ML17138B069

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 791001-05
ML17138B069
Person / Time
Site: Susquehanna  
Issue date: 11/15/1979
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17138B066 List:
References
50-387-79-32, 50-388-79-17, NUDOCS 8002140423
Download: ML17138B069 (1)


Text

APPENDIX A NOTICE OF VIOLATION Pennsylvania Power and Light Company Docket No. 50-387 Based on the results of the NRC inspection conducted on October.

1-5, 1979, it appears that one of your activities was not conducted. in full compliance with NRC regulations and conditions of your licenses as indicated below:

10 CFR 50, Appendix B, Criterion V, states, in part, "Activities affecting quality shall be prescribed and shall be accomplished in accordance with these instructions, procedures.

PSAR Section D.2.5 states, in part, "Activities affecting quality will be pre-scribed by documented instructions, procedures PSAR Section D.3.3.7 states, in part, ".

. use of qualified procedures and application thereof as required by established standards will be rigidly en-forced."

Specification C-72, Revision 4, paragraph 4.1.6 states, in part, "For concrete structures the minimum distance between expansion anchor centerlines shall be 10 nominal diameters unless otherwised specified by the project engineer."

On October 5, 1979, contrary to the above, flow, transmitter FT-08612B, and level transmitter LT-15776B rigid seismic support brackets were installed with ex-pansion anchor centerlines measuring 3-3/4 inches instead of the required 5

inches.

This is an infraction.