ML17053A521

From kanterella
Jump to navigation Jump to search
Scheduling of Initial Operator License Examinations - Quad Cities Nuclear Power Station, Units 1 and 2
ML17053A521
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 02/22/2017
From: Robert Orlikowski
Operations Branch III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
Download: ML17053A521 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 February 22, 2017 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS -

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2

Dear Mr. Hanson:

We have received your corporate letter RS-17-015, dated January 25, 2017, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2016-09, Preparation and Scheduling of Operator Licensing Examinations. In these letters, you requested initial operator licensing examinations be scheduled for July 2018 and March 2020 at the Quad Cities Nuclear Power Station. In response, we have scheduled initial operator licensing examinations for the weeks of:

  • July 16 and 23, 2018, with an onsite validation date the week of June 18, 2018.
  • March 16 and 23, 2020, with an onsite validation date the week of February 17, 2020.

In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions and make arrangements to administer the examination at a mutually acceptable date.

We understand that your staff will develop the examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for 2 weeks. Please inform us if the number of candidates change for any examination as this will impact the examination schedule. Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.

A supplementary letter will be sent to the training department approximately 210 days prior to the examination informing the training manager of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.

B. Hanson This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 cc: Distribution via LISTSERV Edward J. Pannell, Training Manager

B. Hanson Letter to Bryan C. Hanson from Robert J. Orlikowski dated February 22, 2017

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS -

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 DISTRIBUTION:

Jeremy Bowen RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Nancy Salgado Colleen Schmidt ADAMS Accession Number: ML17053A521 OFFICE RIII RIII RIII RIII NAME RKWalton:jw ROrlikowski DATE 02/10/17 02/22/17 OFFICIAL RECORD COPY