Amend 75 to License NPF-14,correcting Error in Tech Specs for Facility Drywell Cooling Fans
ML17146B045
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 11/19/1987
From: Butler W
Office of Nuclear Reactor Regulation
To:
Shared Package
ML17146B046 List:
References
NUDOCS 8712030256
Download: ML17146B045 (9)


Text

~gS RECy, (4

P0 Cy

~i

~v Cl C

O C

Vl O~

Cy V/

+~

~O

+>>*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O. C. 20555 PENNSYLVANIA POWER 8( LIGHT COMPANY ALLEGHENY ELECTRIC COOPEPATIVE, INC.

DOCKET NO. 50-387 SUS UEHANNA STEAM ELECTRIC STATION, UNIT I AMENDMENT TO FACILITY OPERATING LICENSE Amendmert No. 75 License No. NPF-14 1.

The Nuclear Regulatory Commission (the Commission or the NRC) having found.

that:

A.

The application for the amendment filed by the Pennsylvania Power 5

Light Company, dated March 27, 1986 complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's regulations set forth in 10 CFR Chapter I; 8.

The facility will operate fn conformity with the application, the provisions of the Act, and the regulations of the CoIImIission; C.

There is reasonable assurance:

(i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifica-tions as indicated fn the attachment to this license amendment and paragraph 2.C.(2) of the Facility Operating License No.

NPF-14 is hereby amended to read as follows:

(2)

Technical S ecifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 75 and the Environmental Protection Plan con-tained in Appendix 8, are hereby incorporated in the license.

PP8L shall operate the facility in accordance with the Technical Specifica-tions and the Environmental Protection Plan.

3.

This license amendment is effective as of its date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

Attachment:

Changes to the Technical Specifications Date of Issuance:

November 19, 1987

/s/

Walter R. Butler, Director Project Directorate I-2 Division of Reactor Projects I/II y/gg87 DI-2/PM MThadani l~ /$7/87 l /

/87 PDI-2/D WButler.

() /gg/87

t 4I 3.

This license amendment is effective as of its date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION p2u~j~ >2WM

@alter R. Butler, Director Project Directorate I-2 Division of Reactor Projects I/II

Attachment:

Changes to the Technical Specifications Date of Issuance:

November 19,

].997

ATTACHMENT TO LICENSE AMENDMENT N0.75 FACILITY OPERATING LICENSE NO.

NPF-14 DOCKET NO. 50-387 Replace the following pages of the Appendix A Technical Specifications with enclosed pages.

The revised page is identified by Amendment number and contains vertical lines indicating the area of change.

The overleaf page is provided to maintain document completeness.*

REMOVE 3/4 6-37 3/4 6-38 INSERT 3/4 6-37*

3/4 6-38

~

CONTAINMENT SYSTEMS 3/4.6.6 PRIMARY CONTAINMENT ATMOSPHERE CONTROL DRYWELL AND SUPPRESSION CHAMBER HYDROGEN RECOMBINER SYSTEMS LIMITING CONDITION FOR OPERATION 3.6.6.

1 Two drywell and two suppression chamber hydrogen recombiner systems shall be OPERABLE.

APPLICABILITY:

OPERATIONAL CONDITIONS 1 and 2.

ACTION:

With one drywell and/or one suppression chamber hydrogen recombiner system inoperable, restore the inoperable system to OPERABLE status within 30 days or be'n at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

SURVEILLANCE RE UIREMENTS 4.6.6. 1 Each drywell and suppression chamber hydrogen recombiner system shall be demonstrated OPERABLE:

aO At least once per 6 months by energizing the recombiner system to at least 10 kw for

> 5 minutes.

b.

At least once per 18 months by:

1.

Performing a

CHANNEL CALIBRATION of all recombiner operating instrumentation and control circuits.

2.

Verifying the integrity of all heater electrical circuits by performing a resistance to ground test following the above required energization.

The resistance to ground for any heate~

phase shall be greater than or equal to 10,000 ohms.

3.

Verifying through a visual examination that there is no evidence of abnormal conditions within the recombiner enclosure; i.e, loose wiring or structural connections, deposits of foreign materials, etc.

SUS)UEHANNA - UNIT 1 3/4 6-37

CONTAINMENT SYSTEMS DRYWELL AIR FLOW SYSTEM LIMITING CONDITION FOR OPERATION 3.6.6.3 Drywell unit cooler fans 1V414 A&B, 1V416 A8B and recirculation fans lV418 ABB shall be OPERABLE at low speed.

APPLICABILITY:

OPERATIONAL CONDITIONS 1 and 2 ~

ACTION:

With one fan in one or more of the above pairs of fans inoperable at low speed, restore the inoperable fan(s) to OPERABLE status within

'30 days or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

b.

With both fans in any pair inoperable at low speed, follow the requirements of Specification

3. 0. 3.

SURVEILLANCE RE UIREMENTS 4.6,6.3 Each of the fans required above shall be demonstrated OPERABLE at least once per 92 days by:

a.

Starting each fan at low speed from the control

room, and b.

Verifying that each fan operates for at least 15 minutes.

SUSQUEHANNA - UNIT 1 3/4 6-38 Amendment No. 75