Emergency Plan Implementing Procedures
ML17116A124
Person / Time
Site: Cooper Entergy icon.png
Issue date: 04/17/2017
From: Shaw J
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NLS2017038
Download: ML17116A124 (2)


Text

H Nebraska Public Power District NLS2017038 April 17,2017 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Always there when you need us

Subject:

Emergency Plan Implementing Procedures Cooper Nuclear Station, Docket No. 50-298, License No. DPR-46

Dear Sir or Madam:

50.54(q)

The purpose of this letter is to report a change to the following Emergency Plan Implementing Procedures (EPIP) and provide a summary of the associated 10 CPR 50.54(q) analysis for the changes to the EPIPs:

EPIP 5.7.1 EPIP 5.7.17 EPIP 5.7.17.1 Revision 57 Revision 49 Revision 3 Emergency Classification CNS-Dose Assessment Dose Assessment (Manual)

This letter contains no commitments.

If you have any questions regarding this submittal, please contact me at (402) 825-2788.

Sincerely,

/bk

Attachment:

Report of Change and Summary of50.54(q) Analysis Emergency Plan Implementing Procedure 5. 7.1, Revision 57

Enclosures:

1. Emergency Plan Implementing Procedure 5. 7.1, Revision 57
2. Emergency Plan Implementing Procedure 5.7.17, Revision 49
3. Emergency Plan Implementing Procedure 5. 7.1 7.1, Revision 3 COOPER NUCLEAR STATION P.O. Box 98 /Brownville, NE 68321-0098 Telephone: (402) 825-3811 /Fax: (402) 825-5211 www.nppd.com

NLS2017038 Page 2 of2 cc:

Regional Administrator, w/ attachment and enclosures (2)

USNRC - Region IV Director, Spent Fuel Project Office, w/ attachment and enclosures Office of Nuclear Material Safety and Safeguards Senior Resident Inspector, w/ attachment (enclosures per controlled document distribution)

USNRC-CNS NPG Distribution, w/ attachment and w/o enclosures CNS Records, w/ attachment and w/o enclosures