ML17034A466

From kanterella
Jump to navigation Jump to search
Requalification Program Inspection - Peach Bottom Atomic Power Station, Units 2 and 3
ML17034A466
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 02/02/2017
From: Diane Jackson
Operations Branch I
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Jackson D
Shared Package
ML16210A443 List:
References
Download: ML17034A466 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 February 2, 2017 Mr. Bryan Hanson Senior Vice President, Exelon Generation, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.

Warrenville, IL 60555

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3

Dear Mr. Hanson:

In a telephone conversation on January 31, 2017, Mr. Brian Fuller, Senior Operations Engineer, and Ms. Julie McDonald, Senior Operations Instructor, made arrangements for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Peach Bottom Atomic Power Station, Units 2 and 3 facility. The inspection is planned for the week of February 27, 2017, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past two years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past two years on simulator performance problems; 3) an index or summary of simulator performance test results in the past two years; and 4) the examination schedule, sample plan, written examinations and operating test scheduled for the week of the inspection to the NRC by February 13, 2017. Ms.

McDonald has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C.

20503.

B. Hanson The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Brian Fuller at (610) 337-5077.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56 cc: Distribution via ListServ

B. Hanson Letter to Mr. Bryan C. Hanson from Mr. Donald E. Jackson.

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3, dated February 2, 2017 cc: Distribution via ListServ Distribution w/encl: (via E-mail)

DDorman, RA (R1ORAMAIL RESOURCE)

DLew, DRA (R1ORAMAIL RESOURCE)

MScott, DRP (R1DRPMAIL RESOURCE)

DPelton, DRP (R1DRPMAIL RESOURCE)

RLorson, DRS (R1DRSMAIL RESOURCE)

JYerokun, DRS (R1DRSMAIL RESOURCE)

DSchroeder, DRP JHeinly, DRP, SRI JBowen, RI, OEDO SBarber, DRP BSmith, DRP, RI BFuller, DRS Examiner, DRS ATurilin, DRP SSchmitt, DRP, AA DJackson, DRS Operations Branch Chief RidsNrrPMPeachBottom Resource N. L. Salgado, NRR/DIRS/IOLB RidsNrrDorlLpl1-2 Resource Distribution:

DRS Master Exam File (C. Bixler) (w/concurrences)

DOCUMENT NAME: G:\DRS\Operations Branch\FULLER\Requal FY17 Peach Bottom\PB Requal Notification.docx (ADAMS TEMPLATE NRR-079)

ADAMS PKG: ML16210A443 ADAMS ACCESSION NO.: ML17034A466 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME BFuller/DEJ for DEJackson/DEJ DATE 02/02/2017 02/02/2017 OFFICIAL RECORD COPY