|
---|
Category:Annual Operating Report
MONTHYEARML22055A5772022-02-0404 February 2022 Dow Chemical Co., Submittal of Annual Report for 2021 ML20062A1872020-02-24024 February 2020 Dow Chemical Co., Submittal of Annual Report ML19063A4972019-02-22022 February 2019 Annual Report for the Dow Triga Research Nuclear Reactor, Docket No. 50-264 ML18060A0792018-02-22022 February 2018 2017 Annual Report for the Dow Triga Research Reactor ML17061A5102017-02-24024 February 2017 Annual Report for the Dow Triga Research Nuclear Reactor ML16068A1772016-02-29029 February 2016 Dow Triga Research Nuclear Reactor - Transmittal of Annual Report for 2015 ML15051A3672015-02-17017 February 2015 Annual Report 2014 for the Dow Triga Research Nuclear Reactor ML14070A1792014-03-0707 March 2014 Dow Triga Research Reactor - Annual Report - 2013 ML12066A1282012-03-0202 March 2012 Annual Report for the Dow Triga Research Nuclear Reactor ML1004903992010-01-25025 January 2010 Transmittal of 2009 Annual Report for the Dow Triga Research Nuclear Reactor ML0807905212008-03-0606 March 2008 Submittal of 2007 Annual Report for the Dow Triga Research Nuclear Reactor ML0410405842004-03-26026 March 2004 Annual Report for the Dow Triga Research Nuclear Reactor - 2003 2022-02-04
[Table view] Category:Letter
MONTHYEARIR 05000264/20242012024-05-22022 May 2024 Dow Chemical Company - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000264/2024201 ML24066A1472024-03-11011 March 2024 Dow Chemical Company - Change of Facility Project Manager ML24057A0092024-02-21021 February 2024 Dow Triga Research Reactor Annual Report - 2023 IR 05000264/20232012023-08-0101 August 2023 Dow Chemical Company - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000264/2023201 - Cover Letter and Enclosure ML23062A1132023-02-28028 February 2023 Dow Chemical Co., Submittal of Annual Report for 2022 ML22284A0472022-10-0606 October 2022 Closure of Level 1 Finding for the Quad Cities Generating Station ML22062B6492022-05-24024 May 2022 Supplemental Information Needed for Acceptance of Proposed Alternative to Use ASME Code Case N-921 IR 05000264/20222012022-04-15015 April 2022 Dow Chemical Company - U.S. Nuclear Regulatory Commission Routine Inspection Report 05000264/2022201 ML22080A0722022-03-11011 March 2022 Dow Chemical Company - Management Change ML22055A5772022-02-0404 February 2022 Dow Chemical Co., Submittal of Annual Report for 2021 ML21271A0952021-10-0404 October 2021 Dow Chemical Company Change of Facility Project Manager IR 05000264/20212022021-08-10010 August 2021 Dow Chemical Company U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000264/2021202 IR 05000264/20212012021-05-27027 May 2021 Dow Chemical Company - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000264/2021201 ML21153A1642021-05-26026 May 2021 Dow Chemical Company - Management Change Update ML21063A2492021-02-16016 February 2021 Dow Triga Research Reactor Annual Report - 2020 ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20247J3712020-09-0303 September 2020 Examination Confirmation Letter No. 50-264/OL-21-01, Dow Chemical Company Reactor ML20062A1872020-02-24024 February 2020 Dow Chemical Co., Submittal of Annual Report ML19339F8002020-02-0606 February 2020 Dow Chemical Co., Notice of Consideration of Approval of Indirect License Transfer and Conforming Amendment and Opportunity for a Hearing and Petition for Leave to Intervene ML19330E2442019-11-22022 November 2019 Dow Chemical Co., Transmittal of Consent for an Indirect License Transfer IR 05000264/20192022019-10-30030 October 2019 Cover Letter - Dow Chemical Company - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000264/2019202 IR 05000264/20192012019-10-30030 October 2019 Dow Chemical Company Nuclear Regulatory Commission Routine Inspection Report No. 05000264/2019201 ML19063A4972019-02-22022 February 2019 Annual Report for the Dow Triga Research Nuclear Reactor, Docket No. 50-264 ML18365A3552019-01-0808 January 2019 Dow Chemical Company - Change of Facility Back-Up Project Manager IR 05000264/20182012018-10-19019 October 2018 Dow Chemical Company - U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000264/2018201 ML18060A0792018-02-22022 February 2018 2017 Annual Report for the Dow Triga Research Reactor IR 05000264/20172012017-11-0808 November 2017 Dow Chemical Co., NRC Routine Inspection Report 05000264/2017201 ML17067A2792017-03-23023 March 2017 Dow Chemical Company - Non-Power Reactor Closeout of Generic Letter 2016-01, "Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools," for the Dow TRIGA Research Reactor, Docket No. 50-264 (CAC No. A11010) ML17061A5102017-02-24024 February 2017 Annual Report for the Dow Triga Research Nuclear Reactor IR 05000264/20162022016-09-16016 September 2016 Dow Chemical Company, NRC Security Related Inspection Report 05000264/2016202 IR 05000264/20162012016-09-14014 September 2016 Dow Chemical Company - NRC Routine Inspection Report 05000264/2016201, July 19-21, 2016 ML16166A4152016-06-13013 June 2016 the Dow Triga Research Reactor, Response to NRC Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools ML16068A1772016-02-29029 February 2016 Dow Triga Research Nuclear Reactor - Transmittal of Annual Report for 2015 ML15364A3732016-01-19019 January 2016 Dow Chemical Company TRIGA Research Reactor - Closure of Confirmatory Action Letter No. NRR-04-009 on Site-Specific Compensatory Measures Implementation Plan ML14290A4862015-06-0303 June 2015 Y020140127 - Withdrawal of Order EA-05-007, Order Imposing Additional Security Measures ML15051A3672015-02-17017 February 2015 Annual Report 2014 for the Dow Triga Research Nuclear Reactor IR 05000264/20142012014-09-15015 September 2014 IR 05000264/2014201 on August 26-28, 2014 at Dow Chemical Company -NRC Routine Inspection Report No. 50-264/2014-201 ML14202A3282014-07-23023 July 2014 Dow Chemical Company Review of the Surety Bond Increase Rider and Updated Standby Trust Agreement (TAC No. M79548) ML14129A2742014-05-27027 May 2014 Dow Chemical Company - Change of Facility Backup Project Manager ML14100A3492014-04-0909 April 2014 the Dow Chemical Co., Submittal of Responses to RAI Letter Dated 03/06/2014 and Dtrr Revised Technical Specifications ML14133A0182014-03-0707 March 2014 Dow Chemical Company Surety Bond Increase Rider and Updated Standby Trust Agreement Schedules (TAC M79548) ML14070A1792014-03-0707 March 2014 Dow Triga Research Reactor - Annual Report - 2013 ML14058B1342014-03-0606 March 2014 Dow Chemical Company Request for Additional Information Regarding Renewal of Facility Operating License No. R-108 for Dow Chemical Triga Research Reactor IR 05000264/20132012013-09-27027 September 2013 IR 05000264-13-201 on August 26-29, 2013 at Dow Chemical Company - NRC Routine Inspection Report ML13261A0262013-09-16016 September 2013 Letter from Dow Chemical Company Regarding Transmittal of Documents in Support of License Renewal ML13226A0702013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13196A2992013-07-11011 July 2013 Dow Chemical Company Response to RAI Letter Dated June 26, 2013 and Dtrr Revised Technical Specifications ML13157A4122013-06-26026 June 2013 Dow Chemical Company - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-108 for the Dow Chemical Triga Research Reactor ML13113A0012013-05-0606 May 2013 Dow Chemical Company - Letter to Licensee Notification of Supplemental Federal Register for Environmental Assessment Waste Confidence Rule ML13059A4592013-02-27027 February 2013 Dow Triga Research Reactor Annual Report - 2012 2024-05-22
[Table view] |
Text
'*
The Dow Chemical Company Midland, Michigan 48667 February 24, 2017 Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555
Dear Sir:
Enclosed is the annual report for The Dow TRIGA Research Nuclear Reactor, Docket No. 50-264. If you have any questions, please contact me at (989) 638-6185.
Paul J. O'Connor Facility Director Dow TRIGA Research Reactor Enclosure CC: Geoff Wertz; USNRC Wayde Konze, 1897 Siaka Yusuf, 1602 Bryan Haskins, 1602 James Weldy, 1803
- Michael Buchmann, 1897 Paul O'Connor, 1897
DOW TRIGA RESEARCH REACTOR ANNUAL REPORT- 2016 There was one US NRC inspection in 2016 during which all aspects of the Dow TRIGA Research Reactor programs were examined. There were no violations found. The annual peer review audit was conducted by Mr. Joseph Talnagi of Ohio State University (Retired) in December of 2016. The audit also examined all aspects of the Dow TRIGA nuclear reactor facility programs and there were no safety concerns or non-compliances with US NRC requirements.
The regular in-house audits of the radiation protection program, safety and housekeeping, and ~ecords were also performed by the Dow Chemical Company Radiation Safety Officer and there were no issues found.
- There were no significant changes to the facility during 2016. There was, however, one Reactor Operation Committee member change towards the end of the year.
A. Staff, Licenses, and Training The current reactor staff members are:
P. J. O'Connor Facility Director S. 0. Yusuf Reactor Supervisor B. D. Haskins Assistant Reactor Supervisor B. B. Vanchura Trainee There are two Senior Reactor Operators and their operator licenses are current. Dr. Yusuf renewed his Senior Reactor Operator's license in 2012. Mr. Haskins renewed his Senior Reactor Operator's license also in 2012.
The annual re-qualification program was carried out according to the NRC approved program, dated September 6, 2011. All operators are up-to-date in their quarterly re-qualification participations, including operating experience, participation in emergency preparedness drills, Reactor Operation Committee meetings, operating examinations, and the annual fuel inventory.
Operation of the reactor is an important part of the training program, thus, the reactor is operated on an as-needed basis which results in numerous operations. Each operation involves reactivity manipulations, use of the control console, placement and retrieval of samples and handling of radioactive materials. The reactor was operated for a total of 244 hours0.00282 days <br />0.0678 hours <br />4.034392e-4 weeks <br />9.2842e-5 months <br /> in 2016 by the two Senior Reactor Operators.
DOW TRIGA RESEARCH REACTOR ANNUAL REPORT- 2016 The one membership change to the Reactor Operations Committee (ROC) in 2016 was due to retirement. The ROC is currently composed of the following staff members:
W. V. Konze ROC Chairman P. J. O'Connor Facility Director S. 0. Yusuf Reactor Supervisor J. R. Weldy Radiation Safety Officer M. E. Buchmann Process Analytical Global Leader Dr. Konze is the first level manager for the facility on behalf of Analytical Sciences and serves as the chairman for the ROC. Dr. O'Connor is the level 2 manager and the facility director. Dr. Yusuf is the level 3 manager and the reactor supervisor for the facility. Yusuf is the reactor operations staff member of the ROC. Mr. Weldy is the Dow Midland location Radiation Safety Officer as well as the TRIGA Radiation Safety Officer and reports through the Dow Environmental, Health and Safety department. Mr. M. E. Buchmann is a Process Analytical Global Leader and reports through the Dow Global Process Analytical. Mr. Buchmann serve as the outside member, (neither a member of reactor operation nor a member of analytical sciences), of the ROC.
B. Reactor Operating Experience The reactor was operated for 1.204 Megawatt-days during 2016 for a total of 244 hours0.00282 days <br />0.0678 hours <br />4.034392e-4 weeks <br />9.2842e-5 months <br />.
Operational experience is being optimized as indicated by these numbers. The main purpose of operations at the Dow facility is to perform neutron activation analysis. About 5,543 samples were irradiated in 2016, down by 23% from 2015 numbers, and consistent with the number of licensed operators and focus.
C. Major Changes There were no changes made to the facility in 2016.
D. Unscheduled Shutdowns There were 14 unscheduled shutdowns (scrams) during 2016, slightly up from 2015 numbers. 13 of these scrams were due to a computer function, specifically, the DIS064 device which processes the signals into the DAC computer. Even though this is only an operational nuisance and rarely happens at steady power, the vendor has been requested to work on a solution to this situation.
- Page 2
DOW TRIGA RESEARCH REACTOR ANNUAL REPORT- 2016 E. Major Preventive and Corrective Maintenance of Safety Significance There was no maintenance which had safety significance, performed during 2016. There were however, 19 preventive and corrective maintenance items in 2016. These were related to replacements of water purification cartridges, adjustments on the NMlOOO safety channel, adjustments on the NPlOOO safety channel, Pneumatic tube blower valves, and Heat exchanger routine valves inspections.
F. Radioactive Effluents The only radioactive material normally released to the environment from the facility is argon-41.
This is produced from activation of the natural argon dissolved in the pool water and subsequently escapes from the pool into the reactor room and from there to the outside of the building. Ar-41 is also produced from the natural argon present in the air used to transport samples from a laboratory into a terminus in the core of the reactor.
Overall, any release, after dilution is estimated to be less than 25% of the allowed or recommended maximum concentration in 10CFR20.
G. .Radiation Exposures Radiation exposures received by facility personnel and visitors are monitored using film badges and thermolurninescent detectors. No persons have received exposures approaching 25% of those allowed or recommended in 10CFR20.
H. Outside Sampling and Monitoring There were no incidences requiring outside sampling or monitoring during the year 2016.
-=r~ A. '() l~~~
P. J. O'Com~r Facility Director Dow TRIGA Research Reactor February 24, 2017
- Page 3