ML17139A387
| ML17139A387 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 06/30/1981 |
| From: | Ebneter S, Paolino R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17139A385 | List: |
| References | |
| 50-387-81-12, 50-388-81-06, 50-388-81-6, NUDOCS 8108110334 | |
| Download: ML17139A387 (13) | |
See also: IR 05000387/1981012
Text
8
~8
U.S.
NUCLEAR REGULATORY COMMISSION
OFFICE
OF INSPECTION
AND ENFORCEMENT
Region
I
50-387/81-12
R 3
N
. ~50-388
81-06
D
2
N
. ~566382
-388
CPPR-101
License
No. CPPR-102
Pri ori ty
B
Category
A
Licensee:
Penns
1 vania
Power and Li ht
Com an
2 North Street
Allentown
Penns
1 vania
18101
Facility Name:
Sus
uehanna
Steam Electric Station,
Units
1 and
2
Inspection at:
Berwick, Pennsylvania
Inspection conducted:
May 18-22,
1981
Inspectors:
.. Paolino,
Reactor Inspector
date signed
date signed
Approved by:
S.D. Ebneter,
Chief,
P ant Systems
Section-DETI
date signed
date sig ed
,Ins ection
Summar
~Cbi dl
1
101<<1
d2
8
1822
1381
C
01
dR
Nos.
50-387/81-12
and 50-388/81-06
Areas
Ins ected:
Routine unannounced
inspection
by one regional
based
inspector
o
licensee
wor activities
and documentation
pertaining to the installation
of safety related electrical
cables
and instrument
components;
review of
previously identified items; facility inspection
and discussions
with craft
personnel.
The inspection involved 10 inspection-hours
on the Unit
1 site
and 28 inspection-hours
on the Unit 2 site for one regional
based
inspector.
Results:
Of the four areas
inspected
no items of noncompliance
were identified
in two areas;
one item of noncompliance
in the electrical
area
(raceway/
conduit-separation);
one item of noncompliance
in the instrumentation
area
(tagging of nonconforming items).
Region I Form 12
(Rev. April 77)
(
8108110334
810727
'.
ADOCK 05000387
G
PDR.
DETAILS
1.
Persons
Contacted
Penns
lvania Power and Li ht
Com an
~R. Beckley,
Resident
Nuclear
QAE
P. Brady, Project Engineer
"P. 'Capatosto,
Project
- W. Curtis, Project Director
- S. Denson,
Project Construction
Manager
"R. Featenby,
Assistant Project Director
T. Quinn, Project Electrical
Engineer
Bechtel
Power Cor oration
- G. Bell,
Lead Project
QAE
R. Bhatia,
Resident Electrical
Engineer
M. Danielowicz,
QC Electrical
- D. Dinato, Assistant Project Field
QCE
S. Dinyar, Resident Electrical
Group Leader
G. Gelinas, Assistant Project Field
QCE
J.
Hershey,
Resident
Engineer
- J. Hoagland,
Storage/Maintenance
Supervisor
S.
Hoffman, Assistant
Resident Project Engineer
J.
Khandar,
QAE
M. Roke, Assistant
Lead Instrument, Engineer
A. Konjura,
QAE
J.
Kramer, Electrical
Foreman
P.
Mahood,
Lead Field Seismic Engineer
R. Matthews,
QA Records
Supervisor
- T. Minor, Project Field Engineer
W. Nelle,
QAE
- J. O'ullivan, Assistant Project Field Engineer
R. Roberts,
Area Field Engineer
S. Sheety,
QC Electrical
- C. Turnbow, Field Constructi,on
Manager
F. Wellock,
QCE
U.S. Nuclear
Re ulator
Commission
"G.
Rhoads,
Acting Senior Resident
Inspector
"denotes
personnel
present at exit meeting.
2.
~FiT
2
The inspector
observed
work activities in progress,
completed work and
plant status
in several
areas
of the plant during
a general
inspection
of Units
1 and 2.
The inspector
examined work items for obvious
defects
or noncompliance with NRC requirements
or licensee
commitments.
Particular note
was, taken regarding
the presence
of quality control in-
spectors
and indications of quality control activities through visual
evidence
such
as inspection
records,
material identifications,
nonconformance
and acceptance
tags.
In addition, the inspector
interviewed craft and
supervisory
personnel
encountered
in the work areas.
No items of noncompliance
were identified.
3.
Status of Previousl
Identified Items
Closed
Licensee Identified Item 387/80-00-29
and 388/8Q-00-29 per-
taining to derating of Westinghouse
Breakers.
The inspector
examined
licensee
documents
PLA-774 dated
May ll, 1981
and MCAR-1-65 dated
December
16,
1980.
The PLA-774 document revises
the manufacturers
production
run dates
used in identifying derated
breakers
manufactured
for Westinghouse.
The revised production
run dates,'ave
been determined
to exclude the breakers
in use or on order for the
Susquehanna
site.
This item is closed.
Closed
Licensee Identified Item 387/78-00-05
and 388/78-00-05 per-
taining to the Reactor Protection
System
Mode switch replacement
and
the installation of locking rings to secure
General Electric Control
.
switches
No.
CR-2940.
The inspector
reviewed licensee/vendor
correspondence,
work authorizations
and completed corrective action for both items
noted
above
and determined
the action taken to be acceptable.
This
item is closed.
I
Closed
Licensee Identified Item 387/78-00-02
and 388/78-00-02 per-
taining to the seismic qualification of the Westinghouse
switchgear
assemblies
for the
5
KV Trunion mounted Potential ITransformer
Assembly.'he
inspector
reviewed licensee
documentation
including the MCAR-1-22
report,
the nonconformance
report NCR-2514,
the
PP5L audit report CL-
29 verifying installation of the Potential
Transformer Kits, and the
seismic qualifications document
NgD-145-00.
The inspector determined
the action taken to be acceptable.
This item is closed.
Closed
Item of Noncom liance 387/80-06-01 pertaining to instrument
line slope.
The inspector
examined
licensee corrective action
and
steps
taken to prevent reoccurrence.
The inspector determined
action
taken to be adequate.
This item is cl'osed.
0 en
Item of'Noncom liance 387/80-06-02 pertaining to the thermal
element bracket support.
The inspector
examined
licensee
documentation
and resolution for selection
and installation of thermal
element
brackets.
Discussions with licensee
and Architect/Engineer
representatives
indicate that static loading
on the mounting brac)et
was the only
design consideration'."-'he
seismic 'effect on the system
as a.whole
(Instrument function and bracket)
was not considered.
This item
remains
open.
l
f,
\\ ~
E
(0 en
Unresolved
Item'387/'81-01-03 pertaining to separation
crstersa
externa
to e ectrlca
equipment
and panels.
The inspector
reviewed the revision to the Field Procedure
FP-E-10 which was modified
to include separation
external
to electrical
panels/equipment.
However,
the licensee's. corrective action does not address
existing separation
violations nor action to be taken to preclude further noncompliances.
This item remains
open.
(0 en) Unresolved
Item 387/ 81-01-02
ertaining to maintenance
and
survei
ance of e ectrical
pane s/equipment in storage.
The inspector
reviewed the licensee's
program for maintenance/surveillance
of storage
requirements for stored equipment.
The
inspector determined that
implementation of the program (consisting of scheduled daily surveillance
by elevation
and areas)
appeared
to be inadequate.
The inspector
examined
areas
30 and
32 at elevation 683'-0 of Unit 2.
Panel
Nos.
2C0201,
2C022 and
2D274 were not heated
as requi'red.
In addition, the
protective cover for 2C021
was tom in several
places,
exposing the
panel to dirt and dust.
Construction
personnel
stated this area
had
been inspected earlier that morning.
This item remains 'open.
4.
Electrical
Cables
and Terminations
- Work Observations
The inspector observed
work performance, partially completed
work and
completed work, as appropriate,
relative to select cables,
raceways
and conduit to determine whether the requirements
of applicable specifications,
work procedures
and inspection
procedures
are being accomplished
in
accordance
with NRC requirements
and licensee commitments.'reas
examined include handling,
use of specified materials,
routing, separation,
and
QC inspections.
a.
For this determination
the inspector witnessed
cable pulls (Unit
2)
FK2Q0810C from 2B227Q23 to 2TC623-B,
and
FK2Q0808C from 2B227Q22
to 2TC623-B.
The inspector reviewed the following applicable
documentation.
Wiring Drawing E-155.
Cable
Reel
No. 2-L12-8.
Field Procedure
FP-E-5, revision 4, part I and II (cable
pulling).
Specification 8856-E-59, revision ll, on Cable
and Wire
Installation Procedure.
bI
0
s<
Cable Pull Card routing schedule
and check-off sheet.
No items of noncompliance
were identified.
b.
The inspector
examined safety related cable raceway/conduit
installations located at .elevation
670 in the Units
1 and
2
Reactor
Building and made the following observations.
Unit 2
Conduit No.
E2K307 (red division) less
than
1 inch from tray
No
~
F2KG61,62 (green division)
~
Conduit No.
E2MOSS (red division) less
than
1 inch from ad-
jacent unlabeled
conduit and conduit
FIK793 (green division).
Unit
1
Conduit No.
IP0059 (non-Q) less
than
1 inch from Conduit No.
EIP349 (red division).
Conduit No.
IKG040 (non-Q) less
than
1 inch from Conduit No.
FIKG07 (green division).
Conduit No.
FIP057 (green division) less
than
1 inch from
conduit No.
EIK684 (red division).
QC inspection
completed
April 14,
1979
and
December
6,
1980.
Conduit No.
FIP479 (green division) less
than
1 inch from
adjacent fire line conduit and conduit No.
EIK994 (red
division).
Section 2.3.4 of drawing E-49,
sheet
9 revision
10 on conduit and
cable tray Notes
and Defects states,
in par t, that:
"The minimum
separation
distances
required
between totally enclosed
raceways
located in areas
not subject to fire.
. .or mechanical
damage
shall
be as follows:
2.3.4. 1
One inch minimum between
class
IE wireways,
cable trays
or conduits.
2.3.4.2
One inch minimum between
class
IE wireways,
cable trays
or condui ts and simi liar non-class
IE raceways.
The licensee
was informed that this is an item of noncompliance
and
a violation of 10 CFR 50, Appendix 8, Criterion
Ijt.
50-
387/81-12-01;
50-388/81-06-01
For this determination
the inspector
examined electrical
grounding
between trays/conduits.
'I
- ,"'f,> f
~
Cf)9
"> 'y
3<
~
)3 '>f.."Vif&
~
~
~ !
<> f,'tf)'j'f
'
) I
.~i'i~lj
~ "<>< ">"/"t<1 i~ "f"'8:"'.
3.
9'>>i
3 ~"BG
0
The inspector observed that the electrical
ground conductor
(No.
4/0) was attached
to the side of tray No.
FIPF07 (el 670, Area
28) for a distance of 6 ft then crosses
over at right angle
adjacent parallel conduits
coming into contact with conduit Nos.
FIP479 (green)
EIK995 (red)
and the non-g fire line conduit.
This installation
has the effect of reducing the
1 inch separation
to 1/2 inch.
Placement of the electrical
ground between
the tray
and the conduit appears
to defeat the purpose of maintaining the
required
1 inch separation
between
the tray and conduit.
The
1
inch air gap has
been determined
as the minimum separation
requirements
to prevent
damage
from overheating
to adjacent
raceways/conduits.
Discussions
with licensee
.and construction
personnel
indicate
this concern
was not addressed
in installation procedures
or
instructions.
This item is unresolved
pending
NRC review of licensee resolution
and corrective action (50-387/81-12-02;
50-388/81-06-02).
d.
The inspector
reviewed the following documents
to ascertain
the
status of the D-11 cable problem that was identified in licensee
letters
PLI-8176 dated
May 21,
1980 and PLI-12396 dated
June
12,
1979.
Deficiency Report
No.
92 issued
January 4, 1979, verified
completion
March 23,
1981.
Deficiency Report
No.
0096 dated
June
12, 1979.
Non-conformance
Reports
3699
and
3972.
Field Procedure-FP-E-5
revision 4.
Field Procedure-FP-E-8
revision l.
gAL-1007 dated
October 29,
1980
gAL-884 dated April 10,
1980
gAL-756 dated
September
5,
1979
gAL-726 dated July 16,
1979.
Licensee/Contractor
test results indicating 10-12/ conductor
failure rate.
Based
on the above test results
the licensee
is removing all
damaged
D-11 cable in trays
and conduits.
In addition,
cable~s
adjacent to the damaged
D-11 cables (in conduits only) are also
being replaced.
The licensee is not purchasing
any more D-11 cables.
Existing D-
11 cables in storage will be used
on Unit 2, but only if the
cable runs in trays/conduit is less
than
50 ft.
The inspector
had no further questions.
'0
5.
Instrumentation
Com onents/S
stems
Work Observations
The inspector
observed
work performance, partially completed work and
completed work, as appropriate,
relative to the instrument
components
selected
below and related
equipment to determine
whether the require-
ments of applicable specifications,
work procedures
and inspection
procedures
are accomplished
in accordance
with NRC requirements
and
licensee
commitments.
Items examined for this determination
include:
No.
HDM-27534G, Area 30, el 818'-0.
No.
HDM-27534A, Area 32, el 799'-0.
No.
HDM-27514A, Area 34, el 799'-0.
No.
HDM-27514B, Area 34, el 799'-0.
The inspector
noted that the solenoid valve no.
SV-27534A for Damper
No.
HDM-27534A appeared
to have
had its flex-conduit connection cut
and
on the floor with the valve.
Solenoid valve No.
SV-27514B was
missing
and appeared
to have
been
taken
from the damper control unit
pipe coupling which still contained
pipe
compound in the thread
arear'onstruction
QC personnel
with the .inspector indicated it was
common
practice to remove
components for use in other areas
to meet turnover
schedule
dates.
The inspector also observed that although the sole-
noid valves
noted above are
non-Q and are being
used in safety related
systems
none of the components
referenced
were tagged to identify the
non-conforming component.
Section 4.4. 1 of Field Procedure
FIP-G-3,
on Hold Tags,
states,
in
part:
".
.
.The Quality Control Engineer shall
prepare
a hold for QC
clearance
tag and affix it to the non-conforming item.
Section 4.4.2 of Field Procedure
FIP-G-3, states,
in part ".
. ;The
tag shall
remain
on the item until
a disposition
has
been
implemented
and the re-inspection
accepted
by
QC Engineer.
The licensee
was informed that this was
an item of noncompliance
and
a
violation of 10 CFR 50 Appendix B, Criterion V. (50-388/81-06-03)
6.
Unresolved
Items
Unresolved
items are matters
about which more information is required
in order to ascertain
whether they are acceptable
items or items of
n'oncompliance.
', An unresolved
item is discussed
in Details,
Paragraph
4c.
P
,4
II
t
/s ~3 ~It)*$
Cg",f 'I)
~ kw
The inspector
met with licensee
and construction
representatives
(de-
noted in Oetai ls, Paragraph
1) at the conclusion of the inspection
on
May 22,
1981.
The inspector
summarized
the purpose
and
scope of the
inspection
and identified the inspection findings.
The
NRC Acting
Senior Resident
Inspector
was present for this meeting.