Text
Docket No. 50-323 JAN 2 4 1285 MEMORANDUM FOR:
Dennis Kirsch, Acting Director Division of Reactors Safety and Projects, Region V
FROM:
SUBJECT:
Darrell G. Eisenhut, Director Division of Licensing REQUEST FOR SELECTED INSPECTIONS/AUDITS AND SSER INPUT DIABLO CANYON UNIT 2 We request that you conduct the specific inspections/audits listed in the enclosure and provide us with the results.
Some of the matters have been previously identified to you or your staff by Hans Schierling.
The information is needed to close out certain activities in a safety evaluation in preparation for issuance of a license for Unit 2.
We request you provide the information by January 31, 1985 (draft is acceptable).
If you have any questions please call Hans Schierling.
Enclosure:
As stated
, DISTRIBUTION
~L
.-33=.373/333 PRC System LB¹3 Reading JLee HSchierling LChandler, OELD JPKnight JWermiel FCoffman RHeishman CLiang PTKuo CGrimes Original signeg hy Darrell G. zi eq Darrell G. Eisenhuf -EI)hector Division of Licensing I +~+8 CI DL:LB¹3 D
-B¹3 HSchierl'yt G
ighton 1/ $ 85 1/I J/85
~L
/L T
ovak 1/g/85 6'ut 1
85
P rl lh II I
ll '
1 t
N r>"
'4 e
I
>II '
Enclosure Request for Selected Inspections/Audits 1.
Design Verification and Modification
Reference:
1.
PGSE letter November 2, 1984 DCL-84-344 2.
PG8E letter December 7,
1984 OCL-84-378 Audit the following IRP packages as described in the reference and inspect the associated modifications:
1.
2-0034:
CCW System Reference 1 and 2
2.
2-1088:
CCW System Reference 1
3.
2-8010:
AFW Turbine Reference 1
2.
RHR System Low Flow Alarm
Reference:
SSER 26 Alleqation 39 and 45 PGSE letter September 5,
1984 DLC 84-301 PGSE letter January 11, 1985 OLC 85-012 Verify the installation of the RHR low flow alarm for Unit 2 as you did for Unit 1
~
3.
Seismically Induced Systems Interaction Program (SISIP)
Reference:
SSER 26 Allegation 48 Reqion V Inspection Report 50-275/84-09 Telecon H. Schierling/T.
Corwley January 15, 1985 Determine the status of the four issues identified in the reference inspection report.
Audit selected SISIP packages at the OCP offices and determine the status of modifications.
4.
equality Assurance Program and Implementation
Reference:
Telecon K. Schierling/D.
Kirsch January 14, 1985 Transcript of Hearing November 18, 1983 SSER 18 Section 2 and 5.2 Memo O.
G. Eisenhut/Division Directors, January ll, 1985 Review references, in particular Region V related matters.
Identify any audits/inspections on design and construction gA program and implementation for Diablo Canyon, particular ly Unit 2.
Provide input on gA for SSER on design verification as appropriate for Region V.
1%
'E