MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARIR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23279A2082023-10-0505 October 2023 Issuance of Formal RAIs - Vogtle, Units 1 and 2 - Proposed LAR and Proposed Alternative Request to Revise TS 3.4.14.1 and IST ALT-VR-02 (EPIDs L-2023-LLA-0061 and L-2023-LLR-0023) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23248A3482023-09-0505 September 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 6 - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23188A1512023-08-0909 August 2023 Round 2 RAIs for LAR 22-002 TS 3.8.3 Inverters-Operating, Completion Time Extension ML23200A0112023-07-18018 July 2023 Document Request for Vogtle Unit 3 RP Inspection ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23193A7832023-07-12012 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23065A0612023-03-0303 March 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 14 - Vogtle - AST, TSTF-51, TSTF-471, and TSTF-490 LAR (L-2022-LLA-0096) ML23006A0882023-01-0606 January 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle - Accident Source Term (Ast), TSTF-51, TSTF-471, and TSTF-490 LAR (L-2022-LLA-0096) ML22348A0332022-12-13013 December 2022 NRR E-mail Capture - for Your Action - RAI - Vogtle, Unit 2 - Steam Generator Tube Inspection Report (L-2022-LRO-0120) ML22192A1042022-08-0101 August 2022 Acceptance of Requested Licensing Action Amendment Request Application to Allow Use of Lead Test Assemblies for Accident Tolerant Fuel with Request for Additional Information ML22157A0902022-06-0606 June 2022 NRR E-mail Capture - RAIs - Vogtle, Unit 1 - Refueling Outage (RFO) 1R23 Steam Generator (SG) Tube Inspection Report ML22104A1312022-04-14014 April 2022 NRR E-mail Capture - Request for Additional Information - Farley and Vogtle - Relocate Piping Inspection License Amendment Request (L-2021-LLA-0235) ML22026A3942022-01-26026 January 2022 NRR E-mail Capture - Request for Additional Information - Vogtle, Units 1 and 2, TS 3.7.2 LAR ML21350A1032021-12-16016 December 2021 NRR E-mail Capture - Request for Additional Information - Vogtle, Units 1 and 2, TS 3.7.2 LAR ML21321A3762021-11-15015 November 2021 NRR E-mail Capture - Request for Additional Information - Vogtle, Units 1 and 2, TS 3.7.2 LAR ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21033B1072021-02-0202 February 2021 NRR E-mail Capture - RAI - Vogtle Unit 1 - SG Report (L-2020-LRO-0059) ML20338A1512020-12-0303 December 2020 NRR E-mail Capture - RAIs for Vogtle GSI-191 LAR (L-2020-LLA-0182) ML20325A0432020-11-20020 November 2020 NRR E-mail Capture - for Your Review - Draft RAIs for Vogtle GSI-191 LAR (L-2020-LLA-0182) ML20297A3052020-10-22022 October 2020 NRR E-mail Capture - RAIs for Vogtle Relief Request - EPRI Report (L-2020-LLR-0109) ML20293A0752020-10-14014 October 2020 NRR E-mail Capture - RAIs for SNC Fleet EP LAR (L-2020-LLA-0150 and L-2020-LLA-0151) ML20149K6252020-05-27027 May 2020 NRR E-mail Capture - RAIs for SNC Fleet Fire Protection Exemption Requests ML19263A6432019-09-19019 September 2019 NRR E-mail Capture - RAI - Vogtle End State License Amendment Request (LAR) to Revise the Technical Specifications (Tss) for Vogtle, Units 1 and 2 (L-2019-LLA-0148) ML19156A1872019-06-0505 June 2019 NRR E-mail Capture - Request for Additional Information (RAI) for Vogtle Unit 2 Core Operating Limits Report, Cycle 21 ML19105B1632019-04-15015 April 2019 NRR E-mail Capture - Request for Additional Information (RAI) for Voglte TSTF-412 Adoption LAR (L-2018-LLA-0731) ML18355A4772019-01-0404 January 2019 Request for Additional Information Revise TS 5.2.2.g and Update Emergency Plan Minimum On-Shift Staff Tables ML18337A4032018-12-0606 December 2018 Request for Additional Information Revise Technical Specification 5.2.2.G and Updating Emergency Plan Minimum On-Shift Staff Tables ML18236A4452018-08-30030 August 2018 Review of Response to RAI License Amendment Request for Approval to Utilize the Tornado Missile Risk Evaluator to Analyze Tornado Missile Protection Non-Conformances ML18227A0222018-08-15015 August 2018 Notification of Inspection and Request for Information ML18225A3362018-08-13013 August 2018 NRR E-mail Capture - Request for Additional Information Regarding Relief Request VEGP-ISI-RR-03 ML18197A0602018-07-13013 July 2018 Us NRC Final RAI No. 1 for Vogtle 3 and 4 LAR-18-015, Fire Protection System Non-Safety Cable Spray Removal ML18197A1882018-07-13013 July 2018 Us NRC Final Request for Additional Information (Final RAI) No. 4 on Vogtle LAR-17-024, Technical Specification Updates for Reactivity Controls and Other Miscellaneous Changes ML18197A1052018-07-13013 July 2018 Us NRC Final Request for Additional Information (Final RAI) No. 1 on Vogtle 3 and 4 LAR-17-043, Containment Pressure Analysis ML18192C0782018-07-11011 July 2018 RAI (LAR 18-009) - Vogtle Electric Generating Plant, Unit 3 and 4 ML18192B7692018-07-11011 July 2018 Us NRC Draft Request for Additional Information (Draft RAI) No. 4 on Vogtle LAR-17-024, Technical Specification Updates for Reactivity Controls and Other Miscellaneous Changes ML18136A4972018-06-0101 June 2018 Request for Additional Information, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis ML18109A1152018-05-0101 May 2018 Request for Additional Information ML18079A9572018-03-28028 March 2018 Request for Additional Information Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process (CAC Nos. MF9861 and MF9862; EPID L-2017-LLA-0248) ML18058A0812018-02-27027 February 2018 Enclosurequest for Additional Information(Rai for Review of Southern Nuclear Operating Company'S Decommissioning Funding Plan Updates for Joseph M. Farley,Unit 1 and 2;Edwin I. Hatch,Units 1 and 2; and Vogtle Electric Generating Plant, Unit ML18030B0622018-02-0808 February 2018 Request for Additional Information Reverse Technical Specification 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (CAC Nos. MG0240, MG0241; EPID L-2017-LLA-0295) ML17355A1012018-01-11011 January 2018 Request for Additional Information (CAC Nos. MF9685 and MF9686; EPID L-2017-TOP-0038) ML17354A7822018-01-0505 January 2018 Request for Additional Information Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process (CAC Nos. MF9861 and MF9862; EPID L-2017-LLA-0248) ML17318A0352017-11-22022 November 2017 Request for Additional Information 2024-01-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 23, 2017 Mr. Brian K. Taber Site Vice President Southern Nuclear Operating Company, Inc.
Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT - EMERGENCY PREPAREDNESS INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Taber:
From May 8-12, 2017, the U.S. Nuclear Regulatory Commission (NRC) will perform a baseline Emergency Preparedness program inspection at the Vogtle Electric Generating Plant. The inspection will evaluate activities in the Emergency Preparedness cornerstone using NRC Inspection Procedures (IPs) 71114.02, Alert and Notification System Evaluation; 71114.03, Emergency Response Organization Staffing and Augmentation System; 71114.04, Emergency Action Level and Emergency Plan Changes; 71114.05, Maintenance of Emergency Preparedness; and Emergency Preparedness sections of 71151 Performance Indicator Verification.
Experience has shown that this inspection is resource-intensive for both the NRC inspectors and your staff. To minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up-to-date, and complete, to minimize the number of additional documents requested during the preparation, and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff, and understand that our regulatory contact for this inspection will be Mr. Steve Brown (706-826-3792) of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Steven Sanchez at 404-997-4418 (steven.sanchez@nrc.gov), or the Chief, Plant Support Branch 1, Brian Bonser at 404-997-4653.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter, and its Enclosure, will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records(PARS)
B. Taber 2 component of NRC's Agencywide Documents Access and Management System (ADAMS);
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA: Wade T. Loo for/
Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-424 and 50-425 License Nos. NPF-68 and NPF-81
Enclosure:
Document Request List cc: Distribution via Listserv
B. Taber 2 component of NRC's Agencywide Documents Access and Management System (ADAMS);
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, RA: Wade T. Loo for/
Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-424 and 50-425 License Nos. NPF-68 and NPF-81
Enclosure:
Document Request List cc: Distribution via Listserv DISTRIBUTION:
S. Sandal, RII, DRP C. Rapp, RII, SR PE D. Mas-Peneranda, RII, PE E. Powell, RII, RIDP E. Coffman, RII, SRI A. Alen, RII, RI S. Price, RII, ORA/RC RIDSNRRDIRS Public PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE NON-SENSITIVE ADAMS: Yes ACCESSION NUMBER: SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS/PSB1 RII:DRS/PSB1 RII:DRS/PSB1 SIGNATURE JDH9 WTL FOR SPS WTL FOR BRB1 NAME J. Hickman S. Sanchez B. Bonser DATE 1/19/2017 1/ 23/2017 1/ 23 /2017 E-MAIL COPY YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\DRSII\PSB1\RFI INFORMATION REQUEST LETTERS\VOGTLE\2017\VOGTLE EP RFI 2017-001.DOCX
Document Request List Inspection Dates: May 8-12, 2017 Inspection Procedures (IPs): 71114.02 Alert and Notification System Evaluation 71114.03 Emergency Response Organization Staffing and Augmentation System 71114.04 Emergency Action Level and Emergency Plan Changes 71114.05 Maintenance of Emergency Preparedness 71151 Performance Indicator Verification Note: This is a list of the documents to be provided to the inspectors. The current version of these documents is expected unless specified otherwise. About 3 weeks prior to the inspection, provide, as a minimum, an electronic version of the Emergency Plan (E-Plan), 10 CFR 50.54(q) evaluation/screening packages of changed Emergency Action Level (EAL), E-Plan, and EP implementing procedures, and Corrective Action Program (CAP) entries relating to EP, for the 2-year inspection period (including those written by Corporate). The preferred file format is Word or searchable .pdf files on CDROM. [Note that the inspectors cannot accept data provided on USB or flash drives due to NRC IT security policies.] Please organize the information as it is arranged below (e.g., a folder labeled Miscellaneous). It is not the intent that large or burdensome data be scanned for this purpose (e.g., Performance Indicator documents). This data will be inspected using original documentation. Material can be provided prior to the inspection to the NRC Region II Office (ATTN: Steven Sanchez), 245 Peachtree Center Avenue, NE, Suite 1200, Atlanta, GA 30303-1257. If there are questions regarding the documents requested, please do not hesitate to contact the lead inspector.
71114.02 Alert and Notification System Evaluation Federal Emergency Management Agency (FEMA) approved Alert and Notification System (ANS) report and any currently associated correspondence ANS testing procedure ANS equipment technical manual ANS equipment testing results (raw data) for the 2-year inspection period ANS equipment maintenance records for the 2-year inspection period Changes to the ANS system, implementing procedures, testing procedures, and the maintenance program including any supporting FEMA approval letters for the past 2 years Information provided to the public inside the 10-mile plume exposure pathway CAP entries related to the ANS for the 2-year inspection period (including those written by Corporate) 71114.03 Emergency Response Organization Staffing and Augmentation System Current Emergency Response Organization (ERO) roster ERO Duty Roster in-effect during the week of the inspection (can be provided upon arrival)
ERO and augmentation implementing procedures and changes made over the past 2 years NUREG 0654 Table B1 site equivalent ERO training program procedure Emergency Preparedness (EP) staff training program and qualification records ERO augmentation testing results for the 2-year inspection period CAP entries related to ERO staffing and augmentation for the 2-year inspection period (including those written by Corporate)
Enclosure
2 71114.04 Emergency Action Level and Emergency Plan Changes Governing document for 10 CFR 50.54(q) evaluation process 10 CFR 50.54(q) evaluator training program and qualification records 10 CFR 50.54(q) evaluation/screening packages of changed Emergency Action Level (EAL),
E-Plan, and EP implementing procedures (including corporate procedures)
Current and immediately previous revisions of EAL, E-Plan, and EP procedures (electronic version of current E-Plan requested about 3 weeks before inspection)
CAP entries related to EAL and E-Plan changes since the last NRC EP inspection (including those written by Corporate) 71114.05 Maintenance of Emergency Preparedness Governing documents for the assessment process All EP program assessments, not including INPO performed assessments, for the 2-year inspection period 10 CFR 50.54(t) audits, audit checklists, and subsequent State/local correspondence for the 2-year inspection period Drill and exercise critiques for the 2-year inspection period Critiques of actual events resulting in implementation of the E-Plan over the past 2 years Governing documents for 10 CFR 50.54(q) evaluation process Emergency Response Facility (ERF) activation procedures, including backup and alternate facilities Completed maintenance records and availability-tracking information for equipment important to EP (e.g., Heating and Ventilation system in ERFs and Radiation Monitors called out in EALs, etc.) for the 2-year inspection period Last Evacuation Time Estimates Analysis and annual review documentation CAP governing procedures CAP entries relating to EP (abbreviated format, i.e., identifier and brief description only) for the 2-year inspection period with the risk-significant related entries separated (including those written by Corporate) 71151 Performance Indicator Verification Governing document for the performance indicator (PI) process Drill and Exercise Performance (DEP), ERO, and ANS PI data submitted since the last NRC EP inspection (hard copies can be provided upon arrival)
DEP documentation and evaluations since the last NRC EP inspection CAP entries related to PIs, that is DEP, ERO training and participation, and ANS since the last NRC EP inspection (including those written by Corporate)
Miscellaneous Procedures and Records Safety Evaluation Report approved E-Plan and EALs Corporate and Departmental processes or procedures for EP staff Matrix of Drill Types performed and accounted for during the 8-year cycle Lead Inspector Contact Information:
Steven Sanchez 404-997-4418 steven.sanchez@nrc.gov