ML17031A005

From kanterella
Jump to navigation Jump to search

Staff Review of Mitigation Strategies Assessment Report of the Impact of the Reevaluated Seismic Hazard Developed in Response to the March 12, 2012, 50.54(f) Letter (CAC Nos. MF7817 and MF7818)
ML17031A005
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/02/2017
From: Frankie Vega
Japan Lessons-Learned Division
To: Peters K
TEX Operations Company
Vega F, NRR/JLD 415-1617
References
CAC MF7817, CAC MF7818, EA-12-049
Download: ML17031A005 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 2, 2017 Mr. Ken J. Peters Senior Vice President and Chief Nuclear Officer Attention : Regulatory Affairs TEX Operations Company LLC P.O. Box 1002 Glen Rose, TX 76043

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2- STAFF REVIEW OF MITIGATION STRATEGIES ASSESSMENT REPORT OF THE IMPACT OF THE REEVALUATED SEISMIC HAZARD DEVELOPED IN RESPONSE TO THE MARCH 12, 2012, 50.54(f) LETTER (CAC NOS. MF7817 AND MF7818)

Dear Mr. Peters:

The purpose of this letter is to provide the U.S. Nuclear Regulatory Commission's (NRC's) assessment of the seismic hazard mitigation strategies assessment (MSA), as described in a January 26, 2017, letter (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML17030A044) submitted by TEX Operations Company LLC (the licensee),

doing business as Luminant Power, for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Comanche Peak). The MSA confirms that the licensee has adequately addressed the reevaluated seismic hazard within its mitigating strategies for beyond-design-basis external events.

BACKGROUND By letter dated March 12, 2012 (ADAMS Accession No. ML12053A340), the NRC issued a request for information pursuant to Title 1O of the Code of Federal Regulations (1 O CFR),

Section 50.54(f) (hereafter referred to as the 50.54(f) letter). The 50.54(f) letter was issued as part of implementing lessons learned from the accident at the Fukushima Dai-ichi nuclear power plant. Enclosure 1 to the 50.54(f) letter requested licensees reevaluate the seismic hazard using present-day methodologies and guidance. Concurrent with the reevaluation of seismic hazards, the NRC issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML12054A736). The order requires holders of operating power reactor licenses and construction permits issued under 10 CFR Part 50 to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling following a beyond-design-basis external event.

K. Peters By letter dated March 27, 2014 (ADAMS Accession No. ML14099A197), the licensee provided its reevaluated seismic hazard for Comanche Peak in response to the 50.54(f) letter.

On December 1O, 2015 (ADAMS Accession No. ML16005A621 ), the Nuclear Energy Institute (NEI) submitted Revision 2 to NEI 12-06, including guidance for MSAs regarding reevaluated hazard information . The NRC subsequently endorsed NEI 12-06, Revision 2, with exceptions, clarifications , and additions, in Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2012-01 , Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML15357A163).

MITIGATION STRATEGIES ASSESSMENT By letter dated January 22, 2016 (ADAMS Accession No. ML16014A125), the NRC staff documented its review of the licensee's reevaluated seismic hazard, also referred to as the mitigating strategies seismic hazard information. The staff confirmed the licensee's conclusion that its reevaluated seismic hazard is bounded by the current design basis at all frequencies above 1 Hertz (Hz). In addition, the staff concluded that the ground motion response spectrum determined by the licensee adequately characterizes the reevaluated seismic hazard for the Comanche Peak site.

Appendix H of NEI 12-06, Revision 2, describes acceptable methods for demonstrating that the reevaluated seismic hazard is addressed within the Comanche Peak mitigating strategies for beyond-design-basis external events. The licensee stated that the Comanche Peak MSA was performed consistent with NEI 12-06, Revision 2. The NRC staff confirmed that the licensee's seismic hazard MSA is consistent with the guidance in Appendix H.4.1 of NEI 12-06, Revision 2, as endorsed by JLD-ISG-2012-01 , Revision 1. Therefore , the methodology used by the licensee is appropriate to perform an assessment of the mitigation strategies that addresses the reevaluated seismic hazard.

The NRC staff has reviewed the seismic hazard MSA for Comanche Peak. The NRC staff concludes that sufficient information has been provided to demonstrate that the licensee's plans for the development and implementation of guidance and strategies under Order EA-12-049 appropriately address the reevaluated seismic hazard information stemming from the 50.54(f) letter.

K. Peters If you have any questions, please contact me at (301) 415-1617 or via e-mail at Frankie.Vega@nrc.gov.

Sincerely, Frank1:.:z::ager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc : Distribution via Listserv

ML17031A005 *via e-mail OFFICE NRR/JLD/JHMB/PM NRR/JLD/LA NRR/JLD/JHMB/BC(A) NRR/JLD/J HMB/PM NAME FVega Slent GBowman FVega DATE 02/01 /2017 01 /31 /2017 02/02/2017 02/02/2017