ML17095A922
ML17095A922 | |
Person / Time | |
---|---|
Site: | LaSalle ![]() |
Issue date: | 11/16/2016 |
From: | Chuck Zoia NRC/RGN-III/DRS/OLB |
To: | Exelon Generation Co |
Shared Package | |
ML15274A405 | List: |
References | |
Download: ML17095A922 (241) | |
Text
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 1 Op-Test No.: 2016301 Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Unit 1 is at 7%4% power during a Startup.
Turnover: Secure the RWCU drain to the Main Condenser. Continue control rod withdrawal in preparation for taking the Mode Switch to RUN.
Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Secure RT Reject IAW LOP-RT-09 2 none R (ATC) Control Rod Withdrawals 3 none T (SRO) Damage to Fire Hose Station 109 Reported (TRM) 4 mni018 I (ATC) A IRM INOPfails UPSCALE, Half SCRAM 5 g8c75g14 C (BOP) TBCCW Header Pressure Low 6 B EHC Pump TRIP, Standby Pumps Fails to meh002 C (BOP)
Auto-Start 7 R0601 T (SRO) Low ADS Bottle Bank Nitrogen Pressure (TS) 8 mrd279 C (ATC) CRD FCV Fails CLOSED 9 RWCU Leak in RT Pump Room, RWCU Fails to mrw010 M (ALL)
Isolate 10 Two Areas Above Max Safe, Emergency RPV none M (ALL)
Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-1 Rev. 0 07/20/2016 DEVELOPED BY: Colin Betken 8/15/2016 Instructor Date VALIDATED BY: Draper / Messina / Gallick / Jozwiak 8/1/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Exam Author Date
NRC 15-1-1 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-1 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 1. Secure RT Reject IAW LOP-RT-09 As a continuation of the unit startup the crew will secure RT Reject per LGP-1-1
- 2. Control Rods Withdrawals The crew is expected to withdraw Control Rods per LGP-1-1 to continue the Unit Startup.
- 3. Damage to Fire Hose Station 109 Reported (TRM)
Unit 1 Rounds Operator will report damage to a fire station and the Unit Supervisor will determine TRM requirements.
- 4. A IRM fails INOP, Half SCRAM The crew will determine A IRM is INOP and Bypass it A IRM, then reset the half scram
- 5. TBCCW Header Pressure Low The crew will respond by starting the standby pump and pressures will return to normal.
- 6. B EHC Pump TRIP, Standby Pumps Fails to Auto-Start The crew will respond by manually starting the standby EHC Pump.
- 7. Accumulator Trouble Alarm (TS)
- 8. CRD FCV Fails CLOSED The crew will have to transfer to the standby FCV when the online FCV fails.
- 9. RWCU Leak in RT Pump Room RT will experience a steam supply leak and the isolation valves will fail to automatically and manually isolate. The crew will manually scram the reactor per LGA-002
- 10. RWCU Fails to Isolate When the crew attempts to manually isolate RT due to the automatic isolations failure, RT will fail to isolate.
- 11. Two Areas Above Max Safe, Emergency RPV Blowdown The crew may anticipate Blowdown. When a second area parameter exceeds a Max Safe value, The LGA-004 Blowdown will be performed.
Critical Tasks
- 1. With a primary system discharging into the secondary containment, and discharge cannot be isolated or isolation attempt failed, scram the reactor, before any area exceeds the maximum safe operating levels..
- 2. With a primary system discharging into the secondary containment, and temperatures/radiation levels exceeding maximum safe values in more than one area, INITIATE emergency depressurization. (or anticipates Blowdown and depressurizes rapidly via the main turbine bypass valves.)
Page 2 of 38
NRC 15-1-1 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 3 of 38
NRC 15-1-1 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall IC 3322 Password 3323
- 2. Place simulator in RUN.
- 3. Load and run the Smart Scenario: NRC15-1-1.ssf
- 4. Place Protected Equipment rings and/or robust barriers on the following components: None
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the following panel manipulations:
- Place B EHC Pump in RUN
- Place A EHC Pump in STBY
- Place A WT Pump in RUN
- Place B WT Pump in STBY
- Verify IRMs between 19 and 75
- Verify RCMS prompting is set to RAISE
- Verify the Main Condenser Low Vacuum Isolation Logic Bypass Switches are in NORM with Keys removed.
- 7. Place the following Tags: none
- 8. Have a copy of the following procedures:
- LGP-1-1, completed up to Step E.6.4, IRM/APRM overlap completed per E.6.5 through E.6.8, and E.6.10 complete
- LOP-RM-01, completed up to Step E.2
- LOP-NR-02, completed up to Step E.2.1.8
- LOP-RT-09, completed up to Step E.3. (Note: Step E.2 is N/A)
- One copy of LOP-RT-09, (blank) for Unit Supervisor
- Mark up Rod sheet to current rod per RCMS
- 9. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 4 of 38
NRC 15-1-1 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 1 Op-Test No.: 2016301 Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Unit 1 is at 7% power during a Startup.
Turnover: Secure the RWCU drain to the Main Condenser. Continue control rod withdrawal in preparation for taking the Mode Switch to RUN.
Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Secure RT Reject IAW LOP-RT-09 2 none R (ATC) Control Rod Withdrawals 3 none T (SRO) Damage to Fire Hose Station 109 Reported (TRM) 4 mni018 I (ATC) A IRM fails INOP, Half SCRAM 5 g8c75g14 C (BOP) TBCCW Header Pressure Low B EHC Pump TRIP, Standby Pumps Fails to 6 meh002 C (BOP)
Auto-Start 7 R0601 T (SRO) Low ADS Bottle Bank Nitrogen Pressure (TS) 8 mrd279 C (ATC) CRD FCV Fails CLOSED RWCU Leak in RT Pump Room, RWCU Fails to 9 mrw010 M (ALL)
Isolate Two Areas Above Max Safe, Emergency RPV 101 none M (ALL)
Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification Formatted Table Formatted: Indent: Left: 0", First line: 0" ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 6 BOP Normal: 1 Malfunction(s) after EOP (1-2): 1 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 5 EOP Contingencies (0-2): 1 SRO Tech Spec (2 per set): 2 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 2 Formatted: Indent: Left: 0", Hanging: 0.62", Space Before: 7.2 pt Formatted: Line spacing: single, Tab stops: Not at 0.5" APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 5 of 38
NRC 15-1-1 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC Provided initial indications, respond to a CRD failures from the Main Control 25.048 Room IAW station procedures.
Provided initial conditions, perform Control Room actions for a loss of 42.003 SRM/IRM indication IAW station procedures.
Given Unit Supervisor authorization, perform a Notch Withdrawal of a Control 47.001 Rod IAW station procedures.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given Unit Supervisor authorization, perform a normal unit startup from Mode 300.020 Switch in START-HOT STBY through RR pump upshift IAW station procedures.
Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 RO - BOP/ASSIST Maintain Reactor Vessel Water Level By Rejecting Water Via the Reactor 27.009 Water Cleanup System to either the Main Condenser or to Radwaste.
Perform Control Room actions to EVALUATE a breach of Secondary 70.021 Containment.
73.005 Perform the in plant actions to shift EHC pumps.
Perform the Main Control Room Actions for an Instrument Nitrogen System 97.016 Trouble Alarm.
Perform the Main Control Room actions for a Turbine Building Closed Cooling 113.016 Water (TBCCW) Pump Discharge Pressure Low Alarm Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given Unit Supervisor authorization, perform a normal unit startup from Mode 300.020 Switch in START-HOT STBY through RR pump upshift IAW station procedures.
Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-02, Secondary Containment Control, in progress, evaluate plant 417.000 conditions and control temperature in secondary containment by operation of ventilation, IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Page 6 of 38
NRC 15-1-1 Revision 00 SRO - UNIT SUPERVISOR Provided initial indications, respond to a CRD failures from the Main Control 25.048 Room IAW station procedures.
Maintain Reactor Vessel Water Level By Rejecting Water Via the Reactor 27.009 Water Cleanup (RWCU) System to either the Main Condenser or to Radwaste.
Provided initial conditions, perform Control Room actions for a loss of 42.003 SRM/IRM indication IAW station procedures.
Given Unit Supervisor authorization, perform a Notch Withdrawal of a Control 47.001 Rod IAW station procedures.
Perform Control Room actions to EVALUATE a breach of Secondary 70.021 Containment.
73.005 Perform the in plant actions to shift EHC pumps.
Perform the Main Control Room Actions for an Instrument Nitrogen System 97.016 Trouble Alarm.
Perform the Main Control Room actions for a Turbine Building Closed Cooling 113.016 Water (TBCCW) Pump Discharge Pressure Low Alarm Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given Unit Supervisor authorization, perform a normal unit startup from Mode 300.020 Switch in START-HOT STBY through RR pump upshift IAW station procedures.
Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-03, Primary Containment Control, in progress, cool the 421.000 Suppression Pool IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Page 7 of 38
NRC 15-1-1 Revision 00 Event-1
==
Description:==
Secure RT Reject per LOP-RT-09 Initiation: TurnoverOn direction of Lead Evaluator Cues: LGP-1-1 Objective Position EXPECTED OPERATOR RESPONSE Per LOP-RT-09
- VERIFY CLOSED 1G33-F031, RWCU Reject Header Orificea Bypass Valve o If required, THROTTLE 1G33-F042, RWCU Return Upstream Isolation Valve, to establish desired RWCU System Flow (360 gpm max) 27.009 BOP
- VERIFY CLOSED the following:
- From Control Room Panel 1H13-P602 VERIFY:
o RWCU Reject Flow Indicator 1G33-R602 shows no flow (expected) o Reactor level is stable at desired level ATC
- Monitor Reactor Level and inform Unit Supervisor of any changes 27.009 US
- Direct above actions Page 8 of 38
NRC 15-1-1 Revision 00 Event - 1
==
Description:==
Secure RT Reject per LOP-RT-09 Simulator Operator Actions With the concurrence of the Lead Evaluator Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: When RT Reject is secured.
Page 9 of 38
NRC 15-1-1 Revision 00 Event-2
==
Description:==
Withdraw Control Rods to raise power Initiation: TurnoverFollowing crew assuming shift, on direction of Lead Evaluator Cues: LGP-1-1 Objective Position EXPECTED OPERATOR RESPONSE
- Monitors control room panels and notify the CRS of any unusual or unexpected Formatted: Font: 10 pt 300.020 BOP conditions. Formatted: Font: 10 pt
- Peer checks movements.
Per LGP-1-1 Formatted: Font: 10 pt, Bold
- Continue to increase CTP with control rod withdrawal Formatted: Font: 10 pt o Monitor IRM and APRM recorders o Verify Main Turbine BPVs open as reactor power increases o Formatted: Indent: Hanging: 0.01", Bulleted + Level: 1 +
Per LOP-RM-01: Aligned at: 0" + Indent at: 0.25"
- Verify Rod desired to be positioned is selected on the Rod Select Display Formatted: Font: 10 pt, Bold
- Verify rod position information is correct on the Rod Select display/Status Formatted: Font: 10 pt Display/Core Map Display
- Verify no insert or withdraw block indications on the Rod Select Display
- Verify CRD Drive Flow Trip Circuit Bypass Switch is in the BYPASS position
- CRD Drive Flow Trip Circuit Test Switch is in the NORMAL position.
- Simultaneously DEPRESS and HOLD both CONTINUOUS WITHDRAW and WITHDRAW push-button. Selected rod will Formatted: Indent: Left: 0.25", No bullets or numbering
- continuously withdraw until one (1) push-button is released.
- Rod Withdraw Sequence begins:
o Rod INSERT indication appears on the ROD SELECT Display or Formatted: Bulleted + Level: 1 + Aligned at: 0.25" +
STATUS Display. Indent at: 0.5", Tab stops: Not at 0.49" o Rod WITHDRAW indication appears on the ROD SELECT Formatted: Font: (Default) Arial 300.020 Display or STATUS Display. Formatted: List Paragraph, No bullets or numbering ATC 47.001 DEPRESS rod WITHDRAW push-button and CHECK control rod withdrawal Formatted: Font: 10 pt sequence begins:
Formatted: Indent: Hanging: 0.01", Bulleted + Level: 1 +
Rod insert indication appears on the Rod Select or Status Display Aligned at: 0" + Indent at: 0.25", Tab stops: Not at 0.49" Rod withdraw indication appears on the Rod Select or Status Display Formatted: Indent: Left: 0.48", Hanging: 0.01", No bullets Control Rod motion is indicated on the Rod Select or Status Display or numbering, Tab stops: 0.49", List tab RELEASE rod WITHDRAW pushbutton and CHECK: Formatted: Font: 10 pt Rod position indication on Rod Select Display, Status Display or Core Map shows new rod position Observe changes in nuclear instrumentation indications Rod settle light is lit for ~2 seconds Repeat for each Control Rod movement o Control Rod continuous motion is indicated on the ROD SELECT Formatted: Font: (Default) Arial Display or STATUS Display. Formatted: Font: 10 pt
- OBSERVE changes in nuclear instrumentation indications. Formatted: List Paragraph, Indent: Left: 0.25", Space
- When either push-button is released, Rod SETTLE indication is lit for Before: 0 pt, After: 0 pt, No bullets or numbering, approximately 2 seconds. Widow/Orphan control, Adjust space between Latin and Asian text, Adjust space between Asian text and numbers
- New rod position will be indicated on the ROD SELECT Display, STATUS Display and CORE MAP Display. Formatted: List Paragraph, Indent: Left: 0.25", Space o If control rod is withdrawn to position 48, PERFORM Rod Coupling Before: 0 pt, After: 0 pt, No bullets or numbering, Widow/Orphan control, Adjust space between Latin and Asian Check per Step E.7, as applicable.
text, Adjust space between Asian text and numbers Page 10 of 38
NRC 15-1-1 Revision 00
- SIMULTANEOUSLY DEPRESS both CONTINUOUS WITHDRAW and WITHDRAW push-buttons. Formatted: Font: (Default) Arial
- CHECK to ensure that the control rod does NOT go to the withdrawn Formatted: Font: 10 pt Overtravel position using as many of the following indications as are available Formatted: List Paragraph, Indent: Left: 0.49", Space Before: 0 pt, After: 0 pt, No bullets or numbering, o OBSERVE that the "+ +" position indication goes blank then returns to Widow/Orphan control, Adjust space between Latin and Asian the "+ +" position on the ROD SELECT Display or STATUS Display. text, Adjust space between Asian text and numbers, Tab o OBSERVE that drive flow drops from normal flow to stall flow. stops: 0.49", List tab o OBSERVE that CRD OVERTRAVEL does NOT alarm. Formatted: Font: (Default) Arial
- Repeat for each Control Rod movement Formatted: Font: 10 pt
- Upon completion of Control Rod moves, verify CRD Drive Flow Circuit BYPASS Switch is in the ACTIVE position Formatted: Font: (Default) Arial 300.020 Formatted: Font: 10 pt US
- Direct above action 47.001 Formatted: Font: (Default) Arial Formatted: Font: 10 pt Formatted: Font: 10 pt Formatted: Left Page 11 of 38
NRC 15-1-1 Revision 00 Event - 2
==
Description:==
Withdraw Control Rods to raise power Simulator Operator Actions none Simulator Operator Role Play None Floor Instructor Notes/OPEX/TRs None Terminus: When indicated APRM power has risen by 2% or at the discretion of the Lead Evaluator Page 12 of 38
NRC 15-1-1 Revision 00 Event-3
==
Description:==
Damage to Fire Hose Station F109 Initiation: On direction of Lead Evaluator Cues: Phone call Objective Position EXPECTED OPERATOR RESPONSE
- Monitor Plant conditions and update crew as required
- Declare the Fire Hose Station INOP
- Enter TRM 3.7.m Action A.1, place additional fire hose from operable hose station to protect the affected area in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> AND Required Action A.3.1, restore the inoperable station to an operable 201.011 US status in 14 days OR Required Action A.3.2, prepare the corrective action report in 14 days
- Direct Field Supervisor to make preparations to support TRM requirements
- Inform Fire Marshall Page 13 of 38
NRC 15-1-1 Revision 00 Event - 3
==
Description:==
Damage to Fire Hose Station F109 Simulator Operator Actions With the concurrence of the Call the 2307 and follow role play below.
Lead Evaluator Simulator Operator Role Play With the concurrence of the Lead Evaluator:
Call as MMD and report, While performing TRM Fire Hose Station inspections, per LMS-FP-15, I you discovered Fire Hose Station F109 on Reactor Building 820, Location F9, the hose reel is benthas a bent hose reel and will not allow unwinding of the hose.
Role Play in plant operators as necessary if asked to confirm the report of hose station damage.
Floor Instructor Notes/OPEX/TRs none Terminus: Following phone call to Shift Manager for TRM requirements.
Page 14 of 38
NRC 15-1-1 Revision 00 Event-4
==
Description:==
A IRM Fails INOP, Half SCRAM Initiation: On direction of Lead Evaluator, release Event 4 Cues:
Automatic Actions: Half Scram Expected Annunciators:
1H13-P603-A308, ROD OUT BLOCK 1H13-P603-B304, CHANNEL A IRM HI-HI/INOP 1H13-P603-B206, CHANNEL A1 AND B1 NEUTRON MONITOR TRIP Key Parameter Response: A RPS solenoids de-energize Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor plant parameters and update the crew as required Per LOR-1H13-P603-B304
- Verify Automatic Actions
- VERIFY A IRM Range Switch in the correct position
- If one IRM in Channel A has failed High or is Inop, BYPASS that IRM and INITIATE corrective action to restore operability.
- Stop all Control Rod motion / Power changes Formatted: Indent: Left: 0.24", No bullets or numbering
- Check IRM indications
- Direct above actions 42.003 US
- REFER to Tech Spec 3.3.1.1 and TRM 3.3.c (No timeclocks applicable)
- Inform Shift Manager Page 15 of 38
NRC 15-1-1 Revision 00 Event - 4
==
Description:==
A IRM Fails INOP, Half SCRAM Simulator Operator Actions With the concurrence of the Release Event 4 Lead Evaluator Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs None Terminus: When Half Scram Reset Page 16 of 38
NRC 15-1-1 Revision 00 Event-5
==
Description:==
TBCCW Header Pressure Low Initiation: On direction of Lead Evaluator, release Event 5 Cues:
Automatic Actions: none Expected Annunciators: LOR-1PM10J-A304, Turbine Building Closed Cooling Water Pump Discharge Header Pressure Low Key Parameter Response: Lowering TBCCW Header Pressure Objective Position EXPECTED OPERATOR RESPONSE 113.016 Per LOR-1PM10J-A304
- CHECK Turbine Building Closed Cooling Water Pump Discharge Header pressure is less than or equal to Alarm setpoint
- START a standby Turbine Building Closed Cooling Water Pump
- DISPATCH operator to TB 735 to INSPECT Turbine Building Closed Cooling Water Pump for proper operation per LOP-WT-02, Startup and Operation of Turbine Building Closed Cooling Water System BOP
- INITIATE appropriate corrective action as required OR Per LOA-WT-101
- CHECK TBCCW Discharge Header pressure - GREATER THAN 50 psig.
- START standby TBCCW pump (B). Formatted: Font: Not Bold Formatted: Indent: Left: 0.24", No bullets or numbering
- Observe and report plant parameters 113.016
- Direct above actions US
- Set WT temperature pressure as critical parameter
NRC 15-1-1 Revision 00 Event - 5
==
Description:==
TBCCW Header Pressure Low Simulator Operator Actions With the concurrence of the Release Event 5 Lead Evaluator Simulator Operator Role Play When dispatched to 1A WT Pump while it is still running, wait 2 minutes and report, there is rumbling noise coming from 1A TBCCW pump.
Floor Instructor Notes/OPEX/TRs Terminus: When the 1B TBCCW Pump has been started and the 1A TBCCW Pump has been secured.
Page 18 of 38
NRC 15-1-1 Revision 00 Event-6
==
Description:==
B EHC Pump TRIP, Standby Pumps Fails to Auto-Start Initiation: On direction of Lead Evaluator, release Event 6 Cues:
Automatic Actions: none (Auto Start Fails)
Expected Annunciators:
1PM02J-B401, EHC HYDRAULIC FLUID PUMP AUTO TRIP Key Parameter Response: EHC Pressure lowering and EHC Pump Auto Trip Light illuminated Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM02J-B401
- VERIFY Standby EHC hydraulic Fluid Pump has STARTED
- Monitor EHC Pump and system parameters return to normal, refer to LOP-EH-04 as necessary
- DISPATCH operator to Bus 132A to INSPECT EHC Hydraulic Fluid Pumps breaker for abnormalities
- Monitor Reactor Power, level and pressure and update the crew as ATC necessary
- Dispatch Equipment Operator to investigate Tripped EHC Pump
- Direct above actions 73.005 US
- Notify Shift Manager Page 19 of 38
NRC 15-1-1 Revision 00 Event - 6
==
Description:==
B EHC Pump TRIP, Standby Pumps Fails to Auto-Start Simulator Operator Actions With the concurrence of the Release Event 6 Lead Evaluator Simulator Operator Role Play If sent to investigate B EHC Pump report that the motor is hot to the touch.
Floor Instructor Notes/OPEX/TRs If the standby EHC Pump is not started by 1100 psig EHC pressure (~2 minutes) the Main Turbine will trip and the Reactor will scram.
Terminus: When A EHC Pump is running and parameters have returned to normal and/or at the discretion of the Lead Evaluator.
Page 20 of 38
NRC 15-1-1 Revision 00 Event-7
==
Description:==
Low ADS Bottle Bank Nitrogen Pressure Initiation: On direction of Lead Evaluator, release Event 7 Cues:
Automatic Actions: none Expected Annunciators:
LOR-1PM13J-A404, INSTRUMENT NITROGEN SYSTEM TROUBLE Key Parameter Response: none Objective Position EXPECTED OPERATOR RESPONSE ATC
- Assists BOP Operator as directed Per 1PM13J-A404 Report and take actions per annunciator 1PM13J-A404, INSTRUMENT 97.016 NITROGEN SYS TROUBLE:
- If alarm is due to R0601, refer to LOP-IN-05 (yes-R0601)
BOP Per LOP-IN-05:
- Direct bottles replaced when pressure is less than 800 psig.
- NOTE that 4 bottles should be replaced when 1PM13J-A404 alarms
- Direct above Actions
- Make call to Shift Manager, enter T.S. 3.5.1, required Action G.1, be in 97.016 US mode 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> AND Required Action G.2, reduce reactor Steam 201.011 Dome Pressure to < 150 psig in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> Page 21 of 38
NRC 15-1-1 Revision 00 Event - 7
==
Description:==
Low ADS Bottle Bank Nitrogen Pressure Simulator Operator Actions With the concurrence of the Release Event 7 Lead Evaluator Wait until the Tech Spec From the Summary Screen, delete Malfunction r0601 and then call has been made and at perform the Role Play #2 below least 3 minutes after being directed to restore N2 Simulator Operator Role Play Role-Play #1: As the EO, wait 1 minute and report that the South Bottle Bank pressure is 490 psig.
You will restore the bottle bank immediately.
- If asked, the Reserve Bottle Pressure is 1000 psig and as the EO, you will replace the reserve bottle also.
- If asked, the area has been inspected and there is no indication of a leak. The nitrogen bottle pressures are stable.
When annunciator 1PM13J-A404 has reset, Role-Play #2: As the EO, and report that the bottle bank is restored and pressure reads 1580psig.
- If asked, the reserve bottle is restored and pressure reads 2040 psig.
Floor Instructor Notes/OPEX/TRs none Terminus: After Tech Spec call.
Page 22 of 38
NRC 15-1-1 Revision 00 Event-8
==
Description:==
CRD FCV Fails Closed Initiation: On direction of Lead Evaluator, release Event 8 Cues:
Automatic Actions: PPC alarm CRD low flow Expected Annunciators:
1H13-P603-A403, CRD HYD TEMP HI Key Parameter Response: CRD Flow Controller Position Demand downscale; CRD System Flow, Cooling Water Pressure, and CRD Cooling Flow indications lowering, inability to withdraw control rods Objective Position EXPECTED OPERATOR RESPONSE
- Provide peer checks as required
- At 1H22-P007, on CRD/RX Vessel Temperature Recorder, determine which of the CRDs initiated the alarm Per LOA-RD-101
- Check no control rods drifting
- Check CRD parameters normal:
- CRD system flow approximately 63 gpm
- Cooling header differential pressure <30 psid
- Transfer flow controller, 1C11-R600, to Manual
- ManuallyAttempt to adjust flow controller output using open/close pushbuttons to return parameters to normal (WILL NOT WORK)
- Determine flow controller output will not adjust, and then locally Formatted: Indent: Left: 0.25", No bullets or numbering 25.048 ATC verify instrument air is lined up to and is available to CRD manual/auto station (YES)
- Determine Flow Control valve is still not controlling CRD system flow at approximately 63 gpm
- Determine CRDFCV is not controlling at approximately 63 gpm , and direct EO to transfer to standby FCV per Attachment B
- Coordinate with EO in local control to restore system parameter to normal
- Direct above actions 25.048 US
- Establish CRD temperatures as critical parameter Page 23 of 38
NRC 15-1-1 Revision 00 Event - 8
==
Description:==
CRD FCV Fails Closed Simulator Operator Actions With the concurrence of the Release Event 8 Lead Evaluator Simulator Operator Role Play As EO, when requested, wait 1 minute and report that instrument air is lined up and available to the CRD M/A station (step 2.1.2)Acknowledge reports as required.
When directed to place A FCV in Local Manual (step 4.1), follow above Sim Op action, wait 2 minutes and report that the FCV will not open in local manual.
If asked, 1C11-F601A and 1C11-F602A are open.
When ordered to perform Attachment B, coordinate to perform the following (if the crew does not attempt to coordinate with the EO for Attachment B then perform the following actions an report Attachment B complete):
- When ordered to open 1C11-F046B (B.1.1.1), wait 10 seconds and report 1C11-F046B is open.
- When ordered to open 1C11-F047B (B.1.1.2), follow above Sim Op action and report 1C11-F047B is open.
- When ordered to open 1C11-F602B (B.1.1.3), follow the above Sim Op action to delete malfunction; and report 1C11-F602B is open.
- When ordered raise flow in local manual using 1C11-F600B, use above Sim Op action and report when complete (B.1.1.4).
- if asked, 1C11-R301B is reading the same as 1C11-R301A (B.1.1.4).
- When ordered to close 1C11-F602A (B.1.1.5), wait 10 seconds and report it is closed.
- When ordered to close 1C11-F046A (B.1.1.6), wait 10 seconds and report it is closed.
- When ordered to close 1C11-F047A (B.1.1.7), perform above Sim Op action and report that it is closed.
- Adjust 1C11-F600B as requested using Sim Op action above Floor Instructor Notes/OPEX/TRs Terminus: AB CRD FCV operating in RemoteLocal Manual mode.
Page 24 of 38
NRC 15-1-1 Revision 00 Event-9
==
Description:==
RWCU Leak in RT Pump Room, RT Fails to isolate Initiation: On direction of Lead Evaluator, release Event 9 Cues:
Automatic Actions: (automatic isolation valves have been failed)
Expected Annunciators:
1H13-P601-B408, C511, C411, & B507, RT system High Flow and High Flow 1H13-P601-E&F204, RB and RB Vent Rad levels high Key Parameter Response: RT system Flow and Flow indications Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1H13-P601-C411
- Attempt to identify and correct cause of high diff flow
- If this cannot be cleared in 45 seconds and system trips, perform the 70.021 BOP following:
- Verify auto action occurs
- Verify RT Pump, 1G33-C001A/B trips
- Dispatch an operator to investigate for leaks and abnormalities
- Refer to LOA-RT-101 Page 25 of 38
NRC 15-1-1 Revision 00
- Formatted: Indent: Left: 0.25", No bullets or numbering, Tab stops: Not at 0.55" Per LOA-RT-101
- Check RWCU - Isolated o 1G33-F001, RWCU Suct Inbd Isol Vlv - CLOSED o G33-F004, RWCU Suct Otbd Isol Vlv - CLOSED 70.021 BOP Response not obtained
- Close valves as necessary
- Check RWCU pump TRIPPED Response not obtained
- Trip running RWCU pump
- Formatted: Indent: Left: 0.25", No bullets or numbering Per LOA-AR-101
- Notify and evacuate personnel from affected areas
- Restrict access to affected areas
- Dispatch RP Technician to survey and sample the affected areas
- Refer to LGA-002 ATC
- Check cause of high radiation Formatted: Bulleted + Level: 1 + Aligned at: 0" + Tab after: 0.25" + Indent at: 0.25", Tab stops: 0.55", List tab +
4.03", Left
- Dispatch EO to isolate if possible Formatted: Indent: Left: 0.25", No bullets or numbering
- Check area Formatted: No bullets or numbering controlled by RP personnel Formatted: No bullets or numbering, Tab stops: Not at
- Have RP determine exposure of personnel 0.55" Per LGA-002 Formatted: No bullets or numbering, Tab stops: 0.55", List
- Operate area coolers, if possible and Reactor Building Vent, if permitted tab + 4.03", Left
- Report to the Unit Supervisor the RT System failed to isolate and Formatted: Font: 11 pt 304.010 manual isolation attempts failed 417.000 BOP
- Before any area temperature, radiation, or water level reaches max safe Formatted: Font: 11 pt 413.000 value the scram and enter LGA-001 Formatted: No widow/orphan control
- Monitor area temperature, radiation levels and trends and reports trends Formatted: Font: 11 pt to Unit Supervisor Formatted: Font: 11 pt Formatted: Indent: Left: 0.25", No bullets or numbering, Performs Reactor Scram and LGP 3-2 on US direction. (CT) No widow/orphan control
- PLACE Reactor Mode Switch in SHUTDOWN
- INSERT SRMs
- CHECK Control Rods INSERTED and Power Decreasing
- INFORM Unit Supervisor of Control Rod Status and Reactor Power 304.010
- Operate Feedwater and/or ECCS as necessary to maintain RPV Water ATC Level 20" to 50" or as specified by Unit Supervisor 413.000
- Place LFFRV in AUTO o Verify FRV closed in MANUAL
- REPORT to the Unit Supervisor the status of RPV Level and Pressure
- If needed for level control:
o Place the FRV in AUTO o Reset the Scram o Dispatch an EO to close 1C11-F034, Charging Water Supply Valve Page 26 of 38
NRC 15-1-1 Revision 00
- STABILIZE Reactor Pressure <1020 psig o If Main Condenser is available, open Bypass Valves
- Maintains RPV water level as directed
- Maintains RPV pressure as directed
- Direct above actions
- Directs isolation of RWCU 413.000
- When two areas are above Max Safe of the same parameter enter LGA-004 Page 27 of 38
NRC 15-1-1 Revision 00 Event - 9
==
Description:==
RWCU Leak in RT Pump Room Simulator Operator Actions With the concurrence of the Release Event 9 Lead Evaluator Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: continued Page 28 of 38
NRC 15-1-1 Revision 00 Event-10
==
Description:==
RWCU Fails to Isolate Initiation: continued Objective Position EXPECTED OPERATOR RESPONSE Per LGA-002
- Operate area coolers, if possible and Reactor Building Vent, if permitted 304.010
- If any area temperature or radiation above max normal or any floor drain sump is overflowing then isolate all discharges into affected areas 417.000 BOP except the systems needed for Damage Control or LGA actions 413.000
- If any area temperature, radiation, or water level reaches max safe value the scram and enter LGA-001
- Wait until two or more areas above max safe value in the same parameter and enter LGA-004 Performs Reactor Scram and LGP 3-2 on US direction. (CT)
- PLACE Reactor Mode Switch in SHUTDOWN
- INSERT SRMs
- CHECK Control Rods INSERTED and Power Decreasing
- INFORM Unit Supervisor of Control Rod Status and Reactor Power
- Operate Feedwater and/or ECCS as necessary to maintain RPV Water Level 20" to 50" or as specified by Unit Supervisor 304.010
- REPORT to the Unit Supervisor the status of RPV Level and Pressure
- If needed for level control:
o Place the FRV in AUTO o Reset the Scram o Dispatch an EO to close 1C11-F034, Charging Water Supply Valve
- STABILIZE Reactor Pressure <1020 psig o If Main Condenser is available, open Bypass Valves
- Direct above actions US 413.000
- Directs isolation of RWCU Page 29 of 38
NRC 15-1-1 Revision 00 Event - 10
==
Description:==
RWCU Fails to Isolate Simulator Operator Actions none Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: continued Formatted: Left Page 30 of 38
NRC 15-1-1 Revision 00 Event-101
==
Description:==
Two Areas Above Max Safe, Emergency RPV Blowdown Initiation: continued Objective Position EXPECTED OPERATOR RESPONSE ATC
- Maintains RPV water level as directed during Blowdown Formatted: Font: 10 pt
- Monitors Reactor Building areas for rising Temperature and/or rad levels
- Notifies Unit Supervisor of two area radiations are above Max Safe (CT)
Per LGA-004 428.000 Formatted: Font: 10 pt BOP
- Arms and depresses both Div 1 ADS MANUAL INITIATION pushbuttons
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons
- o If directed, opens Turbine Bypass Valves Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- Per LGA-003
- When directed, starts all available Pool Cooling per LGA-RH-103
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, START first RHR Service Water Pump:
- 1A or 1B/C or D
- When indicated flow reaches 3000 gpm, START second RHR Service Water 421.000 Pump Formatted: Font: 10 pt BOP 421.010
- Startup RHR
- Start 1A/1B RHR Pump
- Throttle 1E12-F024A/B (Test Valve) OPEN to establish RHR flow of 1500 to Formatted: Font: 10 pt 7450 gpm
- Close 1E12-F048A/B (HX Bypass) o Place A/B HTX Bypass Throttle/Seal in switch to THROTTLE and THROTTLE CLOSED 1E12-F048A/B or o Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/B
- o May anticipates Blowdown and direct actions to rapidly depressurize via turbine Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent bypass valves at: 0.25"
- Directs LGA-004, RPV Blowdown, when 2 areas above Max Safe Radiation 428.000 and unable to isolate leak. enters and directs LGA-004 (CT) Formatted: Font: 10 pt 421.000 US
- Verifies Suppression Pool level is greater thanabove -18 ft.
421.010
- Directs a manual initiation of ADS
- o If Suppression Pool Water Temperature exceeds 105°F or Suppression Pool Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent Level exceeds +3, enters and directs LGA-003 at: 0.25" Page 31 of 38
NRC 15-1-1 Revision 00 Event - 101
==
Description:==
Two Areas Above Max Safe, Emergency RPV Blowdown Simulator Operator Actions none Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: When Blowdown has been performed and/or at the discretion of the Lead Evaluator Page 32 of 38
NRC 15-1-1 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-002 SECONDARY CONTAINMENT CONTROL 009
- 3. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 4. LGA-004 RPV BLOWDOWN 009
- 5. LGP-1-1 NORMAL UNIT STARTUP 115
- 7. LOP-RT-09 017 COOLANT REJECTION
- 8. LOP-NR-02 INTERMEDIATE RANGE MONITOR OPERATION 019
- 9. LOR-1H13-P603-B304 CHANNEL A IRM HI-HI INOP 003 TURBINE BUILDING CLOSED COOLING WATER
- 12. LOR-1PM13J-A404 INSTRUMENT NITROGEN SYSTEM TROUBLE 008 LEAK DETECTION REACTOR WATER CLEANUP
- 13. LOR-1H13-P601-C411 007 FLOW HIGH LEAK DETECTION REACTOR WATER CLEANUP
- 14. LOR-1H13-P601-B507 005 FLOW HIGH CONTROL ROD DRIVE HYDRAULIC TEMPERATURE
- 15. LOR-1H13-P603-A403 006 HIGH
- 16. LOA-RD-101 CONTROL ROD DRIVE ABNORMAL 020
- 17. LOA-RT-101 LOSS OF REACTOR WATER CLEANUP SYSTEM 019 UNIT 1 AREA RADIATION MONIYORING SYSTEM
- 18. LOA-AR-101 004 ABNORMAL Unit 1 A and B RHR Operations in the LGAs and 012
- 19. LGA-RH-103 SAMGs
- 20. LOP-RM-01 ROD CONTROL MANAGEMENT SYSTEM 043 TECHNICAL REQUIREMENTS MANUAL FIRE HOSE 024
- 21. LMS-FP-15 STATION INSPECTION
- 22. LOA-NR-101 NEUTRON MONITORING TROUBLE 019 LOSS OF TURBINE BUILDING CLOSED COOLING 004
- 23. LOA-WT-101 WATER (TBCCW)
REPLACING NITROGEN BOTTLES ON INSTRUMENT 025
- 24. LOP-IN-05 NITROGEN SYSTEM SHIFTING PUMPS AND PRESSURE ADJUSTMENT IN 017
- 25. LOP-EH-04 THE ELECTRO HYDRAULIC CONTROL SYSTEM Page 33 of 38
NRC 15-1-1 Revision 00 COMPUTER AIDED EXERCISE PROGRAM (CAEP)
ESG NRC 15-1-1 Revision: 00 Revision Date: 6/30/16 Developed By: C. Betken Page 34 of 38
NRC 15-1-1 Revision 00 Page 35 of 38
NRC 15-1-1 Revision 00 Page 36 of 38
NRC 15-1-1 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 37 of 38
NRC 15-1-1 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 2 OLR: Green Work Week: Non-Div Unit 1 power level Unit 2 power level
- 7 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- Startup in progress following
- None maintenance outage per LGP-1-1 Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- 1. Next step is to secure RT Reject per
- Non-Div workweek LGP-1-1 step E.6.9 and LOP-RT-09
- OLR is Green
- 2. Followed by withdrawing Control Rods to 10% per LGP-1-1 step E.6.4
- Non-Div workweek
- OLR is Green Page 38 of 38
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 2 Op-Test No.: _2016301_______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% power Turnover: SPE Blower swap IAW LOP-GS-05 Event Malf. No. Event Event No. Type* Description 1 none N (BOP) SPE Blower SWAP IAW LOP-GS-05 2 none T (SRO) U-2 Reports DIV 2 DG INOPERABLE 3 mcw014 C (BOP) 1A WR Pump TRIP 4 r0342 R (ATC) 1E MPT Transformer Hot Spot 5 r0742 T (SRO) SBLC Squib Valve Continuity Lost 6 none C (BOP) B VR SupplyExhaust Fan TRIP mcw015 C (ALL) Complete Loss of RBCCW 7
mcw013 8 mrp017 M (ALL) Electrical ATWS 9 none C (ATC) ARI Fails (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-2 Rev. 0 07/29/2016 DEVELOPED BY: Colin Betken 8/15/2016 Instructor Date VALIDATED BY: J. Martin / Hawkins / Jozwiak / Clark 7/31/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Exam Author Date
NRC 15-1-2 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-2 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 2. U-2 Reports DIV 2 DG INOP The crew will enter Tech Specs.
- 4. 1E MPT Transformer Hot Spot The crew will lower Reactor Power to lower transformer temperature.
- 5. SBLC Squib Valve Continuity Lost The crew will enter Tech Specs.
- 6. B VR Supply Fan TRIP The crew will start the standby VR Supply Fan
- 8. Electrical ATWS The crew will take action to insert Control Rods and shutdown the core.
- 9. ARI Fails Critical Tasks
- 1. With a reactor scram required and insufficient control rod worth inserted to maintain the reactor shutdown under all conditions without boron; take action to insert control rods, and if reactor power is above 3% or unknown following recirculation flow reduction, inject boron.
- 2. With a reactor scram required and insufficient control rod worth inserted to maintain the reactor shutdown under all conditions without boron, inhibit ADS and prevent ECCS.
- 3. During an ATWS with reactor power above 3% or unknown, rapidly lower RPV water level to at least -60 inches.
3.4. During an ATWS with reactor power above 3% or unknown, and RPV water level lowered to less than -60 inches, use Preferred ATWS Systems to hold RPV water level between -60 inches and -150 inches on Wide Range.
Page 2 of 30
NRC 15-1-2 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 3 of 30
NRC 15-1-2 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall a full power IC 151.
- 2. Place simulator in RUN.
- 3. Load and run the Smart Scenario: NRC 15-1-2.ssf
- 4. Place Protected Equipment rings and/or robust barriers on the following components: None
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the following panel manipulations:
- Verify A WR Pump is Running
- Verify 0 and B WR Pumps are in Standby
- Verify A and B VR trains are running
- Verify an edge rod is selected
- 7. Place the following Tags: None
- 8. Update the Tech Spec Timeclock Sheet as follows:
- 9. Have a copy of LOP-GS-05
- 10. Verify keys 85 and 87 are in the proper location in the key storage locker Formatted: Font: (Default) Arial, 11 pt 10.11. Verify Thermal Power is less than 3546 MWth, lower using RR ganged flow. Formatted: Indent: Left: 0.5", No bullets or numbering 11.12. Perform the pre-scenario checklist. TQ-LA-150-0308 Page 4 of 30
NRC 15-1-2 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 2 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% power Turnover: SPE Blower swap IAW LOP-GS-05 Event Malf. No. Event Event No. Type* Description 1 none N (BOP) SPE Blower SWAP IAW LOP-GS-05 2 none T (SRO) U-2 Reports DIV 2 DG INOPERABLE 3 mcw014 C (BOP) 1A WR Pump TRIP 4 r0342 R (ATC) 1E MPT Transformer Hot Spot 5 r0742 T (SRO) SBLC Squib Valve Continuity Lost 6 none C (BOP) B VR Supply Fan TRIP mcw015 C Formatted: Centered 7 Complete Loss of RBCCW mcw013 (ALLTC) 8 mrp017 M (ALL) Electrical ATWS 8 none C (ATC) ARI Fails (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor Formatted: Indent: Left: 0", First line: 0" ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 6 BOP Normal: 1 Malfunction(s) after EOP (1-2): 1 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 3 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 1 ATC I/C (4 / set): 2 EOPs (1-2): 1 SRO-I I/C (4 / set inc 2 as ATC): 4 EOP Contingencies (0-2): 1 SRO Tech Spec (2 per set): 2 Critical Tasks (2-3): 3 ALL Major Transients (2 per set): 1 Formatted: Indent: Left: 0", Hanging: 0.62", Space Before: 7.2 pt APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 5 of 30
NRC 15-1-2 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and insert 431.010 control rods IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.020 perform SBLC injection, IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 432.000 maintain a Heat Sink, IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 433.000 maintain RPV water level IAW LGA-010.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and control 434.000 reactor power by maintaining RPV water level IAW station procedures.
RO - BOP/ASSIST Respond to a Transformer Trouble and take the appropriate actions to 2.010 restore.
Perform Control Room actions to startup and shutdown Gland Seal Steam 71.033 System, Perform the Main Control Room actions for a Trip of a Reactor Building 114.019 Closed Cooling Water (RBCCW) Pump.
Perform the Main Control Room actions for a Reactor Building Closed Cooling 114.027 Water (RBCCW) Pump Discharge Pressure Low Alarm 114.029 Perform Control Room actions for a loss of RBCCW.
119.014 Start-up the Turbine Building Ventilation System (VT).
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 432.000 maintain a Heat Sink, IAW station procedures.
Page 6 of 30
NRC 15-1-2 Revision 00 SRO - UNIT SUPERVISOR Respond to a Transformer Trouble and take the appropriate actions to 2.010 restore.
Perform Control Room actions to startup and shutdown Gland Seal Steam 71.033 System, Perform the Main Control Room actions for a Trip of a Reactor Building 114.019 Closed Cooling Water (RBCCW) Pump.
Perform the Main Control Room actions for a Reactor Building Closed Cooling 114.027 Water (RBCCW) Pump Discharge Pressure Low Alarm 114.029 Perform Control Room actions for a loss of RBCCW.
119.014 Start-up the Turbine Building Ventilation System (VT).
Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and insert 431.010 control rods IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.020 perform SBLC injection, IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 432.000 maintain a Heat Sink, IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 433.000 maintain RPV water level IAW LGA-010.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and control 434.000 reactor power by maintaining RPV water level IAW station procedures.
Page 7 of 30
NRC 15-1-2 Revision 00 Event-1
==
Description:==
SPE Blower swap IAW LOP-GS-05 Initiation: TurnoverFollowing crew assuming shift, on direction of Lead Evaluator Cues: Turnover Objective Position EXPECTED OPERATOR RESPONSE Per LOP-GS-05
- Start the idle Blower associated with the operating Steam Packing Exhauster 1CD01SAB
- While maintaining Steam Packing Exhauster Inlet Header A/B at between 5-12 W.C. on 1PI-GS032, perform the following:
- Partially throttles open the suction valve for the idle Blower until the SPE Steam Inlet Header vacuum increases to 12 W.C.
- Partially throttle shut the suction valve for the Blower that was initially in the operation until the SPE Steam Inlet Header vacuum decreases 71.033 BOP to 5 W.C. or until the suction valve for the blower that was initially operating is closed
- Alternately repeat steps 1 and 2 above until the suction valve for the Blower that was initially in operation indicates closed
- Adjust the position of the Blower suction valve for the on-line Blower, as necessary, to maintain an SPE Steam Inlet Header vacuum of 8-12 W.C.
- Close the Steam Packing Exhauster Blower Suction Valve that was initially open, 1N62-MOV-D1/2 or 1N62-MOV-D3/4
- Stop the A/B Steam Packing Exhauster Blower that was initially in operation ATC
- Monitor Plant parameters and update crew as required.
US
- Direct above actions.
Page 8 of 30
NRC 15-1-2 Revision 00 Event - 1
==
Description:==
SPE Blower swap IAW LOP-GS-05 Simulator Operator Actions none Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs None Terminus: When SPE Blowers have been swapped.
Page 9 of 30
NRC 15-1-2 Revision 00 Event-2
==
Description:==
U-2 Reports DIV 2 DG INOPERABLE Initiation: On direction of Lead Evaluator Cues: Call from the Booth Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor Plant conditions and update the crew as required.
- Monitor Plant conditions and update the crew as required.
- Call Shift Manager
- Enter Tech Spec 3.8.1
- Condition B - Required opposite unit division 2 DG inoperable
- Required Action
- B.1 - perform SR 3.8.1.1 for operable required offsite circuits in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> 201.011 US AND
- B.2 - Declare features supported by DG INOP in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> OR
- B.3.2 - perform SR 3.8.1.2 AND
NRC 15-1-2 Revision 00 Event - 2
==
Description:==
U-2 Reports DIV 2 DG INOPERABLE Simulator Operator Actions With the concurrence of the Make call to crew with role play below.
Lead Evaluator Simulator Operator Role Play Call 2300 to the Unit Supervisor and report, Unit 2 A Diesel Generator has been declared INOP due to LOS-DG-M2 Floor Instructor Notes/OPEX/TRs If the crew attempts to perform offsite power lineup, inform the Unit Supervisor that the Unit 2 Assist NSO is performing the offsite power lineup.
Terminus: After Tech Spec call.
Page 11 of 30
NRC 15-1-2 Revision 00 Event-3
==
Description:==
1A WR Pump TRIP Initiation: On direction of Lead Evaluator, release Event 3 Cues:
Automatic Actions: A WR Pump Trip Expected Annunciators:
1PM10J-A101, REACTOR BUILDING CLOSED COOLING WATER PUMP AUTOMATIC TRIP 1PM10J-A201, RBCCW PMP DSCH HDR PRESS LO (if RT isolates the following annunciators are expected) 1H13-P602-A106, REACTOR WATER CLEANUP RECIRCULATION PUMP AUTO TRIP 1H13-P602-A203, REACTOR WATER CLEANUP FILTER INLET TEMPERATURE HIGH 1H13-P602-A206, REACTOR WATER CLEANUP RECIRCULATION PUMPS FLOW LOW 1H13-P602-A303, RWCU FILTER INLET TEMP HI-HI 1H13-P602-B103, REACTOR WATER CLEANUP FILETER DEMIN TROUBLE Key Parameter Response: Lowering WR pressure and rising WR temperature Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM10J-A101
- Verify automatic action occurs
- Start standby Reactor Building Closed Cooling Water Pump
- Dispatch operator to Bus 133 for Pump 1A to inspect breaker for 114.019 Reactor Building Closed Cooling Water Pump for abnormalities BOP 114.027
- Dispatch operator to El 786 in Reactor Building to inspect Reactor Building Closed Cooling Water Pump for abnormalities
- Refer to LOA-WR-101, Loss of Reactor Building Closed Cooling Water o Refer to LOP-WR-02, Startup and Operation of the Reactor Building Closed Cooling Water System Per LOA-WR-101 114.019
- Check RBBCW header discharge pressure - greater than 50 psig 114.027 BOP Response not obtained 114.029
- Start standby RBCCW pump
- Monitor Plant parameters and update the crew as required.
ATC o Refer to LOA-RT-101 114.019
- Direct above actions 114.027 US 114.029 Page 12 of 30
NRC 15-1-2 Revision 00 Event - 3
==
Description:==
1A WR Pump TRIP Simulator Operator Actions With the concurrence of the release Event 3 Lead Evaluator Simulator Operator Role Play If sent to investigate the A WR Pump as the Operator in the field, wait 2 minutes and report, A WR Pump tripped on Overcurrent If asked, as Unit 2 inform the Unit 1 that the Common WR Pump is aligned to Unit 1.
Floor Instructor Notes/OPEX/TRs RT may isolate due to WR Pump trip. RT recovery will not be performed.
Terminus: When a standby WR Pump is running.
Page 13 of 30
NRC 15-1-2 Revision 00 Event-4
==
Description:==
1E MPT Transformer Hot Spot Initiation: On direction of Lead Evaluator, release Event 4 Cues:
Key Parameter Response: none Expected Annunciators:
1PM01J-A204, MAIN TRANSFORMER 1 EAST TROUBLE Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM01J-A204
- DISPATCH an operator to 1E Transformer 2.010 BOP
- Verify alarm
- Toggle local alarm switch to determine status of alram Per LOA-TRAN-101 section B.5
- Check power available to fans and pumps
- Check all fan and pump banks - operating
- Refer to attachment C and attachment E for MPT 1E/1W operating parameters/limits 2.010 BOP
- Check MPT Hot Spot Temperature below 160C (YES)
- Check MPT Hot Spot Temperature below 120C (NO)
Response not obtained
- Reduce transformer load to reduce MPT Hot Spot temperature
<120C
- Record time transformer temperature exceeded 120C
- Contact system engineering and EMD for transformer repairs
- Lower Reactor Power to reduce MPT Temperature to below 120C 2.010 ATC o Reduce RR Flow Formatted: Justified, Bulleted + Level: 1 + Aligned at: 0" +
Indent at: 0.25"
- o Insert Cram Rods
- Direct above actions US
- Inform TSO Page 14 of 30
NRC 15-1-2 Revision 00 Event - 4
==
Description:==
1E MPT Transformer Hot Spot Simulator Operator Actions With the concurrence of the Release Event 4 Lead Evaluator When asked to take alarm toggle switch to From Smart Summary place r0342 in OFF RESET/OFF When asked to take alarm From Smart Summary place r0342 in ON toggle switch to ON When asked to take alarm toggle switch to From Smart Summary place r0342 in OFF RESET/OFF When Reactor Power has been reduced 100 MWeWith concurrence from DELETE from smart summary r0342 the Lead Evaluator (Satisfactory Reactivity Manipulation)
Simulator Operator Role Play when dispatched to the 1E transformer, wait 2 minutes and report that 1E Transformer has a Hot spot and Temperature is 125 degrees Celsius and rising one degree every 2 minutes and the oil temperature alarm is in.
If asked, inform the crew all fan banks and pumps are running and power is available.
If asked, 6 coolers are running and ambient temperature is 23 degrees Celsius.
If asked to take the oil temperature toggle Switch follow the above Sim Op Actions After initial down power, if the crew stops lowering power prior to 100 MWe inform them temperature is at 125 degrees Celsius and stable.
When power has been lowered by 100 MWe and with concurrence of the Lead Evaluator, call and Formatted: Underline inform the crew, transformer oil temperature is 115 degrees Celsius and lowering Acknowledge reports as required Floor Instructor Notes/OPEX/TRs none Terminus: When power is lowered 100 MWe or at the discretion of the Lead Evaluator.
Page 15 of 30
NRC 15-1-2 Revision 00 Event-5
==
Description:==
SBLC Squib Valve Continuity Lost Initiation: On direction of Lead Evaluator, release Event 5 Cues:
Key Parameter Response: none Expected Annunciators:
1H13-P603-A105, SBLC SQUIB VALVE CONTINUITY LOSS Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor Plant conditions and update the crew as necessary Per LOR-1H13-P603-A105
- At back panel 1H13-P603:
- If M1 Meter Relay 1C41-M600A/B milliamp reading is < 0.2 ma, declare Squib Valve INOP
- Check fuse F1, 2, 3/F4, 5, 6 (1/4 amp feed to M1 Relay)
- Verify circuit breakers ON at MCC 135X-1 Compt D1, Ckt Bkr 19 for A pump or MCC 136X-2 Compt E1, Ckt Bkr 14 for B pump
- Refer to Tech Spec 3.1.7
- Initiate Action Request to have M1 Meter Relay 1C41-M600A/B circuit repaired
- Direct above actions
- Enter Tech Spec 3.1.7, inform Shift Manager 201.011 US
- Condition A, One SLC subsystem inoperable
NRC 15-1-2 Revision 00 Event - 5
==
Description:==
SBLC Squib Valve Continuity Lost Simulator Operator Actions With the concurrence of the Release Event 5 Lead Evaluator Simulator Operator Role Play Role Play EO dispatched to a SBLC Pump breaker at MCC 135X-1, Compartment D1, Breaker 19:
Wait 2 minutes and then report that:
The Breaker is still closed and there are no obvious signs of damage.
Role Play EMD as necessary if contacted to investigate this failure.
Floor Instructor Notes/OPEX/TRs If clarification of indications is required, inform the Crew member who checks the SBLC M1 Meter Relay fuses (in 1H13-P603 interior) that fuses F1, F2, and F3 are sat..
Terminus: Ttech Spec call is made or at the discretion of the Lead Evaluator.
Page 17 of 30
NRC 15-1-2 Revision 00 Event-6
==
Description:==
B VR Supply Fan TRIP Initiation: On direction of Lead Evaluator, release Event 6 Cues:
Key Parameter Response: Reactor Building D/P Expected Annunciators:
1PM06J-A406, REACTOR BUILDING VENTILATION SUPPLY FAN AUTO TRIP Automatic Actions: B VR Supply Fan Trip Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM06J-A406
- CHECK automatic action occurs
- MONITOR temperature as needed
- IF less than 2 supply fans are running, PERFORM following to bypass Group 1 Main Steam Isolation valve logic before restarting fans:
- INSTALL MSL Pipe Tunnel Diff. Temperature Bypass Keys (Control key Number 85 and 87) at Panel 1H13-P642 for control switches. MSL 119.014 BOP PIPE TUNNEL DIFF TEMP BYPASS DIV 2 SIG B/D.
- PLACE keylock switches at Panel 1H13-P642 to bypass
- Start appropriate time clock
- DISPATCH operator to investigate cause of alarm at SWGR 132X, Cub 503B
- START standby Reactor Building Ventilation Supply Fan ATC
- Monitor Plant parameters and update the crew as necessary
- Direct above actions
- Enter Tech Spec 3.3.6.1 for MSL Pipe Tunnel Diff Temp bypass
- Condition A - one or more channels INOP
- Required Action A.1- to place channel in trip in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> when Formatted: Indent: Left: 0.49", Tab stops: 0.74", List tab 119.014 US key lock switches are in bypass + Not at 0.25" + 0.49"
- Condition B - one or more automatic function with isolation capability not maintained
- Required Action B.1- restore isolation capability in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Formatted: Indent: Left: 0.49", Tab stops: 0.74", List tab
+ Not at 0.25" + 0.49" Formatted: Indent: Left: 0.25", No bullets or numbering Page 18 of 30
NRC 15-1-2 Revision 00 Event - 6
==
Description:==
B VR Supply Fan TRIP Simulator Operator Actions With the concurrence of the Release Event 6 Lead Evaluator Simulator Operator Role Play As the operator in the field, if told to investigate VR Fan trip, wait 3 minutes and report, B Supply Fan tripped on Overcurrent Floor Instructor Notes/OPEX/TRs none Terminus: Standby VR Supply Fan started and parameters return to normal.
Page 19 of 30
NRC 15-1-2 Revision 00 Event-7
==
Description:==
Complete Loss of RBCCW Initiation: On direction of Lead Evaluator, release Event 7 Cues:
Key Parameter Response: Lowering RBBCW Header Pressure and rising RBCCW temperatures Expected Annunciators:
1PM10J-A101, RBCCW PMP AUTO TRIP 1PM10J-A201, RBCCW PMP DSCH HDR PRESS LO Automatic Actions: RBCCW Pump Auto Trip Objective Position EXPECTED OPERATOR RESPONSE Per LOA-WR-101
- Check RBBCW header discharge pressure - greater than 50 psig Response not obtained
- Start standby RBCCW pump 114.019
- If NO RBBCW Pump can be started go to Section B.2 114.027 BOP
- Monitor RR pump temperatures per LOR-1H13-P602-B507 114.029
- Check open 1WR029, 1WR040, 1WR179, and 1WR180
- Check RR Pumps running in slow speed Response not obtained
- Manually SCRAM Reactor
- Performs Reactor Scram and LGP 3-2 on US direction.
- PLACE Reactor Mode Switch in SHUTDOWN 304.010 ATC
- CHECK Control Rods INSERTED and Power Decreasing
- INFORM Unit Supervisor of Control Rod Status and Reactor Power 114.019 114.027 US
- Direct above actions 114.029 Page 20 of 30
NRC 15-1-2 Revision 00 Event - 7
==
Description:==
Complete Loss of RBCCW Simulator Operator Actions With the concurrence of the Release Event 7 Lead Evaluator Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs Crew will Scram on Loss of RBCCW Terminus: continued Page 21 of 30
NRC 15-1-2 Revision 00 Event-8
==
Description:==
Electrical ATWS Initiation: On direction of Lead Evaluator Cues:
Key Parameter Response: Rod position and Reactor Power Expected Annunciators: multiple Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LGA-010
Per the PRESSURE Leg BOP
- STABILIZE pressure <1059 psig using main turbine bypass valves Formatted: Font: 9.5 pt
- VERIFY required automatic actions occur o May request LGA-RH-101 jumper installation Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent
- RUNBACK Reactor Recirculation flow to minimum at: 0.25"
- If power is >3% then TRIP RR Pumps Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent
- Recognize that all rods did not insert and notify US (Electrical ATWS) at: 0.25" Per the POWER Leg, if Control Rod remains out Formatted: Indent: Left: 0.24", Bulleted + Level: 1 +
- If control rods remain out: Aligned at: 0" + Indent at: 0.25"
- Initiate ARI
- If power is above 3%, initiate SBLC (CT)
- Insert Control rods per LGA-NB-01 (CT) 431.000 Formatted: Font: 9.5 pt
- Method 3 Single Rod Insert 431.010
- Bypass RWM 431.020
- Insert control rods using Continuous Insert or Insert Button 433.000 434.000
- WAIT until rods full in except one OR all rods in to at least 02 OR Reactor will stay shutdown under all conditions without boron per QNE.
- WAIT until Reactor is Shutdown or Cold Shutdown Boron is injected (<3050 gal in SBLC Tank)
Per the Level Leg
- If reactor power > 3% or unknown then Rapidly LOWER Level to at least -60 inches (minimizes Feedwater injection) (CT) and use only preferred systems to hold level between -100 and -60 inches. (CT)
- When directed, stops SBLC pump
- VERIFY Main Turbine and Generator Trip 304.010 Formatted: Font: 9.5 pt ATC
- STABILIZE Reactor Pressure <1020 psig 433.000
- Monitors and reports RPV water level throughout
- Controls injection from Condensate and Feed system
- Method 4 Reset Scram/Drain SDV/Re-Scram 431.010 Formatted: Font: 9.5 pt
- Direct Unit 2 Assist to Install jumpers for resetting the scram
- Reset Scram/Drain SDV/Re-Scram
- If all rods are not in to at least 02 and the reactor will not stay shutdown without Formatted: Font: 9.5 pt 431.000 Boron then EXIT LGA-001 and ENTER LGA-010 431.010 US
- Directs controlling level -100 to -60.(CT)
Page 22 of 30
NRC 15-1-2 Revision 00 433.000
- Directs start of SBLC and/or insert control rods.(CT) (PRA) 434.000
- Directs method of control rod insertion per LGA-NB-01 Method 1 (CT)
- Direct Method 1 Remove Scram/Discharge fuses Formatted: Bulleted + Level: 1 + Aligned at: 0.25" + Tab o May direct Method 3 Single Rod Insert after: 0.5" + Indent at: 0.5" o May direct Method 4 Reset Scram/Drain SDV/Re-Scram
- Directs bypassing MSIV low level isolation per LGA-MS-01 Event - 8
==
Description:==
Electrical ATWS Simulator Operator Actions With the concurrence of the Lead Evaluator when Release Method 1 requested to remove A RPS fuses (Attachment
- Removes A RPS fuses and SDV Vent and Drain fuses 1B/1E) for Method 1 LGA-NB-01 With the concurrence of the
- From the RNI display - JMP Screen - click on LGA-NB-01 (2 Lead Evaluator when LGA-jumpers)
NB-01 Method 4 is called
- Select INSTALLED then INSERT for
- De-energize ARI using iaaride1 and iaaride2 LGA-RH-101 With the concurrence of the
- From the RNI display - JMP Screen - click on LGA-RH-101 (1 Lead Evaluator when LGA-jumper)
RH-101 is called for
- Select INSTALLED then INSERT LGA-MS-01 With the concurrence of the
- From the RNI display - JMP Screen - click on LGA-MS-01 Lead Evaluator when LGA- jumpers (5 jumpers)
MS-01 is called for
- Install only jumper #4
- Select INSTALLED then INSERT When requested to reinstall From Smart Summary Select isdvf18a and isdv18b, install and insert SDV Vent and Drain Fuses Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs The Failure of ARI is intended for the ATC and is part of their normal ATWS choreography.none Terminus: When all Control Rods are full in, SBLC is secured, and at the discretion of the Lead Evaluator.continued Page 23 of 30
NRC 15-1-2 Revision 00 Event-8 (Continued)
Objective Position EXPECTED OPERATOR RESPONSE
- As directed perform LGA-NB-01 Method 3 431.010
- Method 4 Reset Scram/Drain SDV/Re-Scram 433.000 ATC
- Direct Unit 2 Assist to deenergize ARI
- Direct Unit 2 Assist to Install jumpers for resetting the scram
- Reset Scram/Drain SDV/Re-Scram
- RUNBACK Reactor Recirculation flow to minimum BOP
- If power is >3% then TRIP RR Pumps Page 24 of 30
NRC 15-1-2 Revision 00 Event-8 (Continued) Formatted: Centered
==
Description:==
ATWS, After Control rods inserted Objective Position EXPECTED OPERATOR RESPONSE
- When directed, stops SBLC pump
- VERIFY Main Turbine and Generator Trip 304.010 ATC
- STABILIZE Reactor Pressure <1020 psig 433.000
- Monitors and reports RPV water level throughout
- Controls injection from Condensate and Feed system
- Monitors reactor to ensure operations remain within established bands BOP
- Monitors control room panels and notifies the SRO of any unusual or unexpected conditions
- When rods inserted, direct securing SBLC injection
- When rods inserted, exits LGA-010 and re-enters LGA-001
- Enters and directs actions of LGA-001 LEVEL LEG 433.000 US
- Directs water level band of +11" to +59.5" (+20" to +50" preferred)
- Enters and directs actions of LGA-001 PRESSURE LEG
- STABILIZE Reactor Pressure below 1059 psig Page 25 of 30
NRC 15-1-2 Revision 00 Floor Instructor Notes/OPEX/TRs None Terminus: When all Control Rods are full in, SBLC is secured, or when sufficient Control Rods have been inserted at the discretion of the Lead Evaluator.
Page 26 of 30
NRC 15-1-2 Revision 00 Formatted: Left REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-010 FAILURE TO SCRAM 015 UNIT 1 A AND B RHR OPERATIONS IN THE LGAS
- 3. LGA-RH-103 012 AND SAMGS
- 4. LGA-SC-101 INITIATION OF SBLC UNIT 1 002
- 5. LGA-NB-01 ALTERNATE ROD INSERTION 018
- 6. LGP-3-1 POWER CHANGES 062
- 7. LGP-3-2 REACTOR SCRAM 072 REACTOR BUILDONG CLOSED COOLING WATER
- 8. LOR-1PM10J-A101 002 PUMP AUTOMATIC TRIP
- 9. LOR-1H13-P603-A105 SBLC SQUIB VALVE CONTINUITY 004 REACTOR BUILDING VENTILATION SUPPLY FAN
- 10. LOR-1PM06J-B406 001 1RT01CB AUTOMATIC TRIP LOSS OF REACTOR BUILDING CLOSED COOLING
- 11. LOA-WR-101 014 WATER (RBCCW)
REACTOR WATER CLEANUP RECIRCULATION
- 12. LOR-1H13-P602-A106 004 PUMP AUTO TRIP REACTOR WATER CLEANUP FILTER INLET
- 13. LOR-1H13-P602-A203 001 TEMPERATURE HIGH REACTOR WATER CLEANUP RECIRCULATION
- 14. LOR-1H13-P602-A206 003 PUMPS FLOW LOW
- 15. LOR-1H13-P602-A303 RWCU FILTER INLET TEMP HI-HI 002 REACTOR WATER CLEANUP FILETER DEMIN
- 16. LOR-1H13-P602-B103 001 TROUBLE
- 18. LOA-TRAN-101 TRANSFORMER TROUBLE 025 CHANGE OVER OF GLAND SEAL STEAM
- 19. LOP-GS-05 003 PACKING EXHAUSTER BLOWERS
- 20. LOA-RT-101 LOSS OF REATOR WATER CLEANUP SYSTEM 019
- 21. LOR-1PM01J-A204 MAIN TRANSFORMER 1E TROUBLE 004 PLANT PROCESS COMPUTER MISCELLANEOUS
- 22. LOP-CX-07 016 FUNCTIONS Page 27 of 30
NRC 15-1-2 Revision 00 SMART SCENARIO ESG NRC 15-1-2 Revision: 00 Revision Date: 7/29/15 Developed By: C. M. Betken Page 28 of 30
NRC 15-1-2 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 29 of 30
NRC 15-1-2 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Green Work Week: Non-Div Unit 1 power level Unit 2 power level
- 100 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- None
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- Non-Div workweek LOP-GS-05 from 1A SPE Blower A to
- OLR is Green 1A SPE Blower B
- Non-Div workweek
- OLR is Green Page 30 of 30
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 3 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% Reactor power, RCIC is OOS ready to be returned to Standby.
Turnover: Warm RCIC Steam Line and return to Standby IAW LOP-RI-05 step E.9 Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Warm RCIC Steam Lines and Return to Standby (Optional) 2 mrw001 C (BOP) RT Pump TRIP 3 r0414 C (BOP) OG Building Exhaust Fan TRIP 4 mcn017 R (ATC) Earthquake Below OBE/SSE Limit, Small Condenser Air Leak 4 none T (SRO) Seismic Event 5 k3k02p1y C (ATC) Failure of the RR Ganged Controller in AUTO 6 mca014 M (ALL) Scram, Suppression Pool Leak 7 mrd040 C (ATC) Five Control Rods Remain Out 8 none M (ALL) Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-3 Rev. 0 07/13/2016 DEVELOPED BY: Colin Betken 8/15//2016 Instructor Date VALIDATED BY: Tutich / Reyes / Nicoll / Dejewski 7/16/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Exam Author Date
NRC 15-1-3 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-3 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 1. Warm RCIC Steam Lines and Return to Standby. The crew will return RCIC following maintenance performed on it.
- 2. RT Pump TRIP. The crew will respond to the Reactor Water Cleanup Pump Trip and Restart the RT System.
- 3. OG Building Exhaust Fan TRIP. The crew will respond to the Off Gas Building Exhaust fan Trip by securing the on service train of ventilation and starting the standby train.
- 4. Earthquake Below OBE/SSE Limit, Suppression Pool Leak. Following the validation of the Earthquake, the crew will see a lowering Suppression Pool Level and send operators to investigate and will notice a leak in the Suppression Pool. The crew will respond by Scramming the Reactor.
- 5. Small Condenser Air Leak. The crew will see the rising Backpressure and will attempt to lower Reactor Power using Reactor Recirculation flow or Control Rods to alter the trend of backpressure
- 6. Failure of the RR Ganged Controller in AUTO. When attempting to lower Reactor Power using Reactor Recirculation flow, they will attempt to use the lower pushbutton on ganged RR flow control. With this being unsuccessful the crew should attempt to take manual control of the Reactor Recirculation Flow Control Valves and lower flow.
- 7. Five Control Rods Remain Out. Following the Reactor Scram, five Control Rods will remain out, placing the Reactor in an ATWS (Anticipated Transient Without Scram) condition. This will force the crew to use alternate means of inserting Control Rods.
- 8. Blowdown. The crew will Blowdown the Reactor Vessel using ADS (Automatic Depressurization System) due to Suppression Pool level approaching -12 feet.
Critical Tasks
- 1. With a reactor scram required and insufficient control rod worth inserted to maintain the reactor shutdown under all conditions without boron; take action to insert control rods, and if reactor power is above 3% or unknown following recirculation flow reduction, inject boron.
- 2. When suppression pool level cannot be maintained > -12 feet, initiate emergency depressurization.
(Or anticipate Blowdown and depressurize rapidly via the main turbine bypass valves.)
- 3. During an ATWS with emergency depressurization required and Suppression Pool Level above -18 feet, the crew will terminate and prevent all injection except Boron, CRD, RCIC. (If the crew exits LGA-010 prior to blowing down, this Critical Task will not be applicable)
Page 2 of 34
NRC 15-1-3 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 3 of 34
NRC 15-1-3 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 2. Place simulator in RUN.
- 3. Load and run the Smart Scenario: NRC 15-1-3.ssf Formatted: Font: Not Bold 3.4. If intending to perform event 1: complete 5 through 9, otherwise they are N/A 4.5. Place Protected Equipment rings and/or robust barriers on the following components for RCIC Inoperable:
HPCS Pump C/S HPCS DG C/S 1E22-F004 C/S 1E22-F015 C/S HPCS WLP C/S HPCS DGCWP C/S 1E22-F012 C/S 1E22-F023 C/S 5.6. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time T.S. 3.5.3 RCIC A.1 Verify HPCS is operable Immediately Completed T.S. 3.5.3 RCIC A.2 Restore to OPERABLE 14 Days 12 Days from status now 6.7. Perform the following panel manipulations:
Isolate the RCIC Steam Lines as follows:
- Close the following RCIC Steam Supply Valves:
- Open the Steam Supply Drain Trap Bypass valve; 1E51-F054
- Close 1E51-F054 7.8. Verify the following:
- The 1B RWCU Pump is running
- The 0A Offgas Building Supply and Exhaust fans are running
- 9. Have a copy of LOP-RI-05 marked up, with E.8 the next step to be completed.
- 10. Verify Power is less than 3546 MWth 8.11. Following the Scenario: check paper copies of LOP-RT-02 and LOP-VO-01 for marks and replace as required.
9.12. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 4 of 34
NRC 15-1-3 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 3 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% Reactor power, RCIC is OOS ready to be returned to Standby.
Turnover: Warm RCIC Steam Line and return to Standby IAW LOP-RI-05 step E.9 Event Malf. No. Event Event No. Type* Description 1 none Warm RCIC Steam Lines and Return to Standby N (BOP)
(Optional) 2 mrw001 C (BOP) RT Pump TRIP 3 r0414 C (BOP) OG Building Exhaust Fan TRIP 4 mcn017 Earthquake Below OBE/SSE Limit, Small R (ATC)
Condenser Air Leak 4 none T (SRO) Seismic Event 5 k3k02p1y C (ATC) Failure of the RR Ganged Controller in AUTO 6 mca014 M (ALL) Scram, Suppression Pool Leak 7 mrd040 C (ATC) Five Control Rods Remain Out 8 none M (ALL) Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 6 BOP Normal: 1 Malfunction(s) after EOP (1-2): 1 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 4 EOP Contingencies (0-2): 2 SRO Tech Spec (2 per set): 0 Critical Tasks (2-3): 3 ALL Major Transients (2 per set): 2 Formatted: Indent: Left: 0", Hanging: 0.62" APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 5 of 34
NRC 15-1-3 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC Given various plant conditions, predict how the RR System will respond to 22.00.21 various system component failures while operating the system or on an exam in accordance with station procedures.
Given Unit Supervisor authorization, respond to a Loss of Condenser Vacuum 111.002 IAW station procedures.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and insert 431.010 control rods IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 432.000 maintain a Heat Sink, IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 433.000 maintain RPV water level IAW LGA-010.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and control 434.000 reactor power by maintaining RPV water level IAW station procedures.
RO - BOP/ASSIST Perform the Main Control Room actions to Warm Up, Flush and Startup the 27.001 Reactor Water Cleanup (RWCU) System.
Perform Control Room actions to reset a RCIC System isolation or Turbine 32.006 trip.
Given Unit Supervisor authorization, respond to a Loss of Condenser Vacuum 111.002 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Evaluate plant conditions and control and maintain Suppression Pool Level 422.000 below the SRVTPL Limit.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 423.000 conditions and control and maintain Suppression Pool Level above -12 feet IAW station procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Page 6 of 34
NRC 15-1-3 Revision 00 SRO - UNIT SUPERVISOR Perform the Main Control Room actions to Warm Up, Flush and Startup the 27.001 Reactor Water Cleanup (RWCU) System.
Perform Control Room actions to reset a RCIC System isolation or Turbine 32.006 trip.
Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Evaluate plant conditions and control and maintain Suppression Pool Level 422.000 below the SRVTPL Limit.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 423.000 conditions and control and maintain Suppression Pool Level above -12 feet IAW station procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and insert 431.010 control rods IAW station procedures Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 432.000 maintain a Heat Sink, IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 433.000 maintain RPV water level IAW LGA-010.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and control 434.000 reactor power by maintaining RPV water level IAW station procedures.
Page 7 of 34
NRC 15-1-3 Revision 00 Event-1
==
Description:==
Warm RCIC Steam Lines and Return to Standby Initiation: Following crew assuming shift, on direction of Lead Evaluator Cues: Turnover Objective Position EXPECTED OPERATOR RESPONSE Per LOP-RI-05
- Perform the following to warm up the RCIC Steam Line
- Reset the RCIC Turbine Trip as follows:
- If an Isolation caused turbine trip, RESET isolation signal on division that was tripped
- Slowly throttle open 1E51-F008
- Slowly throttle open 1E51-F076
- Verify RCIC steam line pressure reaches reactor supply pressure by observing the pressure indicated on 1E51-R602 on Control Room Panel 1H13-P601
- Verify water in the section of pipe downstream of 1E51-F063, RCIC Steam Supply Inbd Isol Valve, has been forced out of the piping.
- When Reactor pressure and RCIC pressure match, as indicated on 32.006 BOP the 1E51-R602, open 1E51-F063, RCIC Steam supply Inbd Isol Valve
- Open 1E51-F360, RCIC Turb Trip & Throttle Vlv. Verify both sets of RCIC Turb Trip & Throttle Vlv Red/Green lights indicate open
- Perform the following to properly align RCIC:
- Verify RCIC governor valve is open
- Close 1E51-F004, Baro Cndsr Pmp Upstm Stop
- Open 1E51-F004, Baro Cndsr Pmp Upstm Stop
- Open 1E51-F005, Baro Cndsr Pmp Dwnst Stop
- Close 1E51-F005, Baro Cndsr Pmp Dwnst Stop
- Cycle open and close the RCIC Steam Drain Pot isolation valves
- Verify the RCIC pushbutton collars and logic is RESET
- Monitor Plant parameters and update the crew as required
- Direct above actions 32.006 US
- Refer to Tech Spec 3.3.6.1 Page 8 of 34
NRC 15-1-3 Revision 00 Event - 1
==
Description:==
Warm RCIC Steam Lines and Return to Standby Simulator Operator Actions When requested to perform Attachment A to bypass the Release Event 1 High Steam Line Flow switches When requested to restore the High Steam Flow From the Summary Page, DELETE Remote Function: iarihisf switches per Steps 19-24 Simulator Operator Role Play Role Play as the EO/IMD directed to bypass Flow switches per Steps 2-9:
(Time Compression) Wait 1 minute then perform the SIMOP action above and report that Attachment A Steps 2-9 are complete.
Role Play as the EO/IMD directed to bypass Flow switches per Steps 10-16:
(Time Compression) Wait 1 minute then report that Attachment A Steps 10-16 are complete.
Role Play as the EO/IMD directed to restore the High Steam Flow switches per Steps 19-24:
(Time Compression) Wait 1 minute then perform the SIMOP action above and report that Attachment A Steps 19-24 are complete.
Floor Instructor Notes/OPEX/TRs None Terminus: When RCIC Turbine Trip & Throttle Valve, 1E51-F360 has been opened per Step E.9.7 Page 9 of 34
NRC 15-1-3 Revision 00 Event-2
==
Description:==
RT Pump TRIP Initiation: On direction of Lead Evaluator, release Event 2 Cues:
Key Parameter Response: 1B RWCU Pump indications, RT System flow, Expected Annunciators: 1H13-P602-A107, 1B RWCU RECIRC PUMP AUTO TRIP Automatic Action: RWCU Filter Demineralizers isolate Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1H13-P602-A107 - Refer to LOA-RT-101:
- Start Standby RWCU pump per LOP-RT-02 Per LOP-RT-02
- Direct an EO to verify RBCCW is valved in to 1A RWCU Pump Heat Exchanger: 1WR007A open and 1WR008A throttled for 35-45 gpm
- Direct an EO to verify 1A suction and Discharge valves are open:
- 1G33-F043A, Pump Suction Header Upstream Stop
- 1G33-F005A, Pump Suction Header Downstream Stop 27.001 BOP
- 1G33-F013A, Pump Discharge Valve
- Determine Reactor Vessel Water Temperature/RR Pump suction Temp
- Verify difference between Pump casing temp and RPV water temp is less than 100ºF
- Start the 1A RWCU Pump
- Adjust system flow by throttling open the filter Demin Bypass valve, 1G33-F354 (Nominal 270 - 300 gpm, Maximum 360 gpm)
- Direct an EO to backwash the filters that were in service (Per LOA-RT-101)
- Monitor Plant conditions and update the crew as required.
- Dispatch an Equipment Operator to investigate RT Pump TRIP
- Direct above actions 27.001 US
NRC 15-1-3 Revision 00 Event - 2
==
Description:==
RT Pump TRIP Simulator Operator Actions With the concurrence of the Release Event 2 Lead Evaluator When directed by the crew to PLACE the A/B/C Vessel Release RT F/D Isolation Control Switch to ISOLATE Simulator Operator Role Play NOTE: Time compress as necessary with Lead Evaluator concurrence.
As an EO, if requested to investigate the 1B RT Pump trip, report the breaker is tripped As an EO, when directed to place RWCU F/D control switches in ISOLATE; perform the SIMOP actions above and then report that the F/Ds are isolated.
As an EO, when directed to verify 1A RWCU Pump Suction and Discharge valves are open; report that 1G33-F043A, F005A and F013A are open.
As an EO, when directed to verify RBCCW is valved in to 1A RWCU Pump Heat Exchanger; report that 1WR007A is open and 1WR008A is throttled for 35-45 gpm.
As an EO, when directed to verify 1A RWCU Pump Suction and Discharge valves are open; report that 1G33-F043A, F005A and F013A are open.
As an EO, when directed to verify CRD purge flow; report that 1A RWCU Pump purge flow is 1.0 gpm.
As an EO, when directed to 1A RWCU Pump local casing temperature; report 1A RWCU Pump casing temperature at 480ºF.
As an EO, when directed to close the 1A Pump discharge Check Bypass Valve; report that the 1A Pump discharge Check Bypass Valve is closed.
As an EO, when directed to backwash the filters that were in service; acknowledge this directive. (No further action is necessary)
If asked to report cause of Demin Trouble Alarm (1H13-P602-B103) report the is caused by Filter Demin Low Flow Floor Instructor Notes/OPEX/TRs none Terminus: RWCU System returned to service on the 1A RWCU Pump Page 11 of 34
NRC 15-1-3 Revision 00 Event-3
==
Description:==
OG Building Exhaust Fan TRIP Initiation: On direction of Lead Evaluator, release Event 3 Cues:
Key Parameter Response: Offgas Building Exhaust Fan 0VO03CA indicating lights Expected Annunciators: 1PM06J-A106, OFFGAS BLDG 0A EXH FAN AUTO TRIP Automatic Action: Off Gas Building HVAC Exhaust Fan 0VO03CA trips Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM06J-A106
- Verify automatic actions occurred
- Start the standby Off Gas Building HVAC Train per LOP-VO-01
- o INITIATE action request if applicable Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- Direct an EO to Verify OGFB (Off Gas Filter Building) is at negative pressure. If OGFB is at a positive pressure notify Reactor Protection to sample for the presence of Noble Gas Per LOP- VO-02 o PLACE OV001CA, Off Gas Supply fan in the STOP position Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent o PLACE OV003CA, Off Gas Exhaust fan in the STOP position at: 0.25" Formatted: Font: (Default) Arial, 11 pt Per LOP- VO-01 Formatted: Space Before: 0 pt, After: 0 pt, Bulleted +
- PLACE the oncoming OV003CB, Off Gas Exhaust fan in the AUTO Level: 1 + Aligned at: 0" + Indent at: 0.25", Widow/Orphan control, Adjust space between Latin and Asian text, Adjust BOP position space between Asian text and numbers, Tab stops: Not at
- PLACE the oncomingOV001CB, Off Gas Supply fan in the START 4.03" position for 10 seconds and RELEASE
- VERIFY the Supply fan starts
- VERIFY the oncoming Exhaust fan starts
- Monitor Plant conditions and update the crew as required
- Direct above actions
- Enter ODCM 12.4.5 US
- Condition A, one or more VENTILATION EXHAUST TREATMENT SYSTEMS inoperable
- Required Action A.1, restore system to OPERABLE status within 31 days Page 12 of 34
NRC 15-1-3 Revision 00 Event - 3
==
Description:==
OG Building Exhaust Fan TRIP Simulator Operator Actions With the concurrence of the Release Event 3 Lead Evaluator Simulator Operator Role Play Role Play as EO dispatched to Off Gas Building:
When asked to investigate at 480V MCC 134Y-2:
- Wait 2 minutes, then report that the 0A Off Gas Exhaust Fan breaker is tripped.
During shutdown of A Train (LOP-VP-02, if ordered)
- (Step E.3) When asked, the A HVAC Heating Train is secured
- (Step E.4) When asked, the Off Gas Refrigeration Unit is shutdown During startup of B Train (LOP-VO-01)
- (Step E.3.1) When asked, the B Off Gas Bldg Supply Dampers are open.
- (Step E.3.2) When asked, all five LOW FLOW Alarms have cleared.
- (Step E.3.3) When asked, the B Off Gas Bldg Exhaust Dampers are open.
- (Step E.5) When asked, B Train differential pressures are normal.
- (Step E.8) When directed, report the B Train heaters have been started.
IF asked, wait 12 minutes and report, The Off Gas Filter Building is at a negative pressure.
Floor Instructor Notes/OPEX/TRs none Terminus: When the 0B Off Gas Bldg Supply and Exhaust Fans have been started.
Page 13 of 34
NRC 15-1-3 Revision 00 Event-4
==
Description:==
Earthquake Below OBE/SSE Limit, Small Condenser Air Leak Initiation: On direction of Lead Evaluator, release Event 4 Expected Annunciators: 1PM10J-B504 STRONG MOTION SEIS INSTR SYSTEM INITIATED (In Formatted: Font: 10 pt approximately 7 minutes) 1N62-P600-B506, OFF GAS CHARCOAL ADSORBER TRAIN HI DP (In approximately 7 minutes) 1N62-P600-B204 OFF GAS OUTLET FLOW ABNORMAL (In approximately 9.5 minutes) 1PM03J-B511, CONDENSER VACUUM LOW (In approximately 7 minutes) 1N62-P600-B506, OFF GAS CHARCOAL ADSORBER TRAIN HI DP (In approximately 7 minutes) 1N62-P600-B204 OFF GAS OUTLET FLOW ABNORMAL (In approximately 9.5 minutes) 1PM03J-B511, CONDENSER VACUUM LOW Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM10J-B504:
- Determine if an actual seismic event can be confirmed:
- CALL several people at different locations of the plant, (RW Control Room, MAF ) and ASK if ground motion was felt.
- If additional confirmation of seismic activity is required to confirm a Seismic event, CALL the National Earthquake Information Center (Emergency Response Facilities Telephone Directory) and request conformation of seismic activity.
- If a Confirmed Seismic event occurred:
- Inform shift management of the need to review EALs and implement the Formatted: Font: 11 pt Emergency Plan as appropriate
- NOTIFY System Engineering to evaluate data collected from seismic event.
- MONITOR Primary Containment and continued operability of instrumentation in T.S. Table 3.3.3.1-1 and TRM Table T3.3.d-1.
- REFER to LOA-DIKE-001; dispatch personnel to inspect the cooling lake dike for leaks
- Direct an EO to inspect Hi-Storm Fuel casks for damage or blocked vents
- Contact CMO to perform thermography on switchyard components
- Obtain accelerometer data
- Formatted: Font: 11 pt Per LOR-1PM03J-B511 Formatted: Indent: Left: 0.11", No bullets or numbering
- Monitor Condenser Vacuum indication. DO NOT operate with sustained condenser vacuum less than:
- 23.5 HG (6.5 backpressure) with Reactor Power greater than 75%
- VERIFY SJAE are operating properly per LOP-OG 07, startup of Off Gas 111.002 BOP System Formatted: Font: 11 pt
- VERIFY Circulating Water System is operating properly per LOP-CW-03, startup of Circulating Water System Formatted: Font: 11 pt
- If condenser Formatted: Indent: Left: 0.11", No bullets or numbering vacuum decreases to point of turbine trip point (21.6) refer to:
Page 14 of 34
NRC 15-1-3 Revision 00
- LOA-TG-101, Unit 1 Turbine Generator
- Initiate appropriate corrective action as required Per LOR-1PM03J-B511
- If condenser vacuum continues to decrease, REDUCE Reactor Power per LGP-3-1 as necessary (lowering RR flow), to a point at which condenser vacuum has stabilized. If vacuum cannot be stabilized and Turbine Trip is 111.002 ATC Formatted: Font: 11 pt imminent, MANUALLY scram reactor(Event 6) per LGP-3-2 (When the crew attempts to lower Reactor Power using RR ganged flow (Event 5) it will not work)
- Formatted: Font: 11 pt
- Directs actions above. Formatted: Indent: Left: 0.11", No bullets or numbering
- Notifies Shift Manager.
- References TRM 3.3.o, Condition C for a valid seismic eventfor Seismic Monitoring Instrumentation
- Condition A - one or more Seismic Monitoring Instruments INOP
- Required Action A.1 - restore instrument to operable status in 30 days Formatted: Indent: Left: 0.11", Hanging: 0.19"
- Condition C - one or more Seismic Instruments actuated during a valid Seismic event > 0.01g 201.011 US
- Required Action C.1 - restore actuated instrument to operable in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Formatted: Indent: Left: 0.11", Hanging: 0.19"
- Required Action C.2 - perform TSR 3.3.o.3 for each actuated instrument in 5 days
- Required Action C.3 - analyze data retrieved from instruments in 10 days Formatted: Font: 10 pt
- Required Action C.4 - prepare a corrective action report describing the event and effect on facility features important to safety in 10 days
- C.1, return instruments to operable in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Formatted: No bullets or numbering
- C.2 perform TSR 3.3.o.3 for each activate instrument in 5 days Event - 4
==
Description:==
Earthquake Below OBE/SSE Limit, Small Condenser Air Leak Simulator Operator Actions With the concurrence of the Release Event 4 (Earthquake)
Lead Evaluator Following Tech Spec Call and wWith the concurrence Release Event 4 (Condenser Air leak initial) of the Lead Evaluator Simulator Operator Role Play As EO, if sent to seismic system, report the seismic SYSTEM TRIGGERED light is ON, but no OBE or SSE light lit. Report a seismic monitor reading of 0.015 g.
As System Engineer, role play as necessary and acknowledge the directive to evaluate the datae collected from the seismic event.
As personnel in plant, If requested, report you did feel movement.
If requested to obtain peak acceleration data from the OPA11J panel, report that when you lifted the Page 15 of 34
NRC 15-1-3 Revision 00 laptop screen, nothing displayed (procedures states to notify IMs).
If requested to check SBLC and Suppression Pool levels, verify the commands have been deleted have been deleted and then report that SBLC and Suppression Pool levels are normal.
Floor Instructor Notes/OPEX/TRs Two separate triggers to allow Crew time to calm down following the Earthquake.
Terminus: continued Formatted: Left Page 16 of 34
NRC 15-1-3 Revision 00 Event-5
==
Description:==
Failure of the RR Ganged Controller in AUTO Initiation: continued Cues:
Key Parameter Response: RR Master controller does not respond; flow in the Recirc Loops does not lower; Reactor power does not lower when using Ganged Controller Expected Annunciators: None Automatic Actions: None Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor Plant conditions and update the crew as necessary Per OP-LA-101-111-1002
- Take Manual Control of a failed AUTO controller to maintain a process parameter
- Lower Reactor Power using RR flow in MANUAL Formatted: List Paragraph, Space Before: 0 pt, After: 0 pt, Widow/Orphan control, Adjust space between Latin and Asian
- On the A & B Recirc Loop Flow Controller M/A Stations text, Adjust space between Asian text and numbers
- VERIFY manual light on Recirc Flow Control M/A Station A & B is on Formatted: Font: (Default) Arial, 11 pt 22.00.21 ATC
- Press LOWER pushbutton(s) and observe flow indications (two Formatted: Indent: Left: 0.3", Hanging: 0.19", Bulleted +
handed operation is authorized) Level: 1 + Aligned at: 0" + Indent at: 0.25"
- Lower Reactor Power using RR flow in MANUALMaintain Recirculation Loop Flow Mismatch as read from 1B21-R611A and 1B21-R611B within:
o 5.425 Mlbm/hr if core flow is > 79.95 Mlbm/hr o 10.85 Mlbm/hr if core flow is < 79.95 Mlbm/hr o Lower Reactor power Using Control Rods
- Direct above actions 304.010 US
NRC 15-1-3 Revision 00 Event - 5
==
Description:==
Failure of the RR Ganged Controller in AUTO Simulator Operator Actions none Simulator Operator Role Play Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs After Reactor Power is lowered by taking Reactor Recirc to manual , Condenser Vacuum will continue to lower and conditions will dictate a manual Scram due to High Condenser Backpressure.
Terminus: continued Page 18 of 34
NRC 15-1-3 Revision 00 Event-6
==
Description:==
Scram (from Condenser Air Leak), Suppression Pool Leak Initiation: On direction of Lead Evaluator Cues:
Key Parameter Response: Lowering Suppression Pool Level Expected Annunciators: Multiple Automatic Actions: None Objective Position EXPECTED OPERATOR RESPONSE
- Monitor Condenser Backpressure and report when backpressure Formatted: List Paragraph, Indent: Left: 0", Hanging:
reaches or exceeds 6.5 backpressure 0.24", Bulleted + Level: 1 + Aligned at: 0.5" + Indent at:
0.75"
- Refer to LOA-TG-101 Formatted: Font: (Default) Arial, 11 pt Per LOR-1PM13J-B203 Formatted: List Paragraph, Indent: Left: 0.24"
- Check Suppression Pool water level is less than or equal to alarm 422.000 BOP setpoint as indicated from computer analog point number L124
- DISPATCH operator into Reactor Building to confirm Suppression Pool low level at local sight glass
- MONITOR major plant systems that take suction on Suppression Pool, for possible reason of water level decrease
- ENTER LGA-003 at -4.5 Suppression Pool Level
- Hold Suppression Pool Level above -4.5 (No)
- Cannot hold level above -4.5 go to block 20 421.000
- Hold Suppression Pool level above -12 feet 423.000
- Before Suppression Pool level reaches -12 feet SCRAM and enter LGA-001
- IF cannot restore level above -12 feet (downcomers) and hold it there BLOWDOWN Performs Reactor Scram and LGP 3-2 on US direction
- PLACE Reactor Mode Switch in SHUTDOWN ATC 413.000
- CHECK Control Rods INSERTED and Power Decreasing (5 Rods Out)
- INFORM Unit Supervisor of Control Rod Status and Reactor Power
- Direst above actions 421.000
- Inform Shift Manager 421.010 *o May Direct Closing MSIVs and control pressure using SRVs Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent US at: 0.25" 422.000
- Set Suppression Pool Level as Critical parameter 423.000
- REFER to Tech Spec 3.5.2 and 3.6.2.2
- Enter LGA-003 Page 19 of 34
NRC 15-1-3 Revision 00 Event - 6
==
Description:==
Scram (from Condenser Air leak), Suppression Pool Leak Simulator Operator Actions Following the crew lowering Reactor Power and with concurrence from the Lead Release Event 4 (Condenser Air leak that leads to Scram)Release evaluatorWith the Event 6 concurrence of the Lead Evaluator Simulator Operator Role Play As the operator sent to investigate a Suppression Pool Leak, wait 2 minutes and report, Report that water is flowing out of what appears to be a crack 8 feet below the grating on 694. Its coming out pretty quick and filling the bottom of the raceway.
As the operator for any safety precautions (such as entering from 694 elevation). [Entering from 673 may not be possible depending on how much water is in the raceway, and it could jeopardize the corner room you enter from.]
Floor Instructor Notes/OPEX/TRs The leak in the Suppression Pool is at -12 feet.
Terminus: continued Page 20 of 34
NRC 15-1-3 Revision 00 Event-7 Formatted Table
==
Description:==
Five Control Rods Remain Out, ATWS Initiation: continuedOn direction of Lead Evaluator Cues:
Key Parameter Response: Rod position indication for stuck rods Expected Annunciators: None Automatic Actions: None Objective Position EXPECTED OPERATOR RESPONSE Per LGA-010
- Inhibit ADS
Per the PRESSURE Leg BOP o STABILIZE pressure <1059 psig using main turbine bypass valves Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent
- o STABILIZE pressure <1059 psig using SRVs at: 0.25"
- VERIFY required automatic actions occur (See event 6)
- o May request LGA-RH-101 jumper installation Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25" LGA-010
- Recognize that all rods did not insert and notify US (Hydraulic ATWS)
Per the POWER Leg if control rods remain out:
- If control rods remain out:
- Initiate ARI 432.000
- If power is above 3%, initiate SBLC (No) 433.000
- Insert Control rods per LGA-NB-01 (CT) 434.000 ATC
- Method 3 Single Rod Insert 431.000
- Bypass RWM 431.010
- Place CRD Drive Flow Trip Circuit in BYPASS
- Insert control rods using Continuous Insert or Insert Button o May request LGA-NB-01 Method 4 Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent
- WAIT until rods full in except one OR all rods in to at least 02 OR at: 0.25" Reactor will stay shutdown under all conditions without boron per QNE.
- Formatted: Indent: Left: 0.25", No bullets or numbering
- Directs LGA-001 and LGA-010 actions
- Directs Inhibit ADS
- Formatted: Indent: Left: 0", Hanging: 0.5" 432.000
- When only one Rod remaining out, transition back to LGA-001 433.000
- Directs Inhibit ADS 434.000 US
- Set Reactor Level and Pressure Bands 431.000
- Directs LGA-NB-01 (CT) Formatted: Indent: Left: 0", Hanging: 0.5" 431.010
- Directs method of Control Rod insertion per LGA-NB-01
- Direct Method 3, Single Rod Insertion Formatted: Indent: Left: 0.3", Hanging: 0.25", Tab stops:
0.55", List tab + Not at 0.25"
- o May direct Method 4, Reset Scram/Drain SDV/Re-ScramMay direct Method 3 Single Rod Insert Formatted: Indent: First line: 0.05", Bulleted + Level: 1 +
Aligned at: 0" + Indent at: 0.25", Tab stops: Not at 0.43" Page 21 of 34
NRC 15-1-3 Revision 00 Event - 7
Description:
Five Control Rods Remain Out, ATWS Simulator Operator Actions Immediately after Scram, From the Summary Page, MODIFY the Rod Friction Malfunctions reduce the friction on the (mrd046, 042, 209, 215, & 033) to 20% Severity to allow the stuck stuck rods control rods to be driven in.
LGA-MS-01
- From the RNI display - JMP Screen - click on LGA-MS-01 jumpers (5 jumpers)
- Install only jumper #4
- Select INSTALLED then INSERT When directed by the crew, insert ATWS Jumpers and LGA-NB-01 Method 4 pull fuses. These actions
- From the RNI display - JMP Screen - click on LGA-NB-01 jumpers should take approximately 5 (1 set) minutes - or- as directed by
- Select INSTALLED then INSERT the Lead Examiner/Floor Instructor. Actions may be
- From the CRD Screen (RD1), close CRD 34 when directed: irf delayed to allow completion vhrd034d 0 of actions.
- From the Action List Remote Function (RD), deenergize ARI Logic when directed:
irf iaaride1 de-energize and irf iaaride2 de-energize LGA-RH-101
- From the RNI display - JMP Screen - click on LGA-RH-101 (1 jumper)
- Select INSTALLED then INSERT Simulator Operator Role Play Role Play Unit 2 operators as necessary to support the Remote Functions above Floor Instructor Notes/OPEX/TRs Per LGA-NB-01 Step C.2.b, the method of rod insertion per LGA-NB-01 should be Method 3 for Single Rod insertion. Formatted: Font: Bold Terminus: When all control rods are fully inserted Page 22 of 34
NRC 15-1-3 Revision 00 Event - 7
==
Description:==
Five Control Rods Remain Out, ATWS Simulator Operator Actions Immediately after Scram, From the Summary Page, MODIFY the Rod Friction Malfunctions reduce the friction on the (mrd046, 042, 209, 215, & 033) to 20% Severity to allow the stuck stuck rods control rods to be driven in.
LGA-MS-01
- From the RNI display - JMP Screen - click on LGA-MS-01 jumpers (5 jumpers)
- Install only jumper #4
- Select INSTALLED then INSERT When directed by the crew, insert ATWS Jumpers and LGA-NB-01 Method 4 pull fuses. These actions
- From the RNI display - JMP Screen - click on LGA-NB-01 jumpers should take approximately 5 (1 set) minutes - or- as directed by
- Select INSTALLED then INSERT the Lead Examiner/Floor Instructor. Actions may be
- From the CRD Screen (RD1), close CRD 34 when directed: irf delayed to allow completion vhrd034d 0 of actions.
- From the Action List Remote Function (RD), deenergize ARI Logic when directed:
irf iaaride1 de-energize and irf iaaride2 de-energize LGA-RH-101
- From the RNI display - JMP Screen - click on LGA-RH-101 (1 jumper)
- Select INSTALLED then INSERT Simulator Operator Role Play Role Play Unit 2 operators as necessary to support the Remote Functions above Floor Instructor Notes/OPEX/TRs Per LGA-NB-01 Step C.2.b, the method of rod insertion per LGA-NB-01 should be Method 3 for Single Rod insertion. This event is intended for the ATC.
Terminus: When all control rods are fully inserted Page 23 of 34
NRC 15-1-3 Revision 00 Event-8
==
Description:==
RPV Blowdown Initiation: Suppression Pool Level cannot be maintained above -12 feetOn direction of Lead Evaluator Cues:
Key Parameter Response: Suppression Pool Water Level Expected Annunciators: 1PM13J-B203, SUP POOL WTR LVL LO Automatic Actions: None Formatted: Space Before: 6 pt, After: 6 pt Objective Position EXPECTED OPERATOR RESPONSE Per LGA-006
- IF all rods in to at least 02 or all rods full in except one or Reactor will stay shutdown under all conditions without boron per QNE
- Exit this procedure and enter LGA-004
- CRD 423.000
- Arms and depresses both Div 1 ADS MANUAL INITIATION pushbuttons
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons Formatted: Indent: Hanging: 0.01", Space Before: 0 pt,
- Verify all 7 ADS valves open (Yes) After: 0 pt, Widow/Orphan control, Adjust space between Latin and Asian text, Adjust space between Asian text and
- Return to ATWS level numbers, Tab stops: Not at 4.03"
Formatted: Font: 10 pt
- Wait until Shutdown Cooling pressure Interlock clears (143 psig)
Formatted: Font: 9.5 pt
- Cool down to cold shutdown using Shutdown Cooling (LOP-RH-07)
- Formatted: Bulleted + Level: 1 + Aligned at: 0" + Tab after: 0.25" + Indent at: 0.25" Per LGA-004
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons
- Verify 7 SRVs are open (Yes) Formatted: Indent: Left: 0.25"
- Wait until Shutdown Cooling pressure Interlock clears (143 psig) Formatted: Font: 9.5 pt
- Cool down to cold shutdown using Shutdown Cooling (LOP-RH-07)
Per LGA-003 Formatted: Indent: Left: 0.25", No bullets or numbering
- When directed, starts all available Pool Cooling per LGA-RH-103
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, BOP START first RHR Service Water Pump Formatted: Font: 9.5 pt
- Startup RHR
- Start 1A/1B RHR Pump
- Throttle 1E12-F024A/B OPEN to establish RHR flow of 1500 to 7450 gpm
- Close 1E12-F048A/B (HX Bypass)
Page 24 of 34
NRC 15-1-3 Revision 00 Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/BPer LGA-003
- Start Suppression Pool Cooling ATC
- Maintain RPV level as directed by Unit Supervisor per LGA-001 and LGA-010 Formatted: Font: 9.5 pt
- If cannot restore level above -12 feet and hold it there per LGA-003 then blowdown per LGA-004/006 (CT) 423.000
- Direct actions per LGA-0046/0064 and LGA-001/010 Formatted: Font: 9.5 pt US 428.000
- Performs emergency blowdown (CT)
- Inform Shift Manager Page 25 of 34
NRC 15-1-3 Revision 00 Event - 8
==
Description:==
RPV Blowdown Simulator Operator Actions None Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: RPV Blow down complete. RPV level restored and being maintained in normal operating range with containment parameters stable or improving.
Page 26 of 34
NRC 15-1-3 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 3. LGA-004 RPV BLOWDOWN 009
- 4. LGA-006 ATWS BLOWDOWN 009
- 5. LGA-010 FAILURE TO SCRAM 015
- 6. LGA-NB-01 ALTERNATE ROD INSERTION 018 USING MAIN CONDENSER AS A HEAT SINK IN AN
- 7. LGA-MS-01 014 ATWS ALTERNATE VESSEL INJECTION USING SHUTDOWN
- 8. LGA-RH-101 004 COOLING RETURN UNIT 1 A AND B RHR OPERATIONS IN THE LGAS AND 012
- 9. LGA-RH-103 SAMGS
- 10. LGP-3-1 POWER CHANGES 062
- 11. LGP-3-2 REACTOR SCRAM 072 PREPARATION FOR STANDBY OPERATION OF THE
- 12. LOP-RI-05 033 REACTOR CORE ISOLATION COOLING SYSTEM STARTUP AND OPERATION OF THE OFF GAS
- 13. LOP-VO-01 013 BUILDING HVAC SYSTEM
- 14. LOP-VO-02 SHUTDOWN OF AN OFF GAS BUILDING HVAC TRAIN 012 REACTOR WATER CLEANUP SYSTEM STARTUP AND
- 15. LOP-RT-02 048 PUMP TRANSFER
- 16. LOA-DIKE-001 LAKE DIKE DAMAGE FAILURE 011
- 18. LOR-1PM06J-A106 003 AUTO TRIP STRONG MOTION SEISMIC INSTRUMENT SYSTEM
- 19. LOR-1PM10J-B504 024 IMITATED
- 20. LOR-1PM13J-B203 SUPPRESSION POOL WATER LEVEL LOW 004
- 21. OP-LA-101-111-LASALLE OPERATIONS PHILOSOPHY HANDBOOK 066 1002
- 22. LOR-1H13-P602- REACTOR WATER CLEANUP RECIRC PUMP 1B 004 A107 AUTOMATIC TRIP
- 23. LOA-RT-101 LOSS OF REACTOR WATER CLEANUP SYSTEM 019 Page 27 of 34
NRC 15-1-3 Revision 00 COMPUTER AIDED EXERCISE PROGRAM (CAEP)
ESG NRC 15-1-3 Revision: 00 Revision Date: 7/5/16 Developed By: C. M. Betken Page 28 of 34
NRC 15-1-3 Revision 00 Page 29 of 34
NRC 15-1-3 Revision 00 Page 30 of 34
NRC 15-1-3 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 31 of 34
NRC 15-1-3 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Yellow Work Week: RCIC Unit 1 power level Unit 2 power level
- 100 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- None
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- RCIC, 12 days left, T.S. 3.5.3
- IMD is standing by to perform Attachment A of LOP-RI-05 LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- Online Risk - YELLOW
- Div 2 workweek
- PROTECTED: HPCS
- OLR is Green
- RCIC Workweek Page 32 of 34
NRC 15-1-3 Revision 00 Page 33 of 34
NRC 15-1-3 Revision 00 U1 SUPERVISOR TURNOVER (Alternate)
Shift: 2 Date: Today Mode: 1 OLR: Green Work Week: RCIC Unit 1 power level Unit 2 power level
- 100 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- None
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- None
- Div 2 workweek
- OLR is Green
- OLR is Green
- RCIC Workweek Page 34 of 34
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 4 Op-Test No.: __NRC 15-12016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% Reactor power, C CD/CB OOS Turnover: Swap VR Supply/Exhaust Fans IAW LOP-VR-01 Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Swap VR Supply/Exhaust Fans IAW LOP-VR-01 2 mms056 R (ATC) Abnormal Turbine Generator Vibrations mai006 Station Air Compressor TRIP, Standby Fails to 3 C (BOP) Auto Start mai007 4 mni073 I (ATC) LPRM Fails Downscale 5 mrd353 I (ATC) Loss of RPIS 56 mrd353 T (SRO) Loss of RPIS Abnormal Turbine Generator Vibrations, Manual 67 mms056 M (ALL)
SCRAM 78 mcf034 M (ALL) Feedwater Rupture Inside Primary Containment C HPCS Fails to Auto-Start 89 mes032 (BOPALL
)
9 none M (ALL) RPV Blowdown (Contingency)
(N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 7 BOP Normal: 1 Malfunction(s) after EOP (1-2): 2 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 4 EOP Contingencies (0-2): 0 SRO Tech Spec (2 per set): 1 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 2 Formatted: Indent: Left: 0", Hanging: 0.62"
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-4 Rev. 0 07/20/2016 DEVELOPED BY: Colin Betken 8/15/2016 Instructor Date VALIDATED BY: Murphy / Hawkins / Nicoll / Adams 7/23/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Exam Author Date
NRC 15-1-4 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-4 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 1. Swap VR Supply/Exhaust Fans IAW LOP-VR-01.
Following turnover the crew will place the standby VR Supply and Exhaust Fan on service and secure a running VR Supply and Exhaust Fan
- 2. Abnormal Turbine Generator Vibrations.
Following the VR swap, vibes will slowly increase until the crew takes action and lowers Reactor Power. After Reactor Power is lowered vibes will slowly return to normal.
- 3. Station Air Compressor TRIP, Standby Fails to Auto Start.
The crew will take action to start the 0 Station Air Compressor following the TRIP of the Unit 1 Station Air compressor and Service/Instrument header pressures will return to normal.
- 4. LPRM Fails Downscale.
The crew will respond to the failed Local Power Range Monitor and Bypass that LPRM.
- 5. Loss of RPIS.
Rod 38-19 will loss position indication and the rod will have to fully inserted and electrically disarmed.
- 6. Abnormal Turbine Generator Vibrations, Manual SCRAM Turbine Generator Vibes will return and continue to increase forcing the crew to SCRAM and TRIP the Main Turbine.
- 7. Feedwater Rupture Inside Primary Containment.
Following the SCRAM the Feedwater System will develop a leak inside the Drywell. The crew should take action to attempt to isolate the leak by isolating the Feedwater System and commence cooling the Containment.
- 8. HPCS Fails to Auto-Start.
- 9. HPCS will fail to automatically start on a high drywell signal from the LOCA. The crew should Formatted: Indent: Left: 0.25", No bullets or numbering take action to manually start HPCS to maintain RPV level.
- 9. RPV Blowdown (Contingency)
If the crew is unable to maintain level >-150 they will blowdown per LGA-004 Formatted: Indent: Left: 0.25", No bullets or numbering
- 10. HPCS Fails to Auto-Start.
HPCS will fail to automatically start on a high drywell signal from the LOCA. The crew should take action to manually start HPCS to maintain RPV level.
Critical Tasks
- 1. Identify failures of automatic system response, and where such response is needed to maintain adequate core cooling, take manual action to place the system in operation.
Page 2 of 35
NRC 15-1-4 Revision 00
- 2. With suppression chamber pressure above 12 psig, containment flood level below 722 feet, and Formatted: Font: 11 pt drywell parameters below the Drywell Spray Initiation Limit; trip all recirculation pumps and start drywell sprays using RHR pumps not needed for adequate core cooling.
- 3. With available injection systems unable to hold RPV water level above -150 inches on Wide Range, INITIATE emergency depressurization when RPV water level drops to -150 inches on Wide Range. (N/A if the crew is able to maintain RPV Level >-150)
- 4. Place the Residual Heat Removal (RHR) heat exchangers in service to establish containment cooling. (N/A if the crew is able to maintain RPV Level >-150)
- 1. Start drywell spray before exceeding the PSP curve.
- 2. With primary containment pressure above 1.93 psig, containment flood level below 723 feet, and pumps not needed for core cooling available; start suppression chamber spray.
Page 3 of 35
NRC 15-1-4 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 4 of 35
NRC 15-1-4 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall a full power IC.
- 2. Place simulator in RUN.
- 3. Load and run the smart scenario: NRC 15-1-4
- 4. Place Protected Equipment rings and/or robust barriers on the following components:
- Place protected path rings on A, B, and D CD/CB Pumps
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the following panel manipulations:
- Place C CD/CB Pump in PTL
- 7. Place the following Tags:
- Hang OOS on C CD/CB Pump
- 8. Verify the following:
- Unit 1 SAC is Running
- 0 SAC is in STBY
- 9. Have a copy of LOP-VR-01 and LOP-PR-04
- 10. Verify a stopwatch is available 9.11. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 5 of 35
NRC 15-1-4 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 4 Op-Test No.: ____2016301____
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: 100% Reactor power, C CD/CB OOS Turnover: Perform LOP-VR-01 to swap VR Supply/Exhaust Fans Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Swap VR Supply/Exhaust Fans IAW LOP-VR-01 2 mms056 R (ATC) Abnormal Turbine Generator Vibrations mai006 Station Air Compressor TRIP, Standby Fails to 3 C (BOP) Auto Start mai007 4 mni073 I (ATC) LPRM Fails Downscale 5 mrd353 I (ATC) Loss of RPIS 56 mrd353 T (SRO) Loss of RPIS 67 Abnormal Turbine Generator Vibrations, Manual mms056 M (ALL)
SCRAM 78 mcf034 M (ALL) Feedwater Rupture Inside Primary Containment C HPCS Fails to Auto-Start Formatted: Centered 89 mes032 (ALLBOP
)
9 none M (ALL) RPV Blowdown (Contingency) Formatted: Centered (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes: Formatted: Indent: Left: 0", First line: 0" Total Malfunctions (5-8): 7 BOP Normal: 1 Malfunction(s) after EOP (1-2): 2 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 4 EOP Contingencies (0-2): 0 SRO Tech Spec (2 per set): 1 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 2 Formatted: Indent: Left: 0", Hanging: 0.62" APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 6 of 35
NRC 15-1-4 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC 43.001 Perform Control Room actions for a Local Power Range Monitor Failure, Perform the Main Control Room actions for a Loss of Control Rod Position 47.012 Information System.
Perform Control Room actions for Main Turbine Generator high vibration or 71.030 noise.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 413.010 Evaluate plant conditions and control RPV water level using CRD RO - BOP/ASSIST 71.029 Perform Control Room actions for Main Turbine Generator trip (load > 25%),
Perform Control Room actions for Main Turbine Generator high vibration or 71.030 noise.
97.025 Perform Control Room actions for a loss of Instrument Air/Service Air, Evaluate plant conditions and control secondary containment by operation of the following ventilation systems, 415.000 (a) VR (b) VG (c) VQ Given LGA-03, Primary Containment Control, in progress, evaluate plant 419.000 conditions and control and maintain Primary Containment pressure less than 1.93 psig IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the 419.020 Suppression Pool IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the Drywell 419.030 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 420.000 conditions and control and maintain Drywell Temperature less than 340F IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Page 7 of 35
NRC 15-1-4 Revision 00 SRO - UNIT SUPERVISOR Perform the Main Control Room actions for a Loss of Control Rod Position 47.012 Information System.
71.029 Perform Control Room actions for Main Turbine Generator trip (load > 25%),
Perform Control Room actions for Main Turbine Generator high vibration or 71.030 noise.
97.025 Perform Control Room actions for a loss of Instrument Air/Service Air, Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 413.010 Evaluate plant conditions and control RPV water level using CRD Evaluate plant conditions and control secondary containment by operation of the following ventilation systems, 415.000 (a) VR (b) VG (c) VQ Given LGA-03, Primary Containment Control, in progress, evaluate plant 419.000 conditions and control and maintain Primary Containment pressure less than 1.93 psig IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the 419.020 Suppression Pool IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the Drywell 419.030 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 420.000 conditions and control and maintain Drywell Temperature less than 340F IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Page 8 of 35
NRC 15-1-4 Revision 00 Event-1
==
Description:==
Swap VR Supply/Exhaust Fans IAW LOP-VR-01 Initiation: Following crew assuming shift, on direction of Lead Evaluator Cues: Turnover Objective Position EXPECTED OPERATOR RESPONSE Per LOP-VR-01 o If desired, maintain CRD room Fan 1VR03CA/B running by quickly placing the C/S in START
- STOP one running VR supply fan 1VR01CA by placing the control switch in the STOP position
- IMMEDIATELY STOP one VR Exhaust Fan 1VR02A by placing the control switch in the STOP position 415.000 BOP
- START on standby VR Exhaust Fan 1VR02CC
- IMMEDIATELY start one VR Supply Fan 1VR01CC
- o VERIFY Station Vent Stack WRGM sample flow is isokinetic Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25" o If a CRD room Fan 1VR03CA/B was placed in START quickly place the C/S in AUTO ATC
- Monitor plant parameters and update the crew as required 415.000 US
- Direct above actions Page 9 of 35
NRC 15-1-4 Revision 00 Event - 1
==
Description:==
Swap VR Supply/Exhaust Fans IAW LOP-VR-01 Simulator Operator Actions none Simulator Operator Role Play As the operator in the field, when ordered to check the status of dampers in the field at the 1PL27J, wait 1 minute and report, 1VR01YA and 1VR02YA are CLOSED following the securing of the off going supply and exhaust fan.
As the operator in the field, when ordered to check the status of dampers in the field at the 1PL27J, wait 1 minute and report, 1VR01YC and 1VR02YC are OPEN following the starting of the oncoming supply and exhaust fan.
Floor Instructor Notes/OPEX/TRs None Terminus: VR Supply and Exhaust Fans swapped.
Page 10 of 35
NRC 15-1-4 Revision 00 Event-2
==
Description:==
Abnormal Turbine Generator Vibrations Initiation: On direction of Lead Evaluator, release Event 2 Cues:
Key Parameter Response: Rising Turbine Generator Vibrations Expected Annunciators: 1PM02J-B405, U1 TUBINE VIBRATIONS HI HI Automatic Action: none Objective Position EXPECTED OPERATOR RESPONSE Per 1PM02J-B405 Formatted: Font: Bold
- Refer to LOA-TG-101 Formatted: List Paragraph, Indent: Left: 0", Hanging:
0.24", Bulleted + Level: 1 + Aligned at: 0.5" + Indent at:
0.75" Per LOA-TG-101 Formatted: Font: (Default) Arial, 11 pt
- CHECK vibration level - REFER to the limits identified in Attachment A Formatted: List Paragraph, Indent: Left: 0.24"
- Request EMD to take Shaft Voltage per LEP-TG-101
- CHECK Turbine Lube Oil temp within the following limits:
- Turbine Oil is being maintained at 110F to 120F
- CHECK Temperature rise across bearings 71.030 BOP
- COMPARE Turb Bearing Metal Temp
- DISPATCH an Operator to the Turbine Generator area to listen around Turbine Generator - NO abnormal noise
- CHECK Turbine Lube Oil System - OPERATINGOPEARTING NORMALLY
- CHECK Steam Seal system - pressure greater than 4 psig
- CHECK Turbine hood temperature less - than 175F
- CHECK Main Generator Bearings 9 and 10 - Not affected Per LOA-TG-101 71.030 ATC
- At direction of Unit Supervisor REDUCE Reactor Power using Reactor Recirculation Flow or Control Rods
- Direct above actions
- Set Critical Parameter Turbine Vibes
- Designate Scram Criteria 71.030 US
- Inform Shift Manager
- Contact Generation Dispatch of MWe reduction Page 11 of 35
NRC 15-1-4 Revision 00 Event - 2
==
Description:==
Abnormal Turbine Generator Vibrations Simulator Operator Actions With the concurrence of the Release Event 2 Lead Evaluator When the Crew lowers From smart summary change mms056, change the initial value to the Reactor Power and at the current value of vibes and change the final value to 0 and ramp over 2 discretion of the Lead minutes Evaluator Simulator Operator Role Play As the equipment operator sent to the TSI panel, wait 4 minutes and report to the Main Control Room requested information using RNI Panel view at 1PM02J-03 for bearing vibrations (mils)
As the operator sent to the turbine deck, wait 3 minutes and report, There are NO abnormal sounds from the Turbine Generator on the Turbine Deck.
Floor Instructor Notes/OPEX/TRs Turbine Vibration Limits per Attachment A of LOA-TG-101:
- Bearings 1 through 10 - 12 mils or 10 mils for 15 minutes
- Bearings 11 and 12 - 10 mils (must indicate greater than value on both X and Y TSI panel indicators to meet the criteria for a manual turbine trip.
Terminus: Reactor Power lowered and Turbine Vibrations trend turned.
Page 12 of 35
NRC 15-1-4 Revision 00 Event-3
==
Description:==
Station Air Compressor TRIP, Standby Fails to Auto Start Initiation: On direction of Lead Evaluator, release Event 3 Cues:
Key Parameter Response: Lowering Air Pressures Expected Annunciators: 1PM10J-B104, UNIT 1 STATION AIR COMPRESSOR AUTO TRIP Automatic Action: Unit 1 Station Air Compressor Automatic Trip Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM10J-B104
- Verify auto actions occur
- If air pressure is dropping, START standby air compressor per LOP-SA-01/02
- DISPATCH operator to Local Control Panel to CHECK for cause of 97.025 BOP TRIP
- If low oil pressure is indicated at Local Control Panel:
- VERIFY lube oil reservoir level is proper
- CHANGE lube oil filters as necessary o If Station Air pressure drops below 100 psig and the standby air Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent compressor has not started, start 0SA01C at: 0.25" Per LOP-SA-02
- Dispatch an operator to perform post start checks on the Unit 0 Station BOP Air Compressor
- Verify system parameters return to normal, and adjust as necessary ATC
- Monitor plant parameters and update the crew as required
- Direct above actions 97.025 US
- Inform Shift Manager
- Contact EMD Page 13 of 35
NRC 15-1-4 Revision 00 Event - 3
==
Description:==
Station Air Compressor TRIP, Standby Fails to Auto Start Simulator Operator Actions With the concurrence of the Release Event 3 Lead Evaluator Simulator Operator Role Play As the equipment operator sent to investigate the Unit 1 Station Air Compressor, wait 4 minutes and report, Unit 1 Station Air Compressor tripped on low oil pressure.
Floor Instructor Notes/OPEX/TRs Low lube oil pressure trip setpoint is 8 psig for Unit 1 Station Air Compressor. Station Air Compressor will Auto start set point is 100 psig header pressure.
Terminus: Startup of 0 Station Air Compressor and parameters return to normal.
Page 14 of 35
NRC 15-1-4 Revision 00 Event-4
==
Description:==
LPRM Fails Downscale Initiation: On direction of Lead Evaluator, release Event 4 Formatted: Font: Bold Cues:
Key Parameter Response: LPRM Downscale and lowering D APRM Power Expected Annunciators:
1H13-P603-A407, LOCAL POWER RANGE MONITOR DOWNSCALE 1H13-P603-B507, OPRM / INOP TROUBLE Automatic Action: none Objective Position EXPECTED OPERATOR RESPONSE
- Monitor Plant parameters and update the crew as required BOP
- REFER to LOA-NR-101, Neutron Monitor Trouble
- Verify core power and flow.
Per LOA-NR-101
- STOP all control rod motion/power changes
- SELECT a control rod that will display suspect LPRM on the 1H13-P603 display of four LPRM strings
- EVALUATE LPRM indication - NORMAL for plant conditions.
- NOT Upscale/Downscale Response not obtained
- REFER to Attachment B to assist in determining the operability of associated APRM
- SELECT control rod that displays affected LPRM detector and VERIFY downscale reading on the meter
- BYPASS the failed LPRM Detector
- o If desired, UNBYPASS the APRM Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- NOTIFY QNE
- VERIFY, using the Process Computer and the core mentoring software system, that LPRM inputs are zero
- o Initiate an IR Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- Direct above actions
- Contact QNE US
- Contact Shift Manager
- Refer to Tech Spec 3.3.2.1 and 3.3.1.3 Page 15 of 35
NRC 15-1-4 Revision 00 Event - 4
==
Description:==
LPRM Fails Downscale Simulator Operator Actions With the concurrence of the ReleaseELEASE Event 4 Lead Evaluator Simulator Operator Role Play Respond as QNE and Shift Manager.
Floor Instructor Notes/OPEX/TRsLPRM 08-33A is in input to D APRM per Attachment B of LOA-NR-101 The downscale light for the LPRM is not modeled on the back panel of the simulator, if questioned, inform the examinee that the downscale light is illuminated.
Terminus: D APRM Bypassed / 08-33A LPRM Bypassed Page 16 of 35
NRC 15-1-4 Revision 00 Event-5
==
Description:==
Loss of RPIS for Control Rod 38-19 Initiation: On direction of Lead Evaluator, release Event 5 Cues:
Key Parameter Response: Data Fault On Rod Display Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE
- Monitor plant parameters and update the crew as required BOP
- Formatted: Font: 10 pt
- Provide peer checksProvides peer checks as required Formatted: Font: 10 pt Formatted: Font: 10 pt Per LOA-RM-101 Formatted: Font: 10 pt
- CHECK Control Rod Position indicates XX
- CHECK Control Rod NOT at position 00/Full InOut prior to indication loss. Formatted: Font: 10 pt
- CHECK Control Rod NOT at position 48/Full Out prior to indication loss. (NO) Formatted: Font: 10 pt
- Apply 2 second withdraw jog:
Formatted: List Paragraph
- Place CRD Drive Flow Trip Circuit Bypass Switch to BYPASS
- Bypass RWM
- Navigate to Withdraw Jog under SURVEILLANCE with RCMS
- Apply 1 to 2 second duration Withdraw Jog command using withdraw and Formatted: Indent: Left: 0.24", Tab stops: 0.49", List tab continuous withdraw pushbuttons and observe withdraw drive flow and + Not at 0.25" withdraw and continuous withdraw indicators
- Check rod indicates valid position (NO)INSERT withdraw Jog
- INSERT control rod one notch:
º VERIFY RWM Bypass Switch in BYPASSBypass the Rod within RCMS per Formatted: Font: 10 pt LOP-RM-02 47.012 ATC
- APPLY one single notch insert command only, Formatted: Font: 10 pt
- OBSERVE Drive Flow and INSERT/SETTLE indicators
- CHECK Control Rod - INDICATES new, valid position. (no)
- Fully insert rod per attachment A
- Fill out Attachment A table/check list Formatted: Font: (Default) Arial, 10 pt
- REVIEW and PRINT PPC LPRM Status Display for LPRM power readings Formatted: Font: (Default) Arial, 10 pt, Font color: Black before inserting any control rod Formatted: Font: 10 pt
- INSERT control rod, by depressing and holding the INSERT Pushbutton while Formatted: Font: 10 pt timing and observing the following: Formatted: Font: 10 pt
- Expected LPRM power decay.
- Expected DECREASE in Reactor Power. Formatted: Indent: Hanging: 0.01"
- Control rod full in should be indicated by:
- Stall Flow is observed Formatted: Font color: Black
- IMD verification of full in reed switch actuation Formatted: Normal, Indent: Left: 0.24", Space Before: 0 pt, After: 0 pt, Bulleted + Level: 1 + Aligned at: 0.75" +
- Control rod insertion time is approximately equal to the previous LOS-RD- Indent at: 1", Widow/Orphan control, Adjust space between SR5 value from the time the insert PB was initially depressed Latin and Asian text, Adjust space between Asian text and numbers, Tab stops: 0.49", List tab Page 17 of 35
NRC 15-1-4 Revision 00
- Release the Control Rod INSERT Pushbutton
- Electrically Disarm Control Rod Formatted: Font: 10 pt
- Direct above actions Formatted: Normal, Space Before: 0 pt, After: 0 pt,
- Contact QNE Widow/Orphan control, Adjust space between Latin and Asian text, Adjust space between Asian text and numbers 47.012
- Enter Tech Spec 3.1.3 Condition C US Formatted: Font: 10 pt 201.011
- Required action C.1 fully insert inop control rod in 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> AND C.2 disarm the associated CRD in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
- Formatted: Indent: Left: 0.24", Bulleted + Level: 1 +
Aligned at: 0" + Tab after: 0.25" + Indent at: 0.25", Tab stops: 0.49", List tab + Not at 0.25" Formatted: Left Page 18 of 35
NRC 15-1-4 Revision 00 Event - 5
==
Description:==
Loss of RPIS for Control Rod 38-19 Simulator Operator Actions With the concurrence of the Release Event 5 Lead Evaluator Simulator Operator Role Play As QNE, is asked the previous stroke time was 56.3 seconds and the previous recorded stall flow was 1.9 gpm when last pperformedperformed.
As IMD, when asked inform the crew, standing by to read RPIS probe locally As IMD, when the rod is fully inserted, inform the crew the rod indicates fully inserted by local reading.
Floor Instructor Notes/OPEX/TRs none Terminus: when Rod is electrically disabled disarmed and Tech Spec call is made Page 19 of 35
NRC 15-1-4 Revision 00 Event-6
==
Description:==
Abnormal Turbine Generator Vibrations, Manual SCRAM Initiation: On direction of Lead Evaluator, release Event 6 Cues:
Key Parameter Response: Rising Turbine Generator Vibrations Expected Annunciators: 1PM02J-B405, U1 TUBINE VIBRATIONS HI HI Automatic Action: none Objective Position EXPECTED OPERATOR RESPONSE Per LOA-TG-101
- CHECK vibration level - REFER to the limits identified in Attachment A
- Determine turbine vibration levels exceed limits and inform the Unit Supervisor
- TRIP and PERFORM Subsection B.1 of this procedure
- CHECK Reactor Power - below 25% and stable Response not obtained
- SCRAM Reactor
- CHECK Turbine Bypass Valves - controlling Reactor Pressure
- CHECK Turbine TRIPPED
- CHECK at least one of the following - CLOSED o All MSVs (Yes) 71.029 Formatted: Font: 10 pt BOP o All CVs (Yes) 71.030
- VERIFY Load Limiter at 2.0%
- CHECK Generator OCBs 9-10 and 10 OPEN
- CHECK Generator field breaker - OPEN
- CHECK Voltage Regulator in - MANUAL
- CHECK In-house loads transferred to SAT
- CHECK Heater Valve alignment
- MONITOR Turbine parameters throughout coastdown:
- Speed (decreasing)
- Bearing Vibrations (<10 mils)
- Bearing Metal Temperatures (<190F)
- Turbine Lube Oil Temperatures Per LOA-TG-101
- If directed by Unit Supervisor REDUCE Reactor Power using Reactor 71.030 ATC Formatted: Font: 10 pt Recirculation Flow or Control Rods
- Scram Reactor
- Direct above actions
- Set Critical Parameter Turbine Vibes Formatted: Font: 10 pt 71.029 US
- Designate Scram Criteria 413.000
- Inform Shift Manager
- Contact Generation Dispatch of MWe reduction Page 20 of 35
NRC 15-1-4 Revision 00 Event - 6
==
Description:==
Abnormal Turbine Generator Vibrations, Manual SCRAM Simulator Operator Actions With the concurrence of the Formatted Table Release Event 6 Lead Evaluator Following the Turbine Trip Ramp mns056 to 0 over 2 minutes Simulator Operator Role Play As the equipment operator sent to the TSI panel, wait 4 minutes and report to the Main Control Room requested information using RNI Panel view at 1PM02J-03 for bearing vibrations (mils)
As the operator sent to the turbine deck, wait 3 minutes and report, There is NO abnormal sounds from the Turbine Generator on the Turbine Deck.
Formatted: Left Page 21 of 35
NRC 15-1-4 Revision 00 Event contd
==
Description:==
Abnormal Turbine Generator Vibrations, Manual SCRAM Objective Position EXPECTED OPERATOR RESPONSE
- Manually TRIP the Main Turbine 71.029 BOP
- Monitor Plant parameters and update the crew as required.
Performs Reactor Scram and LGP 3-2 on US direction.
- PLACE Reactor Mode Switch in SHUTDOWN
- CHECK Control Rods INSERTED and Power Decreasing
- INFORM Unit Supervisor of Control Rod Status and Reactor Power
- Operate Feedwater and/or ECCS as necessary to maintain RPV Water Level 20" to 50" or as specified by Unit Supervisor
- Place LFFRV in AUTO o Verify FRV closed in MANUAL 304.010
- REPORT to the Unit Supervisor the status of RPV Level and Pressure
- If needed for level control:
o Place the FRV in AUTO o Reset the Scram o Dispatch an EO to close 1C11-F034, Charging Water Supply Valve
- VERIFY Reactor Recirculation Pumps have downshifted
- VERIFY Main Turbine and Generator Trip
- STABILIZE Reactor Pressure <1020 psig o If Main Condenser is available, open Bypass Valves
- Maintains RPV water level as directed
- Maintains RPV pressure as directed
- Direct above actions 413.000 SRO
- Order Reactor Scram and Turbine TRIP
- Direct actions of LGA-001 Formatted: Left Page 22 of 35
NRC 15-1-4 Revision 00 Floor Instructor Notes/OPEX/TRs Turbine Vibration Limits per Attachment A of LOA-TG-101:
- Bearings 1 through 10 - 12 mils or 10 mils for 15 minutes
- Bearings 11 and 12 - 10 mils (must indicate greater than value on both X and Y TSI panel indicators to meet the criteria for a manual turbine trip.
Terminus: Turbine tripped and speed lowering.
THIS PAGE INTENTIONALLY LEFT BLANK Page 23 of 35
NRC 15-1-4 Revision 00 Event-7
==
Description:==
Feedwater Rupture Inside Primary Containment Initiation: Automatic Cues:
Key Parameter Response: Rising DW Pressure Expected Annunciators: Multiple Automatic Action: none Objective Position EXPECTED OPERATOR RESPONSE
- When directed places Suppression Pool Cooling in service: (CT) Formatted: Font: Bold
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, START first RHR Service Water Pump:
1A or 1B/C or D
- When indicated flow reaches 3000 gpm, START second RHR Service Water Pump.
- Startup RHR 419.000
- Start 1A/1B RHR Pump 419.020
- Establish RHR flow of 1500 to 7450 gpm:
419.030
- Throttle 1E12-F024A/B (Test Valve) OPEN.
420.000 BOP
- Close 1E12-F048A/B (HX Bypass) 421.000 o Place A/B HTX Bypass Throttle/Seal in switch to THROTTLE 421.010 and THROTTLE CLOSED 1E12-F048A/B.
o Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/B
- When directed establish Suppression Chamber Spray: (CT)
- VERIFY 1A/1B RHR Pump is running
- OPEN 1E12-F027A/B
- When directed establish Drywell Spray: (CT)
- VERIFY 1A/1B RHR Pump is running
- THROTTLE 1E12-F024A/B CLOSED
- OPEN:1E12-F016A/B and 1E12-F017A/B 413.000 ATC
- Monitors and reports trends in RPV level and pressure
- When Drywell Pressure exceeds 1.93 psig, enters and directs LGA-003
- Before Suppression Chamber Pressure exceeds 12 psig
- Verifies Containment Flood level below 723 ft.
419.000
- Directs start of Suppression Chamber Sprays 419.020
- When Suppression Chamber Pressure exceeds 12 psig, direct initiation of 419.030 Drywell sprays (CT) 420.000 US
- Verifies Containment Flood level below 722 ft.
421.000
- Verifies Drywell Pressure and Temperature permit Drywell Sprays per 421.010 Figure D
- Verifies both Recirc Pumps are tripped
- Direct initiation of Drywell sprays
- When Suppression Pool temperature exceeds 105ºF initiation of Ddirect initiation of Suppression Pool Cooling (CT)
Page 24 of 35
NRC 15-1-4 Revision 00 Event contd
Description:
Feedwater Rupture Inside Primary Containment Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitors plant parameters and updates the crew as required.
- Isolate the source of the leak
- Prevent Injection from Feedwater or Condensate/Condensate Booster:
o CLOSE 1B21-F065A and B Feedwater Stops o CLOSE 1FW010A and B, TDRFP Discharge Valves, and 1FW003, Feed ATC Reg Valve Isolation and 1FW145, LFCV Upstream Stop o CLOSE 1FW015A and B, High Pressure Heater Outlets, and 1FW013, High Pressure Heater Bypass Stop.
- Report if the source of the leak is isolated using RPV level and pressure trends
- Direct actions of LGA-001 US
- Direct actions of LGA-003
- May direct isolation of the Feedwater System Event - 7
==
Description:==
Feedwater Rupture Inside Primary Containment Simulator Operator Actions Auto event Released when the Reactor Mode Switch is in Shutdown Simulator Operator Role Play Role play as required.
Floor Instructor Notes/OPEX/TRs The ATC should notice RPV trends as well as the deviation between FW header flows to determine the leak is in the Feedwater System.
Terminus: continued Page 25 of 35
NRC 15-1-4 Revision 00 Formatted: Left Formatted: Left Event contd
==
Description:==
Feedwater Rupture Inside Primary Containment Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitors plant parameters and updates the crew as required.
- Isolate the source of the leak
- Prevent Injection from Feedwater or Condensate/Condensate Booster:
o CLOSE 1B21-F065A and B Feedwater Stops o CLOSE 1FW010A and B, TDRFP Discharge Valves, and 1FW003, Feed ATC Reg Valve Isolation and 1FW145, LFCV Upstream Stop o CLOSE 1FW015A and B, High Pressure Heater Outlets, and 1FW013, High Pressure Heater Bypass Stop.
- Report if the source of the leak is isolated using RPV level and pressure trends
- Direct actions of LGA-001 US
- Direct actions of LGA-003
- May direct isolation of the Feedwater System Page 26 of 35
NRC 15-1-4 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 27 of 35
NRC 15-1-4 Revision 00 Event-8
==
Description:==
HPCS Fails to Auto-Start Initiation: Automatic Cues:
Key Parameter Response: HPCS Pump Discharge Pressure and Run Lights Expected Annunciators: Multiple Automatic Action: none (HPCS Fails to Auto Start)
Objective Position EXPECTED OPERATOR RESPONSE
- If directed, starts a second CRD pump per LGA-RD-01
- Align 2 Drive Water Filters and 2 Suction Filters
- Open Minimum flow valves
- Defeat the CRD Low Suction Pressure trips
- Starts the second CRD Pump
- If directed, starts SBLC per LGA-SC-102
- Starts only one SBLC pump
- Place A SBLC Pump in Sys A
- Place B SBLC Pump in Sys B
- Check that the Storage tank Outlet valve opens on the selected pump
- Check that the selected SBLC Pump starts
- Check that SBLC Discharge Pressure rises above RPV pressure
- When RPV water level cannot be maintained above 11 inches, directs actions to maintain level above -150 inches
- Directs use of Alternate Injection systems 413.010 US
- Starting both CRD pumps
- Injecting with SBLC
- Direct actions of LGA-001 and LGA-003 Page 28 of 35
NRC 15-1-4 Revision 00 Event - 8
==
Description:==
HPCS Fails to Auto-Start Simulator Operator Actions Event it is Auto released Align the off service CRD Pump using RNI RD1 drawing (wait one minute between valve operations)
When requested to perform
- OPEN 1C11-F021A and B LGA-RD-01 field actions to
- CLOSE 1C11-F014A or B for the Standby Pump Pump
- ISOLATE the low suction pressure trip for both CRD Pumps (iardalst and iarbalst)
Using RNI RD1 Following the Standby CRD Pump Start
- OPEN 1C11-F014A/B
- Restore both low suction pressure trip switches to normal Simulator Operator Role Play As the operator sent to perform LGA-RD-01, perform actions above and report to the crew when they are complete using LGA-RD-01 as a reference.
Floor Instructor Notes/OPEX/TRs The crew should notice that HPCS does not start due to a Hi Drywell initiation signal (1.93 psig)
Terminus: RPV level is stable in band and at the direction of the Lead Evaluator Page 29 of 35
NRC 15-1-4 Revision 00 Event-9
==
Description:==
RPV Blowdown Initiation: if unable to restore and maintain RPV level greater than -150 Cues:
Key Parameter Response: LOWERING RPV PRESSURE Expected Annunciators: NONE Automatic Actions: 7 SRVs OPEN Objective Position EXPECTED OPERATOR RESPONSE 413.000 ATC
- Maintains RPV water level as directed
- If directed, opens Turbine Bypass Valves o If directed, prevents LPCS, LPCI, and HPCS not needed for core cooling.
- Arms and depresses both Div 1 ADS MANUAL INITIATION pushbuttons
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons
- Verifies 7 ADS valves open (CT) o May anticipate Blowdown and directs actions to rapidly depressurize via turbine bypass valves
US
- Verifies DW pressure at or above 1.77 psig.
428.000 o May direct NSO to prevent LPCS and LPCI not needed for cooling
- Verifies SP level greater than -18 ft.
- Directs NSO to initiate ADS.
Page 30 of 35
NRC 15-1-4 Revision 00 Event - 9
==
Description:==
RPV Blowdown Simulator Operator Actions none Simulator Operator Role Play none Floor Instructor Notes/OPEX/TRs none Terminus: when ADS has been initiated or blowdown anticipated and at the discretion of the Exam lead.
Page 31 of 35
NRC 15-1-4 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 3. LGP-3-1 POWER CHANGES 062
- 4. LGP-3-2 REACTOR SCRAM 072
- 5. LOP-VR-01 REACTOR BUILDING VENTILATION SYSTEM 048 STARTUP AND OPERATION
- 6. LOA-TG-101 UNIT 1 TURBINE GENERATOR 017
- 7. LOA-NR-101 NEUTRON MONITORING TROUBLE 019
- 8. LOR-1PM10J-B104 UNIT 1 STATION AIR COMPRESSOR AUTOMATIC TRIP 004
- 9. LOR-1H13-P603- LOCAL POWER RANGE MONITOR DOWNSCALE 002 A407
- 10. LOR-1H13-P603- OPRM / INOP TROUBLE 005 B507
- 11. LOR-1H13-P602- RRFCS TROUBLE 002 A507
- 12. LOR-1PM02J-B405 U1 TURBINE GENERATOR VIBRATION HIGH 001
- 13. LOR-1H13-P601- DRYWELL PRESSURE HIGH 003 A106
- 14. LOR-1H13-P601- DRYWELL PRESSURE HIGH 004 A107
- 16. LGA-RD-01 013 PUMPS
- 18. LOA-RM-101 UNIT 1 RCMS ABNORMAL SITUATIONS 018 STATION AIR COMPRESOR STARTUP AND 038
- 19. LOP-SA-02 SHUTDOWN Page 32 of 35
NRC 15-1-4 Revision 00 SMART SCENARIO ESG NRC 15-1-4 Revision: 00 Revision Date: 7/13/2016 Developed By: C. M. Betken Page 33 of 35
NRC 15-1-4 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 34 of 35
NRC 15-1-4 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Green Work Week: Non-Div Unit 1 power level Unit 2 power level
- 100 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- None
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- C CD/CB Pump
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- Perform LOP-VR-01 Section E.3.6 to
- Non-Div workweek swap from A to C VR Supply/Exhaust
- OLR is Green Fans
- Non-Div workweek
- OLR is Green Page 35 of 35
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 5 Op-Test No.: _2016301_______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Shutdown in progress at approximately 35% power. Currently at Step E.1.9, ready to downshift RR Pumps to Slow Speed per LOP-RR-08.
Turnover: Continue Shutdown and swap to the A VP Chiller and follow-up with RR downshift.
Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Swap VP Chiller Trains IAW LOP-VP-02 2
none R (ATC) Downshift RR Pumps IAW LOP-RR-08 3
k2h06jti C (ATC) RR Pump TRIPs to Zero Speed after Downshift 3
none T (SRO) RR Pump TRIPs to Zero Speed after Downshift 4
k1k21p1n C (BOP) Spurious LPCS Initiation 4
none T (SRO) Spurious LPCS Initiation 5
k9d782rr I (BOP) Primary Containment Pressure Controller Fails 6
vhtm60ad C (ATC) TDRFP Oil Leak 7
mrc041 M (ALL) RR LOCA 8 mrp018 C (ATC) B RPS Channel Fails to De-Energize (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-5 Rev. 0 07/30/2016 DEVELOPED BY: Colin Betken 8/16/2016 Instructor Date VALIDATED BY: J. Martin / Hawkins / Jozwiak / Clark 7/31/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Exam Author Date
NRC 15-1-5 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-5 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
The crew is directed at the beginning of their shift to continue the down power to shutdown by downshifting RR pumps IAW LGP-2-1 and LOP-RR-08.
- 3. Following the downshift the A RR Pump will Trip The crew will take action to prevent reverse flow of the pump.
- 4. Spurious LPCS Initiation.
An inadvertent initiation of LPCS. The crew responds, and when it is confirmed that no initiation signal is present, the crew shuts down LPCS. The US will declare LPCS inoperable.
- 5. Primary Containment Pressure Controller Fails.
Primary Containment Pressure Controller fails resulting in 1H13-P603-B501, Primary Containment Pressure HI/LO. The BOP takes manual control of the malfunctioning instrument and may perform a primary containment vent to lower drywell pressure per LOP-VQ-04.
- 6. RR Pump TRIPs to Zero Speed after Downshift.
A RR Pump will trip and the crew will take action per LOA-RR-101 to verify location and the power to flow map and enter applicable Tech specs.
8.6. TDRFP Oil Leak.
The crew performs an emergency shutdown per LOP-FW-05.
A Recirc Suction line breaks in the Drywell. This will drive the crew into the LGAs. The crew will take actions per LGA-001 and establish RPV Level and Pressure control. Per LGA-003 they will take actions in the Containment Pressure Leg, including Chamber Sprays and Drywell Sprays.
10.8. B RPS Channel Fails to De-Energize When the reactor is scrammed, the crew will discover that RPS Trip System B has failed to scram..
When it is recognized that the rods did not insert, the ATC will manually initiate Alternate Rod Insertion (ARI). Rods will go full in. The crew may enter LGA-010 but should exit it promptly after ARI is initiated. The scenario is terminated when the crew has RPV and Containment parameters stable and under control and with the concurrence of the lead examiner Critical Tasks
- 1. With a reactor scram required and insufficient control rod worth inserted to maintain the reactor shutdown under all conditions without boron; take action to insert control rods (ARI)Manually insert control rods by initiating ARI.
- 2. With suppression chamber pressure above 12 psig, containment flood level below 722 feet, and drywell parameters below the Drywell Spray Initiation Limit; trip all recirculation pumps and start Page 2 of 33
NRC 15-1-5 Revision 00 drywell sprays using RHR pumps not needed for adequate core coolingPlace the Residual Heat Removal (RHR) heat exchangers in service to establish containment cooling.
Page 3 of 33
NRC 15-1-5 Revision 00
- 3. TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 4 of 33
NRC 15-1-5 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall a 35% Ready to Downshift IC: 326 Passwrd: 3263
- 2. Place simulator in RUN.
- 3. Load and run the smart scenario: NRC 15-1-5.ssf
- 4. Place Protected Equipment rings and/or robust barriers on the following components: None
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the pre-scenario checklist. (TQ-LA-150-0308)
- 7. Perform the following panel manipulations:
8.7. Provide copiscopies of the following procedures:
- LGP-2-1 marked up to Step E.1.9
- LOP-RR-08 marked up to Step E.2
- LOP-RR-07 Sections B, C, and D marked up
- LOP-VP-02 Sections B, C, and D marked up 9.8. Verify the following:
- B VP Train Online
- A TDRFP Online
- Check CRD drive flow and pressure are normal
- Both VP Trains online
- 1PL78J - DW Light is off 10.9. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 5 of 33
NRC 15-1-5 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 5 Op-Test No.: _2016301__
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Shutdown in progress at approximately 35% power. Currently at Step E.1.9, ready to downshift RR Pumps to Slow Speed per LOP-RR-08.
Turnover: Continue Shutdown and swap to the A VP Chiller and follow-up with RR downshift.
Event Malf. No. Event Event No. Type* Description 1
none N (BOP) Swap VP Chiller Trains IAW LOP-VP-02 2
none R (ATC) Downshift RR Pumps IAW LOP-RR-08 3 C (ATC) k2h06jti RR Pump TRIPs to Zero Speed after Downshift 34 none T (SRO) RR Pump TRIPs to Zero Speed after Downshift 45 k1k21p1n C (BOP) Spurious LPCS Initiation 46 none T (SRO) Spurious LPCS Initiation 57 k9d782rr I (BOP) Primary Containment Pressure Controller Fails 68 vhtm60ad C (ATC) TDRFP Oil Leak 79 mrc041 M (ALL) RR LOCA 810 mrp018 C (ATC) B RPS Channel Fails to De-Energize (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 6 BOP Normal: 1 Malfunction(s) after EOP (1-2): 1 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 1 ATC I/C (4 / set): 3 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 5 EOP Contingencies (0-2): 0 SRO Tech Spec (2 per set): 2 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 1 Formatted: Indent: Left: 0", Hanging: 0.62" APPROXIMATE SCENARIO RUN TIME 90xx Minutes Page 6 of 33
NRC 15-1-5 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC Given Unit Supervisor authorization, transfer Reactor Recirc Pumps from Fast 22.004 to Slow Speed IAW station procedures.
Given Unit Supervisor authorization, perform CR actions to respond to a loss 22.015 of one or both RR pumps IAW station procedures.
Given Unit Supervisor authorization, Perform the in plant actions to respond to 77.046 a turbine driven reactor feed pump low hydraulic oil pressure alarm IAW station procedures.
Given Unit Supervisor authorization, respond to a primary containment 93.013 pressure high or low alarm IAW station procedures.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor, IAW station procedures.
RO - BOP/ASSIST Given Unit Supervisor authorization, transfer Reactor Recirc Pumps from Fast 22.004 to Slow Speed IAW station procedures.
Given Unit Supervisor authorization, perform Control Room actions to 63.006 shutdown LPCS following an auto initiation IAW station procedures.
Given Unit Supervisor authorization, Perform the in plant actions to respond to 77.046 a turbine driven reactor feed pump low hydraulic oil pressure alarm IAW station procedures.
Given Unit Supervisor authorization, respond to a primary containment 93.013 pressure high or low alarm IAW station procedures.
Given Unit Supervisor authorization, startup the Primary Containment Chilled 96.001 Water and Ventilation System IAW station procedures.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-01, RPV Control in progress, evaluate plant conditions and restore RPV water level to > -150 inches on WR or > -185 inches on FZ using 414.000 preferred injection systems and if needed alternate injection systems IAW station procedures.
Given entry in LGA-01, RPV Control, evaluate plant conditions and control 414.040 RPV water level using LPCI, IAW LGA-RH-103 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Page 7 of 33
NRC 15-1-5 Revision 00 SRO - UNIT SUPERVISOR Given Unit Supervisor authorization, transfer Reactor Recirc Pumps from Fast 22.004 to Slow Speed IAW station procedures.
Given Unit Supervisor authorization, perform CR actions to respond to a loss 22.015 of one or both RR pumps IAW station procedures.
Given Unit Supervisor authorization, perform Control Room actions to 63.006 shutdown LPCS following an auto initiation IAW station procedures.
Given Unit Supervisor authorization, Perform the in plant actions to respond to 77.046 a turbine driven reactor feed pump low hydraulic oil pressure alarm IAW station procedures.
Given Unit Supervisor authorization, respond to a primary containment 93.013 pressure high or low alarm IAW station procedures.
Given Unit Supervisor authorization, startup the Primary Containment Chilled 96.001 Water and Ventilation System IAW station procedures.
Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-01, RPV Control in progress, evaluate plant conditions and restore RPV water level to > -150 inches on WR or > -185 inches on FZ using 414.000 preferred injection systems and if needed alternate injection systems IAW station procedures.
Given entry in LGA-01, RPV Control, evaluate plant conditions and control 414.040 RPV water level using LPCI, IAW LGA-RH-103 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the 419.020 Suppression Pool, IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the Drywell, 419.030 IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given entry in LGA-10, Failure to Scram, evaluate plant conditions and 431.000 shutdown the reactor, IAW station procedures.
Page 8 of 33
NRC 15-1-5 Revision 00 Event-1
==
Description:==
Swap VP Chiller Trains IAW LOP-VP-02 Initiation: Following crew assuming shift, on direction of Lead Evaluator Cues:
Key Parameter Response: turnover Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE
- Per LOP-VP-02
- SHUTDOWN B VP Loop per Section E.16
- SHUTDOWN B VP Chill Water Pump
- Stop B VP Containment Ventilation Supply Fan
- o Secure Primary Containment Area Cooler Fans as desired Formatted: Indent: Left: 0.24", Hanging: 0.19", Bulleted +
Level: 1 + Aligned at: 0" + Indent at: 0.25", Tab stops: Not
- Monitor plant parameters and update the crew as required. at 0.43" ATC
- Perform peer checks 96.001 US
- Direct above actions of LOP-VP-02 Page 9 of 33
NRC 15-1-5 Revision 00 Event - 1
==
Description:==
Swap VP Chiller Trains IAW LOP-VP-02 Simulator Operator Actions When ordered by the control room to stop B VP From RNI drawing VP1 stop B VP Chiller Chiller Simulator Operator Role Play As the field operator IAW LOP-VP-02 step E.15.2 when ordered to secure B VP Chiller - wait 1 minute and STOP B Primary Containment Vent Chiller using above Sim Op actions and report when complete.
As the operator in the field, when ordered to perform to secure Area cooler fans for B VP Loop IAW LOP-VP-02 step E.16.2.2 wait 1 minute and report that they are secured.
Floor Instructor Notes/OPEX/TRs None Terminus: B VP Loop secured..
Page 10 of 33
NRC 15-1-5 Revision 00 Event-2
==
Description:==
Downshift RR Pumps IAW LOP-RR-08 Initiation: On direction of Lead Evaluator Cues:
Key Parameter Response: turnover Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE
- Monitor plant parameters and update the crew as required 22.004 BOP Formatted: Font: 10 pt
- Provide peer checks Per LOP-RR-08
- At the 1DS001 Operator Station RRFC Process Overview Screen, for A and B RR Loops, CHECK the Accumulated Time for Delta Temp Low
- CLOSE the MG Set Motor Feeder Breakers 1A and 1B
- Verify LFMG parameters are normal
- VERIFY FCL is <67.7% or value determined by QNE
- Turn Motor Control Breaker 3 Control Switches for both A and B Reactor Recirc Pumps to TRANSFER-MG position and observe the following:
- The 3A and 3B breakers open
- The MG Set Generator output Breaker 2A and 2B close (2A Breaker does not close)
- A and B pump speed stabilizes at 445 RPM
- A and B Pump differential pressure stabilizes at approximately 30 psid
- A and B MG set amps stabilize at approximately 60 amps.
- Monitor for core instabilities while continuing in this procedure.
22.004 ATC
- OPEN 1B33-F060A to 100%. Formatted: Font: 10 pt
- Verify the MANUAL light on A Recirc Loop Flow Controller M/A Station is ON
- Press the RAISE pushbutton and observe Flow and Valve Position Indication Formatted: Font: 10 pt
- LOCK UP 1B33-F060A per LOP-RR-07.
- At the 1DS001 operator station, RRFC HPU Status Loop A Screen
- Select Solenoid Valve Lockup
- Press Confirm Button
- OPEN 1B33-F060B to 100%
- Verify the MANUAL light on B Recirc Loop Flow Controller M/A Station is ON
- Press the RAISE pushbutton and observe Flow and Valve Position Formatted: Indent: Left: 0.24", Hanging: 0.19", Tab stops:
Indication 0.43", List tab + Not at 0.25"
- LOCK UP 1B33-F060B per LOP-RR-07. Formatted: Font: 10 pt
- At the 1DS001 operator station, RRFC HPU Status Loop B Screen
- Select Solenoid Valve Lockup
- Press Confirm Button
NRC 15-1-5 Revision 00
- Formatted: Font: 10 pt
- Direct above actions Formatted: Indent: Left: 0.25", No bullets or numbering 22.004 US
NRC 15-1-5 Revision 00 Event - 2
==
Description:==
Downshift RR Pumps IAW LOP-RR-08 Simulator Operator Actions When requested by the Reset CP trouble alarm crew Simulator Operator Role Play If asked, prestart & post start checks are complete sat.
If a CP trouble alarm comes in acknowledge the report and reset the CP trouble alarm.
Respond as required.
Floor Instructor Notes/OPEX/TRs Terminus: continued Page 13 of 33
NRC 15-1-5 Revision 00 Event-3
==
Description:==
A RR Pump TRIPs to Zero Speed after Downshift Initiation: Automatic on 1B RR Breaker taken to CLOSEOn the direction of the Lead Evaluator release Event 3 Formatted: Font: Bold Cues:
Key Parameter Response: Lowering Reactor Power, flow, and level Expected Annunciators:
1H13-P602-B405, 1B REACTOR RECIRC PUMP MOTOR AUTO TRIP OR LOW SPEED TRANSFER 1H13-P602-A405, 1A REACTOR RECIRC PUMP MOTOR AUTO TRIP OR LOW SPEED TRANSFER 1H13-P603-A309, FEEDWATER CONTROL REACTOR WATER LEVEL 7 1H13-P603-A408, OPRM TRIP ENABLE Automatic Actions: 1A RR Pump TRIP Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor plant parameters and update the crew as necessary Per LOA-RR-101
- Checks at least one Recirc Pump operating (Yes)
- 1H13-P603-A109, OPRM Hi Alarm - CLEAR
- PERFORM Subsection B.1, Thermal Hydraulic Instabilities, while continuing below.
- CHECK OPRM trip capability not maintained
- VERIFY both RR Loop M/A stations are in MANUAL
- CHECK operating Reactor Recirc Pump in HIGH SPEED (No)
Response not obtained.
22.015 ATC
- At 1DS001, initiate TADS by DEPRESSING TDR icon
- DECREASE FCV position to minimum for tripped Recirc Pump
- When less than 350 rpm, place breakers on tripped Recirc Pump in PTL
- o If unit in operation will continue for >24 hours Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- CLOSE 1B33-F067A, RR discharge to prevent reverse flow rotation
- o After 5 minutes, RE-OPEN valve closed above to re-establish flow in the Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent idle loop at: 0.25"
- INITIATE a Special Log to monitor Recirc Loop delta T
- INITIATE Tech Spec 3.4.1 Required Action C.1 requirements for Single 22.015 Loop Operation (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />)
US 201.011
- Notify IMD to perform LIS-NR-107, Unit 1 APRM/OPRM/RBM Flow Converter to Total Core Flow Adjustment Page 14 of 33
NRC 15-1-5 Revision 00 Event - 3
==
Description:==
A RR Pump TRIPs to Zero Speed after Downshift Simulator Operator Actions On the direction of the Lead Release Event 3 Formatted: Font: Not Bold Evaluatornone Simulator Operator Role Play Respond as IMD and QNE as needed.
Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs This Event is intended for the ATC Formatted: Font: Bold Inform base line data gathering and special log will be handled by Unit 2.
Terminus: After Unit Supervisor Tech Spec call.
Page 15 of 33
NRC 15-1-5 Revision 00 Event-4
==
Description:==
Spurious LPCS Initiation Initiation: On direction of Lead Evaluator, release Event 4 Cues:
Key Parameter Response: RPV Water Level and Pressure remain stable Expected Annunciators:
1H13-P601-C109, LPCS SYSTEM ACTUATED 1H13-P601-C208, LPCS PMP BKR CLOSED Automatic Actions: LPCS Initiation Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1H13-P601-C109
- VERIFY LPCS Pump running
- CHECK the following parameters to determine cause for automatic action:
- Drywell pressure (NO)
- Reactor Vessel Level (NO)
- Manual Initiation Pushbutton (NO) 63.006 BOP
- If initiation is NOT valid, REFER to LOP-LP-03, Shutdown of Low Pressure Core Spray after Automatic Initiation
- VERIFIES OPEN 1E21-F011, LPCS Min Flow Bypass valve o Places LPCS Pump in PTL OR o Places LPCS on Full Flow Test ATC
- Confirms RPV water level stable and assist BOP as directed o Discuss LPCS availability Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent Discuss contingency plans at: 0.25" 63.006 o US 201.011
- Refers to TS 3.3.5.1 Page 16 of 33
NRC 15-1-5 Revision 00 Event - 4
==
Description:==
Spurious LPCS Initiation Simulator Operator Actions With the concurrence of the Release Event 4 Lead Evaluator Simulator Operator Role Play If asked investigate the cause of the spurious LPCS start, wait 2 minutes as the operator in the field, and report, there are no abnormal indicates (locally and instrument rack) for the spurious LPCS initiation.
As the operator in the field, when ordered to check the status of Div 1 ECCS Room ventilation report, Ventilation is not running Floor Instructor Notes/OPEX/TRs none Terminus: LPCS Pump has been stopped or placed in Full Flow Test mode and the Unit Supervisor has made the Tech Spec call and at the discretion of the Lead Evaluator.
Page 17 of 33
NRC 15-1-5 Revision 00 Event-5
==
Description:==
Primary Containment Pressure Controller Fails Initiation: On direction of Lead Evaluator, release Event 5 Cues:
Key Parameter Response: Rising Drywell Pressure on 1PR-CM031 Expected Annunciators: 1H13-P603-B501, PRIMARY CONTAINMENT PRESSURE HI/LO
(~7 Minutes from initiation)
Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1H13-P603-B501
- VERIFIES Primary Containment Chill Water and Ventilation System is operating properly
- VERIFIES proper operation of Suppression Pool/Drywell Vent or Purge Systems
- VENT to maintain pressure <0.75psig (will not be allowed from Unit 1) 93.013 BOP
- Recognizes the failure of the automatic Drywell pressure controller 1PC-VQ019
- Notifies Unit Supervisor
- Takes manual control and stabilizes Containment Pressure Per LOR-1H13-P603-B501 93.013 ATC
- Checks Primary Containment Pressure greater than or equal to HI alarm setpoint or less than or equal to LO alarm setpoint
- Directs above actions
- Notifies IMD of failed controller 93.013 US *o If Drywell Pressure is >0.75 psig enter TS 3.6.1.4 Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25" o A.1 restore Drywell pressure within limits within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Page 18 of 33
NRC 15-1-5 Revision 00 Event - 5
==
Description:==
Primary Containment Pressure Controller Fails Simulator Operator Actions With the concurrence of the Release Event 5 Lead Evaluator Simulator Operator Role Play As the operator in the field, if dispatched to the N2 makeup control valve, wait 1 minute and report, I do not see anything obviously wrong with the valve and it is ______(use position from RNI VQ1 drawing).
If the crew begins to go down the path to vent the containment, inform them that Unit 2 will handle containment venting.
Floor Instructor Notes/OPEX/TRs noneIf the crew begins to go down the path to vent the containment, inform them that Unit 2 will handle containment venting.
Terminus: When Primary Containment Pressure is stable and in manual.
Page 19 of 33
NRC 15-1-5 Revision 00 Event-6
==
Description:==
TDRFP Oil Leak Initiation: On direction of Lead Evaluator, release Event 6 Cues:
Key Parameter Response: 1PI-FW050 & 51, Lube Oil Press meters lowering Expected Annunciators: LOR-1PM03J-A104, 1A/1B TDRFP BRG OIL PRESS LO (if pressure reaches 5 psig)
Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE 77.046 BOP
- Assist ATC Operator as directed o May notice TDRFP Vibrations Formatted: List Paragraph, Bulleted + Level: 1 + Aligned at:
0" + Indent at: 0.25" Per LOR-1PM03J-A104 Formatted: Font: (Default) Arial, 11 pt
- Confirm that 1A TDRFP has low bearing oil pressure Formatted: List Paragraph
- Verify reactor power is within the capacity of the MDRFP
- May enter LOA-TO-101 to monitor 1A TDRFP oil and bearing temps
- Dispatch an EO to inspect TDRFP bearing oil system for abnormalities o May shutdown affected TDRFP per LOP-FW-05
- Verify Minimum flow M/A station in AUTO
- Open Min Flow valve to at least 60% open
- Transfer RWLC M/A Station to MANUAL
- Slowly reduce 1A TDRFP flow until controller demand is at minimum 77.046 ATC and pump is not feeding the RPV
- Verify A TDRFP Minimum Flow opens as flow decreases
- Depress the Turning Gear Engage Reset pushbutton
- Depress the Turbine Trip pushbutton for at least 10 seconds
- Verify that the Stop and Control valves close
- Verify the Turbine trip light comes on and RPM start lowering
- Verify the Minimum Flow valve closes
- Open drain valves: 1B21-F426A, 428A, 425A, 427A, 432A, & 430A
- Closes steam inlet Stop Valves: 1B21-F423A and 422A
- Closes Discharge Stop Valve: 1FW010A
- When RPM reads 0, verify 1A TDRFP goes on the Turning Gear o May trip 1A TDRFP o Direct EO to isolate lube oil to TDRFP
- Direct actions per LOR-1PM03J-A104 77.046 US
- Verify reactor power is within the capacity of the MDRFP
- o May direct tripping the 1A TDRFP Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25" Page 20 of 33
NRC 15-1-5 Revision 00 Event - 6
==
Description:==
TDRFP Oil Leak Simulator Operator Actions Monitor 1A TDRFP Oil pressure. If the crew has not identified that pressure is lowering by 8 psig, perform the Role Play below.
With the concurrence of the Release Event 6 Lead Evaluator Simulator Operator Role Play At 8 psig oil pressure on 1A TDRFP or if dispatched to investigate as an EO:
Call the ATC at extension 2308.
Role-play: Report: that there is oil spraying everywhere, approximately 1 gpm collecting in the floor drain and it appears to be located on the Turbine side, Bearing Oil Header.I cant get close enough to tell where it is coming from.
Floor Instructor Notes/OPEX/TRs NoneThis event is intended for the ATC Formatted: Font: Bold Terminus: When 1A TDRFP has been secured Page 21 of 33
NRC 15-1-5 Revision 00 Event-7
==
Description:==
RR LOCA Initiation: On direction of Lead Evaluator, release Event 7 Cues:
Key Parameter Response: Drywell Pressure rises rapidly, B Scram Solenoid Group lights remain on, Control Rods do not insert Expected Annunciators:
1H13-P603-B501, PRI CNMT PRESSURE HI/LO (if not already in from previous event) 1PM13J-A302, RB NORTH/DW FLR SUMP TROUBLE 1PM13J-A204, DW COOLER COND FLOW RATE HI Automatic Actions: Reactor Scram (faulted) & ECCS initiations Objective Position EXPECTED OPERATOR RESPONSE 304.010
- Verifies the status of the Electric Plant 413.000 BOP
- Verifies HPCS operation 414.000
- Controls HPCS injection as necessary
- Performs Reactor Scram and LGP-3-2 Attachment E (hardcard):
- PLACE Reactor Mode Switch in SHUTDOWN
- CHECK Control Rods INSERTED and Power Decreasing (See Event 8)
ATC 413.000
- REPORT to the Unit Supervisor the status of RPV Level and Pressure
- VERIFY Main Turbine and Generator Trip
- STABILIZE Reactor Pressure <1020 psig
- REFER to LGP-3-2 o May direct a manual reactor scram prior to reaching 1.93 psig in the 304.010 Drywell 413.000 US o Close MSIVs due to loss of CW 414.000
- Enters and directs actions of LGA-001 LEVEL LEG 414.040
- Direct actions to start all available high pressure injection (continued)
Page 22 of 33
NRC 15-1-5 Revision 00 Event - 7
==
Description:==
RR LOCA Simulator Operator Actions With the concurrence of the Release Event 7 Lead Evaluator Simulator Operator Role Play As required.
Floor Instructor Notes/OPEX/TRs none Terminus: continued Page 23 of 33
NRC 15-1-5 Revision 00 Event contd
==
Description:==
RR LOCA Objective Position EXPECTED OPERATOR RESPONSE
- Monitors and reports containment parameters throughout
- When directed places Suppression Pool Cooling in service:
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, START first RHR Service Water Pump:
1A or 1B/C or D
- When indicated flow reaches 3000 gpm, START second RHR Service Water Pump.
- Startup RHR
- Start 1A/1B RHR Pump 414.040
- Establish RHR flow of 1500 to 7450 gpm:
421.000 BOP
- Throttle 1E12-F024A/B (Test Valve) OPEN
- Close 1E12-F048A/B (HX Bypass) (CT) o Place A/B HTX Bypass Throttle/Seal in switch to THROTTLE and THROTTLE CLOSED 1E12-F048A/B. o o Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/B
- When directed establish Suppression Chamber Spray:
- VERIFY 1A/1B RHR Pump is running
- OPEN 1E12-F027A/B
- When directed establish Drywell Spray: (CT)
- o THROTTLE 1E12-F024A/B CLOSED Formatted: Bulleted + Level: 1 + Aligned at: 0.25" + Tab after: 0.5" + Indent at: 0.5"
- OPEN:1E12-F016A/B and 1E12-F017A/B (CT)
- Maintain RPV level and pressure per LGA-001
- When Drywell Pressure exceeds 1.93 psig, enters and directs actions of LGA-003
- Before Suppression Chamber Pressure exceeds 12 psig
- Verifies Containment Flood level below 723 ft.
419.020
- Directs start of Suppression Chamber Sprays 419.030
- When Suppression Chamber Pressure exceeds 12 psig, direct initiation US of Drywell sprays (CT) 421.000
- Verifies Containment Flood level below 722 ft.
- Verifies Drywell Pressure and Temperature permit Drywell Sprays per Figure D
- Verifies both Recirc Pumps are tripped
- Direct initiation of Drywell sprays (CT)
- Initiate Suppression Pool Cooling Page 24 of 33
NRC 15-1-5 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 25 of 33
NRC 15-1-5 Revision 00 Event-8
==
Description:==
B RPS Channel Fails to De-Energize Initiation: continuedOn direction of Lead Evaluator Cues:
Key Parameter Response: Control Rods fail to insert; B RPS Scram solenoid group White Lights remain on Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE
- Monitors containment parameters throughout BOP o If directed, inhibits ADS and prevents ECCS injection Takes actions per LGP-3-2 Hard Card and LGA-010:
o Inform SRO no rod motion, power > 3%
- Verifies all control rods fully inserted and informs SRO
- Returns to LGP 3-2 actions (Event 7)
- Informs SRO the status of Control Rods and Reactor Power o Enters and directs LGA-010 o Verify ARI has been initiated (CT) Formatted: Indent: Hanging: 0.01" 431.000 US o May direct inhibiting ADS (if manual ARI has not yet been attempted) o When all control rods are inserted, returns to LGA-001 Page 26 of 33
NRC 15-1-5 Revision 00 Event - 8
==
Description:==
B RPS Channel Fails to De-Energize Simulator Operator Actions Release Remove B RPS Fuses With the concurrence of the Lead Evaluator when From remote functions remove SDV Vent/Drain Valve fuses requested to remove A RPS fuses (Attachment
- RP-isdvf18a removed 1B/1E)
- RP-isdvf18b removed LGA-RH-101 With the concurrence of the
- From the RNI display - JMP Screen - click on LGA-RH-101 (1 Lead Evaluator when LGA-jumper)
RH-101 is called for
- Select INSTALLED then INSERT LGA-MS-01 With the concurrence of the
- From the RNI display - JMP Screen - click on LGA-MS-01 Lead Evaluator when LGA- jumpers (5 jumpers)
MS-01 is called for
- Install only jumper #4
- Select INSTALLED then INSERT Simulator Operator Role Play none Floor Instructor Notes/OPEX/TRs none Terminus:
- After the RR Suction line leak has completed ramping in (10 minutes),
- And when RPV water level has been restored,
- And Primary Containment parameters are under control,
- And at the discretion of the Lead Examiner Page 27 of 33
NRC 15-1-5 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 3. LGA-010 FAILURE TO SCRAM 015
- 4. LGP-2-1 NORMAL UNIT SHUTDOWN 111
- 5. LGP-3-2 REACTOR SCRAM 072 STARTUP OPERATION AND SHUTDOWN OF
- 6. LOP-VP-02 PRIMARY CONTAINMENT CHILLED WATER AND 050 VENTILATION SHUTDOWN OF TURBINE DRIVEN REACTOR FEED 035
- 7. LOP-FW-05 PUMP CHANGING REACTOR RECIRC PUMP SPEED FROM 039
- 8. LOP-RR-08 FAST TO SLOW SPEED SHUTDOWN OF LOW PRESSURE CORE SPRAY
- 9. LOP-LP-03 014 SYSTEM AFTER AN AUTOMATIC INITIATION UNIT 1 A AND B RHR OPERATIONS IN THE LGAS 012
- 10. LGA-RH-103 AND SAMGS
- 11. LOR-1H13-P601-C109 LPCS SYSTEM ACTUATED 005
- 15. LOR-1H13-P603-A309 FEEDWATER CONTROL REACTOR WATER LEVEL 7 002
- 16. LOR-1H13-P603-A408 OPRM TRIP ENABLE 003
- 17. LOA-RR-101 REACTOR RECIRCULATION SYSTEM ABNORMAL 035 TURBINE DRIVEN REACTOR FEED PUMP BEARING 001
- 18. LOR-1PM03J-A104 OIL PRESSURE LOW
- 19. LOA-TG-101 UNIT 1 TURBINE OIL ABNORMAL 006 Page 28 of 33
NRC 15-1-5 Revision 00 SMART SCENARIO ESG NRC 15-1-5 Revision: 00 Revision Date: 7/5/16 Developed By: C. M. Betken Page 29 of 33
NRC 15-1-5 Revision 00 Page 30 of 33
NRC 15-1-5 Revision 00 Page 31 of 33
NRC 15-1-5 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 32 of 33
NRC 15-1-5 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Green Work Week: Non-Div Unit 1 power level Unit 2 power level
- 35 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- Shutdown in progress per LGP 2-1
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- 1. Both VP Loops are running, secure B
- Non-Div workweek VP Loop and Chiller (Station heat
- OLR is Green recovery is not in operation, C VP Chiller is valved-out, not in low heat operation)
- 2. Shutdown in progress currently at step E.1.9 of LGP 2-1, ready to downshift RR Pumps to Slow Speed per LOP-RR-08.
- Non-Div workweek
- OLR is Green Page 33 of 33
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 6 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Unit 1 is at 100% Reactor Power, Suppression Pool water level is currently at 1, Non-Divisional Work Week Turnover: Lower Suppression Pool water level to 0 IAW LOP-RH-16 to Main Condenser.
Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Lower Suppression Pool Water Level to 0 IAW LOP-RH-16 2 r1211 C (BOP) Gland Steam Packing Exhaust Blower Trip 3 mvp001 C (BOP) VP Chiller TRIP 4 r0591 CC (ATC) A RR Pump Loss of Cooling Water Flow r0593 5 none R (ATC) Single Loop Operation 5 none T (SRO) Single Loop Operation (TS) 6 k1n32e12 CR (ATC) Spurious MSIV Closure, Fuel Failure mnb103 7 mrp005 C (ALL) B RR Pump TRIP, Automatic SCRAM Fails 8 mnb106 M (ALL) Main Steam Line Leak in Main Steam Tunnel 9 none C (ALL) D Inboard and Outboard MSIVs Fail to Isolate 10 none M (ALL) 1VT79YA/B/C Fail OPEN, High Off-site Release, Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-6 Rev. 0 07/21/2016 DEVELOPED BY: Colin Betken 8/16/2016 Instructor Date VALIDATED BY: Draper / Messina / Gallick / Jozwiak 8/1/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/17/2016 Operations Manager Date APPROVED BY: Dan Moren 8/17/2016 Operations Training ManagerExam Author Date
NRC 15-1-6 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-6 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 1. Lower Suppression Pool Water Level to 0 IAW LOP-RH-16
- 2. Gland Steam Packing Exhaust Blower Trip Crew will start the standby blower.
- 4. A RR Pump Loss of Cooling Water Flow When the RR Cooling Water Flow annunciates a second time from the second R-point, the crew will trip A RR pump.
- 5. Single Loop Operation (TS)
The Crew will verify location on the P/F Map.
- 6. Spurious C MSIV Closure, Fuel Failure
- 7. The crew will respond by taking RWLC to Single element to prevent Reactor Level from going Formatted: Indent: Left: 0.25", No bullets or numbering high.
8.7. B RR Pump TRIP, Automatic SCRAM Fails The crew will manually scram the Reactor.
9.8. Main Steam Line Leak in Main Steam Tunnel.
The crew will enter LGA-002 and attempt to isolate the leak.
10.9. D Inboard and Outboard MSIVs Fail to Isolate 11.10. 1VT79YA/B/C Fail OPEN, High Off-site Release, Blowdown The crew will blowdown from LGA-009 Critical Tasks
- 1. With a primary system discharging outside primary and secondary containment, manually scram Formatted: Font: 11 pt the reactor if a reactor scram has not yet been initiated, enter LGA-001, and INITIATE emergency Formatted: List Paragraph depressurization before offsite release rate reaches the General Emergency level. Formatted: Font: 11 pt
- 2. With the Reactor at power andhen no Reactor Rrecirculation Ppumps are running, take action to Formatted: Font: 11 pt manually scram the Rreactor.
Formatted: Font: 11 pt Formatted: Font: 11 pt Formatted: Font: 11 pt Formatted: Font: 11 pt Page 2 of 31
NRC 15-1-6 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 3 of 31
NRC 15-1-6 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall IC 324 Password 2175
- 2. Place simulator in RUN.
- 3. Load and run Smart Scenario: NRC-15-1-6.ssf
- 4. Place Protected Equipment rings and/or robust barriers on the following components: None
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the following panel manipulations: none
- 7. Place the following Tags: none
- 8. Verify the following:
- A VP train is online,
- 1A SPE Blower B is online with
- 1A Blower A secured.
- 9. Have a copy of LOP-RH-16 with Sections B, C, and D already marked up.
- 10. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 4 of 31
NRC 15-1-6 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 6 Op-Test No.: ___2016301_____
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Unit 1 is at 100% Reactor Power, Suppression Pool water level is currently at 1, Non-Divisional Work Week Turnover: Lower Suppression Pool water level to 0 IAW LOP-RH-16 to Main Condenser.
Event Malf. No. Event Event No. Type* Description 1 none N (BOP) Lower Suppression Pool Water Level to 0 IAW LOP-RH-16 2 r1211 C (BOP) Gland Steam Packing Exhaust Blower Trip 3 mvp001 C (BOP) VP Chiller TRIP 4 r0591 CR (ATC) A RR Pump Loss of Cooling Water Flow r0593 5 none R (ATC) Single Loop Operation 5 none T (SRO) Single Loop Operation (TS) 6 k1n32e12 C (ATC) Spurious MSIV Closure, Fuel Failure mnb103 7 mrp005 C B RR Pump TRIP, Automatic SCRAM Fails (ATCALL
)
8 mnb106 M (ALL) Main Steam Line Leak in Main Steam Tunnel 9 none C (ALL) D Inboard and Outboard MSIVs Fail to Isolate 10 none M (ALL) 1VT79YA/B/C Fail OPEN, High Off-site Release, Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes: Formatted: Indent: Left: 0", First line: 0" Total Malfunctions (5-8): 8 BOP Normal: 1 Malfunction(s) after EOP (1-2): 2 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 3 SRO-I I/C (4 / set inc 2 as ATC): 5 EOP Contingencies (0-2): 1 SRO Tech Spec (2 per set): 1 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 2 APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 5 of 31
NRC 15-1-6 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC Perform the Control Room actions to respond to a loss of one or both RR 22.015 pumps.
Perform the Control Room actions to respond to a high reactor water level 31.007 (levels 7 & 8) 91.001 Determine PCIS status.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Evaluate plant conditions and rapidly depressurize the RPV using SRVs via 428.000 the ADS system, RO - BOP/ASSIST 52.035 Respond to a High Rad Release rate 70.043 Perform Control Room actions to evaluate Main Steam Tunnel atmosphere Perform Control Room actions to raise and lower Suppression Pool level with 64.033 the RHR System, Given Unit Supervisor authorization, perform Control Room actions to startup 71.033 and shutdown Gland Seal Steam System IAW station procedures.
91.001 Determine PCIS status.
96.001 Startup the Primary Containment Chilled Water and Ventilation System Given LGA-02, Secondary Containment Control, in progress, evaluate plant 416.000 conditions and control water level in secondary containment by operation of sumps IAW station procedures Given LGA-02, Secondary Containment Control, in progress, evaluate plant 417.000 conditions and control temperature in secondary containment by operation of ventilation, IAW station procedures.
Given LGA-02, Secondary Containment Control, in progress with a system 418.000 discharging into an area, evaluate plant conditions and terminate the release to the Secondary Containment per LGA-002.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Evaluate plant conditions and rapidly depressurize the RPV using SRVs via 428.000 the ADS system, Page 6 of 31
NRC 15-1-6 Revision 00 SRO - UNIT SUPERVISOR Perform the Control Room actions to respond to a loss of one or both RR 22.015 pumps.
Perform the Control Room actions to respond to a high reactor water level 31.007 (levels 7 & 8) 52.035 Respond to a High Rad Release rate Perform Control Room actions to raise and lower Suppression Pool level with 64.033 the RHR System, 70.043 Perform Control Room actions to evaluate Main Steam Tunnel atmosphere Given Unit Supervisor authorization, perform Control Room actions to startup 71.033 and shutdown Gland Seal Steam System IAW station procedures.
91.001 Determine PCIS status.
96.001 Startup the Primary Containment Chilled Water and Ventilation System Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-02, Secondary Containment Control, in progress, evaluate plant 416.000 conditions and control water level in secondary containment by operation of sumps IAW station procedures Given LGA-02, Secondary Containment Control, in progress, evaluate plant 417.000 conditions and control temperature in secondary containment by operation of ventilation, IAW station procedures.
Given LGA-02, Secondary Containment Control, in progress with a system 418.000 discharging into an area, evaluate plant conditions and terminate the release to the Secondary Containment per LGA-002.
Given LGA-03, Primary Containment Control, in progress, evaluate plant 421.000 conditions and control and maintain suppression pool temperature less than HCTL IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Evaluate plant conditions and rapidly depressurize the RPV using SRVs via 428.000 the ADS system, Page 7 of 31
NRC 15-1-6 Revision 00 Event-1
==
Description:==
Lower Suppression Pool Water Level to 0 IAW LOP-RH-16 Initiation: Following crew assuming shift, on direction of Lead Evaluator Objective Position EXPECTED OPERATOR RESPONSE Per LOP-RH-16
- VERIFY Open 1E12-F004A, 1A RHR Pump Suction Vlv from Suppression Chamber
- START RHR Pump 1E12-C002A
- THROTTLE OPEN 1E-12-F024A RHR Test to Sp Vlv, to maintain flow 5000 to 7000 gpm as indicated on RHR Pump Flow Indicator 1E12-R603A
- OPEN 1E12 -F049A RHR Blowdown Upstream Isolation
- VERIFY 0 DG Cooling Water Pump Starts
- Align reject to Main Condenser
- OPEN 1G33-F345, 1A RHR Reject To Main Condenser Vlv.
64.033 BOP
- THROTTLE OPEN 1E12-F040A, 1A RHR Hx Blowdown Dwnst Isol.
- Monitor Suppression Pool Water Level
- When Suppression Pool is at desired level secure RHR lineup
- VERIFY CLOSED 1E12-F040A, 1A RHR Hx Blowdown Dwnst Isol.
- VERIFY CLOSED 1E12-F049A, 1A RHR Hx Blowdown Upstrm Isol. and PLACE the handswitch for 1E12-F049A in PTL.
- VERIFY CLOSED 1G33-F345; 1A RHR Reject To Main Condenser Vlv.
- CLOSE 1E12-F024A RHR test to SP Vlv
- STOP RHR Pump 1E12-C002A
- o When room temperature drops below 104 F VERFIY locally 1A RHR Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent Pump Room Ventilation Supply Fan STOPS at: 0.25"
- Monitor plant parameters and update the crew as required
- Direct above actions 64.033 US
- Set Suppression Pool Level as Critical Parameter Page 8 of 31
NRC 15-1-6 Revision 00 Event - 1
==
Description:==
Lower Suppression Pool Water Level to 0 IAW LOP-RH-16 Simulator Operator Actions none Simulator Operator Role Play As, the operator in the field, when asked if the Pump Room Supply Fan is in auto IAW LOP-RH-16 step E.1.1, immediately report back that, the Pump Room Supply Fan is in Auto.
If asked Prestart checks are sat for the 1A RHR Pump and Div 1 DG Cooling Water Pump.
As the operator in the field, when ordered to verify Pump Room Ventilation is secured, wait 1 minute and call back and inform the crew, Pump Room Ventilation is secured.
If asked if you required the 0 DG Cooling Water Pump, report that you do not require the 0 DG Cooling Water Pump.
Floor Instructor Notes/OPEX/TRs None Terminus: Suppression Pool level is 0 and RHR lineup is secured.
Page 9 of 31
NRC 15-1-6 Revision 00 Event-2
==
Description:==
Steam Packing Exhauster blower trip Initiation: On direction of Lead Evaluator, release Event 2 Cues:
Key Parameter Response: 1AB SPE Blower B auto trip indications Expected Annunciators:
1PM02J-A305, GLAND SEAL STEAM CNDSR VAC LO 1PM02J-A405, GLAND SEAL STEAM /PACKING EXH BLOWER AUTO TRIP Automatic Actions: None Objective Position EXPECTED OPERATOR RESPONSE ATC
- Monitors control room panels and notifies the SRO of any unusual or unexpected conditions.
- Responds to annunciator and inform the Unit Supervisor Per LOR-1PM02J-A305
- CHECK Gland Seal Steam Condenser Vacuum is equal to or less than 5" H2O Vacuum.
- DISPATCH operator to EL. 754' in Turbine Building to INSPECT Gland Seal Steam Blower for proper operation per procedure LOP-GS-01, Gland Seal Steam System Startup.
- DISPATCH operator to EL. 754' in Turbine Building to VERIFY proper Condensate Flow thru Gland Seal Steam Condenser per LOP-GS-01, Gland Seal Steam System Startup.
- STARTUP idle Gland Seal Steam Packing Exhauster Blower per 71.033 BOP LOP-GS-05, Changeover of Gland Seal Steam Packing Exhauster Blowers
- Start the 1A SPE A Blower
- THROTTLE OPEN the suction valve for the A Blower until the SPE Steam Inlet Header vacuum increases to 12" W.C.
- THROTTLE SHUT the suction valve for the B Blower
- Repeat above steps as necessary until the suction valve for the B Blower is fully closed
71.033 US
- Directs actions of LOR-1PM02J-A305 or LOR-1PM02J-A405 Page 10 of 31
NRC 15-1-6 Revision 00 Event - 2
==
Description:==
Steam Packing Exhauster blower trip Simulator Operator Actions With the concurrence of the Release Event 2 Lead Evaluator Simulator Operator Role Play When sent to investigate the blower as the operator in the field, wait 2 minutes and report, The motor is hot to the touch for 1AB SPE Blower B and the breaker tripped on Overcurrent.
When asked if condensate flow is normal, wait 1 minute and report: Condensate flow through the Gland Seal condenser is normal.
Floor Instructor Notes/OPEX/TRs none Terminus: A Standby SPE Blower is put into service and SPE vacuum is 8" -12" W.C.
Page 11 of 31
NRC 15-1-6 Revision 00 Event-3
==
Description:==
VP Chiller TRIP Initiation: On direction of Lead Evaluator, release Event 3 Cues:
Key Parameter Response:
Expected Annunciators: 1PM06J-A501, PRO CNMT 1A WTR CHLR CONT PNL TROUBLE Automatic Actions:1A VP Chiller TRIP Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM06J-A501
- START 1B Primary Containment Chill Water, Compressor and Vent System per LOP-VP-02 (hardcard)
- Ventilation
- VERIFY 1VP055A/B, PCCW Holdup Tank Bypass Valves closed
- Align Cooler Isolation Valves
- START B Primary Containment Chill Water Pump, 1VP01PB
- START B Primary Containment Ventilation Supply Fan, 1VP02CB by placing control switch to START 96.001 BOP
- Chiller
- AtAt Control Room Panel 1PM06J, CLOSE 1B Primary Containment Vent Chiller, 1VP01CB Feed Breaker
- Direct EO to pPerform prestart checks
- DISPATCH operator to determine cause of trip per local panel annunciator procedures at Chiller Unit 1VP01CA
- Monitor plant parameters and update the crew as required.
- Direct above actions 96.001 US
- Set critical parameter of Drywell Pressure Page 12 of 31
NRC 15-1-6 Revision 00 Event - 3
==
Description:==
VP Chiller TRIP Simulator Operator Actions With the concurrence of the Release Event 3 Lead Evaluator Simulator Operator Role Play If asked, as the operator in the field when ordered to place five air coolers on service wait 3 minutes and report B, C, D, E, and F are running in FAST.
If asked, as the operator in the field, when ordered to perform post start checks of B VP Fan per LOP-VP-02 Section E.10, wait 3 minutes and report completed.
If asked, as the operator in the field, when ordered to perform prestart checks of B VP Chiller per LOP-VP-02 Section E.11, wait 3 minutes and report completed.
When sent to investigate the trip of A VP Chiller wait 1 minute and report, A VP Chiller Tripped on Overload.
Floor Instructor Notes/OPEX/TRs Drywell Pressure will slowly rise while starting the standby VP Chiller.
Terminus: When B VP Train Is online Page 13 of 31
NRC 15-1-6 Revision 00 Event-4
==
Description:==
A RR Pump Loss of Cooling Water Flow Initiation: On direction of Lead Evaluator, release Event 4 Cues:
Key Parameter Response: none Expected Annunciators: 1H13-P602-A304, RR 1A MOTOR COOLING WATER FLOW LOW OR MOTOR WINDING COOLER LEAKAGE Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1H13-P602-A304
- The pump should be TRIPPED immediately if any of the following are met:
o Leakage into the winding occur:
o Both R points are received (YES) o Unexplained winding temp drop (NO) o Winding temp limits are reached o 248F continuous (NO) 22.015 ATC Formatted: Font: 10 pt o 266F intermittent (NO) o Seal temperatures >200F (NO) o Bearing limits are reached (NO) o Bearing Cooler outlet temperature >210F (NO)
- REFER to LOA-RR-101 Formatted: Font: 10 pt
- MONITOR trends or parameters until problem has been fully evaluated Per LOA-RR-101
- Check at least one Reactor Recirc Pump running
- PERFORM section B.1, Thermal Hydraulic Instabilities
- CHECK OPRM trip capability not maintained
- CHECK Reactor Power and core flow - OUTSIDE Regions 1 and 2 CHECK
- Monitor APRM trends and verify gains are in tolerance
- 1H13-P603-A109, OPRM Hi Alarm - CLEAR
- CHECK operating Recirc loop in HIGH SPEED Formatted: Font: 10 pt
- INITIATE TADS at 1DS001
- INITIATE Tech Spec actions
- At 1A RR FCV M/A Station depress lower pushbutton to DECREASE FCV Formatted: Font: 10 pt position to minimum for tripped Recirc Pump
- When less than 350 RPM place all breakers for tripped pump in PTL Formatted: Indent: Left: 0", Hanging: 0.24", Bulleted +
o If Reactor Recirc Pump is expected to be shut down and the unit will remain Level: 1 + Aligned at: 0.5" + Indent at: 0.75" single loop >24 hours CLOSE 1B33-F067A, RR pump discharge o After 5 minutes re-open valve closed previous step Formatted: Font: (Default) Arial BOP
- Monitor plant conditions and update the crew as required Formatted: List Paragraph, Indent: Left: 0", Hanging:
0.24", Bulleted + Level: 1 + Aligned at: 0.5" + Indent at:
- Direct above actions 0.75" 22.015 US
- Refer to Tech Spec 3.4.1 Formatted: Font: 10 pt 201.011
- Contact QNE Formatted: Font: 10 pt Page 14 of 31
NRC 15-1-6 Revision 00 Event - 4
==
Description:==
A RR Pump Loss of Cooling Water Flow Simulator Operator Actions With the concurrence of the Release Event 4 Lead Evaluator Simulator Operator Role Play Respond as QNE.
Floor Instructor Notes/OPEX/TRs The crew should take action to TRIP the RR Pump upon the second R-point.
Terminus: 1A Reactor Recirc Pump TRIPPEDcontinued Page 15 of 31
NRC 15-1-6 Revision 00 Event-5
==
Description:==
Single Loop Operation (TS)
Initiation: continued Cues:
Key Parameter Response: Reactor Power and Core Flow Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOA-RR-101
- INSERT control rods to reduce Rod Line to <65.7% Formatted: Indent: Left: -0.01", Bulleted + Level: 1 +
Aligned at: 0.49" + Indent at: 0.74" BOP
- Monitor plant conditions and update the crew as required
- Contact QNE to evaluate core performance
- Enter Tech Spec 3.4.1 required action C.1 for Single Loop Operation in 22.015 US 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 201.011
- Contact IMD
- Set Scram Criteria Page 16 of 31
NRC 15-1-6 Revision 00 Event - 5
==
Description:==
Single Loop Operation (TS)
Simulator Operator Actions none Simulator Operator Role Play Respond as IMD and QNE.
Floor Instructor Notes/OPEX/TRs none Terminus: Following Tech Spec call, sufficient Control Rods inserted for Reactivity manipulation and at the discretion of the Lead Evaluator. to Shift Manager.
Page 17 of 31
NRC 15-1-6 Revision 00 Event-6
==
Description:==
Spurious MSIV Closure, Fuel Failure Initiation: On direction of Lead Evaluator, release Event 6 Cues:
Key Parameter Response: 1C OUTBOARD MSIV CLOSES AND RPV LEVEL Expected Annunciators: 1H13-P603-B202, 1C/1D MISV INBD/OTBD NOT FULL OPEN Automatic Actions: 1C OUTBOARD MSIV CLOSES Objective Position EXPECTED OPERATOR RESPONSE
- Monitor plant parameters and update the crew as required Per LOA-FW-101
- Response not obtained
- SELECT Single Element at the RWLC Level Setpoint Station Per LOA-MS-101
- If a single MSIV is closed enter LOA-FW-101 to transfer RWLC to Single Element
- Direct above actions 31.007 US
- Contact QNE Page 18 of 31
NRC 15-1-6 Revision 00 Event - 6
==
Description:==
Spurious MSIV Closure, Fuel Failure Simulator Operator Actions With the concurrence of the Release Event 6 Lead Evaluator Simulator Operator Role Play Respond as QNE Floor Instructor Notes/OPEX/TRs If the crew does not place Reactor Water Level Control in Single Element expeditiously, the Reactor will Turbine will trip on Hi Level ( Level 8: +55)
Terminus: When RWLCS is in Single Element and Reactor Level is stable at ~36 inches.
Page 19 of 31
NRC 15-1-6 Revision 00 Event-7
==
Description:==
B RR Pump TRIP, Automatic SCRAM Fails Initiation: On direction of Lead Evaluator, release Event 7 Cues:
Key Parameter Response: Reactor level, flow and power lower Expected Annunciators: Multiple Automatic Actions: none (Auto Scram Fails)
Objective Position EXPECTED OPERATOR RESPONSE BOP
- Monitor Plant conditions and update the crew as required
- Responds to the reactor scram per LGP-3-2 Attachment E (hardcard)
- PLACE Reactor Mode Switch in SHUTDOWN
- CHECK Control Rods INSERTED and Power Decreasing 413.000
- REPORT to the Unit Supervisor the status of RPV Level and Pressure
- VERIFY Main Turbine and Generator Trip
- STABILIZE Reactor Pressure <1020 psig
- REFER to LGP-3-2 304.010
US 413.000
- Direct action of LGA-001 Page 20 of 31
NRC 15-1-6 Revision 00 Event - 7
==
Description:==
B RR Pump TRIP, Automatic SCRAM Fails Simulator Operator Actions With the concurrence of the Release Event 7 Lead Evaluator Simulator Operator Role Play Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs Rods will fully insert when scram pushbuttons are armed and depressed.
Terminus: continued Page 21 of 31
NRC 15-1-6 Revision 00 Event-8
==
Description:==
Main Steam Line Leak in Main Steam Tunnel Initiation: Automatically initiated when the Mode Switch is taken to shutdown Cues:
Key Parameter Response: All MSIVs close (except D)
Expected Annunciators: 1H13-P601-B209, COMMON AREA MONITORS RADIATION HIGH Automatic Actions: Group 1 Isolation Objective Position EXPECTED OPERATOR RESPONSE 70.043 Per LGA-002 416.000
- OPERATE Area Coolers and VR if possible BOP 417.000
- Take LGA-002 data Per LOA-AR-101 BOP
- EVACUATE the power block ATC
- Monitor plant parameters and update the crew as required.
- Direct actions of LGA-002 70.043 US
- Call out for LGA-002 data Page 22 of 31
NRC 15-1-6 Revision 00 Event - 8
==
Description:==
Main Steam Line Leak in Main Steam Tunnel Simulator Operator Actions Automatically initiated when the Mode Switch is taken to shutdown Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: continued.
Page 23 of 31
NRC 15-1-6 Revision 00 Event-9
==
Description:==
D Inboard and Outboard MSIVs Fail to Isolate Initiation: Automatic Cues:
Key Parameter Response: D MSIV Open Indication Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LGA-002
- If any area Temperature or Radiation is above Max Normal or if a sump 91.001 is overflowing, then:
416.000 BOP
- ISOLATE discharges into the area except for those needed to fight 417.000 fires or needed by other LGAs 418.000
- MONITOR release rates for LGA-009 entry conditions
- Any area temperature, radiation, or water level reached max Formatted: Indent: Left: 0.5", No bullets or numbering safe value then:
91.001 ATC
- Maintain Reactor level and pressure per LGA-001 91.001 416.000 US
- Direct above actions 417.000 418.000 Page 24 of 31
NRC 15-1-6 Revision 00 Event - 9
==
Description:==
D Inboard and Outboard MSIVs Fail to Isolate Simulator Operator Actions none Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: continued.
Page 25 of 31
NRC 15-1-6 Revision 00 Event - 10
==
Description:==
1VT79YA/B/C Fail OPEN, High Off-site Release, Blowdown Initiation: On direction of Lead Evaluator Cues:
Key Parameter Response: STACK WRGM EFF RAD LEVELS Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LGA-009
- Operate Ventilation that may be releasing radioactivity
- Isolate all primary system discharges outside primary and secondary containment, except systems needed for LGAs
- If Primary system discharging outside primary and secondary containments 52.035 BOP AND discharges cannot be isolates or isolation attempts fail then:
- ENTER LGA-001
- BLOWDOWN per LGA-004 Per LGA-004
- Arms and depresses both Div 1 ADS MANUAL INITIATION pushbuttons
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons
- Verifies 7 ADS valves open Per LGA-003
- When directed, starts all available Pool Cooling per LGA-RH-103
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, START first RHR Service Water Pump:
- 1A or 1B/C or D
- When indicated flow reaches 3000 gpm, START second RHR Service Water 421.000 Pump BOP 421.010
- Startup RHR
- Start 1A/1B RHR Pump
- Establish RHR flow of 1500 to 7450 gpm:
- Throttle 1E12-F024A/B (Test Valve) OPEN
- Close 1E12-F048A/B (HX Bypass)
- Place A/B HTX Bypass Throttle/Seal in switch to THROTTLE and THROTTLE CLOSED 1E12-F048A/B or
- Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/B 428.000 ATC
- Monitor plant conditions and update the crew as required 52.035 428.000
- VERIFY Suppression Pool level US 421.000
- Direct actions of LGA-009 and LGA-004(CT) 421.010 Page 26 of 31
NRC 15-1-6 Revision 00 Event - 10
==
Description:==
1VT79YA/B/C Fail OPEN, High Off-site Release, Blowdown Simulator Operator Actions none Simulator Operator Role Play Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs The crew may anticipate a blowdown on a previous event.
Terminus: When an RPV blowdown has been performed and at the discretion of the Lead Examiner.
Page 27 of 31
NRC 15-1-6 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-002 SECONDARY CONTAINMENT CONTROL 009
- 3. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 4. LGA-004 RPV BLOWDOWN 009
- 5. LGA-009 RADIOACTIVITY RELEASE CONTROL 007
- 6. LGA-010 FAILURE TO SCRAM 015
- 7. LGP-3-1 POWER CHANGES 062
- 9. LOP-RR-13 014 DATA GATHERING AND OPERABILITY VERIFICATION RAISING AND LOWERING OF SUPPRESSION POOL
- 10. LOP-RH-16 025 LEVEL REACTOR LEVEL FEEDWATER PUMP CONTROL
- 11. LOA-FW-101 011 TROUBLE
- 12. LOA-MS-101 UNIT 1 MAIN STEAM SYSTEM ABNORMAL 013
- 13. LOA-RR-101 REACTOR RECIRCULATION SYSTEM ABNORMAL 035
- 14. LOR-1H13-P603- 1C/1D MISV INBD/OTBD NOT FULL OPEN 003 B202
- 16. LOR-1PM02J-A405 001 TRIP
- 17. LOR-1H13-P601-MAIN STM OTBD ISOL VLV ACCUMULATOR PRESS LO 003 E101
- 20. LGA-RH-103 Unit 1 A and B RHR Operations in the LGAs and SAMGs 012 ALTERNATE VESSEL INJECTION USING SHUTDOWN
- 21. LGA-RH-101 004 COOLING RETURN STARTUP, OPERATION AND SHUTDOWN OF
- 22. LOP-VP-02 PRIMARY CONTAINMENT CHILLED WATER 050 VENTILATION SYSTEM CHANGEOVER OF GLAND SEAL STEAM PACKING
- 23. LOP-GS-05 003 EXHAUSTER BLOWERS Page 28 of 31
NRC 15-1-6 Revision 00 COMPUTER AIDED EXERCISE PROGRAM (CAEP)
ESG NRC 15-1-6 Revision: 00 Revision Date: 7/6/16 Developed By: C. M. Betken Page 29 of 31
NRC 15-1-6 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 30 of 31
NRC 15-1-6 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Green Work Week: Non-Div Unit 1 power level Unit 2 power level
- 100 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- None
- None Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- None
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- Lower Suppression Pool water level to
- OLR is Green Main Condenser.
- Non-Div workweek
- OLR is Green Page 31 of 31
Facility NRC EXAM Scenario __
Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 7 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Reactor power at approximately 71%, Startup is in progress IAW LGP-1-1, Suppression Pool Cooling Online, ACB 1522 OOS.
Turnover: Continue power ascension per LGP-3-1 and QNE direction, Secure Suppression Pool Cooling IAW LOP-RH-13.
Event Malf. No. Event Event No. Type* Description 1 none R (ATC) Continue Power Ascension Using RR FCV 2 none N (BOP) Secure Suppression Pool Cooling IAW LOP-RH-13 3 mrd280 C (ATC) CRD Pump TRIP 4 k5e17prr C (BOP) Hydrogen Cooling TCV Fails CLOSED 5 mrd079 I (ATC) Control Rod Drifts In 6 none T (SRO) INOPERABLE Control Rod 7 none T (SRO) Loss of 135X-2 8 mnb104 M (ALL) MSL Break Inside Primary Containment 9 mca015 C (ALL) Containment Bypass Path 10 none M (ALL) RPV Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification
LaSalle County Station ILT DYNAMIC SIMULATOR SCENARIO GUIDE ESG NRC 15-1-7 Rev. 0 07/29/2016 DEVELOPED BY: Colin Betken 8/16/2016 Instructor Date VALIDATED BY: Martin / Hawkins / Jozwiak / Clark 7/31/2016 SME/Instructor Date REVIEWED BY: Mark Smith 8/16/2016 Operations Manager Date APPROVED BY: Dan Moren 8/16/2016 Exam Author Date
NRC 15-1-7 Revision 00 Facility: LaSalle County Station Scenario No.: NRC 15-1-7 PURPOSE Examine the ILT candidates ability to operate the plant in normal, abnormal, and emergency conditions.
SUMMARY
OF EVENTS
- 2. Secure Suppression Pool Cooling IAW LOP-RH-13
- 4. Hydrogen Cooling TCV Fails CLOSED Hydrogen temperature will rise due the failed TCV forcing the crew to take manual control from the Control Room to maintain temperatures in band.
- 5. Control Rod Drifts In The crew will fully insert the drifting control rod.
- 6. INOPERABLE Control Rod The Unit Supervisor will make Tech Spec call for INOP control rod.
- 7. Loss of 135X-2-B-4 A loss of 135X-2-B-4 results in a loss of 0 diesel generator ventilation.
- 8. MSL Break Inside Primary Containment A steam leak from a Main Steam Line inside primary containment will develop coincident with a primary containment suppression failure.
- 9. Containment Bypass Path The drywell and suppression chamber pressures rises due to a containment bypass failure.
Critical Tasks
- 1. With primary containment pressure above 1.93 psig, containment flood level below 723 feet, and Formatted: List Paragraph pumps not needed for core cooling available; start suppression chamber spray. Formatted: Font: (Default) Arial, 11 pt
- 2. With suppression chamber pressure above 12 psig, containment flood level below 722 feet, and drywell parameters below the Drywell Spray Initiation Limit; trip all recirculation pumps and start drywell sprays using RHR pumps not needed for adequate core cooling.
- 1. With primary containment pressure above 1.93 psig, containment flood level below 723 feet, and pumps not needed for core cooling available; start suppression chamber spray.
2.3. When suppression chamber pressure cannot be maintained below the Pressure Suppression Pressure (PSP), INITIATE emergency depressurization. (or anticipates Blowdown and depressurizes rapidly via the main turbine bypass valves.)
Page 2 of 33
NRC 15-1-7 Revision 00 TRAINING REQUESTS (if applicable)
- 1. None OPEX (if applicable)
- 2. None Operator Fundamentals
- 1. Monitoring plant indications and conditions closely
- 2. Controlling plant evolutions precisely
- 3. Operating the plant with a conservative bias
- 4. Working effectively as a team
- 5. Having a solid understanding of plant design, engineering principles, and sciences SOER 10-2
- 1. Oversight ensures proper focus
- 2. Equipment restoration risk evaluation
- 3. Preparation for high risk evolution
- 4. Control Room resources adequate for EOP response
- 5. Sufficient engagement of others in decision making Record of Revisions (Summary)
Rev. 0 Developed new for the ILT 15-1 NRC Exam Page 3 of 33
NRC 15-1-7 Revision 00 INITIAL SIMULATOR SETUP/REQUIRED DOCUMENTATION
- 1. Recall IC. 325 Password 3253
- 2. Place simulator in RUN.
- 3. Load and run Smart Scenario: NRC 15-1-7.ssf
- 4. Place Protected Equipment rings and/or robust barriers on the following components:
- ACB 1521
- 5. Update the Tech Spec Timeclock Sheet as follows:
TS/TRM/ODCM System/ Required REQUIRED ACTION Completion Expiration Component Action Description Time Date/Time N/A N/A N/A N/A N/A N/A
- 6. Perform the following panel manipulations:
- 7. Place the following Tags:
- OOS - ACB 1522
- 8. Verify the following:
- Suppression Pool Cooling in Service
- A CRD running
- Drive Rod Trip Circuit Bypass is in active
- 9. Have a copy of the following procedures:
- LGP 1-1 marked up to step E.8.32
- LGP 3-1 marked up to step E.1.3 (Recirc Flow) with step E.1.4 complete
- LOP-RH-05 Sections B, C, and D complete
- LOP-RH-13 Sections B, C, and D complete
- 10. Perform the pre-scenario checklist. (TQ-LA-150-0308)
Page 4 of 33
NRC 15-1-7 Revision 00 Appendix D Scenario Outline Form ES-D-1 Facility: LaSalle Scenario No.: NRC Scenario 7 Op-Test No.: __2016301______
Examiners: ____________________________ Operators: _____________________________
Initial Conditions: Reactor power at approximately 71%, Startup is in progress IAW LGP-1-1, Suppression Pool Cooling Online, ACB 1522 OOS.
Turnover: Continue power ascension per LGP-3-1 and QNE direction, Secure Suppression Pool Cooling IAW LOP-RH-13.
Event Malf. No. Event Event No. Type* Description 1 none R (ATC) Continue Power Ascension Using RR FCV 2 none N (BOP) Secure Suppression Pool Cooling IAW LOP-RH-13 3 mrd280 C (ATC) CRD Pump TRIP 4 k5e17prr C (BOP) Hydrogen Cooling TCV Fails CLOSED 5 mrd079 I (ATC) Control Rod Drifts In 6 none T (SRO) INOPERABLE Control Rod 78 r0305 T (SRO) Loss of 135X-2-B-4 d1763 89 mnb104 M (ALL) MSL Break Inside Primary Containment 910 mca015 C (ALL) Containment Bypass Path 101 none M (ALL) RPV Blowdown (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor (T)echnical Specification ES-301-4 Quantitative attributes: ES-301-5 Quantitative attributes:
Total Malfunctions (5-8): 6 BOP Normal: 1 Malfunction(s) after EOP (1-2): 1 ATC Reactivity (1 per set): 1 Abnormal Events (2-4): 4 BOP I/C (4 / set): 2 Major Transient(s) /E-Plan entry (1-2): 2 ATC I/C (4 / set): 2 EOPs (1-2): 2 SRO-I I/C (4 / set inc 2 as ATC): 4 EOP Contingencies (0-2): 1 SRO Tech Spec (2 per set): 2 Critical Tasks (2-3): 2 ALL Major Transients (2 per set): 2 Formatted: Indent: Left: 0", Hanging: 0.62" APPROXIMATE SCENARIO RUN TIME 90 Minutes Page 5 of 33
NRC 15-1-7 Revision 00 GENERAL OBJECTIVE: (USED THROUGHOUT THIS EXERCISE)
During performance of tasks, dynamic learning activities, or formal evaluations, 769.00.01 demonstrate applicable Human Performance behaviors IAW the appropriate procedures.
TASKS RO - ATC 25.048 Respond to a Control Rod Drive failures from the Main Control Room.
Perform the in plant actions for a tripped control rod drive pump, to include 25.032 investigating the cause of the trip.
303.010 Increase power from 50% to 100% power.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 Given LGA-003, Primary Containment Control, in progress Evaluate plant 419.000 conditions and control and maintain Primary Containment Pressure to less than 1.93 psig, IAW station procedures RO - BOP/ASSIST Perform the Main Control Room actions for a loss of Generator Stator Water 9.001 Cooling.
Perform the in plant actions for a tripped control rod drive pump, to include 25.032 investigating the cause of the trip.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures 411.000 Depressurize the RPV at the appropriate cooldown rate.
Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001.
414.000 Stabilize RPV pressure.
Given LGA-003, Primary Containment Control, in progress Evaluate plant 419.000 conditions and control and maintain Primary Containment Pressure to less than 1.93 psig, IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the 419.020 Suppression Pool, IAW station procedures.
Given LGA-03, PC Control, in progress, spray the Drywell, IAW station 419.030 procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Page 6 of 33
NRC 15-1-7 Revision 00 SRO - UNIT SUPERVISOR 25.048 Respond to a Control Rod Drive failures from the Main Control Room.
Perform the in plant actions for a tripped control rod drive pump, to include 25.032 investigating the cause of the trip.
Given a set of plant conditions, identify and prepare the Technical 201.011 Specification required actions IAW Tech Specs.
303.010 Increase power from 50% to 100% power.
Given Unit Supervisor authorization, perform actions for a reactor scram IAW 304.010 station procedures 411.000 Depressurize the RPV at the appropriate cooldown rate.
Given LGA-01, RPV Control, in progress, evaluate plant conditions and 413.000 control RPV level +11 to 59.5 IAW LGA-001 414.000 Stabilize RPV pressure.
Given LGA-003, Primary Containment Control, in progress Evaluate plant 419.000 conditions and control and maintain Primary Containment Pressure to less than 1.93 psig, IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, spray the 419.020 Suppression Pool, IAW station procedures.
Given LGA-03, PC Control, in progress, spray the Drywell, IAW station 419.030 procedures.
Given entry in LGA-4/06, RPV Blowdown, evaluate plant conditions and 428.000 rapidly depressurize the RPV using SRVs via the ADS system IAW station procedures.
Given LGA-03, Primary Containment Control, in progress, cool the 421.010 Suppression Pool IAW station procedures.
Page 7 of 33
NRC 15-1-7 Revision 00 Event-1
==
Description:==
Continue Power Ascension Using RR FCV Initiation: Following crew assuming shift, on direction of Lead Evaluator Cues:
Key Parameter Response: Rising Reactor Power and Core Flow Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE
- Provide peer checks as needed BOP
- Raise power as recommended by QNE or applicable attachment B o Recirc flow changes directed by Unit Supervisor shall be made per LOP-RR-07 Formatted: Indent: Left: 0.49", No bullets or numbering 303.010 ATC o Per LOP-RR-07 Formatted: Indent: Left: 0.24", No bullets or numbering
- VERIFY MANUAL light on recirculation loop flow controller M/A station Formatted: Font: Bold A/B is ON
- CHANGE flow in the operating recirc loops as follows:
- PRESS RAISE button and OBSERVE flow indication to Flow Controller M/A Station 303.010 US
- Direct above actions Page 8 of 33
NRC 15-1-7 Revision 00 Event - 1
==
Description:==
Continue Power Ascension Using RR FCV Simulator Operator Actions none Simulator Operator Role Play As the QNE, if asked limit power ascension to 50 MWe.
Floor Instructor Notes/OPEX/TRs None Terminus: When power ascension is complete.(~50MWe)
Page 9 of 33
NRC 15-1-7 Revision 00 Event-2
==
Description:==
Secure Suppression Pool Cooling IAW LOP-RH-13 Initiation: Turnover Cues:
Key Parameter Response: none Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOP-RH-13
- CLOSE 1E12-F024A, RHR Test to SP Valve
- VERIFY 1E12-F064A, RHR Min Flow Valve OPENS
- STOP 1E12-C002A, RHR Pump
- VERIFY 1E12-F048A, RHR Hx Bypass Valve, Full OPEN
- VERIFY 1E12-F003A, Hx Outlet Valve, Full OPEN
- LOG securing SP Cooling Mode
- VERIFY applicable DG Cooling Water Pump and Ventilation Status
- SHUTDOWN applicable DG Cooling Water Pump, 0DG01P
- SHUTDOWN RHR Service Water System per LOP-RH-05
- Direct EO to lLocally BACKWASH the operating RHR Service Water Strainer per LOP-RH-14, Backwash of the Residual Heat Removal Service Water Strainer BOP
- PLACE the appropriate Thermal Overload Bypass Switches to TEST Formatted: Indent: Left: 0.24", Bulleted + Level: 1 +
Aligned at: 0.49" + Indent at: 0.74", Tab stops: Not at
- PLACE control switch for 1E12-F068A, Hx Water Outlet Valve to 0.49" CLOSE and perform the following:
- When indicated flow decreases to less than 4000 gpm, STOP one RHR Service Water Pump
- STOP the running RHR Service Water Pump when flow rate decreases to 0 gpm on RHR Service Water flow indication
- PLACE the appropriate Thermal Overload Bypass Switch to NORMAL
- Direct EO to VERIFY automatic shutdown of the RHR Service Water Process Radiation Monitor per LOP-PR-06
- Direct EO to lLocally in DG Penthouse VERIFY the Service Water ventilation Fan stop
- VERIFY the appropriate ESF Status Panel Annunciator is CLEAR ATC
- Provide peer checks as required US
- Direct above actions Page 10 of 33
NRC 15-1-7 Revision 00 Event - 2
==
Description:==
Secure Suppression Pool Cooling IAW LOP-RH-13 Simulator Operator Actions none Simulator Operator Role Play As the operator in the field, when asked the status of RHR Pump Room Ventilation, wait 1 minute and report, Pump Room Ventilation is secured. (LOP-RH-13 step E.2.1.8)
As the operator in the field, when ordered to backwash the RHR Service Water Filter, wait 3 minutes and report back, RHR Service Water Strainer has been backwashed. (LOP-RH-05 step E.5.2)
As the operator in the field, when asked the status of RHR Service Water PRM, wait 1 minutes and report, RHR Service Water PRM sample pump is stopped and in AUTO. (LOP-PR-06 sect E.9)
As the operator in the field sent to check the status of RHR Service Water Ventilation in the DG Penthouse, wait 1 minute and report, the Service Water Vent Fan is STOPPED. (LOP-RH-05)
As Unit 2 Unit Supervisor, the 0 DG cooling water pump is not needed and can be secured.
Floor Instructor Notes/OPEX/TRs Time compression is used for the field actions of this event.
Terminus: When Suppression Pool Cooling is fully secured.
Page 11 of 33
NRC 15-1-7 Revision 00 Event-3
==
Description:==
CRD Pump TRIP Initiation: On direction of Lead Evaluator, release Event 3 Cues:
Key Parameter Response: LOWERING CHARGING HEADER PRESSURE Expected Annunciators:
1H13-P603-A103, CONTROL ROD DRIVE FEED PUMP 1A AUOTMATIC TRIP 1H13-P603-A204, CONTROL ROD DRIVE CHARGING WATER PRESSURE LOW 1H13-P603-A302, LOW CHARGING WATER HEADER PRESSURE SCRAM A1 AND B1 Automatic Actions: TRIPS CONTROL ROD DRIVE FEED PUMP 1C11-C001A Objective Position EXPECTED OPERATOR RESPONSE
- Monitor plant parameters and update the crew as required 25.032 BOP
- Send an Equipment Operator to invetigate Per LOR-1H13-P603-A103
- If the standby CRD Pump is available, IMMEDIATELY start standby CRD Pump and CHECK for proper operation.
- IMMEDIATELY refer to LOR-1H13-P603-A204
- DETERMINE cause for TRIP and initiate appropriate corrective action, as required. Possible causes:
- o Low Suction pressure Formatted: Indent: Hanging: 0.01", Bulleted + Level: 1 +
Aligned at: 0" + Indent at: 0.25"
- o Bus 141Y under voltage o Motor overcurrent
- o Swap CRD Room Fans per LOP-RD-01 Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25"
- Refer to Tech Spec 3.1.5 and 3.9.5 25.032 US
- Direct above actions Page 12 of 33
NRC 15-1-7 Revision 00 Event - 3
==
Description:==
CRD Pump TRIP Simulator Operator Actions With the concurrence of the Release Event 3 Lead Evaluator Simulator Operator Role Play As the operator sent to investigate the TRIP of 1A CRD Pump, wait 3 minutes and report, 1A CRD Pump breaker Tripped on Overcurrent.
As the operator sent to perform post-start checks on the 1B CRD Pump, post-start checks are SAT.
Floor Instructor Notes/OPEX/TRs none Terminus: When the standby CRD has been started and parameters return to normal.
Page 13 of 33
NRC 15-1-7 Revision 00 Event-4
==
Description:==
Hydrogen Cooling TCV Fails CLOSED Initiation: On direction of Lead Evaluator, release Event 4 Cues:
Key Parameter Response: Rising H2 Temperature Expected Annunciators:
1PM02J-B101, HYDROGEN PANEL TROUBLE 1PM02J-B301, GENERATOR 1 HYDROGEN TEMPERATURE HIGH OR LOW Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM02J-B301
- CHECK 1TI-WS001, Generator Cold Gas Temp, greater than 51C or less than 30C
- PLACE 1TK-WS001, Gen H2 Coolers Temp Controller, in MANUAL and 9.001 BOP POSITION 1WS043, Gen H2 Coolers WS Outlet Temperature Control Valve, to maintain Generator Cold Gas Temperature between 30C and 56C o If Generator Cold Gas Temperature exceeds 56C on 1TI-WS001 or Hydrogen Cooler H2 Inlet Temperatures exceed 72C REDUCE VARS to approximately 0 ATC
- Monitor plant parameters and update the crew as required.
- Direct above actions US
- o Establish Generator Hydrogen Gas Temperature as a Critical Parameter Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent at: 0.25" Page 14 of 33
NRC 15-1-7 Revision 00 Event - 4
==
Description:==
Hydrogen Cooling TCV Fails CLOSED Simulator Operator Actions With the concurrence of the Release Event 4 Lead Evaluator Simulator Operator Role Play Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs none Terminus: When H2 temperature returns to the normal band. (30-56C)
Page 15 of 33
NRC 15-1-7 Revision 00 Event-5
==
Description:==
Control Rod 34-19 Drifts In Initiation: On direction of Lead Evaluator, release Event 5 Cues:
Key Parameter Response: Rod Drifting Inward Expected Annunciators: 1H13-P603-A504, CONTROL ROD DRIVE DRIFT ALARM Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE BOP
- Provide peer checks Per LOA-RD-101
- Continually check rod status
- CHECK no control rod currently moving (NO)
- At ROD SELECT or STATUS display in CONTROL mode, press drift acknowledge
- SELECT Drifting Control Rod (34-19)
- VERIFY insert block is OFF (NO)
- If required remove insert block
- Place RWM Select switch to BYPASS
- INSERT Control Rod to position 00
- PLACE CONTROL ROD DRIVE FLOW TRIP CIRCUIT BYPASS switch to BYPASS
- Depress and hold insert pushbutton until control rod 34-19 indicates at 25.048 ATC position 00/FI
- CHECK control rod remains at position 04 or less
- If insert pushbutton is NOT being held depressed:
- If desired o PLACE control rod OOS on RCMS o DISARM control rod electrically on RCMS
- Perform LPRM diagnostic
- RUN OD-20
- If required, restore RWM/CRD to normal as follows o PLACE RWM mode to RUN o PLACE Inop Rods OOS per LOP-RM-02 o PLACE CRD DRIVE FLOW TRIP CIRCUIT BYPASS Switch to ACTIVE
- Refer to LOP-RD-29
- Direct above actions
- Set manual Scram criteria o More than 1 rod moving at the same time 25.048 US o More than 3 rods SCRAMMED OR DRIFTED Full in
- Contact system Engineering and QNE
- Contact Shift Manager Page 16 of 33
NRC 15-1-7 Revision 00 Event - 5
==
Description:==
Control Rod 34-19 Drifts In Simulator Operator Actions With the concurrence of the Release Event 5 Lead Evaluator Simulator Operator Role Play Respond as QNE and System Engineering.
Floor Instructor Notes/OPEX/TRs Rod 34-19 Terminus: continued Page 17 of 33
NRC 15-1-7 Revision 00 Event-6
==
Description:==
INOPERABLE Control Rod Initiation: continued Cues:
Key Parameter Response: none Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE BOP
- Provide peer checks as required Per LOP-RM-02
- DETERMINE desired control rod to be Electrically disarmed
- SELECT SET PARAMETERS
- SELECT ELECTRICALLY DISARM/RESTORE ROD on the SET HCU screen
- SELECT control rod to be electrically disarmed
- Press ACCEPT to change the desired control rod to electrically disarm
- ACKNOWLEDGE popup messages
- The electrically disarmed rod will appear in white text on light gray back round with orange border 25.048 ATC
- RETURN to the SELECT screen, if desired, when all ED operations are complete.
o May Place Rod OOS per LOP-RM-02
- SELECT SET PARAMETERS on the ROD SELECT Display or the Formatted: Indent: Left: 0.24", Bulleted + Level: 1 +
STATUS Display, whichever is in the CONTROL mode. Aligned at: 0" + Indent at: 0.25"
- SELECT DECLARE/RESTORE ROD OUT OF SERVICE on the SET HCU/ROD screen.
- SELECT the control rod(s) to be declared out-of-service.
- PRESS ACCEPT to place the control rod out of service.
o* ACKNOWLEDGE the popup message
- Enter Tech Spec 3.1.3 Condition C 25.048
- Required action C.1 fully insert inop control rod in 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> AND C.2 US 201.011 disarm the associated CRD in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
- Refer to Tech Spec 3.1.6 Page 18 of 33
NRC 15-1-7 Revision 00 Event - 6
==
Description:==
INOPERABLE Control Rod Simulator Operator Actions None Simulator Operator Role Play Acknowledge reports as required.
Floor Instructor Notes/OPEX/TRs none Terminus: Tech Spec call is complete and at the discretion of the Lead Evaluator.
Page 19 of 33
NRC 15-1-7 Revision 00 Event-7
==
Description:==
Loss of 135X-2-B-4 Initiation: On direction of Lead Evaluator, release Event 7 Cues:
Key Parameter Response: ESF Panel Alarm Expected Annunciators:
1PM01J- A515, 0 DIESEL GENERATOR HVAC TROUBLE/POWER FAILURE ALARM Automatic Actions: TRIPS 135X-2-B-4, LOSS OF 0VD01C Objective Position EXPECTED OPERATOR RESPONSE Per LOR-1PM01J-A5154
- DISPATCH operator to Local Panel 0PL17J to DETERMINE cause of BOP alarm
- Provide peer checks as required
- Direct above actions
- Enter Tech Spec 3.8.1
- Condition B - Required opposite unit division 0 DG inoperable
- Required Action
- B.1 - perform SR 3.8.1.1 for operable required offsite circuits AND
- B.2 - Declare features supported by DG INOP 201.011 US AND
- B.3.2 - perform SR 3.8.1.2 AND
- B.4 - Restore required DG to operable in 14 days AND 17 days from discovery of failure to meet LCO 3.8.1.a or b Page 20 of 33
NRC 15-1-7 Revision 00 Event - 7
==
Description:==
Loss of 135X-2-B-4 Simulator Operator Actions With the concurrence of the Release Event 7 Lead Evaluator Simulator Operator Role Play As the operator in the field, when requested to investigate 0PL17J,wait 2 minutes and report, the DG ROOM VENT FAN 0VD01C AUTO TRIP alarm is lit As the operator in the field, when requested to investigate 135X-2, wait 2 minutes and report, the feed breaker for 0VD01C in compartment B4 is tripped on overcurrent.
If the crew attempts to perform offsite power lineup, inform the Unit Supervisor that the Unit 2 Assist NSO is performing the offsite power lineup.
Respond as required.
Floor Instructor Notes/OPEX/TRs noneNone.
Terminus: When Tech Spec call has been made and at the discretion of the Lead Evaluator.
Page 21 of 33
NRC 15-1-7 Revision 00 Event-8
==
Description:==
MSL Break Inside Primary Containment Initiation: On direction of Lead Evaluator, release Event 8 Cues:
Key Parameter Response: Drywell Pressure rising Expected Annunciators:
1H13P603-B501 PRI CNMT PRESSURE HI/LO 1PM13J-A302 RB NORTH/DW FLR SUMP TROUBLE 1PM13J-A204 DW COOLER COND FLOW RATE HI Automatic Actions: Reactor Scram, ECCS initiations, PCIS Isolations Objective Position EXPECTED OPERATOR RESPONSE
- To prevent losing Chamber Spray/ECCS runout with DW Spray prior to 500 psig.
- Place Div 1/2 Inj Override Switch to NON-ATWS
- Div I: With an ECCS signal present Verify White Manual Override 419.000 light for 1E12-F042A AND 1E21-F005 Illuminated 304.010 BOP (NOTE: If level 1 is received LPCS override will clear and LPCS will Inject) 414.000
- Div II: With an ECCS signal present Verify White Manual Override light for 1E12-F042B AND 1E12-F042C Illuminated
- Responds to PRI CONT PRESSURE HI/LO annunciator and informs the Unit supervisor
- When directed, manually scrams the reactor
- PLACE Reactor Mode Switch in SHUTDOWN
- CHECK Control Rods INSERTED and Power Decreasing 413.000 ATC
- REPORT to the Unit Supervisor the status of RPV Level and 419.000 Pressure 304.010
- VERIFY Reactor Recirculation Pumps have downshifted
- VERIFY Main Turbine and Generator Trip
- STABILIZE Reactor Pressure <1020 psig
- REFER to LGP-3-2
- Monitors and reports RPV water level throughout
- Controls injection from Condensate and Feed system o May direct a manual reactor scram prior to reaching 1.93 psig in the Drywell 413.000
- Enters and directs actions of LGA-001 LEVEL LEG 419.000 US
- Establishes a RPV water level band of 20 to +50 inches 304.010
- Enters and directs actions of LGA-001 PRESSURE LEG
- STABILIZE Reactor Pressure below 1059 psig (800 psig to 1000 psig per Ops Strategies document)
Page 22 of 33
NRC 15-1-7 Revision 00 Event - 8
==
Description:==
MSL Break Inside Primary Containment Simulator Operator Actions With the concurrence of the Release Event 8 Lead Evaluator Simulator Operator Role Play Respond as required Floor Instructor Notes/OPEX/TRs none Terminus: continued Page 23 of 33
NRC 15-1-7 Revision 00 Event-8 contd
==
Description:==
MSL Break Inside Primary Containment Objective Position EXPECTED OPERATOR RESPONSE
- Monitors and reports containment parameters throughout
- When directed places Suppression Pool Cooling in service:
- Startup RHR Service Water as follows:
- OPEN 1A/1B RHR Hx Service Water Outlet Valve: 1E12-F068A/B
- At approximately 9 to 10 seconds after taking the 1E12-F068A/B switch to OPEN, START first RHR Service Water Pump:
1A or 1B/C or D
- When indicated flow reaches 3000 gpm, START second RHR Service Water Pump.
419.020
- Startup RHR 419.030
- Start 1A/1B RHR Pump 421.000
- Establish RHR flow of 1500 to 7450 gpm:
BOP 421.010
- Throttle 1E12-F024A/B (Test Valve) OPEN.
413.000
- Close 1E12-F048A/B (HX Bypass) o Place A/B HTX Bypass Throttle/Seal in switch to THROTTLE and THROTTLE CLOSED 1E12-F048A/B. o o Place A/B HTX Bypass Throttle/Seal in switch to SEAL IN and CLOSE 1E12-F048A/B
- When directed establish Suppression Chamber Spray: (CT)
- VERIFY 1A/1B RHR Pump is running
- OPEN 1E12-F027A/B
- When directed establish Drywell Spray: (CT)
- VERIFY 1A/1B RHR Pump is running
- THROTTLE 1E12-F024A/B CLOSED
- OPEN:1E12-F016A/B and 1E12-F017A/B ATC
- Maintain RPV level and pressure as directed
- When Drywell Pressure exceeds 1.93 psig, enters and directs actions of LGA-003
- Before Suppression Chamber Pressure exceeds 12 psig 419.020
- Verifies Containment Flood level below 723 ft.
419.030
- Directs start of Suppression Chamber Sprays (CT) 421.000
- When Suppression Chamber Pressure exceeds 12 psig, direct initiation of Drywell sprays 421.010 US
- Verifies Containment Flood level below 722 ft.
- Verifies Drywell Pressure and Temperature permit Drywell Sprays per Figure D
- Verifies both Recirc Pumps are tripped
- Direct initiation of Drywell sprays (CT)
- o When Suppression Pool temperature exceeds 105ºF initiation of direct Formatted: Bulleted + Level: 1 + Aligned at: 0" + Indent initiation of Suppression Pool Cooling at: 0.25" Page 24 of 33
NRC 15-1-7 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 25 of 33
NRC 15-1-7 Revision 00 Event-9
==
Description:==
Containment Bypass Path Initiation: On direction of Lead Evaluator Cues:
Key Parameter Response: Drywell and Suppression Chamber Pressure Rising Uncontrollably Expected Annunciators: none Automatic Actions: none Objective Position EXPECTED OPERATOR RESPONSE 419.000 BOP
- Attempted to lower Primary Containment pressure below 1.93 psig ATC
- Maintain RPV level and pressure as directed
- Direct above actions 419.000 US
- If cannot restore chamber pressure and pool level inside Pressure Suppression Pressure and hold it there, blowdown per LGA-004 or anticipate blowdown using Turbine Bypass Valves.
Page 26 of 33
NRC 15-1-7 Revision 00 Event - 9
==
Description:==
Containment Bypass Path Simulator Operator Actions none Simulator Operator Role Play none Floor Instructor Notes/OPEX/TRs none Terminus: continued Page 27 of 33
NRC 15-1-7 Revision 00 Event-10
==
Description:==
RPV Blowdown Initiation: none Cues:
Key Parameter Response: LOWERING RPV PRESSURE Expected Annunciators: NONE Automatic Actions: 7 SRVs OPEN Objective Position EXPECTED OPERATOR RESPONSE 413.000 ATC
- Maintains RPV water level as directed
- If directed, opens Turbine Bypass Valves o If directed, prevents LPCS, LPCI, and HPCS not needed for core cooling.
- Arms and depresses both Div 1 ADS MANUAL INITIATION pushbuttons
- Arms and depresses both Div 2 ADS MANUAL INITIATION pushbuttons
- Determines if SC pressure will remain within the Pressure Suppression Pressure (PSP) limit.
o May anticipate Blowdown and directs actions to rapidly depressurize via turbine bypass valves 411.000
- Directs actions per LGA-004 if Sup Chamber pressure cannot be US maintained below the PSP limit.(CT) 428.000
- Verifies DW pressure at or above 1.77 psig.
o May direct NSO to prevent LPCS and LPCI not needed for cooling
- Verifies SP level greater than -18 ft.
Page 28 of 33
NRC 15-1-7 Revision 00 Event - 10
==
Description:==
RPV Blowdown Simulator Operator Actions none Simulator Operator Role Play none Floor Instructor Notes/OPEX/TRs none Terminus: when ADS has been initiated or blowdown anticipated and at the discretion of the Exam lead.
Page 29 of 33
NRC 15-1-7 Revision 00 REFERENCES Procedure Title Revision
- 1. LGA-001 RPV CONTROL 017
- 2. LGA-003 PRIMARY CONTAINMENT CONTROL 016
- 3. LGA-004 RPV BLOWDOWN 009
- 4. LGP-3-1 POWER CHANGES 062
- 5. LGP-3-2 REACTOR SCRAM 072
- 6. LOP-RH-13 SUPPRESSION POOL COOLING OPERATION 032
- 7. LOP-RH-05 OPERATION OF THE RHR SERVICE WATER SYSTEM 033
- 8. LOP-RH-14 BACKWASH OF THE RHR SERVICE WATER STRAINERS 014 STARTUP AND OERATION OF THE LIQUID PROCESS
- 9. LOP-PR-06 018 RADIATION MONITORING SUSTEM OPERATION OF THE REACTOR RRECIRCULATION FLOW
- 10. LOP-RR-07 045 CONTROL SYSTEM FILLING, VENTING, AND STARTUP OF THE CONTROL ROD
- 11. LOP-RD-01 033 DRIVE SYSTEM DETERMINATION OF CONTROL ROD DRIVE SYSTEM
- 12. LOP-RD-29 004 PROBLEMS ROD CONTROL MANAGEMENT SYSTEM ON DEMAND
- 13. LOP-RM-02 023 FUNCTIONS
- 14. LOA-RD-101 CONTROL ROD DRIVE ABNORMAL 020
- 15. LOA-PC-101 PRIMARY SECONDARY CONTAINMENT TROUBLE 019
- 16. LOR-1H13-P603-A103 CONTROL ROD DRIVE FEED PUMP 1A AUOTMATIC TRIP 006 CONTROL ROD DRIVE CHARGING WATER PRESSURE LOW
- 18. LOR-1H13-P603-A302 004 AND B1
- 19. LOR-1H13-P603-A403 CONTROL ROD DRIVE HYDRAULIC TEMPERATURE HIGH 006
- 20. LOR-1PM02J-B101 HYDROGEN PANEL TROUBLE 002
- 22. LOR-1H13-P603-A504 CONTROL ROD DRIVE DRIFT ALARM 004 0 DIESEL GENERATOR HVAC TROUBLE/POWER FAILURE
- 23. LOR-1PM01J- A515 001 ALARM
- 26. LOR-1PM13J-A204 DW COOLER COND FLOW RATE HI 005
- 28. LGP-1-1 NORMAL UNIT STARTUP 115 ESF PANEL OPERATION AND RESPONSE TO PANEL 014
- 29. LOP-CX-03 INDICATIONS Page 30 of 33
NRC 15-1-7 Revision 00 COMPUTER AIDED EXERCISE PROGRAM (CAEP)
ESG NRC 15-1-7 Revision: 00 Revision Date: 7/27/16 Developed By: C. M. Betken Page 31 of 33
NRC 15-1-7 Revision 00 THIS PAGE INTENTIONALLY LEFT BLANK Page 32 of 33
NRC 15-1-7 Revision 00 U1 SUPERVISOR TURNOVER Shift: 2 Date: Today Mode: 1 OLR: Yellow Work Week: Non-Div Unit 1 power level Unit 2 power level
- 71 % Power
- 100 % Power U1 Thermal Limit Issues /Power Evolutions U2 Thermal Limit Issues /Power Evolutions
- Startup in-progress currently in step
- None E.8.32 for power ascension In LGP-1-1 Existing LCOs, date of next surveillance Existing LCOs, date of next surveillance
- None
- None LOSs in progress or major maintenance LOSs in progress or major maintenance
- None
- None Equipment removed from service or currently unavailable
- ACB 1522
- None Grid Status is Green Comments, evolutions, problems, etc. Comments, evolutions, problems, etc.
- 1. Continue power ascension per LGP-3-1
- Non-Div workweek Step E.1.8 and QNE direction 50 MWe
- OLR is Green using RR flow
- 2. Following initial power ascension secure Div 1 Suppression Pool Cooling IAW LOP-RH-13
- Non-Div workweek
- OLR is YELLOW Page 33 of 33