ML17146B124

From kanterella
Jump to navigation Jump to search
Insp Rept 50-387/87-21 on 871116-25.No Violations Noted. Major Areas Inspected:Licensee Response to Generic Ltr 84-11,response to Previous Insp Findings & Nonconformance Rept Close Out
ML17146B124
Person / Time
Site: Susquehanna 
Issue date: 01/20/1988
From: Kerch H, Mcbrearty R, Strosnider J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17146B123 List:
References
50-387-87-21, GL-84-11, NUDOCS 8802020201
Download: ML17146B124 (7)


See also: IR 05000387/1987021

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-387/87-21

Docket No.

50-387

License

No.

NPF-14

Priority

Category

C

Licensee:

Penns

lvania Power & Li ht

Com an

2 North Ninth Street

Al 1 entown

Penns

1 vania

18101

Facility Name:

Sus

uehanna

Steam Electric Station

Unit 1

Inspection At:

Berwick

Penns

lvania

Inspection

Conducted:

November

16-25

1987

Inspectors:

/WP C

. A. McBrearty, Reactor

gineer

MPS,

DRS

date

Q c

H.

W. Kerch, Senior Reactor

gineer

MPS,

DRS

Approved by:

R. Strosnider,

Chief, Materials

and

Processes

Section,

EB,

DRS

d

e

Ins ection Summar:

Ins ection

on November

16-25

1987

Ins ection

Re ort

No. 50"387/87"21

A~Add:

A i,

d

i <<d

regional

based

inspectors

of the licensee's

response

to Generic Letter 84-11,

licensee

response

to previous inspection findings,

and non-conformance

report

closeout.

Results:

No violations were identified,

880202020l

880120

PDR

ADDCK 05000387

G

PDR

DETAILS

Persons

Contacted

Penns

lvania Power 5 Li ht

Com an

PPEL

R.

R.

  • 5'
  • F
  • g
    • J

PAR

AD

AAAH

      • R

%AD

  • F

Baker, Coordinating

Engineer -

NQA

Beckley,

General

Supervisor

QC

Byram, Plant Superintendent

Dalpiaz, Technical

Supervisor

Freeman,

Inservice Inspection Specialist

Golden, Plant Engineering

Supervisor

Graham,

Senior Compliance

Engineer

Kichline, Licensing Specialist

McGann,

Compliance

Engineer

Palmer, Jr., Operations

Supervisor

Prego,

QA Supervisor

Operations

Ritter,

Power Production

Engineer

Steingass,

Inservice Inspection Supervisor

U. S. Nuclear

Re ulator

Commission

"J. Stair,

Resident

Inspector

"Denotes those

present at exit meeting

on ll/20 and 11/25.

    • Denotes those

present at exit meeting

on 11/20

  • ""Denotes those present at exit meeting

on ll/25.

2.

Licensee Action on Previous

Ins ection Findin

s

(Closed) Violation (387/86-05-01):

Failure to include longitudinal welds

in the ISI program.

Non-conformance

reports

(NCR) were written by the

licensee

which identified the longitudinal welds which were omitted from

the Unit

1 ten-year

program plan.

The inspector

reviewed the

NCRs,

selected

welds from the listing, and verified that the selected

welds were

now included in the licensee's

ISI ten year program plan.

A similar condition (longitudinal welds omitted from the ISI program

plan)

was identified at Unit 2.

The inspector

found that the Unit 2

welds were identified by the licensee,

and that those welds are

now

included in the current Unit 2 ISI plan.

Based

on the above this item is closed.

(Open) Violation (387/86-05-02):

Failure to respond to audit finding.

NDI-gA-15.3.7 Revision

2 required the Nuclear Support Group to provide

a

qualified visual testing inspector to witness

snubber testing.

The

NgA

audit found that there

was

no evidence that

a qualified inspector

was

provided,

and that the snubber testing

was witnessed

by the contractor

performing the work.

The audited organization

was required to provide

a

written response

to the finding within 30 days,

but failed to do so.

The

licensee

completed its corrective action regarding

the item,

and found

that it was

an isolated

case

based

on

a review of audit records.

The inspector

found that the

NgA audit finding was closed out by the

licensee

based

on deletion of the requirement

from revision

3 of the

controlling document.

Because

the licensee

had failed to provide

a quali-

fied inspector

as required,

the inspector raised

the question

regarding

the qualification of the contractor representative

who witnessed

the

snubber testing

and the validity of the testings

The inspector

stated

that the item will remain

open pending licensee verification that the

witnessing inspector

was qualified to perform that function.

(Open) Unresolved

item (387/85-10-02):

Radiographic film acceptability.

Background:

The recirculation

system riser piping was

removed for the

application of corrosion resistant

cladding

(CRC) as

recommended

by

NUREG 0313 to mitigate the occurrence

of intergranular stress

corrosion

cracking

( IGSCC).

The piping removal

process

resulted

in

a portion of

the original sweepolet-to-riser

weld being left in place,

and the

reinstallation of the piping after the application of CRC resulted

in a

double weld configuration at the location of that weld.

Because

of the

weld configuration

and the various materials

through which the ultrasound

must pass,

the licensee

was unable to perform

a meaningful ultrasonic

examination

using conventional

methods

due to the great

number of

ultrasonic signals which were present

on the cathode

ray tube at one

time.

The licensee

had developed

an automatic

UT technique

which did not

produce the desired results.

For this reason

the licensee

requested

relief from the

ASME Section

XI examination

requirements for preservice

inspection.

At the first refueling outage

the licensee

performed the

Section

XI volumetric examination of those

welds using radiography with

the Miniature Linear Accelerator

(MINAC).

This resulted

in personnel

exposure of 1.5

man

rem per weld,

and required all other activities to

stop while the radiography

was in progress.

The licensee

subsequently

decided to again explore the feasibility of using ultrasonics

as the

examination

method

and developed

a manual

technique

incorporating

the use

of a refracted longitudinal angle

beam.

This technique

was demonstrated

to the

NRC on

a mockup of the double weld,

CRC configuration,

and

was

found to be satisfactory

based

on the demonstration

results.

The licensee

is still evaluating the

UT technique,

and is considering its use

on the

riser welds and the withdrawal of relief request

No. IRR-6.

Relief

Request

No.

IRR-6 involves the licensee's

proposal

to perform the fol-

lowing in lieu of the surface

and volumetric examination

required

by ASME

Section XI:

ALTERNATE PROVISIONS

Visual examination of the weld will be performed during system pressure

tests

required

by IWB-5000 of Section XI.

Volumetric examinations

of the

weld will be performed to the extent practical

due to the geometric

and

metallurgical constraints

described

above.

The Unresolved

item resulted

from the

MINAC radiography that was done

during the first refueling outage.

The following documents

which are

related to the radiography were reviewed

by the inspector:

Southwest

Research

Institute

SWRI

Technical

Discussion

on Peach

Bottom

'Procedure

SWRI-NDT-400-4

'SWRI Justification of Accepting

RT by MINAC

PPLL

Letter dated July 7,

1987 with four attachments

EPRI/BWROG/NRC

'Technical

Basis

Document for the

use of MINAC

In addition to the above the inspector

reviewed the

MINAC radiographs

of

17 weldments in the recirculation

system.

The review was done to verify

the adequacy of the licensee's

volumetric examination of the unique

Susquehanna

sweepolet-to-riser

CRC double weld configuration.

Results

Wide variation in film density

ASME code

and

EPRI Technical

Basis

Document density limitations

were not met

Improper penetrameter

selection

and sensitivity

The practice of film evaluation

using penetrameters

from

adjacent film

The inspector

noted that the radiographs

were

made in a radiation environ-

ment with a 3.5

MEV rated

energy

MINAC unit that was extremely difficult

to manipulate

in a confined

space

such

as the

BWR drywell.

All of the

exposures

were double wall with angle deviations,

and in addition the

piping was filled'ith water at the time the radiographs

were made.

For the above mentioned

reasons

the inspector

determined that existing

radiographic quality was

as

good as

was obtainable

considering

the adverse

conditions

under which the radiographs

were made.

This item remains

open

pending the licensee'

deci sion regarding

the

volumetric examination of the riser double welds,

and the

need for the

relief from ASME code volumetric examination

requi rements.

Licensee Actions Taken to Im lement Generic Letter

GL 84-11

Inspections

which were conducted

pursuant to IE Bulletins 82-03,

Revision

1, 83-02,

and the

NRC Orders of August 26,

1983 revealed

intergranular

stress

corrosion cracking

(IGSCC) in large-diameter

recirculation

and

residual

heat

removal piping in several

operating

BWRs.

As

a result of

these inspections,

Generic Letter 84-11

was issued

on April 19,

1984 to

require

an on-going program for similar reinspections

at all operating

BWRs.

Susquehanna

Unit 1 was not in commercial

operation

when

IEB 83-02

was issued

on March 4,

1983

and was not referenced

by the bulletin.

The

facility began

commercial

operation

on June 8,

1983 and was shutdown for

its first refueling outage

on February 9,

1985.

The licensee

responded

to Generic Letter 84-11 via

PP&L letter PLA-2210

dated June

1,

1984,

and committed to perform induction heating stress

improvement (IHSI) on welds which were considered

non-conforming prior to

IHSI treatment.

The licensee

also committed in its letter that,

subsequent

to IHSI, the non-conforming/conforming

service sensitive

welds

would receive

augmented

inspections

to the extent defined in

NUREG 0313.

The licensee

committed to examine the applicable welds with the

ultrasonic

method,

or by radiography

using the Miniature Linear

Accelerator

(MINAC).

V

The inspector

found that the licensee's

commitments

were met in that

135

welds received

IHSI treatment.

A total of 108 of the welds were ultra-

sonicly examined,

and

17 welds were radiographed with MINAC following the

IHSI treatment.

Of the remaining ten welds eight were

1" diameter

branch

connections

and received

no

NDE, and two were 4" diameter welds which were

inaccessible

due to geometry.

The ultrasonic examinations

and the

radiography

were performed

by personnel

who were qualified in accordance

with IEB 83-02.

The facility technical Specifications identify the required surveillance

measures

for primary system leak detection.

No violations were identified.

4.

Review of Inservice

Ins ection Non-conformance

Re orts

NCR

The inspector

selected for review the following non-conformance

reports

from the

NCR log which is maintained

by the licensee:

NCR No. 87-0355

NCR No. 87-0375

NCR No. 87"0376

NCR No. 87-0409

NCR No. 87-0410

NCR No. 87"0411

NCR No. 87-0421

NRC No. 87-0544

The

NCRs were reviewed to ascertain

that the

NCRs clearly identified the

non-conforming condition, the disposition,

and that they were properly

closed out.

The inspector

found that the

NCRs were writteh for a variety of non-conforming

conditions which did not appear to establish

any particular trend.

Addi-

tionally all of the reviewed

NCRs were closed out based

on

gC verification

that the implemented corrective actions

conformed to the

recommended

disposition.

No violations were identified.

The inspectors

met with licensee

representatives

denoted

in Paragraph

1,

on November 20,

1987,

and at the conclusion of the inspection

on

November 25,

1987.

The inspectors

summarized

the purpose

and

scope of

the inspection,

and the findings.

At no time during this inspection

was

written material

provided by the inspector to the licensee.

The licensee

representatives

did not indicate that this inspection

involved any

proprietary information.

L'

'