ML16342B989

From kanterella
Jump to navigation Jump to search
Notification on 930712 Meeting W/Util in Rockville,Md Re Eagle 21 Reactor Protection Sys Upgrade & Diversity of ATWS Mitigation Actuation Circuitry for Plant
ML16342B989
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 06/29/1993
From: Peterson S
Office of Nuclear Reactor Regulation
To: Quay T
Office of Nuclear Reactor Regulation
References
NUDOCS 9307070203
Download: ML16342B989 (8)


Text

Docket Nos.

50-275 and 50-323 June 29, 1993 MEMORANDUM FOR:

Theodore R.

Quay, Director Project Directorate V

Division of Reactor Projects III/IV/V FROM:

SUBJECT:

DATE 8. TIME:

LOCATION:

PURPOSE:

Sheri R. Peterson, Project Manager Project Directorate V

Division of Reactor Projects III/IV/V MEETING WITH PACIFIC GAS AND ELECTRIC (PG&E)

Monday, July 12, 1993 1:00 pm 3:00 pm US NRC Headquarters One White Flint North 11555 Rockville Pike Room 12 B 11 Rockvi1 1 e, Haryl and 20852 To discuss the Eagle 21 reactor protection system upgrade and the diversity of the ATWS mitigation actuation circuitry for Diablo Canyon Units 1 and 2.

PARTI C IPANTS*:

NRC W. Russell J. Partlow A. Thadani J.

Roe E.

Adensam T.

Quay J.

Wermeil S. Peterson cc:

See next page PGKE W. Fujimoto, et al.

Original signed gy Sheri R. Peterson, Project Manager Project Directorate V

Division of Reactor Projects III/IV/V

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Re ister 28058, 6/28/78.

OFFICE PDV LA

~

PDV PH NAME DATE DFoster-Curseen 93 SPeterson:mc 0 21,93 uay 93 OFFICIAL RECORD COPY DOCUMENT NAME:. DCMTG7. 12

~so7o7o2os 9so~a9 PDR iaocK",osooo27s

~

I PDR J

C

': ygg (g

'i

gQ REQQ

~o v

+

Cy 4.

o )tp*y4 Docket Nos.

50-275 and 50-323 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 29, 1993 MEMORANDUM FOR:

Theodore R. quay, Director Project Directorate V

Division of Reactor Projects III/IV/V FROM:

SUBJECT:

DATE 5 TIME:

LOCATION:

PURPOSE:

Sheri R. Peterson, Project Manager Project Directorate V

Division of Reactor Projects III/IV/V MEETING WITH PACIFIC GAS AND ELECTRIC (PG8EE)

Monday, July 12, 1993 1:00 pm - 3:00 pm US NRC Headquarters One White Flint North 11555 Rockville Pike Room 12 B ll Rockville, Maryland 20852 To discuss the Eagle 21 reactor protection system upgrade and the diversity of the ATWS mitigation actuation circuitry for Diablo Canyon Units 1 and 2.

PARTIC IPANTS*:

NRC W. Russell J.

Partlow A. Thadani J.

Roe E.

Adensam T. quay J.

Wermeil S. Peterson cc:

See next page PGSE W. Fujimoto, et al.

p~. 9 Sheri R. Peterson, Project Manager Project Directorate V

Division of Reactor Projects III/IV/V

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy," 43 Federal Re ister 28058, 6/28/78.

Pacific Gas and Electric Company Diabl o Canyon

~

CC:

NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P. 0.

Box 369 Avila Beach, California 93424 Dr. Richard Ferguson, Energy Chair Sierra Club California 6715 Rocky Canyon Creston, California 93432 Hr. Steve Hsu Radiologic Health Branch State Department of Health Services Post Office Box 942732 Sacramento, California 94234 Regional Administrator, Region V

U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Hs.

Nancy Culver San Luis Obispo Mothers for Peace P. 0.

Box 164 Pismo Beach, California 93448 Hr. Peter H. Kaufman Deputy Attorney General State of California 110 West A Street, Suite 700 San Diego, California 92101 Hs. Jacquelyn C. Wheeler 3303 Barranca Court San Luis Obispo, California 93401 Hanaging Editor The County Telegram Tribune 1321 Johnson Avenue P. 0.

Box 112 San Luis Obispo, California 93406 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, California 93408 Hr. Truman Burns Hr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Rm.

4102 San Francisco, California 94102 Hr. Hark Urban Deputy Attorney General State of California 1515 K Street Sacramento, California 95814 Christopher J. Warner, Esq.

Pacific Gas 5 Electric Company Post Office Box 7442 San Francisco, California 94120 Hr. John Townsend Vice President and Plant Hanager Diablo Canyon Power Plant P.

O.

Box 56 Avila Beach, California 93424 Hr. Gregrory H. Rueger Nuclear Power Generation, B14A Pacific Gas and Electric Company 77 Beale Street, Room 1451 P.O.

Box 770000 San Francisco, California 94177 Diablo Canyon Independent Safety Committee ATTN:

Robert R. Wellington, Esq.

Legal Counsel 857 Cass Street, Suite 0

Honterey, California 93940

~

~

II C

,fA

June 29, 1993

'ISTRIBUTION Docket File NRC

& Local PDRs PD V Reading T. Hurley/F. Hiraglia, 12G18 J. Partlow, 12G18 J.

Roe E.

Adensam T. quay S.

Peterson D. Foster-Curseen A. Chaffee, llAl

OGC, 15B18 E. Jordan, HNBB3701 E. Rossi 9A2 Receptionist, OWFN W. Russell, 12G18 J. Partlow, 12G18 A. Thadani, 8E2 J. Wermeil, 8D24 ACRS (10),

P315

OPA, 2G5 NRR Hailroom, 12G18 P. O'Dell, 12E4 G. Zech, 10A19 J. Hitchell, 17G21 K. Perkins, RV G. Cook, Region V

A 14