rcqucst. reverse direction.

HV-151 F008 E-3 X X 20 G Q,MT, Pressure LT isolation-valve.

HV-151F009 D-1 X X 20 G, X Q,MT, Prcssure LT isolation valve.

RESIDUAL HEAT REMOVAL M-151 Shcct 3 (Continued) g..;;;;;.;;:. c;m:?

'Q',:,Rcljcf.".:,':.';

i:',Rej':d;;:'~@~+

'.'.;";;;:;;,'.";':Valv'c'.'",;'.:w.;~:..:".

IRQUCSt.":. '~ ...'".Ycsttng(~~gj .@OP ih

!': .".,'8.".::-?"-:;.;:;..";.;:.',

..:.':,.;~'p::;,:;.  ::-;,"'Aitcm'ativ'c.';:.: ;:;::R'eiriarks':".'-::

,i;::n..",:

HV-151F015B C-3 X X M X Q,MT, 26 Pressure LT isolation valve.

HV-151F016B 2 A-5 X X 12 GL M X Q,MT, No LT HV-'151F017B 2 C-7 X 24 GL ,X. 0 Q,MT No HV-151F021B 2 A-3 X X 12 'G M X C Q,MT No HV-151 F024 B 2 F-3 X 18 GL M. X C Q,MT No HV-151 F027B 2 E-3 X X 6 GL M X C Q,MT No HV-151F028B 2 CW X 18 G M 'X Q,MT, No LT 151F031B 2 G-8 X 20 C C CV No 151F031D 2 H-8 X 20 C C CV No

lf

'1 1l

RESIDUAL HEAT REMOVAL M-151 Sheet 3 (Continued) i';Relief,""i,'",,

<';R~U est) ':;

jRcsi',d:i';:::.'g~Tcsting

"-":-""Alternativ'e"',"-;:

151F046B 2 F-7 X X C C CV Sce Relief Open test Request. only.

151F046D 2 F-8 X X 4 C C CV Sce Rclicf Open test Rcqu est. only.

HV-151F048B 2 F-9 X 24 GL -M X 0 Q,MT No HV-151 FOSOB 1 C-2 X X X C CV,LT Ycs Prcssure isolation valve.

151F090B 2 B4 2 C 0 CV Sce Rclicf Closure test Rcqu est. only.

HV-151F122B 1 C-2 X X 1 GL A Q,MT, 26 Pressure LT 38 isolation valve.

Rapid acting valve.

I N

h

RESIDUAL HEAT REMOVAL M-151 Sheet 3 (Continued)

.,":,):>v;"

.',"Alternative,";

"'-'A'"'@@B"":."':::-';,::,C::,::":::~D" PSV-151F126 D-2 X X 1 RV LT No

RESIDUAL HEAT REMOVAL M-151 Sheet 4

~F:>

,C ..

.9 s

":,Rcbe'f "..',::::, j&.;;.i'"..
"
,Requ'e'st";; ',.":,'::,':::::":. 'i; 'Testtng:gg

',.:;.Req'd';,'::::,:;,: ",':;:I,;: .;: Ante'r'nativ'e.::"

V.h:( h:4 .P.

HV-151F003B 2 F-4 X 20 G M X O Q,MT No HV-151F011B 2 H-3 X X G H C LT No Disabled HV-151F047B 2 C-2 X 20 G M X 0 Q,MT No PSV-151 FOSSB =2 AP X X RV C LT No SV-151F079B 2 G-5 X GL S X C Q,MT Ycs 38 Sce Relief Rapid Request. acting valve.

HV-151F103B 2 C-7 X 1 GL M X C LT No Leak test in reverse direction.

'S V-15106B 2 F-7 X X X 1 RV C LT No PS V-151F097 2 G-2 X X X RV LT, No SRV

1' CORE SPRAY M-152

) cs

'.iRclicf,':: ",

P~~~~,:4,@

'<?".i Req',d ~.'.,,':

HV-152F001A 2 H-3 X 16 G M X 0 Q,MT, 20 Sce Rclicf Leak test LT Request. ill reverse direction.

-HV-152F001B 2 H-1 X 16 G M X 0 Q,MT, 20 Sce Relief Leak test LT Request. in reverse direction.

152F003A 2 E-5 12 C CV No 152F003B 2 E-8 12 C CV No

-152F003C 2 E< X 12 C CV No 152F003D 2 E-9 12 C CV No

-HV-152F004A 2 D-4 X 12 G M X 0 Q,MT No HV-152F004B 2 B-4 X X 12 G M 0 Q,MT No HV-152FOOSA D-3 X X 12 G M X Q,MT, 45 Pressure LT isolation valve.

l I

CORE SPRAY M-152 (Continued)

Ã":::-""'+A~~>pj's";:":,;:;;.:!

';::Reb'cl',.":";::

g;" ',Vilve'jj~':,:;::;.',:':. .':

Rendu'est:.;". ';:,":,'-: 7~ting:.;::,:;."

5':,:::-".:; <¹mb<er"":.",'." '::Rc'j',d':-'-:"'.':":,':

HV-152FOOSB B-3 X X 12 G M X Q,MT, 45 Pressure LT isolation valve.

HV-152F006A 1 D-3 X X X 12 X C CV,LT Ycs 45 Prcssure isolation valve.

HV-152F006B 1 B-3 X X X 12 X C CV,LT Ycs 45 Prcssure isolation valve.

PS V-152F012A 2 D-7 X X 1'h RV C SRV No PS V-152F012B 2 B-7 X X 1'h RV C SRV No HV-152F015A 2 E-3 10 GL M X Q,MT, No Leak test LT in reverse direction.

HV-152F015B 2 E-3 X 10 GL M X Q,MT, No Leak test LT in reverse direction.

) W 1

lh K

I'

CORE SPRAY M-152 (Continued)

'A:.Y.:. N'.W:::

. 1" 0 ~";.

"Oe "'"'""'Q NF4i;:"'Y.: go,.":,:;;,

.Relief::::"
,~>,:i",:,':-VaIv'c::;.jgP,".
;:;:;;Testa'.::',..4,:

Yjg ;;:

~

~~:;Request

';j:.::";',:::Nuinbcr".:;"".': '.;0".'"': '-::',R'e'q',.d::;:;::.',:,. ,::,':AIter'nitive.';"::": .';.;i:,Re'nI'a'rks'"'":::.

...;::>'A4 152F029A 2 A4 X 2 C 0 CV Sce Relief Request.

152 F029B 2 A4 X X 2 C 0 CV See Rclicf Request.

152F030A 2 A4 X X 2 C 0 CV Sce Relief Request.

-152F030B 2 A-5 X 2 C 0 CV Sce Relief Request.

HV-152F031A 2 F-3 X X M X 0 20 Sec Rclicf Leak test 3 G Q,MT, LT Request. I Icvcrsc direction.

HV-152F031B 2 F-3 X X 3 G 0 Q,MT, 20 See Relief Leak test LT Rcqu est. In Icvctsc direction.

PS V-152F032A 2 GP X 1 RV C SRV No PSV-152F032B 2 H4 X 1 RV C SRV No CO CD pC)

F 't 0

f L

'I Jl 1.

1'

CORE SPRAY M-152 (Continued)

Rehcf g~~j

,,<~~~, Testing@<:,:m i;Request~',

'::";::.:',:.<:',Number',.',:,s,':. -;

, Req'.,d.j~j;.  :,.'AlIer'native~ ,':,':,"".',Rem"arks.-:::;

152F036A 2 E-S X X C CV. Sce Relief Open test Rcqu est. only.

152F036B 2 E-8 X C CV Sce Relief Open test Request. only.

152F036C X X C CV Sce Relief Open test Rcqu est. only.

152F036D 2 E-9 X X C CV See Relief Open test Rcqu est. only.

HV-152F037A 1 D-3 X GL A X Q,MT, 45, Pressure LT 38 isolation valve.

Rapid acting valve.

CORE SPRAY M-152 (Continued)

??y~gj:::c:jap

.',,<<:::.i:t'.$4r.

f~Z jRclie'f:::i,:,'-.'.

HV-152F037B 1 C-3 X X 1 GL X Q,MT, 45, Prcssure LT 38 isolation valve.

Rapid acting valve.

M CO CO CO

0 lt 1

FUEL POOL COOLING & CLEANUP M-153 Sheet 1

xK  ?

'.Rcbe f,';:~".;i

+Ro'jiicst,';':"'.:-.".;::".-';Testm8s~,'"',~"i

,;:.;";'.'Numhcr'.',":.;,'.',"; 'ebel'd'"-: "

i:":'Aitct'nstlYc;i. '"','",R'em'Pk'i'",';-;:,i I-53471 A 3 A-5 X X 8 C CV 13 Scc Relief Open test 65 Request. only.

I-53471B 3 A-5 X 8 C CV 13 Sce Relief Open test 65 Request. only.

L f r e

HIGH PRESSURE COOLANT INJECTION M-155

Relief:.: 0

':::Request:-.",Req'.,d;::;:jg

.:+j.ei":N'u'mbe'r'..',@.;.:";  ;,'.Altcsnative::,:

1-55412 X X 2 C 0 CV Sce Rclicf Request.

I-55%38 E-S X 1 GL H LT No HV-155F001 D-8 X X 10 G M Q,MT No HV-155F002 B-3 X X 10 G M 0 Q,MT,- Yes 20 Sce Relief Leak test in LT Request. IcYctse dueetion.

HV-155F003 1 B-3 X 10 G M X 0 Q,MT, No LT HV-155F004 2 B-8 X X 16 G M X 0 Q,MT No 155 F005 X X 14 C CV No Open test only.

HV-155F006 2 E-5 X X 14 G M X Q,MT Ycs . '29 HV-ISSF007' X X 14 G M X 0 Q,MT No HV-155F008 2 D-5 X X 10 GL M X Q,MT No CI7 CO p

CO

HIGH PRESSURE COOLANT INJECTION M-155 (Continued)

C?:C,.

MPWQC",:

>>>>>>(>>

. C" V>>>>(':.cv', 's?.

..>>< Q':,",:: '.  ;:, @'.E'., Y, '?g>>>>v.',

yY>>,',

?':X>> ?m g,:: ,:;>> .?:;?M

'j>>@

. >>?%'?:.

.:,'.s?:.:c>>

iO;-,".-:;:::.

~ ':,?:

.X/>>  :;%" ..t?;. i:Request: xg: Tcstmg'.'"

,.>>:,.:":,':.:Nu'mbe'r",:.;",',".';:,".";:  ;: Qg:,". .Req'd':;'. ';:";Altern'atiy'e'.,"., ':,'::,",Remarks,:;..::::,

?'A>>>>&'C ?'>> (gC>> '.

?:, >>>>v'.

.,'N

>>??% . >>?'?/ 'M?:;%Y:,&

HV-155F012 2 F-3 X 4 G M Q,MT, 20 Sce Relief Leak test in LT Request. Icvefsc direction.

Verify stroke during pump test.

155F019 2 C-8 X X 16 C CV 32 RR Closure test only.

HV-155F042 2 H-2 X 16 G M X Q,MT, 20 See Relief Leak test in LT Request. reverse direction.

155F045 2 H-3 X X 16 C C CV 31 See Relief Open test 65 Request. only.

155F046 2 F-7 X X X 4 C C CV,LT 28 Sce Rclicf Open test 65 Request. only.

HIGH PRESSURE COOLANT INJECTION M-155 (Continued)

,::;g,'.:: ':."":.'<<a.'.
."...'
:,".;.':.",::,".':Hu'mber",:,.'":,"'.';,';.R'efief,":::"". cating <<@

, Alternative'v 'j'-,.Rcnia'i','i':;:

155F049 G-5 X X 20 C CV,LT Ycs 28, Sce Rclicf Open test Request. only during pump test.

HV-155F066 2 G-3 X 20 G X 0 Q,MT, 20 Sce Relief Leak test in LT Rarest. IcYclse direction.

HV-155F075 2 FQ X X 3 G X 0 Q,MT, No LT 155F076 X X 3 C CV 34 Open test 64 only.

155F077 X X 3 C CV 34- RR Open test 64 only.

HV-155F079 2 F-3 X X 3 G M 0 Q,MT, 20 Sce Relief Leak test in LT Request. Icvcrse direction.

'l lg I,

HIGH PRESSURE COOLANT INJECTION M-155 (Continued)

AC '.

?'A g
<5'.,'.;;  :.';:.;4j;'i

??X(;.)8'.

,C ': ..

"4 Ki:~ :.?<<;:::g-.',:;.

.?'?;

"  ? .?%::..'..

?

"."'Alt?c'inativc,':;:; :":?$,'RcnlhlkS.:,:.;":;..

Ol'?'z':5

,:.':?::

'":,';, A"',";:~!B,:','i:jC,?;:..:,,"=";"9',:,::

HV-155FI00 1 B-3 X X GL C.

X Q,MT, 38 Scc Rclicf Rapid LT Request. acting valve.

HPCI TURBINE - PUMP M-156 Sheet 156F048:=

156F052

'N

.!Pj),>..,';:Valve,'.:;."-","j'j'::"::
<~., g,",', +':,':::.

FV-15612 . 2 2

B-7 G-5 1

X X

X X

X 10 2

2 GL C

C E/

H o%Q Ni~!~

C C

C Q,MT CV CV

~ Re]left~~(

Ycs No 53 Sce Rclicf Request.

Sce Relief Request.

Test during HPCI pump test.

Test during HPCI pump test, open test only.

Test during HPCI pump test, close test only.

156F057 G-5 X 2 C C CV Scc Rclicf Test during Request. HPCI pump test, open test only.

HV-156F059 2 E-'3 2 GL X C Q,MT No Test during HPCI pump test.

PSE-156D003 2 B-5 X X 16 RD C DT No No testing quired.

M CO C)

<<0

HPCI TURBINE - PUMP M-156 Sheet 1 (Continued)

':;Relief;;:;::;.

""Rc'just.':,

,';: -'"..:Niimb'cr';";,':-" .:,:Rej'd i,- ,'"';;;,Alteiiiativ'e'-,"."'.

PSE-156D004 S A-5 X X 16 DT No No testing requited.

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1

":Relief$

,'-:,'iRcjucst'j

";:;:::i:. Numb'n,:.',:::,:':,:.

'"'RYij'd:i:.',,iTes4llg  :.';;Altcrnstiy'e',

K. "":::

HV-15703 2 E-3 X 18 B A X Q,MT, 37 CS Closure test LT only. Leak test in fevers e direction.

HV-15704 2 E-2 X X 18 B A X Q,MT, 37 Closure test LT only.

PSV-15704A1 2 FR X 24 RV A X SRV No PSV-15704A2 2 F4>> X 24 RV A X SRV No PS V-15704B1 2 FC X X 24 RV A X SRV No PSV-15704B2 2 FC X X 24 RV A X SRV No PSV-15704C1 2 F-4 X X 24 RV A X SRV No PSV-15704C2 2 FP 24 RV A X SRV No PS V-15704D1 2 FC X X 24 RV A X SRV No PSV-15704D2 2 F4 24 RV A X SRV No PS V-15704E1 2 F-4 X X 24 RV A X SRV No M

CO C)

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

'F:,'P

X';".C'.

?AYAH%:.

.:,:" s.':s  ;:.': Relic'f.:.:,:;;:.;

i:':":4.:Valy'e:'.!kg'..?."' +..??

Renucst t Y.

i,'.

? cC.:.;:;

?" .Rcj?d'"""': .,'":":,.',Reniarrks'-'"':..

YC >:;%%.

"A%44."B " C l:."

PS V-15704E2 2 24 RV SRV No HV-15705 D-2 X X 2 GL X Q,MT, 37 Closure test LT only.

HV-15711 A-3 X X 2 GL X Q,MT, 37 Closure test LT only.

HV-15713 B4 X 24 B X Q,MT, 37 Closuretcst LT only. Leak test in Icvcrse direction.

HV-15714 B-2 X X 24 B X Q,MT, 37 Closure test LT -

only.

HV-15721 6 B X Q,MT, 37 Closure test LT only.

J'r 't i

j

CONTAINMENTATMOSPHERE CONTROL M-157 Shcct 1 (Continued)

'X4 . N%'.

'%: I'%CC.:M'. :4X4).

X4

.'::Ail 'C

' 'c's .4~',.C

':;CCS .

ii Rchcf-.':--:.

'.-::::,';Nu'rnb'm.'c".',.':.,';.

'I

( Ce ':;: +

CS C4'.C jgv.

g y..',. c;:.Rerlucst,::

~)Alt'e'rn'ativi', '

4X .~ ,.

4F 4X44 Y4

.)CC .X.

IX~,::4 HV-15722 2 C-5 X X X Q,MT, 37 CS Closure test LT only, Leak test in reverse 4 direction.

HV-15723 2 D-7 X X X Q,MT, 37 CS Closure test LT only.

HV-15724 2 E4 X X 18 B A X Q,MT, 37 CS Closure test LT only.

HV-15725 2 E-5 X X 18 B A X',MT, LT 37 CS Closure test only. Leak test in reverse direction.

SV-15734A 2 B4 X X GL S X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

11 I ~I 'I 1,

1 V

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued) r ';.V; 7" jg+s.j>> ' 'C;: ... "

vk:h:::"'"..

'~gSÃ p4'ci.i  : (chef:ji'.

5 et:

:: Request',:

,:,.":.;";;:.'Nu'i'nber,:;:,:.;::,i::;;:,;; ':.'R~'d,:.;; ,i""A'1tcr'n'ative';"';.:

",";::Rent'a'iks,'"';.'i'V-15734B

.:" ':;a:6'

""'N~~':.

2 EW X GL S X Q,LT, 38, See Relief Rapid MT 58 Request. acting valve.

SV-15736A G-3 X X GL S 0 Q,LT, 38, Sce Relief Leak test in MT 58 Request. reverse direction.

Rapid acting valve.

SV-15736B 2 E-6 X X GL S Q,LT, 38, See Rclicf Leak test in MT 58 Request. reverse direction.

Rapid acting valve.

SV-15737 2 GW X X GL S X Q,LT, 38, See Relief Rapid MT 58 Request. acting valve.

I CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

AN v't Rc4efji<.",.

g Request;v.

g R~td'; '"):Testings+'M';'Alt'cinativ'e'.",;:.

.4'Cy SV-15738 2 G4 X GL S X Q,LT, 38, Sce Relief Rapid MT 58 Rcqu est. . acting valve.

SV-15740A 2 BP X GL S X 0 Q,LT, 38, Scc Rclicf Leak test in MT 58 Rcqu est. reverse direction.

Rapid acting valve.

SV-15740B 2 B-5 X GL S X Q,LT, 38, Sce Relief 'Leak test in MT 58 Request. 'everse direction.-

Rapid acting valve.

SV-15742A 2 B-3 X X GL S X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 Rcqu est. acting valve.

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

) Rche f."':

! .j~'",<Tcsttng '@

"":Req'dP.:,;:

SV-15742B B4 X X GL S X Q,LT, 38, See Relief Rapid ,

MT 58 Request. acting valve: ~

SV-15750A GL S X 0 Q,LT, 38, See Relief Leak test. in MT 58 Request. reverse direction.

Rapid acting valve.:,

SV-15750B B-5 X GL S X Q,LT, 38, See Relief Leak test in MT 58 Request. reversc ,

dircction.

Rapid acting valve.

SV-15752A X X GL S X 0 Q,LT, 38, Scc Relief Rapid MT 58 Request. acting valve.

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

@.jx-<

.,,~j'j';Ri';lief,.'"':

-.;:,:,.:..Valve:,,:;;.:.. ~:; RcqUcst.;

i'
'.:::; Numb'cr.','-.:i-';.". .".:,:Rcq d <~'-,". :j':;Altc'netiv'e','-'":

SV-15752B 2 B4 X X 1 GL Q,LT, 38, Sce Relief Rapid MT 58 Request. acting Ch valve.

HV-15766 2 H-5 X 6 G X Q,MT, 20 Sce Rclicf Leak test in LT Request. Ievclse direction.

SV-15767 2 C-5 X X 1 GL X Q,LT, 38, Sce Relief Rapid MT 58 Request. acting valve.

HV-15768 2 HP X X 6 G X Q,MT, No LT SV-15774A 2 C-3 X X 1 GL X 0 Q,LT, 38, Scc Relief Rapid MT 58 Rcqu est. acting valve.

SV-15774B 2 D4 X 1 GL X Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

Ch C) p CO

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

",A.;? . "C

,'.;@gg+w

? M;,,

g4".".:,:;:??i

!,Relief,"';~~

.Rcqucst?

?? eS:: .;:;.'t -".: Rc'q dye ':";<'Altctn'ativc"i

.',,".",  :.R;::,???

+..'.
";r
,r? i:."',""

', ~:",:% C;:

g<,?p<('? .??

x NV???M?

,, x.;? ,;?,. ~ ..,,a xa Yx//ArA OrrrA>

SV-15776A x X 1 GL- X S

0 Q,LT, 38, Sce Relic f Leak test in MT 58 Rcqu est. Icvctsc direction.

Rapid acting valve.

SV-15776B D-5 X X 1 GI C QLT, 38, Sce Rclicf Leak test in MT 58 Request. scvcfsc direction.

Rapid acting valve.

SV-15780A F-3 X 1 GI S X 0 Q,LT, 38, Sce Relief Leak test in MT 58 Request. Icvctsc ditcction.

Rapid acting valve.

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 1 (Continued)

';::;";;:,"::.";Numb'c'r':-:""";"

4af::

~i

.",-;-"'A:;.:':;".."-=Sj';:':'C::,::

iC'>':

.';.4>>,

r

",'(
+ W g?'
?
.;
h'4%.

V?.":::

'; 40 ';:

s'p',:

4

'a

,'C.X:,% .:

t..Relief.:i,':,,">

/Ra'ju?est~<

i R~',d.:"':)

."r." .".?++~/

.';,:;;,;;Test1ng;:,

,',"'V-15780B g "C: '>':::

2 F4 X X GL S X Q,LT, 38, Scc Relief Leak test in MT 58 Rcqu est. reverse direction.

Rapid acting valve.

SV-15782A 2 F-2 X X GL S 0 Q,LT, 38, Sec Relief Rapid MT 58 R~u est. acting valve.

SV-15782B 2 FW X X GL S Q,LT, 38, Sce Relief Rapid MT 58 Request. acting valve.

SV-15789 2 ~ X X GL S X Q,LT, 38, Scc Relief Rapid MT 58 Request. acting valve.

wk N

\

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 5

+Altctnativc~;

.'..,'A'-:;$;::.':B.;:.':"'"".C!4~i';9'.'

s ~N SV-157104 2 E-3 X GL S X Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

SV-157105 2 E-3 GL S X Q,MT, 38, Sec Rclicf Rapid LT 58 Request. acting o valve.

SV-157106 2 F-3 GL S X Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

SV-157107 2 F-3 X GL S X Q,LT, 38, Sce Rclicf Rapid MT 58 Rcqu est. acting valve.

ll A g t

l N

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 6

(

}?

.':K:::::.>>>>

';;..Aitcinatiye;::

"i,A""':"':'.:,'B'-:::,";:..';::.::::.C:':::.-'::;."""'"'9""

SV-157100A 2 B-3 X GL S X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 Rcqucst. acting valve.

SV-157101A 2 B-3 X X GL S X 0 Q,LT, 38, Scc Rclicf Rapid MT 58 Request. acting valve.

SV-157102A 2 C-3 X X GL S X 0 Q,LT, 38, Rclicf Rapid MT 58 Request. acting valve.

SV-157103A 2 C-3 X X GL S 0 Q,LT, 38, Sce Relief Rapid MT 58 Request. acting valve.

1J 1(

f 4

1I.

CONTAINMENTATMOSPHERE CONTROL M-157 Sheet 7

s
"",Rchcf':::.':","j
'
,":,'~i 'Numb+::,.:';,:.'!,  :;:'Aitei'natiy'e,.:"

I"A'-':<..".:ll:B'::i"'::::-::::C:;,:'::;:,::;'-.:i.:'9"::

SV-157100B 2 B-3 X X 1 GL 0 Q,LT, 38, Sce Relief Rapid MT 58 Request. acting valve.

SV-157101B 2 B-3 X X 1 GL X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

- SV-157102B 2 C-3 X 1 GL X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 Request. acting valve.

SV-157103 B 2 C-3 X X 1 GL X 0 Q,LT, 38, Sce Rclicf Rapid MT 58 R~u est. acting valve.

LIQUID RADWASTE COLLECTION M-161 Sheet 1

gxc&c5(4
;.,.g ,.'Q@xx.4+5;%.D%::, ': Y, ipiiiP Cj< N

+&.OY~D'>;.RojuM':".:

,"~jgTestulg ';
<

!'.".;-.":";Ãumbcr',":;:.'l;:;.:,:  :;:;::;AIterjiatiye:,;. "'"-Rei'ii'a'de:"'-'.y,,"

g.

HV-16108A1 2 B-3 X X 3 G A Q,MT, No LT HV-16108A2 2 B-5 X X 3 G A X Q,MT, No LT

',MT, HV-16116A1 2 G-3 X X 3 G A X No LT HV-16116A2 2 H-3 X X 3 G A Q,MT, No=,

LT-

I(

1 tip C

l<

V II ip i

CONTROL STRUCTURE CHILLED WATER M-186 SIlcct 1

.".::,::;;".;Testtnj';-.:',:.:". "y'wC'"';:::"".;Rem'a'its:,'.:,

.;.', N'u'mber'.;".
,
;;:,"-'.:;:;".";. .:;"':,:Altcrnatiue:,"

0-86418 DP X CV 40 Sce Rclicf Request.

0-86439 F-5 X X 0 CV 40 Sce Relief Request.

0-86-241 X X 0 CV Sce Rclicf Closure test Request. only.

HV<8601A H-5 X G M X Q,MT No Disabled HV%8602A 3 H-5 X X G M X 0 Q,MT No Disabled HV%8603A 3 H-5 X X G M X Q,MT No Disabled HV48693A 3 A-5 X X B M 40 Sce Rclicf Request.

CONTROL STRUCTURE CHILLED WATER M-186 Sheet 2

'.,%r, wX X(y',.: C".

.'
... 05,::.'.: 1 .

@"":'g c@z'")

X CO .G.(

" O;:Z':

.n '.X9 O::+".

,',:,::,',-,'Testiiig::,",';::",:;

. g:;:::;",::;Niimb'er':".:,';,i ":,: 'Alte'rn'ative::

. egg  :

..C.."...'.',":jRe'maiks",'"'-86-118 N",

>zai4" .

D4 X X 6 C C CV Sce Relief Request.

0-86-139 F-5 X X C C CV Sce Rclicf Rcqu est.

0-86-341 C 0 CV Scc Relief Closure test Rcqu est. only.

HV<8601B H-5 X 2" G M X C Q,MT No Disabled HV8602B H-5 2 'G M X 0 Q,MT No Disabled HV%8603B H-5 X G M X C Q,MT No Disabled HVA8693B A-5 X X ' 8 B C Q 40 Scc Rclicf Request.

CONTROL STRUCTURE CHILLED WATER M-186 Sheet 3 QA?4 l'4,"

,';-'"':..":.j'::Valvei: ',"',g

'"'::A'"'::B'-';...:,::;:,:,C: """"""6'"'

SV-08621A F-8 GL 0 Q Sce Relief 1 Request.

4 1e Ch CO pC)

Jl 1

1: yC

<<4 L

CONTROL STRUCTURE CHILLED WATER M-186 Sheet 4

':,.;:+95 g.:,,;:

.:':ReIIcf:';:,

.; OY$ 'g

'"ReWI'd",;,i?

9?

SV%8621B F-8 X X GL, S See Relief Rcqu est.

I>>

4 ji l 4'I li

'jf I l' p' ~, I

REACTOR BUILDINGCHILLED WATER M-187 Shcct 2

' "oxRehcf::""'j C;.

@"':~Tcstulg':<3

.i.i-.:::'"::-;'Nu'inber",:'.":.,',,"',: ',R'etI',,d:,  :;":.;Alteriiative.',:;:,

~  :"::.v ~;:"" ~

+x; KQ%~"'i gk~

>'V-18781A1 2 H-2 X G A X 0 Q,MT, No LT.=',MT, ~@ 4+

HV-18781A2 2 G-2 X G A X 0 No LT HV-18781B I 2 D-2 X X G A X 0 Q,MT, No, LT HV-18781B2 2 C-2 X G A X 0 Q,MT, No LT" HV-18782AI 2 D-2 X X B A X 0 Q,MT, No LT HV-18782A2 2 C-2 X X B A X 0 ',MT, No LT HV-1&782BI H-2 X B A X 0 Q,MT, No LT HV-18782B2 2 G-2 X X B A X 0 Q,MT, No"'

LT HV-18791AI 2 B-2 X X G A X 0 Q,MT, 39 LT I

0 I

W lf

REACTOR BUILDINGCHILLED WATER M-187 Sheet 2 (Continued)

?..C: >a.':

>.;;>y c;.',Kyx

';S".:-

R'chef-'::"'.,:..'-',~u'est':::..:

.;;
;.;"'estNg,;;:.;
,h','<:Ni'intb'c'r",.':::~"':,'",;: i'Re'q d:,::. ,i'AItc'ini'itiyc
ii '".':,':;Rcnt8Iks?.',

sx "

HV-18791A2 2 A-2 X 3 G A X 0 'Q,MT, 39 CS LT HV-18791B1 2 F-2 X X 3 G A X 0 Q,MT, Ycs 39 CS LT HV-1879 1B2 2 E-2 X X 3 G A X 0 Q,MT, 39 CS LT HV-18792A1 2 F-2 X X 3 B A X 0 Q,MT, Ycs 39 CS LT HV-18792A2 2 F-2 X X 3 B A X 0 Q,MT; 39 CS LT HV-18792B1 2 B-2 X X 3 B 0 Q,MT, 39 CS LT HV-18792B2 2 A-2 X X 3 B A X 0 Q,MT, Yes 39 CS LT CO CO Cl CD

TRAVERSING INCORE PROBE (TIP) (No PAID)

,,Relicf,::',::,"-

';Requeati

':::",,'":::::!Numb'u'~':;.,':;:;::,;".

TIP Chan A N/A X X 3/8 BA Q,MT, No, Man Valve* LT TIP Chan A N/A X 3/8 X 0 DT No Squib Valve**

TIP Chan B N/A X X 3/8 BA X Q,MT, No Man Valve LT TIP Chan B N/A X 3/8 X 0 DT No Squib Valve TIP Chan C N/A X X 3/8 BA X Q,MT, No Man Valve LT TIP Chan C N/A X X 3/8 X 0 DT No Squib Valve TIP Chan D N/A X X 3/8 BA X -

Q,MT, No Man Valve LT TIP Chan D S N/A X X 3/8 X 0 DT No Squib Valve TIP Chan E N/A X 3/8 BA X Q,MT, No Man Valve LT

TRAVERSING INCORE PROBE (TIP) (No PEcID) (Continued) i,Rehcf':;:;".".i:;

YZj':::
.";';:: "'::;Valve'.:"::i::;::::,l!j '4 & .:Requ'est"': ',',,':::Tcstulg<:I '<.

Vl Y<

.'";.'
,;Niimber',::;:'-".-.'".; I CCz', < ",; <Altet'native)

'Cg Pj'j;?

~y'",.%,.<:&:

YNX6Y.. (+".'. 'O'%,O'4,<':

TIP Chan E Squib Valve S N/A X X'/8 0 DT No TIP Channel manual (Ball) isolation valve.

TIP Channel Squib (explosive/shear)'isolation valve.

2

PI ISI-T-100.0 Rev. 7 12/91

PA1UMETER MEASURED 1P202A Residual Heat Exempt X X X X 52 Bypass loop, bearings in Removal-A IWP- 54 main fiow path 4400 55 lubricated by pumped liquid.

1P202B Residual Heat Exempt X X X X 52 Bypass loop, bearings in Removal-B IWP- 54 main flow path 4400 55 lubricated by pumped =

liquid.

1P202C Residual Heat Exempt X X X X 52 Bypass loop, bearings in Removal-C IWP- 54 main flow path 4400 55 lubricated by pumped-liquid.

1P202D Residual Heat Exempt X X X 52 Bypass loop, bearings in Removal-D IWP- 54 main flow path 4400 55 lubricated by pumped liquid.

1P204 and High Prcssure X X X X X 44 Bypass loop, main and 1P209 Coolant Injection 48 booster pumps operate Main Ec Booster 52 in tandem-55 mcasurements taken as 63 onc pump.

I t

PARAMETER MEASURED (Continued)

('(O

""'".':!Number.."'."".',.; .;<<'..::.:;:

'Pump.'.Na'mc'.:.'.,.',:ij,'P206A Core Spray-A Exempt X X X 52 Bypass loop, bearings in IWP- 54 main flow path .

4400 55 lubricated by pumped liquid.

1P206B Core Spray-B Exempt X X X X 52 Bypass loop, bcaiings in IWP- 54 main flow path 4400 55 lubricated by pumped liquid.

1P206C Core Spray-C Exempt X X X X 52 Bypass loop, bearings in IWP- 54 main flow path 4400 55 lubricated by pumped liquid.

1P206D Core Spray-D Exempt X X X X 52 Bypass loop, bearings in IWP- 54 main flow path 4400 55 lubricated by pumped liquid.

IP208A Standby Liquid Exempt Sce Relief X X X 43 Bypass loop.

Control-A IWP- Request 43. 49 4400 52

H Ii H Il a

H

PARAMETER MEASURED (Continued)

:"'i~::: i P'ump','..:,,::,';.,'.

'::::..'N'u'mbe'r"=',,'"".:i ;,: a'i~%.',Pump game g~";.;~;

c:.g:.,

IP208B Standby Liquid Exempt Sce Relief X X X 43 Bypass loop Control-B IWP- Request 43. 49 4400 52 0P504A Emergency Service Exempt X X 52 Bearings in main fiow Water-A IWP- 54 path lubricated by 4400 56 pumped liquid inlet pressure derived from spray pond level.

OPS 04B Emcrgcncy Service Exempt X X X 52 Bearings in main flow Water-B IWP- 54 path lubricated by 4400 56 pumped liquid inlet pressure derived from spray pond Icvcl.

OP504C Emergency Service Exempt X X X X 52 Bearings in main flow Water-C IWP- 54 path lubricated by 4400 56 pumped liquid inlet prcssure derive from spray pond Icvcl.

CO CO CO CO

1,w I' il 4

'I

PARAMETER MEASURED (Continued)

Y+

'.x",.?:%'..:.

g,,(IVY')

, <;i';:.j,:::..::Pgmpg;','::."!  :.'cR,"'8" kgj,Numbe'r.".",'.:i,:"  :;".:-:',":;i':!Pub'jp',Na'm'c",'.,;,-,.'..',,",':i.

':::oi::I.':;V.

~CD'+ .

'C.Y;;

pi::iW$;'.;:

OP504D Emergency Service Exempt X X X X 52 . Bcarmgs m mam fiow Water-D IWP- 54 path lubricated by 4400 56 pumped liquid inlet pressure dcrvicd from spray pond level.

1P506A RHR Service Exempt X X X X 52 Bearings in main fiow Water-A (Unit 1) IWP- 54 path lubricated by 4400 pumped liquid. Inlet pressure dcrivcd from spray pond level.

1P506B RHR Service Exempt X X X Bearings in main fiow Water-B (Unit 1) IWP- path lubricated by 4400 pumped liquid. Inlet pressure derived from spray pond lcvcL OP162A C.S. Chilled Water Exempt Sce Relief Request Number 50. 50 Loop Circ Pump-A IWP-4400

PARAMETER MEASURED (Continued)

~@'.,',;:.<:::N'umb'c'j,'i.-"":. i',";:",:,:::ll;:.'Piim'p'i%a'mc':.,,"',:a,:,',,

OP162B C.S. Chilled Water Exempt Scc Rclicf Rcqucst Number 50. 50 Loop Cire. Pump-B IWP-4400 OP171A Emergency Excmp Scc Rclicf Request Number 50. 50 Condenser Water IWP-Cir. Pump-A 4400 OP171B Emcrgcncy Exempt See Relief Request Number 50. 50 Condcnscr Water IWP-Cir. PUmp-B 4400 OPS 14A Diesel Oil Transfer Exempt Scc Rclicf Request Number 47. 47 Pump A IWP-4400 OP514B Diesel Oil Transfer Exempt See Relief Request Number 47. 47 '-

Pump B IWP-4400 OP514C Diesel Oil Transfer Exempt Sec Relief Request Number 47. 47 Pump C IWP-4400

PARAMETER MEASURED (Continued)

~'.,".<';Pump~~~

,::.,:,-:,,':.::.Numb cl'-@",, :.;.;-'.j." Puijjp','.5a'm'e"";:""".',:':'.;:;

OP514D Diesel Oil Transfer Exempt See Rclicf Request Number 47. 47 Pump D IWP-

'4400 OP514E Dicscl Oil Transfer Exempt Relief Request Number 47. 47 Pump E 4400'ce IWP-See Relief Request 48.

Sce Rclicf Request 54.

Sce Relief Request 49.

Monthly test pcr Technical Specifications.

CD CO p

ISI-T-100.0 Rev. 7 1RRT-1 12/91

ISI-T-100.0 RELIEF RE UEST ER 1 System: Reactor Building Closed Cooling Water P&ID: M-113 Valves: HV-11313 HV-11314 HV-11345 HV-11346 Category: A Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: These valves are in the cooling water supply and return lines for the reactor recirculation pump bearing and seal coolers. Cycling of these valves during power operation would interrupt this cooling water flow, possibly causing pump bearing damage or seal failure.

Alternative Testing: Exercise valves during Cold Shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR1-1 12/91

ISI-T-100.0 RELIEF RE T NUMBER 2 System: Containment Instrument Gas P&ID: M-126 Valves: 1-26-070 1-26-072 1-26-074 1-26-152 1-26-154 1-26-164 Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: These check valves serve the containment isolation function inside containment and are not equipped with remote position indicators.

Downstream of the valves (inside containment) there are no pressure measurement devices or other means of remotely verifying valve position.

The only practical method of closure testing involves pressurizing the downstream side and measuring pressures with temporary instrumentation.

With the inerted containment, such testing can only be performed during a major outage which requires containment purging. This testing, which requires significant effort in the installation and removal of temporary equipment in the high radiation area of the containment drywell, is already performed during Category A leak rate testing.

Two valves, 1-26-152 and 1-26-154, serve a safety function on opening as well as their containment isolation function. The open test cannot be performed as there would be no positive indication (flow measurements) of function. Operation of the equipment serviced by these valves (ADS function of the safety/relief valves) will not verify their proper opening since the accumulators at the SRV operators provide capacity for several lifts.

Rev. 7 1RR2-1 12/91

ISI-T-100.0 RELIEF 'RE T ER 2 (Cont'd.)

Performing continued lifts in an attempt to verify check valve opening will increase the potential for SRV leakage or failure to reseat, will impact proper maintenance of reactor pressure control, and has the potential for degradation of the ADS function.

Alternative Testing: Valve closure is demonstrated by completion of leak rate testing performed once per 24 months. Commencing with the first refueling outage, verification of the opening capability of valves 1-26-152 and 1 154 will also be performed at that time with an air pressure applied through the outboard test valves (1-26-021, 1-26-03 1), opening the inboard test valves (1-26-155, 1-26-153), and observing essentially unrestricted flow.

Rev. 7 1RR2-2 12/91

C I>> [

li

ISI-T-100.0 RELIEF RE 4T System: Containment Instrument Gas P&ID: M-126 Valves: SV-12651 Category: A Class: ,2 Function: Containment Isolation Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: Closing this valve interrupts instrument gas supply to several important valves inside containment such as the Safety/Relief Valves (non-ADS function) and the MSIVs, This could compromise the ability of the SRV's to operate in the relief mode which, while not an ECCS function, is important to safety. Loss of instrument gas could also cause the MSIVs to close, resulting in a severe reactor transient.

Alternative Testing: Exercise valve during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR3-1 12/91

ISI-T-100.0 RELIEF RF. UEST NUMBER 4 I

il I

)

System: Containment Instrument Gas P&ID: M-126 Valves: SV-12654A SV-12654B Category:

Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: Closing these valves will interrupt instrument gas supply to the ADS solenoids of the Safety/Relief Valves, compromising their ability to provide the opening motive force for the ADS valves in support of the long-term cooling ECCS function.

Alternative Testing: Exercise valves during cold shutdown (no more frequently than once per 92 days).

Rev. 7 1RR4-1 12/91

g *I li iI 1;

ISI-T-100.0 RELIEF R ER System: MSIV-Leakage Control P&ID: M-139

'.,i~ii:;;:Catego'ry,:.:,'.:",.::.::::;.:.',; i,::;::;;;:::;:::.:,".:::::;:Chss::,"".',;'i":-:;:.:';::::

HV-139F001 B, F, K, P HV-139F002 B, F, K, P B Function: Containment Isolation; System Initiation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: The MSIV-LCS inboard bleed lines are directly connected to the main steam lines at the outboard MSIV. During power operations, these lines are pressurized with main steam up to the first isolation valve (HV-139F001 B,F,K,P). Double valve isolation is provided by HV-139F002 B,F,K,P. Opening any of these valves during power operations willleave only one barrier against the release of main steam to occupied plant areas through the system piping. Maintenance of double valve isolation is desired for personnel safety considerations and for prevention of inadvertent leakage paths from the main steam lines.

Alternative Testing: Exercise during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RRS-1 12/91

iF ISI-T-100.0 RELIEF RE T ER System: MSIV-Leakage Control P&ID: M-139 Valves: HV-139F006 HV-139F 007 HV-139F008 HV-139F009 Category: B Class:

Function: System Initiation Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: The MSIV-LCS outboard bleed and blowdown lines are directly connected to the main steam system at the steam line drain. During power operations these lines are pressurized with main steam up to the first isolation valve (HV-139F006, HV-139F008), Double valve isolation is provided by HV-139F007 and HV-139F009. Opening any of these valves will leave only one barrier against the release of main steam to occupied plant areas through system piping. Maintenance of double valve isolation is desired for personnel safety considerations and for prevention of inadvertent leakage paths from the main steam lines.

Alternative Testing: Exercise during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR6-1 12/91

ISI-T-100.0 RELIEF R ER 7 System: Nuclear Boiler P&ID: M-141 Valves:. 141F010 A,B Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves closed once per 92 days.

Basis for Relief: These check valves remain open maintaining the flowpath to the vessel whenever the feedwater/condensate,'PCI or RCIC systems are providing makeup to the vessel or when Reactor Water Cleanup is returning flow to the vessel. Due to the necessity of maintaining this flowpath in virtually all modes of operation, closure testing is only practical during extended outages such as refuelings during which these systems are shutdown.

Also, plant design does not provide a practical means of demonstrating closure other than by upstream pressurization performed during leak rate testing. This testing involves significant effort for installation of temporary equipment, and requires complete purging of the inerted reactor containment.

Alternative Testing: Proper valve closure will be verified in by completion of leak rate testing performed once per 24 months.

Rev. 7 1RR7-1 12/91

ISI-T-100.0 RELIEF R ER System: Nuclear Boiler f

P&ID: M-141 Valves; PSV-14137 A,B,C,D,E,F,G,H,J,K,L,M,N,P,R,S Category:

Class: '3 Function: SRV Discharge Pipe Vacuum Breaker Impractical Test Requirement: Setpoint test per PTC 25.3-1976.

Basis for Relief: The ASME performance test code does not provide the most practical method for testing these vacuum relief devices.

Alternative Testing: Commencing with the first refueling outage, the setpoint will be checked once per refueling outage by pouring water into the valve inlet and measuring the height of water column necessary to activate the valve.

Rev. 7 1RR8-1 12/91

I ISI-T-100.0 RELIEF R T NUMBER System: General P&ID: General Valves: General Category: General Class: General Function: As applicable to specific valves.

Impractical Test Requirement; Paragraphs IWV-3417(b) and IWV-3523 of Section XI require that when corrective action is required as a result of tests made during cold shutdown, the condition shall be corrected before startup.

Basis for Relief: For those valves specified therein, the Limiting Conditions for Operation presently contained within the Susquehanna Steam Electric Station Technical Specifications provide the control by which valves and/or systems are declared inoperable. They also control entry into the various operational conditions. Further controls are not necessary for these valves. Valves which are not under the control of the Technical Specifications will be declared inoperable should they fail ISI testing.

Alternative Testing: The requirements contained within Susquehanna SES Technical Specifications will control plant operations and testing with regard to out-of-service valves. For valves which are not addressed in the Technical Specifications, any failures will cause the affected valve(s) to be declared inoperable and corrective action to be initiated as appropriate.

Rev. 7 1RR9-1 12/91

I c ISI-T-100.0 RELIEF R ER 1 System: Nuclear Boiler P&ID: M-141 Valves: PSV-141F013 G,J,K,L,M,N Category: B,C Class:

Function: ADS Valve, Code Safety/Relief Valve Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: The six safety relief valves assigned to the ADS system perform an essential safety function when operated by the pneumatic actuator with gas supplied through the ADS solenoid valves. Operation of these valves is not practical during power operations because this action will vent main steam to the suppression pool, inducing a transient condition and increasing the potentiality for an open failure of a safety relief valve.

Also, no stroke timing is practical as these are pneumatic assisted SRVs.

Since "position indication" of the SRVs is provided by acoustic monitors attached to the valve discharge piping, exercising during cold shutdown cannot be accomplished because of lack of steam flow (and attendant noise).

Alternative Testing: The ADS valves willbe exercised once per 18 months in accordance with Technical Specification 4.5.1.d.2.b, which provides manual opening of each ADS valve with reactor dome pressure greater than or equal to 100 psig and observing either control valve or bypass valve response or corresponding change in measured steam flow. No stroke timing will be done.

Rev. 7 1RR10-1 12/91

ISI-T-100.0 I

RELTEF R ER 11 Boiler P&ID'uclear System:

M-141 Valves: HV-141F022 A,B,C,D HV-141F028 A,B,C,D Category: A Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: During full power operation, it is impractical to full stroke cycle these valves, since the interruption in steam flow would induce a reactor pressure transient with increased probability of reactor scram, main steam line isolation and SRV actuation. Trending of valve stroke times is not necessary due to Technical Specification limits on minimum as well as maximum allowable stroke times with a tolerance of 2 seconds.

Alternative Testing: Full stroke testing will be performed in Operational Condition 1, 2, or 3 when power level is low enough to prevent the above mentioned transients (no more frequently than once per 92 days). No reduction from high power levels will be made specifically to accomplish this testing. No trending of valve stroke times will be done.

Rev. 7 1RR11-1 12/91

4 ' << I

~

p

ISI-T-100.0 RELIEF R T NUMBER 12 System: Nuclear Boiler P&ID: , M-141 Valves: HV-141F032 A,B Category: A, C (HV-141F032B only)

Class:

Function: Containment isolation; HPCI flowpath (HV-141F032B only).

Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: a. These check valves remain open maintaining the flowpath to the vessel whenever the feedwater/ condensate systems are providing makeup to the vessel. Interruption of the feedwater flowpath by motor operator closure of these valves can only be practically accomplished during cold shutdowns.

b. No practical means other than upstream pressurization similar to leak rate testing is available to demonstrate valve closure of HV-141F032B as a check valve.

Alternative Testing: a. Cycle valves shut using stop-check motor operators during cold shutdowns (no more frequent than once per 92 days).

b. Closure testing of HV-141F032B as a check valve willbe demonstrated by completion of leak rate testing to be performed once per 24 months.

Rev. 7 1RR12-1 . 12/91

ISI-T-100.0 RELIEF'R ER 1 System: Fuel Pool Cooling and Clean-Up P&ID: M-153 Valves: 1-53-071 A,B Category:

Class: Non-Code safety function Function: Admit flow to fuel storage pool.

Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: In an alternative flowpath to the fuel storage pool, exercising of these valves utilizing flow can only be accomplished utilizing ESW or RHR water. Use of ESW would introduce "raw" water from the ESSW spray pond, undesirable for chemistry and fuel integrity considerations. While use of the RHR flowpath is possible, the difficulty of operating the RHR system in an abnormal lineup for supplying the fuel pool creates a dynamic control situation that is best minimized.

Alternative Testing: Verify valve operability by a pneumatic open flow path test during periodic pressure test. A pneumatic open flow path test (SE-135-301) is performed once per Inspection Period (as specified by ASME Code Section XI paragraph IWD-2400).

Rev. 7 1RR13-1 12/91

ISI-T-100.0 RELlEF R ER 14 System: Reactor Recirculation P&ID: M-143 Valves: XV-143F017 A,B Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: Closure testing of these excess flow check valves involves depressurization of the CRD system side of the valves and verification that the valve will close and stop excess flow. Such actions require interruption of seal water to the recirculation pumps, which creates a potential for pump seal damage;, disruption of CRD Hydraulic System flow; and installation of temporary equipment.

Alternative Testing: Closure testing will be demonstrated by completion of leak rate testing to be performed once per 24 months.

Rev. 7 1RR14-1 12/91

I'l s','

J

ISI-T-100.0 RELIEF R ER 15 System: Reactor Recirculation P&ID: M-143 Valves: 143F013 A,B Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: These simple check valves serve as containment isolation valves inside containment. The valves are not equipped with remote indication and there is no pressure indication downstream of the valves. For these valves, closure testing is only practical through pressurization downstream of the valve with the upstream piping vented, and verification of the absence of flow upstream. Interruption of the CRD flow (seal purge) during Reactor Recirculation Pump operation to perform this testing could result in seal damage. This type of testing can only be performed during a period when the containment is accessible. The deinerting of the containment will only be performed during major outages and the testing will be performed during Category A leak rate testing.

Alternative Testing: Valve closure is demonstrated by completion of leak rate testing performed once per 24 months.

Rev. 7 1RR15-1 12/91

I I'

ISI-T-100.0 RELTEF R ER 1 System: Reactor Recirculation P&ID: M-143 Valves: HV-143F031 A,B Category: B Class:

Function: Reactor Recirculation Pump Discharge Isolation, LPCI flowpath.

Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: The recirculation pump discharge isolation valves are in the main flowpath of the reactor recirculation system which is necessary to maintain reactivity control of the reactor. Cycling of these valves during power operations would interrupt the driving core flow, possibly resulting in severe changes in core power level.

Alternative Testing: Technical Specification 4.4.1.1.1 provides for and controls the exercising of these valves prior to exceeding 25% power during each startup.

A Rev. 7 1RR16-1 12/91

P

x. f 1

q' I

ISI-T-100.0 l RELIEF RE T ER 17 System: Control Rod Drive P&ID: M-147

~Valv ~ate ~oOrr 147114-001 through 147114-185 C 147115-001 through 147115-185 C XV-147126-001 through XV-147126-185 B XV-147127-001 through XV-147127-185 B 147138-001 through 147138-185 C Class:

Function: Control Rod Scram Impractical Test Requirement: Exercise valves once per 92 days and measure stroke times.

(per IWV-3411 and IWV-3521)

Basis for Relief: These valves located on the h draulic control units for the 185 contro 1 rod drives, perform the active safety function of rapidly inserting the control rods into the reactor core, upon receipt of a reactor scram signal from the reactor protection system. Exercising these valves quarterly during power operations could result in the rapid insertion of one or more control rods more frequently than desired. Where testing could result in the rapid insertion of control rods, thereby causing rapid reactivity transients and wear of the control rod drive mechanisms, the control rod scram test frequency identified in the Plant Technical Specifications will be utilized as the valve testing frequency.

Normal control rod motion has been shown to be an indicator that the associated cooling water header check valve (147138 -001 through -185) moves to its safety position (closed). Normal control rod motion may not occur, if this check valve were to fail in the open position. An additional positive'est of,the closure of this valve can be provided by venting of the cooling water header during Primary Containment Integrated Leakage Testing, conducted per Technical Specification 4.6.1.2.

Normal control rod motion does not serve as an indicator that any scram discharge header check valve (147114 -001 through -185) moves to its Rev. 7 1RR17-1 12/91

I

~ J

ISI-T-100.0 RELIEF RE ER 17 (Cont'd.)

safety position (open), however. Since this check valve is moved to its open position only by scram exhaust flow, a positive test of the opening of the valve can only be provided by the periodic scram testing and control rod insertion timing specified by Technical Specification 4.1.3.2.

Verification that any charging water header check valve (147511 -001 through -185) moves to its safety position (closed), requires that the control rod drive pumps be stopped to depressurize the charging water header. This test cannot be performed during power operations because stopping the pumps would result in loss of cooling water to all control rod drive mechanisms and seal damage could result. This test cannot be performed during each cold shutdown because the control rod drive pumps supply seal water to the reactor recirculation pumps and one of the recirculation pumps might be kept running, thus continuing to need its seal water supply. The HCU accumulator pressure decay test, specified by Technical Specification 4.1.3.5.b.2, provides verification of the closure of its charging water header check valve.

The scram inlet valves (XV-147126 -001 through -185) and the scram exhaust valves (XV-147127-001 through -185) are air operated valves that full-stroke in milliseconds and are not equipped with position indication, thereby rendering measurement of their full-stroke times impractical.

Verifying that the control rod associated with each pair of these valves meets the periodic scram testing rod insertion time limits, specified by Technical Specification 4.1.3.2, is an acceptable alternate method of detecting degradation of these valves. Since these measurements of control rod insertion times are subject to the conservative limitations of Technical Specification 4.1.3.3, and because these measurements cannot be meaningfully correlated with the full-stroke times of the scram inlet and exhaust valves, trending of these scrams time measurements in any manner comparable to that of valve stroke times is both impractical and unnecessary.

N These bases for relief from applicable code testing requirements for these individual control rod scram valves are intended to conform to those provided as guidance by NRC Generic Letter 89-04 (Position ¹7).

Rev. 7 1RR17-2 12/91

5 ISI-T-100.0 I

RELIEF RE ER 17 (Cont'd.)

Alternative Testing: Proper functioning of the scram discharge header check valves (147114-XXX), of the scram inlet valves (XV-147126-XXX), and of the scram exhaust valves (XV-147127-XXX) will be verified by periodic scram testing and control rod insertion timing, with reactor pressure > 950 psig, conducted per Technical Specification 4.1.3.2 and Technical Specification 4.1.3.3:

a) For all control rods prior to thermal power exceeding 40% of rated power, following core alternations or after a reactor shutdown that is greater than 120 days.

b) For specifically affected individual control rods, following maintenance or modification to the control rod or control rod drive system, which could affect the scram insertion time of those specific control rods.

c) For at least 10% of the control rods, on a rotating basis, at least once per 120 days of power operation.

Proper closure of the charging water header check valves (147115-XXX) will be verified by the demonstration that each individual accumulator check valve maintains its associated accumulator pressure above the alarm set point for >10 minutes, with no CRD pump operating, at least once per 18 months, conducted per Technical Specification 4.1.3.5.b.2.

Proper closure of the cooling water header check valves (147138-XXX) will be verified by venting of the cooling water header during Primary Containment Integrated Leakage Testing, at least once per 30 to 50 month interval, conducted per Technical Specification 4.6.1.2.

Rev. 7 1RR17-3 12/91

II

'I k

ISI-T-100.0 RELIEF R ER 1 System: Standby Liquid Control P&ID: M-148 Valves: HV-148F006 Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: To verify proper opening of this stop-check valve, it is necessary to pass fluid through the valve. This action would result in an injection into the reactor vessel and would require actuation of an explosive valve. Both actions are undesirable during power operations. Closure testing as a motor-operated stop-check valve during power operations presents the danger of having the disc stick in the closed position, blocking the only SLC injection flowpath, with no means of detecting the failure.

Alternative Testing: The proper functioning of the Standby Liquid Control System injection flowpath, including opening of HV-148F006, will be demonstrated once per,18 months in accordance with Technical Specification Section 4.1.5.d.

Closure testing of the valve by motor operator willbe performed just prior to the injection testing once per 18 months.

Rev, 7 1RR18-1 12/91

ISI-T-100.0 ELIEF R ER 1 System: Standby Liquid Control P&ID: M-148 Valves: 148F007 Category: A,C Class:

Function: ~

Containment. Isolation Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: To verify proper opening of this check valve, it is necessary to pass fluid through the valve. This action would result in an injection into the vessel and would require actuation of an explosive valve, both undesirable during power operations. 'losure testing is only practical by pressurizing downstream of the valve (the upstream side being vented) and verifying absence of flow in the upstream side. This requires installation of temporary equipment and access to the containment which is inerted during power operation.

Alternative Testing: The proper functioning of the Standby Liquid Control System injection flowpath, including opening of 148F007, will be demonstrated once per 18 months in accordance with Technical Specification Section 4.1.5.d.

Valve closure is demonstrated by completion of leak rate testing performed once per 24 months. See Relief Request Number 18.

Rev. 7 1RR19-1 12/91

l' ISI-T-100.0 RELIEF R ER 20 RCIC HV-149F007 RCIC M-149 HV-149F031 RCIC M-149 HV-149F059 RCIC M-149 HV-149F0 84 M-151 HV-151F004A,B,C,D M-151 HV-151F007A,B M-151 HV-151F022 Core Spray M-152 HV-152F001A,B Core Spray M-152 HV-152F031A,B HPCI M-155 HV-155 F002 HPCI M-155 HV-155F012 HPCI M-155 HV-155F042 HPCI M-155 HV-155F066 HPCI M-155 HV-'155F 079 Containment Atmosphere M-157 HV-15766 Control Category:

Function:- Containment Isolation Impractical Test Requirement: Leak test gate valve with pressure differential in same direction as safety function.

Basis for Relief: These valves are configured such that there is no practical means of pressurizing in the direction of safety function pack of proper isolation valves, test connections, etc.).

Rev. 7 1RR20-1 12/91

p I

ISI-T-100.0 RELIEF RE ER 2 (Cont'd.)

Pressurization in the direction of safety function would require actions such as pressurizing the containment (equivalent to an ILRT) or precisely controlling the entire RCS at the valve test pressure.

Alternative Testing: Leak test each valve in the reverse direction. Penetration willbe subjected to test pressures in the correct direction during containment integrated leak rate tests.

Rev.

1RR20-2 7'2/91

ISI-T-100.0 RELIEF RE UF><' NUMBER 21 System: Reactor Core Isolation Cooling PAID: M-149 Valves: 149F028, 149F040, 149F021 Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: These check valves are not equipped with position indication and system design does not provide any practical method of verifying closure other than pressurization similar to leak rate testing. Such testing requires installation of temporary equipment which is impractical on a quarterly basis, and it would render the RCIC system inoperable during the testing period. While RCIC is not an ECCS system, it is important to safety and can provide an additional margin for prevention or mitigation of reactor transients. Normally, testing of this type is accomplished by required containment local leak rate testing in accordance with 10CFR50, Appendix J. More frequent performance represents an unnecessary burden on the licensee.

Alternative Testing: Demonstrate closure by completion of leak rate testing performed once per 24 months.

Rev. 7 1RR21-1 12/91

ISI-T-100.0 RELIEF RE UEST NIJNIBE<R 22 System: Reactor Core Isolation Cooling P&ID: M-149 Valves: 149F063, 149F064 Category:

Class:

Function: Vacuum Breaker Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: These vacuum breakers installed on the RCIC turbine exhaust line are not provided with position indication equipment nor is there pressure indication installed that would provide positive verification of valve operation. A practical method of testing involves supplying low pressure air upstream of the valve and verifying that flow can be detected downstream of the valve. This test method involves installation of temporary equipment and is not practical except during major outages, and it would render the RCIC system inoperable during the testing period.

While RCIC is not an ECCS system, it is important to safety and can provide an additional margin for prevention or mitigation of reactor transients. More frequent performance represents an unnecessary burden on the licensee.

Alternative Testing: Commencing with the first refueling outage, verify opening once per 24 months in conjunction with leak rate testing.

Rev. 7 1RR22-1 12/91

0 ISI-T-100.0 RELIEF RE UEST NVMHER 23 System: Residual Heat Removal P&ID: M-151 Sh. 2 Valves: HV-151F008, HV-151F009 Category:

Class:

t Function: Containment Isolation (Shutdown Cooling), C Impractical Test Requirement: Exercise valves once per 92 days, v

E P Basis for Relief: These normally closed isolation valves are only required to open when bringing the unit to a cold shutdown condition, providing the flowpath for the shutdown cooling mode of RHR. In accordance with guidance presented in IE Information Notice 84-74, draft R.G. 901-4, and previous NRC concerns regarding intersystem LOCAs, cycling these valves every 92 days during power operation increases the probability of exposing the downstream low pressure piping to reactor coolant pressure (since only one valve would have to be ruptured or failed open to expose the low pressure system to reactor coolant pressure). During reactor operations above approximately 100 psig, interlocks inhibit cycling of these valves for the express purpose of protecting low pressure piping.

Alternative Testing: Exercise valves during cold shutdown (no more frequently than once per 92 days).

Rev. 7 lRR23-1 12/91

I

,I I IS a

I v

ISI-T-100.0 RELIEF R ER 24

';.;Class;::i.:::':;: .:::::.::'::,:.::,,:Cafeg'o'iy'.,:::,':,::,.:

M-151 151FO90A M-151 151FO90B Core Spray M-152 152FO29A Core Spray "

M-152 152FO29B Core Spray M-152 152FO30A Core Spray M-152 152FO30B HPCI M-155 155012 M-186 086241 M-186 086341 Function: Prevent reverse flow out through keepfill line Impractical Test Requirement: Exercise valves to their closed positions once per 92 days (Per IWV-3521).

Basis For Relief: These check valves, located in keepfill lines for the RHR, Core Spray, and HPCI Systems provide Condensate Transfer System water flow into their respective headers, while preventing flow of process water in the reverse direction, during operation of the respective ECCS System. In the RHR and HPCI Systems, test connections exist between the two tandem check valves existing in each line, while in the Core Spray System, a single test connection exists upstream of both check valves, which are located very close together. These configurations allow individual testing of the downstream check valve in the RHR and HPCI Systems, but support only dual testing of each pair of Core Spray System check valves in combination. Using these test connections in RHR, Core Spray, and HPCI to monitor essential restriction of reverse flow involves collecting radioactively contaminated seepage while the process system is pressurized, as during flow testing. This creates the potential for spills and spread of contamination. The increase in potential for water hammer in these systems due to isolation of keepfill lines during testing, the increase in personnel radiation exposure required to perform this testing during Rev. 7 1RR24-1 12/91

1J 1 'I

ISI-T-100.0 RELIEF RK T ER 24 (Cont'd.)

plant operation, and the increase in potential for contamination of personnel and equipment through this testing justify reduced frequency. The stainless steel construction of each check valve and the series configuration of each pair of check valves reduce the probability of failure to restrict reverse flow through any keepfill line.

The relatively small size of each keepfill line minimizes the impact of any such failure. The combination of these mitigating factors warrant reduction in testing frequency.

The single check valves located in the keepfill lines for the ESW System provide Service Water System flow into their respective headers, while preventing flow of process water in the reverse direction, during operation of ESW System. Test connections upstream of each check valve support testing of its reverse flow individually. Using these test connections in ESW to monitor essential restriction of reverse flow involves collecting raw service water seepage, which has the potential to chemically contaminate and degrade the operation of the plant Liquid Radwaste System. The stainless steel construction of each check valve reduces the probability of failure to restrict reverse flow through any keepfill line. The relatively small size of each keepfill line minimizes the impact of any such failure. The combination of these mitigating factors warrant reduction in testing frequency.

I Alternative Testing: Demonstrate closure of each'check valve in the keepfill lines of the RHR and HPCI Systems by monitoring the essential restriction of its reverse flow, through its upstream test connection, once per refueling outage while the process system is pressurized, as during flow testing.

Demonstrate closure of at least one of the two check valves in each pair in the keepfill lines of the Core Spray System by monitoring the essential restriction of their reverse flow, through their upstream test connections, once per refueling outage while the process system is pressurized, as during flow testing.

Demonstrate closure of each check valve in the keepfill lines of the ESW System by monitoring the essential restriction of their reverse flow, through their upstream test connections, once per 18 months (J3 months) while the process system is pressurized, as during flow testing.

Rev. 7 1RR24-2 12/91

e ISI-T-100.0 RELIEF RE T ER 2 Relief Request Deleted.

This Page Intentionally Left 8/ank.

Rev. 7 1RR25-1 12/91

ISI-T-100.0 RELIEF RE UEST NUMBER 2 System: Residual Heat Removal P&ID: M-151 Sh. 1 and Sh. 2 Qa~eo~r HV-151F015A A HV-151F015B A HV-151F022 A HV-151F 023 A HV-151FOSOA A,C HV-151F050B A,C HV-151F122A A HV-151F122B A Class:

Function: Containment Isolation

~

Impractical Test Requirement: Exercise valves once per 92 days, ~

~ ~

Basis for Relief: These normall closed isol at io n va lves serve as the pressure isolation between RHR system piping and reactor coolant pressure. In accordance with guidance presented in IE Information Notice 84-74, draft R.G. 901-4, and previous NRC concerns regarding intersystem LOCAs, cycling these valves every 92 days during power operation increases the probability of exposing the downstream low pressure piping to reactor coolant pressure (since only one valve would have to be ruptured or stuck open to expose the low pressure system to reactor coolant pressure). Maintenance history on these valves has shown that excessive cycling at pressure will reduce the leak tightness of the valves. In addition, failure of these valves during testing to positively re-seat could cause loss of RHR system function.

Alternative Testing: Exercise valves during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR26-1 12/91

ISI-T-100.0 RELIEF R ER 27 System: Emergency Service Water P&ID: M-111 Sheets 1,3 Valves: 0-11-033 . 0-11-037 0-11-513 0-11-034 0-11-038 0-11-514 0-11-035 0-11-039 0-11-036 0-11-040 Category:

Class:

Function: Diesel generator cooling flowpath alignment.

Impractical Test Requirement: Exercise valves once per 92 days and Valve Internals Integrity Verification of NRC IEB 83-03.

Basis for Relief: Individual pressure or flow indication is not provided on ESW cooling lines to the diesel generators, nor is position indication installed, This configuration provides no direct evidence of valve position during system operation. A level of assurance of proper valve operation is provided by observation of appropriate system flows during ESW pump testing and adequate cooling during diesel generator operation.

Due to the sharing of diesel generators between two units, removal of a diesel generator from service to accomplish the alternative inspections will normally occur with one unit in operation.

Minimization of these inspections is indicated.

Alternative Testing: Verify proper valve functioning by valve disassembly. Commencing with the first refueling outage, two valves will be inspected at least once per 18 months (+ 3 months), such that all valves are inspected once per 72 months (+ 6 months).

Rev. 7 1RR27-1 12/91

ISI-T-100.0 RELTEI RK V T NUMBER 28 System: High Pressure Coolant Injection P&ID': M-155 Valves: 155F049, 155F046 Category: A,C Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valve closed once per 92 days.

Basis for Relief: This valve is not equipped with position indication. Its configuration with an open discharge'into the suppression pool prevents usage of reverse flow to demonstrate closure. No practical method exists to perform closure testing other than the downstream pressurization of leak rate testing. Such testing requires installation of temporary equipment and closure of valves which renders the system inoperable.

Alternative Testing: Demonstrate closure once per 24 months by completion of leak rate testing.

Rev. 7 1RR28-1 12/91

I' t hl l l

ISI-T-100.0 RELIEF RE T NUMBER 2 System: High Pressure Coolant Injection M-155 P&ID'alve:

HV-155F006 Category:

Class:

Function: Containment Isolation, HPCI Injection Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: This valve is in the HPCI'injection flowpath. 'The interlocks on this valve prevent its being open unless the Steam Admission and Turbine Stop Valves are open. This. is only possible during pump flow testing.

Cycling this valve during normal plant operation or,HPCI testing may lead to HPCI injection into the vessel. This would affect reactor operations and introduce a thermal transient in the vessel nozzle.

Alternative Testing: Exercise valve during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR29-1 12/91

ISI-T-100.0 ELIEF R ER System: General P&ID: General Valves: All valves specified as tested on a cold shutdown or refueling frequency. ~

Category: As applicable Class: As applicable Function: As applicable Impractical Test Requirement: Paragraph IWV-3417(a) of Section XI requires that should an unacceptable increase in stroke time be observed, the valve test frequency shall be increased to once per month until corrective action is taken.

Basis for Relief: Valves are tested on a cold shutdown or refueling frequency because there is a defined basis for exemption from quarterly testing frequency during power operation (e.g., the plant is put into an unsafe condition, system design does not permit testing). This same reasoning would, therefore, provide the basis for exemption from the monthly testing as well:

Alternative Testing: The testing frequency will remain unchanged. The requirements contained in the Susquehanna Steam Electric Station Technical Specifications will control plant operations with regard to out-of-service valves.

Rev. 7 1RR30-1 12/91

(

4

ISI-T-100.0 RELIEF RE T System: High Pressure Coolant Injection P&ID: M-155 Valves: 155F 045 Category:

Class:

Function: Backflow Prevention Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: To verify proper opening of this valve, it is necessary to initiate HPCI flow while taking suction from the suppression pool. Since the water quality in the suppression pool is not maintained at reactor coolant standards, it is not advisable to initiate this flow at any time during normal operations. The resulting contamination of the HPCI system from such flow testing would affect the condensate storage tank purity and ultimately affect the chemistry control of the reactor coolant system. There exists no other practical method of verifying proper valve operation.

Alternative Testing: Verify operability by inspection during valve disassembly. The valve will be disassembled at least once every other refueling outage on an alternating basis.

Rev, 7 1RR31-1 12/91

ISI-T-100.0 1 V K 'I RELIEF R ER 2 System: High Pressure Coolant Injection P&ID: M-155 Valves: 155F 019 Category:

Class:

Function: Backflow Prevention Impractical Test Requirement: Exercise valve closed once per 92 days.

Basis for Relief: This check valve in the HPCI pump suction line is not installed in a configuration permitting positive verification of valve closure. As stated in Relief Request Number 31, alignment of the HPCI pump to the suppression pool is not desirable. Attempting to verify closure during leak rate testing of 155F045 will not provide positive verification, since there is no appropriate pressure instrumentation provided on the CST side of 155F019, and level changes in the CST would not be readily detected due to the large tank volume.

Alternative Testing: Verify operability by inspection during valve disassembly. The valve will be disassembled at least once every other refueling outage on an alternating basis.

Rev. 7 1RR32-1 12/91

ISI-T-100.0 RELIEF RE T NUMBER 33 Relief Request Deleted.

This Page Intentionally Left Blank.

Rev. 7 1RR33-1 12/91

f p

A h

ISI-T-100.0 RELIEF RE T ER 34 System: High Pressure Coolant Injection P&ID: M-155 Valves: 155F076, 155F077 Category:

Class:

Function: Vacuum Breaker Impractical Test Requirement: Exercise valve once per 92 days.

Basis for Relief: These vacuum breakers installed on the HPCI turbine exhaust line are not provided with position indication equipment nor is there pressure indication installed that would provide positive verification of valve operation. A practical method of testing involves supplying low pressure air upstream of the valves and verifying that flow can be detected downstream of the valve. This test method involves installation of temporary equipment and is not practical except during major outages. Its implementation would also require temporary removal of the HPCI System from service.

Alternative Testing: Commencing with the first refueling outage, verify opening once per 24 months in conjunction with leak rate testing.

h Rev. 7 1RR34-1 12/91

ISI-T-100.0 RELIEF RE UEST NUMBER 35 System: General P&ID: General Valves: All containment isolation valves.

Category: A Class: As applicable to specific valves.

Function: Primary Containment Isolation Impractical Test Requirement: Additional corrective actions specified for valves 6 inches and larger, that exhibit increases in leakage rate, per IWV-3427(b).

Basis for Relief: Containment leakage rate testing is governed by 10CFR50 Appendix J and Susquehanna SES Technical Specification 3/4.6.1.2.

Compliance with these requirementsis described .in FSAR Section 6.2.6 and in FSAR Tables 6.2.-.19 through 6.2-22. The additional corrective actions specified by ASME code Section XI, paragraph IWV-3427(b) are not generally effective. Their usefulness does not justify the burden of complying'ith this requirement.

This basis for relief from all requirements imposed by IWV-3427(b) is intended to comply with that provided as guidance by NRC Generic Letter 89-04 (Position ¹10).

Alternative Testing: Primary Containment isolation valve leak testing (with the exception of identified pressure isolation function) will be performed in accordance with FSAR Section 6.2.6 and FSAR Tables 6.2-19 through 6.2-22. Evaluation of containment isolation valve leak test results will be conducted in accordance with the requirements of 10CFR50 Appendix I and Susquehanna SES Technical Specification 3/4.6.1.2.

Leakage rate measurements shall be compared with previous measurements and with the permissible valve leakage rates specified by the Superintendent of Plant for Susquehanna SES.

Rev. 7 1RR35-1 12/91

ISI-T-100.0 RE T NUMBER 36

'ELIEF This Page Intentionally Left Blank.

Rev. 7 1RR36-1 12/91

V l

ISI-T-100.0 RELIEF RK UFST ER 37 System: Containment Atmosphere Control P&ID: M-157 Sht. 1 Valves: HV-15703 HV-15713 HV-15723 HV-15704 HV-15714 HV-15724 HV-15705 HV-15721 HV-15725 HV-15711 HV-15722 Category: A Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valve once per 92 days.

~ ~

Basis for Relief:it These normally closed containment isolation valves on the containment purge inlet and exhaust lines are not opened during power operations except during startup for inerting purposes and during shutdown procedure to de-inert. It is not good practice to cycle a normally closed containment isolation valve, as this increases the possibility of failure in the open position. Technical Specification 3.6.1.8 controls and limits the amount of time these valves can be open in a one-year period.

Alternative Testing: Exercise valves at cold shutdown (no more frequently than once per 92 days).

Rev. 7 1RR37-1 12/91

I 'l C

ISI-T-100.0 RELIEF RE UEST NUMBER 8 System: Various P&ID: Various Valves: Those designated "Rapid-Acting" in the REMARKS column.

Category: A or B Class: 1or2 Function: Various (sample, containment isolation, etc.)

Impractical Test Requirement: Trend valve stroke times per IWV-3417(a).

Basis for Relief: The listed valves, designated as "rapid acting valves," have stroke times of such short duration that comparison of measurements with previous data for specified percentage increases is not indicative of degrading valve performance. With measurement of stroke times to the nearest second per IWV-3413(b), a very small increase in stroke time willresult in an extremely large percentage change. Verification that valves meet a specified maximum stroke time of short duration provides adequate assurance of operability.

Alternative Testing: The maximum stroke, time will be verified for all these valves when "tested.

Rev. 7 1RR38-1 12/91

ISI-T-100.0 RELTKF RK T NUMBER 3 System: Reactor Building Chilled Water P&ID: M-187 Sh. 2 Valves: HV-18791A1 HV-18792A1 HV-18791 A2 HV-18792A2 HV-1879 1B1 HV-18792B1 HV-18791B2 HV-18792B2 Category:

Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: These containment isolation valves are located in the Reactor Building Chilled Water supply and return lines serving the Reactor Recirculation pump motor coolers. The closure of these valves during power operation will interrupt cooling water flow to the Reactor Recirculation motor coolers, which creates the possibility of overheating and damage.

Alternative Testing: Exercise valves during cold shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR39-1 12/91

ISI-T-100.0 RELIEF RE T NUMBER 40 System: Control Structure Chilled Water P&ID: M-186 0-86-018 0-86-118 0-86-039 Non-Code; Safety Function 0-86-139 C Non-Code; Safety Function HV-08693 A B HV-08693 B B SV-08621A B Non-Code; Safety Function SV-08621B Non-Code; Safety Function 1-11-144 1-11-145 14 I >t Function: Condenser and Chilled Water:Flowpath, "

~

Impractical Test Requirement: Exercise valves once per 92 days.

K Basis for Relief: The ultimate function of these valves is providing chilled water to the cooling coils of the Control Structure HVAC system. Rather than individually testing each valve for proper functioning, operation of the chilled water loop with cooling supplied by the emergency condenser loop (cooled by ESW) provides a functional system test which is indicative of proper operation of all system components. As this is an auxiliary support system rather than a water-supply system, this testing provides more meaningful results than individual valve testing.

Rev. 7 1RR40-1 12/91

ISI-T-100.0 RELIEF RE T ER 4 (Cont'd.)

Individual stroke testing (including stroke time measurement) of power operated valves and check valves in these subsystems is not feasible.. System interlocks require initiation and startup of circulating pumps a'nd/or chiller, after which the valves automatically actuate.,'ime delays and equipment actuation times render any attempts at stroke time measurement meaningless. No provision is made for individual stroking of power operated valves in the circuitry.

Alternative Testing: In conjunction with the chiller pump tests, monitor the chilled water loop chiller discharge temperature and verify that the specified discharge temperatures are maintained.

Rev. 7 1RR40-2 12/91

ISI-T-100.0 RELIEF RE UKST NUMBER 41 System: General P&ID: General Valves: All Fail-Safe Valves Category: As applicable Class: As applicable Function: As applicable Impractical Test Requirement: Paragraph IWV-3415, Section XI Basis for Relief: Valves which have a "fail-safe" requirement at Susquehanna Steam Electric Station will normally be cycled once every 92 days, unless otherwise relieved. This test will accomplish the intent of the "fail-safe" test because normal valve movement is achieved by means of interrupting motive force to the valve.

Alternative Testing: No additional testing of "fail-safe" provisions will be done because normal valve testing will achieve the same results.

Rev. 7 1RR41-1 . 12/91

'I 1

H

ISI-T-100.0 RELIEF RE UEST NUMBER 42 System: General P&ID: General Valves: All pressure relief valves.

Category: As applicable Class: As applicable Function: System Overpressure Protection Impractical Test Requirement: Paragraph IWV-3100, all valves shall be pressure tested after installation and prior to service.

Basis for Relief: Pressure relief valves used at Susquehanna SES have been purchased in accordance with specifications which require performance testing at the manufacturer's shop. Records of these tests are part of the Quality Assurance records. In addition, a technical procedure requires inspection of the sealing mechanism as part of the preoperational/acceptance test program.

Alternative Testing: No additional testing beyond that which was performed as part of the purchase and installation willbe performed. The records will remain part of either the purchase or preoperational records and not part of the ISI files.

Rev. 7 1RR42-1 12/91

J 1k

'f

ISI-T-100.0 RELIEF RE T NUMBER 43 System: Standby Liquid Control P&ID: M-148 Pumps: 1P208 A,B Class:

Function: Standby Liquid Control Pumps Impractical Test Requirement: Measure inlet pressure prior to and during pump test and measure pump delta-p during pump test.

Basis for Relief: System configuration does not provide a pressure indicator on the pump suctions. It is possible to determine suction pressure by calculation from tank level (elevation difference) when the pumps are in normal alignment to the SLC Storage Tank. However, when pump testing is being performed, the tank is valved out and the suctions are aligned to a demineralized water header. While some estimation of the pressure in this alignment is available by the setting of the pressure control valve on the demineralized water header, no direct pressure indication is available. Since the SLC pumps are positive displacement type pumps, suction pressure will not affect developed discharge pressure.

Alternative Testing: Do not measure inlet pressure prior to or during pump tests. Utilize pump discharge pressure reading in lieu of Pump delta-p reading.

Rev. 7 1RR43-1 12/91

ISI-T-100.0 RELIEF RK T ER 44 System: High Pressure Coolant Injection P&ID: M-156 Pumps: 1P204, 1P209 Class:

Function: HPCI Main and Booster Pumps Impractical Test Requirement: If not tested during plant shutdown, the pump shall be tested within one week after the plant is returned to normal operation.

Basis for Relief: The required steam supply pressure for HPCI surveillance flow verification testing is specified in the Technical Specifications. This pressure may not be attained within the above prescribed time interval.

Alternative Testing: Perform HPCI flow verification test in accordance with quarterly schedule. After a shutdown which has exceeded the quarterly limit, "recommence quarterly schedule in accordance with Technical Specification 4.5.1.b.3.

Rev. 7 1RR44-1 12/91

ISI-T-100.0 RELlEF RE T ER 45 System: Core Spray P&ID: M-152 V~lv g Qaae~oig HV-152F 005 A A HV-152F005B A HV-152F006A A,C HV-152F006B A,C HV-152F037A A HV-152F037B A Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days.

Basis for Relief: These normally closed Isolation valves serve as the pressure isolation between CS system piping and reactor vessel pressure. In accordance with guidance presented in IE Information Notice 84-74, draft R.G.

901-4, and previous NRC concerns regarding intersystem LOCAs, cycling these valves every 92 days during power operation increases the probability of exposing the downstream low pressure piping to reactor coolant pressure (since only one valve would have to be ruptured or failed open to expose the low pressure system to reactor coolant pressure). In addition, failure of these valves after testing to positively reseat could cause loss of Core Spray system function.

Alternative Testing: Exercise valves during cold shutdown (no more frequently than once per 92 days).

Rev. 7 1RR45-1 12/91

ISI-T-100.0 RELIEF RE UKST NUMBER 46 System: General P&ID: General Valves/Pumps: General Category: As applicable Class: As applicable Function: As applicable Impractical Test Requirement: Test equipment in accordance with Section XI frequency

~

requirements.

Basis for Relief: With one loop out-of-service in a system, it is not desirable to test the redundant loop per ISI requirements as such testing may increase the chance of failure in a condition where backup equipment is not available. Also, these situations willbe governed by the Susquehanna Steam Electric Station Technical Specifications.

Alternative Testing: Testing will be suspended on equipment in operable loop when there is a redundant loop out-of-service.

Rev. 7 1RR46-1 12/91

ISI-T-100.0 RELIEF RE T NUMBER 47 System: Diesel Fuel Oil Transfer P&ID: M-120 Pumps; OP514 A thru E Valves: 0-20-007/009/012/015/300 Class: Non-Code; Safety Function Function: Fuel Oil Transfer from Storage Tank to Day Tank Impractical Test Requirement: Test in accordance with IWP/IWV.

Basis for Relief: These pumps are a sealed-unit submersible type with the entire unit submerged in the Diesel Oil Storage Tanks. The Susquehanna Steam Electric Station Technical Specifications presently require at least a monthly functional test of these pumps. This test verifies fuel oil flow from the storage tank to each diesels skid-mounted day tank.

Similarly, the diesel oil firing pumps are tested during the diesel functional tests. These pumps take suction from the day tank and supply the diesel cylinders. SSES considers all these pumps an extension of the diesel engine equipment skid, and therefore all are adequately tested per Technical Specifications along with the diesel itself. In addition the actual flowrate for the diesel fuel oil transfer pumps is over five times the required diesel engine fuel usage at rated conditions. Thus, even a large reduction in pump flow will not affect system operability. The pump discharge check valves are similarly tested monthly via plant Technical Specifications.

Alternative Testing: Each pump will continue to be functionally tested at least monthly via Technical Specification 4.8.1.1.2. No other testing need be performed.

Rev. 7 1RR47-1 12/91

ISI-T-100.0 RELIEF R ER 4 System: High Pressure Coolant Injection P&ID: M-156 Pumps: 1P204, 1P209 Class:

Function: HPCI main and booster pumps Impractical Test Requirement: Paragraph IWP-4310, Bearing Temperature Measurement.

Basis for Relief: These pumps are driven by a steam turbine which exhausts steam into the suppression pool. Extended run times necessary to achieve stabilized bearing temperatures could heat the suppression pool water to a temperature exceeding the Technical Specification limitof 105'F.

Alternative Testing: Eliminate bearing temperature measurement. Vibration measurements will give adequate information concerning potential bearing temperature problems.

Rev. 7 1RR48-1 12/91

ISI-T-100.0 RELIEF RE T ER 4 System: Standby Liquid Control P&ID: M-148 Pumps: 1P208 A,B Class; Function: Injection of sodium pentaborate into Rx vessel.

Impractical Test Requirement: a) IWP-3500(b), bearing temperature stabilization.

b) IWP-3500(a), five minute minimum run time.

Basis for Relief: One characteristic of positive displacement pumps is that there is essentially no lag time between starting the pumps and reaching equilibrium conditions. To measure pump flow rate, the measured rate of drainage from the test tank (IT-203) is measured. No installed instrumentation is available to measure flow rate. This testing configuration prevents recirculation of the pump discharge flow through the test tank during the test. Since the capacity of the test tank is 210 gallons and the pumps rated flow is 43 gpm, the tank will overflow before bearing temperature is stabilized. The pump bearings are located in a motor gearbox and no direct measurement of gearbox oil temperature is possible. The gearbox casing is not a reproducible measurement point. In addition, the test tank would be very close to if overflow a five minute run time test is performed.

Alternative Testing: Vibration measurements will give information concerning potential bearing problems. The pump flow rate willbe measured and changes in pump flow rate provide an early indication of degradation in pump performance. The pumps will be run for a period of time which will not cause the capacity of the test tank to be exceeded.

Rev. 7 1RR49-1 12/91

ISI-T-100.0 RELIEF E T NUMBER 50 System: Control Structure Chilled Water P&ID: M-186

,:-';:,-,:'~);.:Pump'::::,,':.:,::i: 'Class,:

OP162A S Chilled water loop circulating pump OP162B S Chilled water loop circulating pump OP171A 3 Emergency condenser water circulating pump OP171B 3 Emergency condenser water circulating pump Impractical Test Requirement: Test pumps once per 92 days per requirements of Section XI, Subsection IWP.

Basis for Relief: The ultimate function of these pumps is to provide chilled water to the cooling coils of the Control Structure HVAC system. Rather than individually testing each pump for proper functioning based on the prescribed measurements required by IWP, operation of the chilled water loop with cooling supplied by the emergency condenser loop provides a functional system test which is indicative of proper operation of all system components. This testing is more practical and provides a method of pump testing which does not require the removal of this safety system from operation. See Relief Request Number 40.

Alternative Testing: Monitor the chilled water loop chiller discharge temperature and verify that the specified discharge temperature is maintained.

Rev. 7 1RR50-1 12/91

ISI-T-100.0 RELIEF R ER 1 System: Emergency Service Water P&ID: M-ill,Sheet 1 Valves: 0-11-001, 0-11-002, 0-11-003, 0-11-004 Category:

Class:

Function: Pump Discharge Check Impractical Test Requirement: Valve Internals Integrity Verification of NRC IEB 83-03.

Basis for Relief: These check valves, located in the pump discharge, are required to open during system operation to permit cooling water flow to system loads. During quarterly pump, tests, the valves are in fact cycled open and design flow passed through, indicating operability.

However, as discussed in IE Bulletin 83-03, such testing in raw water cooling systems may be inadequate to ensure valve mechanical integrity.

Alternative Testing: In addition to quarterly exercising in conjunction with pump tests, verify valve mechanical integrity by visual inspection during disassembly. Commencing with the first refueling outage, 1 valve from each loop will be disassembled at least once pei: 18 months (J 3 months), such that all valves are inspected at least once per 72 months (+ 6 months).

Rev. 7 1RR51-1 12/91

ISI-T-100,0 RELTEF RE T NIJNIBER 52 System: RHR, Core Spray, ESW, RHRSW, HPCI, SBLC PEcID: Various Pumps: All in above systems Class: Various Function: Process flow for above systems ImpracticalTest Requirement: Section XI, Paragraph IWP-3210, Allowable Ranges of Inservice Test Quantities Basis for Relief: Ranges of acceptable instrument accuracies, as established by ASME Section XI paragraph IWP-4110 and Table IWP-4110-1 allow up to 6% error in pump pressure and flow readings due to acceptable instrument accuracy of 6% (2% of full scale range times full scale range 3 times reference value).

In contrast, the acceptable pump pressure and flow values required to result from pump tests, as established by ASME Section XI paragraph IWP-3100 and Table IWP-3100-2, are limited to a range extending only 2% above the corresponding reference value and only 6% flow or 7% pressure below the reference value.

Alternative Testing: Actual instrument accuracies shall be applied to indicated values of pump flow and pressure. The values of pump flow and pressure, so corrected for the effects of instrument accuracy, shall be compared to the allowable ranges for the corresponding test quantities, from Table IWP-3100-2, for determination of acceptability.

Instrument accuracies for use in these corrections shall be determined, as needed, by calibration of the flow and/or pressure instruments utilized for the pump test.

Actual instrument accuracies for use in these corrections shall conform to the acceptable instrument accuracies established for flow instruments and for pressure instruments, by Table IWP-4110-1.

I'RR52-1 Rev. 7 12/91

ISI-T-100.0 RELIEF RE T NUMI)ER 53 System: HPCI P&ID M-156 Valves: FV-15612 Category:

Class:

Function: Opens to admit steam to HPCI turbine, closes to isolate steam in the event of a turbine trip.

Impractical Test Requirements: Stroke time valves when exercised, once per 92 days.

Basis for Relief: The HPCI Turbine Stop Valve, FV-15612, has a design stroke time of 0.5 seconds. In keeping with current philosophy regarding other rapid-acting valves, this valve cannot be timed accurately and thus cannot be trended from test-to-'test. Minor variations in each test could cause needless additional testing, which would require rendering the HPCI system inoperable.

Alternative Testing: Valve willbe tested functionally each time the HPCI turbine is tested (quarterly). No stroke timing or trending will be performed. In addition, response time testing for the HPCI system willbe performed in accordance with Technical Specifications once per 18 months.

Rev. 7 1RR53-1 12/91

I I

II

ISI-T-100.0 RELIEF RE UEST ER 4 System: RHR, Core Spray, ESW, RHRSW P&ID: Various Pumps: All in above systems Class: Various Function: Process flow for above systems Impractical Test Requirement: Measure bearing temperature and lubricant level or pressure during test.

Basis for Relief: The bearings for the pumps listed above are lubricated by the flowing fluid and therefore require no verification of adequate lubrication.

Similarly, the bearing temperatures cannot be accurately measured due to the flowing fluid.

Alternative Testing: None; component vibration readings willserve as indications of pump mechanical condition.

Rev. 7 1RR54-1 '2/91

P 1' ISI-T-100.0 RELIEF RE T ER System: RHR, Core Spray, HPCI P&ID: Various Pumps: All in above systems Class: Various Function: Process suction pressure for above systems Impractical Test Requirement: Section XI Paragraph IWP-4120,'equired range.. of,. test, instruments j

Basis for Relief: Full scale ranges of test instruments, as established by ASME Code Section XI paragraph IWP-4120, are limited to three times the reference value or less. In contrast, the four RHR System Pumps 1P202A/B/C/D have suction pressure reference values as low as 5 PSIG, but have suction pressure gages PI-1R002A/B/C/D permanently installed with full scale ranges 0-200 PSIG. Similarly, the four Core Spray System Pumps 1P206A/B/C/D have suction pressure reference values as low as 7 PSIG, but have suction pressure gages PI-1R001A/B/C/D permanently installed with full scale ranges 0-60 PSIG. Similarly, HPCI System Pump 1P204 has a suction pressure reference value of 18 PSIG, but has suction pressure gauge PI-1R606 permanently installed with a full scale range of 0-85 PSIG.

These permanent plant instruments require the full scale ranges for which they have been designed and installed to be able to cover the full spectrum of operating conditions and configurations of their respective systems. These permanent plant instruments have greater reliability than temporary or permanent test instruments would have.

The permanent plant instruments used for these tests have had the accuracy of their calibration specially enhanced at the nominal values of the test parameters; their accuracy within the range of test values is adequate for test purposes. The use of the permanent plant-instruments for ISI pump testing ensures that pump suction pressures Rev. 7 1RR55-1 12/91

E

  • f h

J L

ISI-T-100.0 REITEF RE UEST ER (Cont'd.)

if are being measured in the same way as they would the pump were operated to fulfill its design safety function. Repeated temporary installation and removal of suction pressure gages is impractical due to high potential for damage to the gages through the transport and work processes.

Alternate Testing: Utilize permanent plant pump suction pressure instruments for ISI pump test suction pressure measurements in RHR, Core Spray, and HPCI Systems.

Rev. 7 1RR55-2 12/91

ISI-T-100.0 RELIEF R P&ID'mergency Service Water System:

M-111 Pumps: , OP504A, OP504B, OP504C, OP504D V

Class:

Function: Process flow for Emergency Service Water System Impractical Test Requirement: The resistance of the system shall be varied until either the measured differential pressure or the measured flow rate equals the corresponding reference value. (Paragraph IWP-3100)

Basis For Relief: Current design of the ESW System does not include provision for variation of system resistance by any positive means, Neither measured flow rate nor measured differential pressure can be set equal to the corresponding reference value by any positive means, The flow rates and the differential pressures produced by non-variable hydraulic resistance factors within the system control the measured values for flowrate and differential pressure obtained during each test.

Alternative Testing: Run the ESW System as designed and measure pump flow rates and differential pressures produced by the system. Evaluate both test quantities independently by the criteria of Table IWP-3100-2.

Rev. 7 1RR56-1 12/91

ISI-T-100.0 RELIEF RE T NUMBER 57 Relief Request Deleted.

This Page Intentionally Left Blank.

Rev. 7 1RR57-1 12/91

ISI-T-100.0 RELIEF R UKST NUMBER 58

isic'm;.-".,.:.: ~g;:PSH)$ : '":,':;;::;:."-:::::,;,,;p>Valve)'Q"--.';::.;:::,'::;: /~Category,,':.;,::

CIG M-126 SV-12605 A Containment Isolation CIG M-126 SV-12643 B Instrument Gas Storage CIG M-126 SV-12644 B Instrument Gas Storage CIG M-126 SV-12648 B Instrument Gas Storage CIG M-126 SV-12649 B Instrument Gas Storage CIG M-126 SV-12651 A Containment Isolation CIG M-126 SV-12654A A Containment Isolation CIG M-126 SV-12654B A Containment Isolation CIG M-126 SV-12661 A Containment Isolation CIG M-126 SV-12671 A Containment Isolation CAC M-157 SV-15734A A,, 2 Containment Isolation'ontainment CAC M-157 SV-15734B A Isolation CAC M-157 SV-15736A A 2 Containnient Isolation CAC M-157 SV-15736B Containment Isolation CAC M-157 SV-15737 A Containment Isolation CAC M-157 SV-15738 A Containment Isolation CAC M-157 SV-15740A A Containment Isolation CAC M-157 SV-15740B A Containment Isolation CAC M-157 SV-15742A Containment Isolation CAC M-157 SV-15742B Containment Isolation CAC M-157 SV-15750A Containment Isolation CAC M-157 SV-15750B Containment Isolation CAC M-157 SV-15752A Containment Isolation CAC M-157 SV-15752B Containment Isolation CAC M-157 SV-15767 A Containment Isolation Rev. 7 1RR58-1 12/91

f 1

I f

RELIEF RE T ER 5 (Cont'd.) ISI-T-100.0

-;:;:-:',Sy'tem',::,,':,",': .'i5P'.,:A)9',",'";;;:i::,'t~9;;.:<':.',.,Vai,ve,:,'!:="i:.'.i.:;;:: ':,.':";,,,.,Ca'f'egoi'y,.:':j; CAC M-157 SV-15774A Containment Isolation CAC M-157 SV-15774B A Containment Isolation CAC M-157 SV-15776A A Containment Isolation CAC M-157 SV-15776B A Containment Isolation CAC M-157 SV-15780A A Containment Isolation CAC M-157 SV-15780B A Containment Isolation CAC M-157 SV-15782A A Containment Isolation CAC M-157 SV-15782B A Containment Isolation CAC M-157 SV-15789 Containment Isolation CAC M-157 SV-157100A A Containment Isolation CAC M-157 SV-157100B Containment Isolation CAC M-157 SV-157101A A Containment Isolation CAC M-157 SV-157101B A Containment Isolation CAC M-157 SV-157102A A Containment Isolation CAC M-157 SV-157102B Containment Isolation CAC M-157 SV-157103A A Containment Isoaltion CAC M-157 SV-157103B A 2 Containment Isolation CAC M-157 SV-157104 Containment Isolation CAC M-157 SV-157105 Containment Isolation CAC M-157 SV-157106 Containment Isolation CAC M-157 SV-157107 A Containment Isolation Impractical Test Requirement: Valves with Remote Position Indicators shall be observed at least once every 2 years to verify that valve operation is accurately indicated.

Basis For Relief: The subject solenoid valves, all of which are manufactured by the Target Rock Corporation, all are constructed in a manner that precludes local verification of valve operation by direct observation. All movements and positions of valve parts are obscured by the valve structure within which they travel and Rev. 7 1RR58-2 12/91

0 0

RELIEF RE UEST NUMBER 58 (Cont'd.) ISI-T-100.0 within which they are sealed. A method for indirect observation of valve movement, utilizing ferritic steel objects (steel shot) moved along the surface of each valve's indicating tube by the permanent magnet attached to the valve stem inside, was devised, used for 18 months, and subsequently abandoned because its employment necessitated partial disassembly of the solenoid valve for the test. This disassembly and reassembly, consisting of removal and reinstallation of the reed switch housing assembly, or cover, has been found to cause damage to the wiring and its connections to the reed switches.

Alternative Testing:, Confirmation of coincident valve movement and remote indication is accomplished by listening to the valve with a stethoscope, for the audible signal of the valve disk arriving at a new position. Accuracy of remote indication of valve operation is essentially verified for these solenoid valves at least once every 2 years by the combination of containment isolation valve leak testing (LLRT) (or instrument gas storage leakdown testing) with accomplishment of General Operating Procedures (GO-100-002) for plant startup and heatup. These activities are completed at least once each refueling shutdown, as follows:

'j':<<:,,:.'.::,"','.,"'(j:,;:::,:;;'::';:.)j!:,':;:,.:;::,:,.::Refuelirig::":::

,.,:.::;:::",i:.':.,,;
;.
,',.:.;;:.:.";;;",::::.:;:,.;Shu endow'ii.':::; .:'.",:::;.',::..:.:.:,Verified".':,.'.

!:'.-.';:-;::,;::;.';;Valvew'Nl';,';,:,',:,:,:.';,';!::;:;;:,':-:':,;::,:::,;.,Startupj!g~;,::.';;.:::::.'4,~:;;,,

I.:,Sj ste'm .;:'..:j:,;::IVaive;:,".,",">>,';. ";,';.:Proiedu're',,':: ,';',,:'Po'sltionj':,":. ','i,'..>II';:%';j<;;:Pro'cedu'ie(s)5<'j',".:':,':;~l',:;.'.'~II q;".'.".,":;:.,Positio'n" ".;.;

CIG SV-12605 SE-159467 Closed OP-125-001/GO-100-002 Open CIG SV-12643 TP-125407 Open OP-125-001/GO-100-002 Open CIG SV-12644 TP-125407 Closed OP-125-001/GO-100-002 Open CIG SV-12648 TP-125409 Open OP-125-001/GO-100-002 Open CIG SV-12649 TP-125-009 Closed OP-125-001/GO-100-002 Open CIG SV-12651 SE-159437 Closed OP-125-001/GO-100-002 Open CIG SV-12654A SE-159446 Closed OP-125-001/GO-100-002 Open CIG SV-12654B SE-159438 Closed OP-125-001/GO-100-002 Open CIG SV-12661 SE-159469 Closed OP-125-001/GO-100-002 Open CIG SV-12671 SE-159-090 Closed OP-125-001/GO-100402 Open Rev. 7 1RR58-3 12/91

RELIEF RK T ER (Cont'd.) ISI-T-100.0

,Sh'u't'do'w'ii'.'.
;
:: :..Jg',,'.Verified::,.',II '",".!3:Ver'lfied":;::;:~:.;

j'ij':,', ";:Vaja:-,:,:':.;::,i::),

.;jSj'steiii ',,::.:':'.',;":i:;",'::",Valise':;;;:,::';. ,:'.;",,::;:Proce'dur'e'l.:'; 'j,':,:.Pos) tl'o'n'~gj;:."::~II.';::::::::::.'::;.i::;.':.'I:'.:Pr'o'ce'dur'e(s);:::;::::i::.,".:::;;:.:;":.:".:; i:.',-:,;:3;:,:.::,Posi.tio'nI"(g'AC SV-15734A SE-159419 Closed OP-173401/60-100-002 Open CAC SV-15734B SE-159420 Closed OP-173401/GO-100-002 Open CAC SV-15736A SE-159419 Closed OP-173401/GO-100402 Open CAC SV-15736B SE-159-020 Closed OP-173401/GO-100-002 Open CAC SV-15737 SE-.159-103 Closed OP-173401/GO-100402 Open CAC SV-15738 SE-159-103 Closed OP-173401/GO-100-002 Open CAC SV-15740A SE-159419 Closed OP-173401/GO-100-002 Open CAC SV-15740B SE-159420 Closed OP-173401/GO-100-002 Open CAC SV-15742A SE-159419 Closed OP-173401/GO-100-002 Open CAC SV-15742B SE-159-020 Closed OP-173-001/GO-100-002 Open CAC SV-15750A SE-159-019 Closed OP-173401/GO-100402 Open CAC SV-15750B SE-159-020 Closed OP-173401/GO-100-002 Open CAC SV-15752A SE-159-019 Closed OP-173-001/GO-100-002 Open CAC SV-15752B SE-159-020 Closed OP-173401/GO-100402 Open CAC SV-15767 SE-159-102 Closed OP-173-001/GO-100402 Open CAC SV-15774A SE-159-019 Closed OP-173-001/GO-100402 Open CAC SV-15774B SE-159-020 Closed OP-173401/GO-100-002 Open CAC SV-15776A SE-159-019 Closed OP-173-001/GO-100-002 Open CAC SV-15776B SE-159-020 Closed OP-173-001/GO-100402 Open CAC SV-15780A SE-159-019 Closed OP-173-001/GO-100-002 Open CAC SV-15780B SE-159-020 Closed OP-173-001/GO-100402 Open CAC SV-15782A SE-159-019 Closed OP-173401/60-100-002 Open CAC SV-15782B SE-159-020 Closed OP-173-001/GO-100-002 Open CAC SV-15789 SE-159-102 Closed OP-173-001/60-100-002 Open CAC SV-157100A SE-159-019 Closed OP-173401/60-100-002 Open Rev. 7 1RR58-4 12/91

1

~ vti 4

RELIEF RE T NUMBER 58 (Cont'd.) ISI-T-100.0

',:;:.,':,':;:R'efiieliiig",",ii

.:,': Shi'it'dowii'i::::;: ;..',:,..."::Verified:';:;:::~a

"';::.Sj"s'te'iii.:  :';':,i.':Posit)'a'ii::::,:,::,:::

'.':.:"::Pr'ocedii'i'e',:'..'.'E-159-020 CAC SV-157100B Closed OP-173401/GO-100-002 Open CAC SV-157101A SE-159-019 Closed OP-173401/GO-100-002 Open CAC SV-157101B SE-159420 Closed OP-173401/GO-100402 Open CAC SV-157102A SE-159419 Closed OP-173401/GO-100-002 Open CAC SV-157102B SE-159-020 'losed OP-173401/GO-100-002 Open CAC SV-157103A SE-159419 Closed OP-173401/GO-100-002 Open CAC SV-157103B SE-159420 Closed OP-173401/GO-100-002 Open CAC SV-157104 SE-159-019 Closed OP-173-001/GO-100-002 Open CAC SV-157105 SE-159-019 Closed OP-173401/GO-100-002 Open CAC SV-157106 SE-159419 Closed OP-173-001/GO-100402 Open CAC SV-157107 SE-159419 Closed OP-173-001/GO-100-002 Open Rev. 7 1RR58-5 12/91

ISI-T-100.0 RELIEF R BER This Page Intentionally Left Blank.

Rev. 7 1RR59-1 12/91

ISI-T-100.0 RELIEF RK T ER

.',..:.-:-;,:Sjstem'::,':l!;:::;,.';,PghH)'-.:g .'::."::j".,~Valv'e!Nu'iiibei','j">'..'iCla'ss', ';..P,:!'Ca't'ej'o'r';:-"~";:-:!i MSIV M-141 141FO24A MSIV M-141 141FO24B C MSIV M-141 141FO24C

'(

MSIV ~ ~ M-141 .,141FO24D: ~ '-.C ""

MSIV M-141 141FO29A MSIV M-141 141FO29B MSIV M-141 "'41FO29C C

MSIV M-141 141FO29D Function: Prevent reverse flow out through MSIV accumulator inlet (air) line.

Impractical Test Requirement: Exercise valves to their closed positions once per 92 days (per IWP-3521).

Basis For Relief: Thesecheck valves, located in MSIV accumulatorinlet(air) lines provide Containment Instrument Gas System and Instrument Air System gas fiow into their respective MSIV accumulators, while preventing flow of gas stored in the MSIV accumulator in the reverse direction, during closure of their respective MSIV's at the onset of a LOCA. Plant configuration and exclusion of personnel from the purged drywell during operation preclude completion of closure exercise testing throughout the period of each plant operating cycle.

Any exercise testing of these check valves requires or causes closure of the associated MSIVs, rendering it impractical except during refueling outages. The design basis of these check valves for the

, inboard MSIVs is established by PP&L Calculations M-MSS-025 and M-MSS-028, from which testing appropriate to their safety function is derived.

Alternative Testing: Demonstrate closure of each MSIV accumulator check valveby monitoring the essential restriction of its reverse flow of gas, through measurement of the rate of decay of pressure in its respective MSIV accumulator (downstream of the check valve under test) once per refueling outage. This MSIV accumulator pressure decay test provides verification of the closure of the inlet check valve.

Rev. 7 1RR60-1 12/91

1

) /

l =.

tt P,

ISI-T-100.0 ELIEF R UEST ER 1 System: Control Rod Drive Hydraulic P&ID: N-147 Valves: XV-147FO10, XV-147FOll XV-147F180, XV-147FI81 Class:

Function: CRD Scram Discharge Volume venting and draining Impractical Test Requirement: Paragraph IWV-3417(a) Corrective Action, increasing test frequency to monthly whenever stroke time increases by

> 25% (when over 10 seconds) or by >50% (when under 10 seconds).

Basis For Relief: These globe valves are air operated and have comparatively complex actuation logic schemes sequencing their start and stop times. P&ID M-147 Notes ¹21 & 22 establish additional restraints, which are satisfied administratively, upon the stroke times and sequencing of these valves. In addition to the common causes of inconsistency in rate of pneumatic actuation of valves, such as variations in air line supply pressure and variations in air regulator output pressure, the pneumatic actuators of these valves have their exhaust airflows metered by needle valves. Their actuation rate is extremely sensitive to the slightest changes in the positions of the needles in these needle valves, as caused by readjustment, by physical shock, or by thermal change. By readjustment of the exhaust needle valve position, these valves are maintained in compliance with the stroke time and sequencing limitations of the P&ID, which, although dissimilar from those of Article IWV-3000, provide a more relevant basis for verifying the operational readiness of these particular valves.

Alternative Testing: Exercise testing of the four valves is to be performed quarterly, per IWV-3410 requirements, except that the IWV-3417(a) stroke time increase limitations (of 25% above 10 seconds and 50% below 10 seconds) willbe replaced by P&ID M-147 Notes ¹21 & 22 limitations

. that the outboard valves fully close > 5 seconds after their respective inboard valves; and start opening > 5 seconds before their respective inboard valves.

Rev. 7 1RR61-1 12/91

0 I

ISI-T-100.0 oi RELIEF R ER 2 System: Reactor Water Cleanup P&ID: M-144 Valves: HV-144FOOl and HV-144FOO4 Category: A Class:

Function: Containment Isolation Impractical Test Requirement: Exercise valves once per 92 days (per IWV-3411).

Basis For Relief: Closure of the reactor is operating causes an isolation of the RWCU System, initiating thermal and pressure transients within that system, which degrade the RWCU pump seals, leading to eventual damage to and consequent failure of the seals. Seal failure causes spread of radioactive contamination throughout affected parts of the reactor building and diminishes the reliability of the RWCU pumps. The necessary replacement of the pump seals requires isolation of the pump from the RWCU System, reducing the ability of the system to remove impurities from the reactor coolant. This results in degraded reactor water purity, which in'urn, stimulates intergranular stress

'corrosion cracking (IGSCC) of the reactor pressure vessel, its internal components, attachments, and associated piping. Additionally, the pump maintenance required to repair the seal failures causes excessive personnel radiation exposure (estimated at 20 Man-Rem/year),

contrary to ALARAprinciples.

Alternative Testing: Exercise valves during Cold Shutdowns (no more frequently than once per 92 days).

Rev. 7 1RR62-1 12/91

II I

~ >> $ >> t, ~

0

'>>>> lt )%, ~

4 I I t

\>> I

ISI-T-100.0 RELIEF R System: High Pressure Coolant Injection P&ID: M-156 Pumps: 1P204 and 1P209 (combination)

Class:

Impractical Test Requirement: Paragraph IWP-3100, Inservice Test Procedure requirement for pump speed to be adjusted to the reference speed.

Basis For Relief: These pumps are driven by a steam turbine which exhausts steam into the suppression pool, heating it toward its Technical Specification limit of 105'F. This is a severe limitation on test duration. Frequent test repetition is not desirable due to the strong transient nature of a HPCI quick start. Such quick starts are recommended by INPO and have been adopted as PP&L's test method. These factors make this test uniquely time-dependent. Pump speed is not directly controllable, but can only be achieved through coordinated manipulation of the pump flow controller and the test system throttling valve. Test results are extremely sensitive to variations in pump speed, from all sources.

Alternative Testing: When pump test speed differs from the reference speed by a measurable amount (10 RPM, or greater), the Corrective Action analysis, permitted by paragraph IWP-3230(c) may include a correction calculation, using the following relationship, to conform the test results at actual test speed to the reference speed:

Di/erential Pressure Developed Head Speed act Digereritial Pressure Developed Head Spec ref ref ref Rev. 7 1RR63-1 12/91

a ISI-T-100.0 RELIEF R ER 64

'..':.Sy'steiii';:::::,.':!'::;'PAID,:','::,';.

M-111 011033 Diesel Generator OG501A cooling ESW M-111 011034 Diesel Generator OG501A cooling ESW M-111 011035 Diesel Generator OG501C cooling ESW M-111 011036 Diesel Generator OG501C cooling M-111 011037 Diesel Generator OG501B cooling ESW M-111 011038 Diesel Generator OG501B cooling ESW M-111 011039 Diesel Generator OG501D cooling M-111 011040 Diesel Generator OGS01D cooling ESW M-111 011513 Diesel Generator OG501E cooling ESW M-111 011514 Diesel Generator OG501E cooling ESW M-111 111144 ESG & Load Center Rooms cooling M-111 111145 ESG & Load Center Rooms cooling RCIC M-149 149F 063 Turbine exh steam line vac brkr RCIC M-149 149F 064 Turbine exh steam line vac brkr M-151 151FO46 A/B/C/D 2 RHR pump minimum flow line LPCS M-152 152FO36 A/B/C/D 2, CS pump minimum flow line HPCI M-155 155F 076 Turbine exh steam line vac brkr HPCI M-155 155F 077 Turbine exh steam line vac brkr Rev. 7 1RR64-1 12/91

RELIEF RE ER (Cont'd.) ISI-T-100.0 Impractical Test Requirement: NRC Generic Letter 89-04 Position 1 requirement that, during opening exercise testing, a check valve's "full-stroke" to the open position be verified by passage of "maximum required accident condition flow" through the check valve; and AS ME Code Section XI Paragraph IWV-3521 requirement that check valves be tested every 3 months.

Basis For Relief: In recognition that establishing design accident flow through these valves for testing could result in degradation or damage to major plant equipment, NRC Generic Letter 89-04 Position 2 establishes that disassembly and inspection 'f these check valves may be used as a positive means of determining that a valve's disk will "full-stroke" open ...,

as permitted by ASME Code Section XI Paragraph IWV-3522. If possible, partial valve stroking quarterly or during cold shutdowns or after reassembly must be performed, additionally. Due to the scope of these inspections, the personnel hazards involved, and system operating restrictions, NRC Generic Letter 89-04 Position 2 establishes that valve disassembly and inspection may be performed during reactor refueling outages. As it is burdensome to disassemble and inspect all of the subject valves each refueling outage, NRC Generic Letter 89-04 Position 2 establishes that a sample inspection plan for groups of up to four identical valves in similar applications may be employed, within the NRC guidelines specified within Position 2, Alternative Testing: Perform partial valve stroke exercise testing at quarterly testing frequency, at cold shutdown testing frequency, or at other frequency, as specified in separate Relief Requests, specific to each check valve. Establish and employ a sample disassembly and inspection plan for groups of up to four identical valves in similar applications. Disassemble, inspect, verify structural soundness of internal components, and manually exercise the disk through its full stroke for one different valve in each group at each successive refueling outage (or 18 month + 3 month period for common plant valves), until the entire group has been inspected.

Rev. 7 1RR64-2 12/91

ISI-T-100.0 RELIEF R ER 65

".,',Syite'in';, ;.';.'::'.P&ID,.'.P. R'":;;Category::::>::! 'Pchss',,"j RCIC M-149 149F 021 C' 2 RCIC pump minimum flow line FPC&C M-153 153071 A/B FPC&C isolation from ESW system HPCI M-155 155F 045 2 HPCI supp pool suction line HPCI M-155 155F 046 HPCI pump minimum flow line HPCI M-156 156F 048 HPCI lube oil cooler return line HPCI M-156 156F057 HPCI lube oil outlet line Impractical Test Requirement: NRC Generic Letter 89-04 Position 1 requirement that, during opening exercise testing, a check valve's "full-stroke" to the open position be verified by passage of "maximum required accident condition flow" through the check valve; and AS ME Code Section XI Paragraph IWV-3521 requirement that check valves be tested every 3 months.

Basis For Relief: In recognition that establishing design accident flow through these valves for testing could result in degradation or damage to major plant equipment, NRC Generic Letter 89-04 Position 2 establishes that disassembly and inspection of these check valves may be used as a positive means of determining that a valve's disk will "full-stroke" open ...,

as permitted by ASME Code Section XI Paragraph IWV-3522. If possible, partial valve stroking quarterly or during cold shutdowns or after reassembly must be performed, additionally. Due to the scope of these inspections, the personnel hazards involved, and system operating restrictions, NRC Generic Letter 89-04 Position 2 establishes that valve disassembly and inspection may be performed during reactor refueling outages. As it is burdensome to disassemble and inspect all of the subject valves each refueling outage, NRC Generic Letter 89-04 Position 2 establishes that a sample inspection plan for groups of up to four identical valves in similar applications may be employed, within the NRC guidelines specified Rev. 7 1RR65-1 12/91

1<

RELIEF RE T ER (Cont'd.) ISI-T-100.0 within Position 2. As the population of identical valves, among those listed above, is extremely small, groups of up to four identical valves in similar applications in both units will be created for sampling.

Alternative Testing: Perform partial valve stroke exercise testing at quarterly testing frequency, at cold shutdown testing frequency, or at other frequency, as specified in separate Relief Requests, specific to each check valve. Establish and employ a sample disassembly and inspection plan for groups of up to four identical valves, shared among both units, in similar applications. Disassemble, inspect,,verify structural soundness of internal components, and manually exercise the disk through its full stroke for one different valve in each group at every "pair" of refueling outages, alternating between the tw'o units, until,the'entire group.has been inspected.

Rev. 7 1RR65-2 12/91

ISI-T-100.0 RELIEF R ER System: Containment Instrument Gas P &ID: M-126 Valves: 126018 and 126029 Category:

Class:

Function: Provide Actuating Gas to Automatic Depressurization Feature of Main Steam Relief Valves.

Impractical Test Requirement: Exercise valves once per.92 days (per IWV-3521).

Basis For Relief: Closure of the subject valves for exercise testing interrupts instrument gas supply to the ADS solenoids of the Safety/Relief Valves, compromising their ability to provide the opening motive force for the ADS valves, in support of the long-term cooling ECCS function. Due to the configuration of the CIG System, depressurization and venting of sufficient pipe lines to permit closure exercise testing of these valves further interrupts instrument gas supply to several important valves inside containment, such as the Safety/Relief Valves (non-ADS relief function) and the MSIV'S. This could compromise the ability of the SRV's to operate in the relief mode which, while not an ECCS function, is important to safety. Loss of instrument gas supply could also cause the MSIV's to close, resulting in a severe reactor transient if operating; or in an undesirable ESF actuation, ifshut down. Loss of instrument gas supply could also cause isolation of the drywell cooling lines, resulting in a drywell temperature excursion.

Alternative Testing: Demonstrate closure of each check valve by monitoring the essential restriction of its reverse airflow, through the test connection downstream of the opposite division check valve, once per refueling outage.

Rev. 7 1RR66-1 12/91

SUSQUEHANNA STEAM ELECTRIC STATION UNIT 1 PUMP AND VALVEINSERVICE INSPECTION

- TESTING PROGIUQM

'. LIST OF EFFECIIVE'AGES Re'vision':;-:'. , Dated' TITLE:

Page 1T-1 12/91 DESCRIPTION:

Page 1D-1 12/91 Page 1D-2 12/91 LEGENDS:

Page 1LV-1 12/91 Page 1LV-2 12/91 Page 1LP-1 12/91 VALVETABLES:

Page 1VT-1 12/91 Page 1VT-2 12/91 Page 1VT-3 12/91 Page 1VTA 12/91 Page 1VT-5 12/91 Page 1VT-6 12/91 Page 1VT-7 12/91 Page 1VT-8 12/91 Page 1VT-9 12/91 Page 1VT-10 12/91 Page 1VT-11 12/91 Page 1VT-12 12/91 Page 1VT-13 12/91 Page 1VT-14 12/91 LEP-1 12/91

ISI-T-100.0

,".,:.,::,".:;-.:;::,.;:.'.:,.'Di(e'dy~":,::,::,:,.:'.;~~~I Page 1VT-43 12/91 Page 1VT-44 12/91 Page 1VT-45 12/91 Page 1VT-46 12/91 Page 1VT-47 12/91 Page 1VT-48 12/91 Page 1VTR9 12/91 Page 1VT-50 12/91 Page 1VT-51 7 12/91 Page 1VT-52 7 12/91 Page 1VT-53 12/91 Page 1VT-54 12/91 Page 1VT-55 12/91 Page 1VT-56 7 12/91 Page 1VT-57 12/91 Page 1VT-58 12/91 Page 1VT-59 12/91 Page 1VT-60 12/91 Page 1VT-61 12/91 Page 1VT-62 Jl 1 .12/91 Page 1VT-63 12/91 Page 1VT-64 12/91 Page 1VT45 12/91 Page 1VT-66 12/91 Page 1VT-67 12/91 Page 1VT<8 12/91 Page 1VT-69 12/91 Page 1VT-70 12/91 LEP-3 12/91

t t

)1 >j ag J

Il

ISI-T-100.0 4'j<0g'j4?i<4g:. <i%'jeep!;::.','.:~/Aim'i,;:Npp!c".:',, N,,"?i':"::N;,':!:;:::::i?!caiNy;:j'::,m

'@i::l":,'Rejisioa"": i""::"':':::.!~j)::.",:;:.':,:;::Piite'd'.".:!"":~ii!'; "l Page 1VT-71 12/91 Page 1VT-72 12/91 Page 1VT-73 12/91 Page 1VT-74 12/91 Page 1VT-75 12/91 Page 1VT-76 12/91 Page 1VT-77 12/91 Page 1VT-78 12/91 Page 1VT-79 12/91 Page 1VT-80 12/91 Page 1VT-81 12/91 PUMP TABLES:

Page 1PT-1 12/91 Page 1PT-2 12/91 Page 1PT-3 12/91 Page 1PT-4 '7 12/91 Page 1PT-5 7 12/91 Page 1PT-6 12/91 Page 1PT-7 12/91 RELIEF REQUESTS:

Page 1RRT-1 12/91 Page 1RR1-1 12/91 Page 1RR2-1 12/91 Page 1RR2-2 12/91 Page 1RR3-1 12/91 Page 1RR4-1 12/91 Page 1RRS-1 12/91 Page 1RR6-1 12/91 LEP-4 12/91

,'I I 5L

ISI-T-100.0 Page 1RR7-1 12/91 Page 1RR8-1 12/91 Page 1RR9-1 12/91 Page 1RR10-1 12/91 Page 1RR11-1 12/91 Page 1RR12-1 12/91 Page 1RR13-1 12/91 Page 1RR14-1 12/91 Page 1RR15-1 12/91 Page 1RR16-1 12/91 Page 1RR17-1 12/91 Page 1RR17-2 12/91 Page 1RR17-3 12/91 Page 1RR18-1 12/91 Page 1RR19-1 12/91 Page 1RR20-1 12/91 Page 1RR20-2 12/91 Page 1RR21-1 12/91 Page 1RR22-1 12/91 Page 1RR23-1 12/91 Page 1RR24-1 12/91 Page 1RR24-2 12/91 Page 1RR25-1 .7 12/91 Page 1RR26-1 12/91 Page 1RR27-1 12/91 Page 1RR28-1 7 12/91 Page 1RR29-1 12/91 Page 1RR30-1 12/91 LEP-5 12/91

ISI-T-100.0 Page 1RR31-1 12/91 Page 1RR32-1 12/91 Page 1RR33-1 12/91 Page 1RR34-1 12/91 Page 1RR35-1 12/91 Page 1RR36-1 12/91 Page 1RR37-1 7 12/91 Page 1RR38-1 12/91 Page 1RR39-1 12/91 Page 1RR40-1 12/91 Page 1RR40-2 12/91 Page 1RR41-1 12/91 Page 1RR42-1 12/91 Page 1RR43-1 12/91 Page 1RR44-1 12/91 Page 1RR45-1 12/91 Page 1RR46-1 12/91 Page 1RR47-1 12/91 Page 1RR48-1 12/91 Page 1RR49-1 12/91 Page 1RR50-1 7 12/91" Page 1RR51-1 12/91 Page 1RR52-1 12/91 Page 1RR53-1 12/91 Page 1RR54-1 12/91 Page 1RR55-1 12/91 Page 1RR55-2 12/91 Page 1RR56-1 12/91 LEP-6 12/91

4