MONTHYEARML24010A0032024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24026A0532024-01-30030 January 2024 Notification of an NRC Fire Protection Team Inspection- (Report 05000348/2024011, 05000364/2024011) and Request for Information IR 05000348/20230402024-01-24024 January 2024 95001 Supplemental Inspection Report 05000348/2023040 and Follow-Up Assessment Letter ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) NL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23346A2222023-12-22022 December 2023 Transmittal of Dam Inspection Report - Public NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23228A1432023-11-22022 November 2023 Issuance of Amendment Nos. 249 and 246 to Revise TS 3.6.3, Surveillance Requirement 3.6.3.5 to Eliminate Event-Based Testing of Containment Purge Valves with Resilient Seals NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection ML23318A0672023-10-31031 October 2023 1 to Updated Final Safety Analysis Report, Updated NFPA 805 Fire Protection Program Design Basis Document, Technical Specification Bases Changes, Technical Requirements Manual Changes, IR 05000348/20230032023-10-24024 October 2023 Integrated Inspection Report 05000348/2023003 and 05000364/2023003 IR 05000348/20230912023-10-19019 October 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter NRC Inspection Report 05000348/2023091 IR 05000348/20234022023-10-18018 October 2023 Security Baseline Inspection Report 05000348/2023402 and 05000364/2023402 IR 05000348/20234412023-10-12012 October 2023 Supplemental Inspection Report 05000348/2023441 and 05000364/2023441 and Follow-Up Assessment Letter (Cover Letter) ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000348/20230902023-08-31031 August 2023 NRC Inspection Report 05000348/2023090 and Preliminary White Finding and Apparent Violation ML23164A1202023-08-30030 August 2023 Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0, to the Requirements of the ASME Code ML23240A0012023-08-30030 August 2023 Correction to Issuance of Amendment Nos. 241, 242, 243, and 244 ML23235A2962023-08-24024 August 2023 Issuance of Amendment Nos. 247 and 244, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, (EPID L-2023-LLA-0116) (Emergency Circumstances) NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit IR 05000348/20330012023-08-14014 August 2023 NRC Operator License Examination Report 05000348/203301 and 05000364/2023302 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal IR 05000348/20230022023-08-10010 August 2023 Integrated Inspection Report 05000348/2023002 and 05000364/2023002, and Apparent Violation ML23221A3062023-08-0909 August 2023 Notification of NRC Supplemental Inspection (95002) and Request for Information (Cover Letter) NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications ML23136B1542023-07-0303 July 2023 Issuance of Amendment Nos. 246 & 243, Regarding License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated Spent Fuel Pool (SFP) Criticality Analysis IR 05000348/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal ML23164A2182023-06-14014 June 2023 Draft Safety Evaluation for License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated SFP Criticality Analysis (EPID L-2022-LLA-0138) - Letter NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 IR 05000348/20234402023-05-0505 May 2023 Reissue Farley Units-Final Significance Determination for a Security-Related Greater than Green Finding, Nov and Assessment Followup LTR, IR 05000348/2023440 and 05000364/2023440 - Cover IR 05000348/20230012023-05-0404 May 2023 Integrated Inspection Report 05000348/2023001 and 05000364/2023001 NL-23-0295, Reply to a Notice of Violation; EA-22-1012023-05-0101 May 2023 Reply to a Notice of Violation; EA-22-101 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 2024-01-30
[Table view] |
See also: IR 05000348/2017007
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
January 27, 2017
Mrs. Cheryl A. Gayheart
Vice President
Southern Nuclear Operating Co., Inc.
Joseph M. Farley Nuclear Plant
7388 North State Highway 95
Columbia, AL 36319
SUBJECT: NOTIFICATION OF JOSEPH M. FARLEY NUCLEAR PLANT DESIGN BASES
ASSURANCE INSPECTION - U.S. NUCLEAR REGULATORY COMMISSION
INSPECTION REPORT 05000348/2017007 AND 05000364/2017007
Dear Mrs. Gayheart:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a Design Basis Assurance Inspection (DBAI) at your Joseph M.
Farley Nuclear Plant during the weeks of May 1-5, and May 15-19, 2017. Mr. Marcus Riley, a
Reactor Inspector, will lead the inspection team. The inspection will be conducted in
accordance with Inspection Procedure 71111.21M, Design Bases Assurance Inspection
(Teams), dated December 8, 2016 (ADAMS ML16238A320).
The inspection will evaluate the capability of components that have been modified and risk-
significant/low-margin components to function as designed and to support proper system
operation. The inspection will also include a review of selected operator actions, operating
experience, and modifications.
During a telephone conversation on January 23, 2017, with Ms. Julie Collier, we confirmed
arrangements for an information-gathering site visit and the two-week onsite inspection. The
schedule is as follows:
- Information-gathering visit: Week of April 10-14, 2017
- Onsite weeks: Weeks of May 1-5, and May 15-19, 2017
The purpose of the information-gathering visit is to meet with members of your staff to identify
components that have been modified, risk-significant components and operator actions.
Information and documentation needed to support the inspection will also be identified. Mr.
George MacDonald, a Region II Senior Risk Analyst, will support Mr. Riley during the
information-gathering visit to review probabilistic risk assessment data and identify components
to be examined during the inspection. Additionally, during the onsite weeks, time may be
needed on the plant-referenced simulator in order to facilitate the development of operator
action-based scenarios.
C. Gayheart 2
The enclosure lists documents that will be needed prior to the information-gathering visit.
Please provide the referenced information to the Region II Office by Monday, March 27, 2017.
Additional documents will be requested following the information-gathering visit. The inspectors
will try to minimize your administrative burden by specifically identifying only those documents
required for inspection preparation. The additional information will be needed in the Region II
office by Friday, April 21, 2017, to support the inspection teams preparation week. During the
information-gathering trip, Mr. Riley will also discuss the following inspection support
administrative details: (1) availability of knowledgeable plant engineering and licensing
personnel to serve as points of contact during the inspection; (2) method of tracking inspector
requests during the inspection; (3) licensee computer access; (4) working space; (5)
arrangements for site access; and (6) other applicable information.
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections,
Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter
and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's
Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible
from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic
Reading Room).
Thank you for your cooperation in this matter. If you have any questions, regarding the
information requested or the inspection, please contact Mr. Riley at 404-997-4888 or contact me
at 404-997-4607.
Sincerely,
/RA/
Jonathan H. Bartley, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-348, 50-364
License Nos.: NPF-2, NPF-8
Enclosure:
Information Request for Joseph M. Farley Nuclear Plant,
Design Basis Assurance Inspection (Teams)
cc: Distribution via Listserv
______________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS RII:DRS
SIGNATURE MAR JHB1
NAME M. RILEY J. BARTLEY
DATE 1/23/17 1/27/2017
E-MAIL COPY? YES NO YES NO
INFORMATION REQUEST FOR JOSEPH M. FARLEY NUCLEAR PLANT
DESIGN BASES ASSURANCE INSPECTION (TEAMS)
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CDROM (or FTP site, SharePoint, etc.). The CDROM (or website) should be indexed and
hyperlinked to facilitate ease of use. The requested items below, identified with an asterisk (*),
should have a date range from December 1, 2013, until present.
1. *List and brief description of safety-related structures, systems, or components (SSCs)
design modifications implemented
2. From your most recent probabilistic safety analysis (PSA) excluding external events and
fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by Risk
Achievement Worth (RAW), and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
c. A list of the top 500 LERF contributors
3. From your most recent PSA including external events and fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW,
and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
4. Risk ranking of operator actions from your site-specific PSA sorted by RAW and human
reliability worksheets for these items
5. List of time-critical operator actions with a brief description of each action
6. *List of components with low-design margins (i.e., pumps closest to the design limit for flow
or pressure, diesel generator close to design-required output, heat exchangers close to
rated design heat removal, and motor-operated valve risk-margin rankings, etc.) and
associated evaluations or calculations
7. *List and brief description of Root Cause Evaluations performed
8. *List and brief description of common-cause component failures that have occurred
9. List and brief description of equipment currently in degraded or nonconforming status as
described in NRC Inspection Manual Chapter 0326, issued December 3, 2015
10. *List and brief description of Operability Determinations and Functionality Assessments
11. *List and reason for equipment that has been classified in maintenance rule (a)(1) status
Enclosure
2
12. *List of equipment on the sites Station Equipment Reliability Issues List, including a
description of the reason(s) why each component is on that list, and summaries (if
available) of your plans to address the issue(s) along with dates added or removed from
the issues list
13. List of current operator work arounds/burdens
14. Copy of Updated Final Safety Analysis Report
15. Copy of Technical Specification(s)
16. Copy of Technical Specifications Bases
17. Copy of Technical Requirements Manual(s)
18. Copy of the Quality Assurance Program Manual
19. Copy of Corrective Action Program Procedure(s)
20. Copy of Operability Determination Procedure(s)
21. List of motor operated valves and air operated valves in the valve program, and their
associated design margin and risk ranking
22. Primary AC and DC calculations for safety-related buses
23. One-line diagram of electrical plant (Electronic only)
24. Index and legend for electrical plant one-line diagrams
25. Piping and instrumentation diagrams (P&IDs) for safety-related systems (Electronic only)
26. Index and legend for P&IDs
27. Index (procedure number, title, and current revision) of station Emergency Operating
Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures
28. Copies of corrective action documents generated from previous CDBI
29. Copy of any self-assessments performed, and corrective action documents generated, in
preparation for current DBAI
30. Contact information for a person to discuss PSA information prior to and during the
information-gathering trip (Name, title, phone number, and e-mail address)