|
---|
Category:License-Operator
MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23193A8602023-07-12012 July 2023 Form 5.1-1 Post Examination Check Sheet (LaSalle 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23171A9542023-06-12012 June 2023 Form 2.1-1 Examination Preparation Checklist (LaSalle 2023) ML23171A9522023-06-12012 June 2023 Form 1.3-1 Exam Security Agreement ML23171A9562023-06-12012 June 2023 Post Exam Ltr ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 ML23067A0552023-03-0808 March 2023 Form 2.3-2 Operating Test Quality Checklist (LCS 2023) - Final ML23067A0562023-03-0808 March 2023 Form 2.3-4 Written Exam Quality Checklist (LCS 2023) - Final RA23-014, 75-Day Exam Submittal Letter2023-02-15015 February 2023 75-Day Exam Submittal Letter ML23065A0542022-12-28028 December 2022 Form 3.4-1 Events and Evolutions Checklist (LCS 2023) ML23065A0472022-12-28028 December 2022 Form 2.3-1 Examination Outline - Op Test ML23065A0442022-12-28028 December 2022 Form 2.3-1 Examination Outline - Written (LCS 2023) RA22-066, 150 Day Submittal Cover Letter2022-12-0202 December 2022 150 Day Submittal Cover Letter ML22251A0732022-09-14014 September 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000373/20203012020-12-17017 December 2020 NRC Initial License Examination Report 05000373/2020301; 05000374/2020301 RA20-058, Licensee Post Exam Submittal Letter2020-12-0202 December 2020 Licensee Post Exam Submittal Letter ML21004A2312020-12-0101 December 2020 County, ES-301-3 ML21004A2302020-12-0101 December 2020 County, Written Exam ML21004A2322020-12-0101 December 2020 County, ES-301-4 ML21005A0432020-12-0101 December 2020 ES-201-2 ML21005A0802020-12-0101 December 2020 RO Admin JPM ML21005A0402020-12-0101 December 2020 Scenario D-1 ML21005A1012020-12-0101 December 2020 in Plant JPM ML21005A0392020-12-0101 December 2020 2020_401-1 and 401-3 ML21005A0922020-12-0101 December 2020 Sim JPM ML21004A2242020-12-0101 December 2020 County, RO Admin JPMs ML21004A2192020-12-0101 December 2020 County, ES-401-6 ML21005A0982020-12-0101 December 2020 SRO Admin JPM ML21005A3722020-12-0101 December 2020 ES-401-9 ML21005A3692020-12-0101 December 2020 ES-401-4 ML21005A2402020-12-0101 December 2020 SRO Ile (Answer Key) ML21005A2382020-12-0101 December 2020 RO Ile (Answer Key) ML21005A3652020-12-0101 December 2020 ES-301-7 ML21005A0202020-12-0101 December 2020 ES-301-1 RO ML21004A2222020-12-0101 December 2020 County, Inplant JPMs ML21005A3802020-12-0101 December 2020 ES-201-1 ML21005A0222020-12-0101 December 2020 ES-301-1 SRO ML21004A2272020-12-0101 December 2020 County, Sim JPMs ML21005A0882020-12-0101 December 2020 Scenarios ML21005A3842020-12-0101 December 2020 ES-403-1 ML21005A3832020-12-0101 December 2020 ES-201-3 ML21005A0232020-12-0101 December 2020 ES-301-2 RO ML21005A0462020-12-0101 December 2020 ES-301-5 ML21004A2332020-12-0101 December 2020 County, ES-301-6 ML21004A2282020-12-0101 December 2020 County, SRO Admin JPMs 2024-09-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23193A8602023-07-12012 July 2023 Form 5.1-1 Post Examination Check Sheet (LaSalle 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23171A9522023-06-12012 June 2023 Form 1.3-1 Exam Security Agreement ML23171A9562023-06-12012 June 2023 Post Exam Ltr ML23171A9542023-06-12012 June 2023 Form 2.1-1 Examination Preparation Checklist (LaSalle 2023) ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 ML23067A0562023-03-0808 March 2023 Form 2.3-4 Written Exam Quality Checklist (LCS 2023) - Final ML23067A0552023-03-0808 March 2023 Form 2.3-2 Operating Test Quality Checklist (LCS 2023) - Final RA23-014, 75-Day Exam Submittal Letter2023-02-15015 February 2023 75-Day Exam Submittal Letter ML23065A0442022-12-28028 December 2022 Form 2.3-1 Examination Outline - Written (LCS 2023) ML23065A0472022-12-28028 December 2022 Form 2.3-1 Examination Outline - Op Test ML23065A0542022-12-28028 December 2022 Form 3.4-1 Events and Evolutions Checklist (LCS 2023) RA22-066, 150 Day Submittal Cover Letter2022-12-0202 December 2022 150 Day Submittal Cover Letter ML22251A0732022-09-14014 September 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000373/20203012020-12-17017 December 2020 NRC Initial License Examination Report 05000373/2020301; 05000374/2020301 RA20-058, Licensee Post Exam Submittal Letter2020-12-0202 December 2020 Licensee Post Exam Submittal Letter ML21004A2272020-12-0101 December 2020 County, Sim JPMs ML21005A0392020-12-0101 December 2020 2020_401-1 and 401-3 ML21005A0262020-12-0101 December 2020 ES-301-2 SRO ML21005A0232020-12-0101 December 2020 ES-301-2 RO ML21005A0402020-12-0101 December 2020 Scenario D-1 ML21005A2402020-12-0101 December 2020 SRO Ile (Answer Key) ML21005A3692020-12-0101 December 2020 ES-401-4 ML21004A2242020-12-0101 December 2020 County, RO Admin JPMs ML21005A3722020-12-0101 December 2020 ES-401-9 ML21005A2382020-12-0101 December 2020 RO Ile (Answer Key) ML21005A1012020-12-0101 December 2020 in Plant JPM ML21005A0982020-12-0101 December 2020 SRO Admin JPM ML21004A2282020-12-0101 December 2020 County, SRO Admin JPMs ML21005A0802020-12-0101 December 2020 RO Admin JPM ML21005A0882020-12-0101 December 2020 Scenarios ML21005A0922020-12-0101 December 2020 Sim JPM ML21005A3652020-12-0101 December 2020 ES-301-7 ML21004A2312020-12-0101 December 2020 County, ES-301-3 ML21004A2322020-12-0101 December 2020 County, ES-301-4 ML21004A2332020-12-0101 December 2020 County, ES-301-6 ML21005A0462020-12-0101 December 2020 ES-301-5 ML21005A0202020-12-0101 December 2020 ES-301-1 RO ML21004A2222020-12-0101 December 2020 County, Inplant JPMs ML21004A2302020-12-0101 December 2020 County, Written Exam ML21004A2192020-12-0101 December 2020 County, ES-401-6 ML21005A3802020-12-0101 December 2020 ES-201-1 ML21005A0432020-12-0101 December 2020 ES-201-2 ML21005A3832020-12-0101 December 2020 ES-201-3 ML21005A3842020-12-0101 December 2020 ES-403-1 2024-09-16
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-l Facility Lq S"lle Date of Examinarion: to/n/tg- tl/l L Developed by: written: Facility E NRC E tl operating Facility F NRc I Chief Target Task Description (Reference) Examiner's Date* lnitials
-1 80 1. Examination administration date confirmed (C.1.a; C.2.a and b) ç.
-1 50 2. NRC examiners and facility contact assigned (C.1 .d; C.2.e) t
-1 50 3. Facilty contact briefed on security and other requirements (C.2.c) a
-'t50 4. Corporate notification letter sent (C.2.d) 4/
I-1201 5. Reference material due (C.1.e; C.3.c; Attachment 3) uln
{-e0} 6. lntegrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301 -1 ,
ES-301 -2, ES-301 -5, ES-D-1, E5401 -1 12, ES-401 N-1 /2, ES-401 -3, ES-401 N-3, ES-401-4, and ES-401 N-4, as applicable (C.1.e and f; C.3.d) t, c85) 7 Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h;C.3.e) ?
{-60} 8. Proposed examinations (including written, walk{hrough JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-30'1-3, ES-301-4, ES-3Ol-5, ES-30't-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1 , or ES-301-2 updates), and reference materials due (C.l.e, f, g and h; c.3.d)
?
-45 9. Written exam and operating test reviews completed. (C.3.f) 9.
-30 10. Preliminary license applications (NRC Form 398's) due (C.l.l; C.2.9; ES-202) /.
-21 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.0 o
-21 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.9) q.
-14 13. Final license applications due and Form ES-201-4 prepared (C.'l .l; C.2.i; ES-202) 0.
-14 14 Written examinations and operating tests approved by NRC supervisor (C.2.i; c.3.h) ?
-7 15 Facility lcensee management queried regarding the licensee's views on the examination. (C.2 j) ç
-7 16 Final applications reviewed; 1 or 2 (i't >10) applicatons audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES-202, C.2.e; ES-204) r
-7 17 Proctoring/written exam administration guidelines reviewed with facility licensee (c.3.k) ?
'18. Approved scenarios, job performance measures, and questions distributed to NRC 7
examiners (C.3.i) ?
- Target dates are generarlly based on facility-prepared examinations and are keyed to the examination date identlfied in the cororate riotification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.