Notification of 990602 Meeting with Util in Arlington,Tx to Discuss Electrical Configuration Planned for Refueling Outage 2R9 During Operation at Midloop
ML16342A787
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/14/1999
From: Brockman K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
NUDOCS 9905260343
Download: ML16342A787 (10)


Text

gyral AQC(

C~

Pp o0

~

e vk

+n

~O UNITEDSTATES NUCLEAR REGULATORYCOMMISSION REGION IV 611 RYAN PLAZADRIVE, SUITE 400 ARLINGTON,TEXAS 76011%064 MAY

) 4 $99 NOTICE OF LICENSEE MEETING Name of Licensee:

Name of Facility:

Docket:

Date and Time of Meeting:

Location of Meeting:

Purpose of Meeting:

NRC Attendees:

Licensee Attendees:

Pacific Gas & Electric Company Diablo Canyon Power Plant 50-275; 50-323 June 2, 1999 8-9:30 a.m. (CDT)

Region IV Executive Conference Room 611 Ryan Plaza Dr. Suite 400 Arlington, Texas Discuss electrical configuration planned for Refueling Outage 2R9 during operation at midloop Ken Brockman, Director, Division of Reactor Projects (DRP)

Linda Smith, Chief, Project Branch E, DRP BillJones, Senior Reactor Analyst, Division of Reactor Safety Greg Pick, Senior Project Engineer, Project, Branch E, DRP David Proulx, Senior Resident Inspector, Project Branch E, DRP Bill Garrett, Director, Operations Mike Norem, Director, Unit 2 Outage Gene Newman, Shift Foreman, Operations Ken Bych, Supervisor, Probalistic Risk Assessment Pat Nugent, Licensing Supervisor, Regulatory Services NOTE:

(1)

This meeting is open to attendance by members of the general public.

(2)

NRC personnel, not listed above, that desire to attend this meeting should notify Linda Smith at (817) 860-8137 by COB on May 27, 1999.

Approved By:

Ken E. Brockman, Director Division of Reactor Projects 9905260343 9905%4 PDR ADOCK 05000275 PDR

)'l

Pacific Gas 8 Electric Company CC:

Gregory M. Rueger, Senior Vice President and General Manager Nuclear Power Generation Bus. Unit Pacific Gas and Electric Company Nuclear Power Generation, B32 77 Beale Street, 32nd Floor P.O. Box 770000 San Francisco, California 94177 Dr. Richard Ferguson Energy Chair Sierra Club California 1100 lith Street, Suite 311 Sacramento, California 95814 Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, California 93448 Chairman San Luis Obispo County Board of Supervisors

- Room 370 County Government Center San Luis Obispo, California 93408 Mr. Truman Bump)!r. Robert Kinosian California Public Utilities Commission 505 Van Ness, Rm. 41 02 San Francisco, California 94102 Robert R. Wellington, Esq.

Legal Counsel Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, California 93940 Mr. Steve Hsu Radiologic Health Branch State Department of Health Services P.O. Box 942732 Sacramento, California 94234

Pacific Gas 8 Electric Company Christopher J. Warner, Esq.

Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 David H. Oatley, Vice President Diablo Canyon Operations and Plant Manager Diablo Canyon Nuclear Power Plant P.O. Box 3 Avila Beach, California 93424 Managing Editor Telegram-Tribune 1321 Johnson Avenue P.O. Box 112 San Luis Obispo, California 93406

Pacific Gas & Electric Company MAY I 4 l999 E-Mail To:

(

)

PMNS PAB FJM BWS BAB2 "SDB1 OEMAIL DLP CAH GFS BWH JAC1, CJG LAT, DLF, LJB1 CLG, LMB, NLH CMS, WSW PDP LPL FOR NRC Attendees Mtg Announcement Coordinator DEDR A/D/NRR Acting, ADT/NRR Acting ADP/NRR S. Bloom, Project Manager, NRR D/OE Senior Resident Inspector C. A. Hackney, RSLO G. F. Sanborn, EO B. Henderson, PAO RA Secretaries DRP Division DRS Division DNMS Division Dean Papa P. Longdo cc:

DMB (IE 45)

OEDO RIV Coordinator (16E15)

ORA File RIV File DOCUMENT NAME: R:+DC>DC6-2MN.DRP To receive co of document, Indicate In box: "C" ~ Co vithout enclosures E" ~ Co with enclosures "N = No co RIV:SPE:D P/E GAPic 05/tV99 C:DRP/E LJSmlth 05/989 RSLO Ctg PAO BWHenderson CAHackne 05$

99 05 99 OFFICIALRECORD COPY D:DRP KEBrockma 05/H99

Pacific Gas & Electric Company MAY I 4 l999 E-Mail To:

(

)

PMNS PAB FJM BWS BAB2 SDB1 OEMAIL DLP CAH

'FS BWH JAC1, CJG LAT, DLF, LJB1 CLG, LMB, NLH CMS, WSW PDP LPL cc:

FOR NRC Attendees Mtg Announcement Coordinator DEDR A/D/NRR Acting, ADT/NRR Acting ADP/NRR S. Bloom, Project Manager, NRR D/OE Senior Resident Inspector C. A. Hackney, RSLO G. F. Sanborn, EO B. Henderson, PAO RA Secretaries DRP Division DRS Division DNMS Division Dean Papa P. Longdo OEDO RIV Coordinator (1 6E15)

ORA File RIV File DOCUMENT NAME: R:+DC>DC6-2MN.DRP To receive co of document, indicate in boxt "C" ~ Co without enctosures E ~ Co with enctosures N ~ No co RIV:SPE:D P/E C:DRP/E PAO RSLO D:DRP GAPic 05/i',

LJSmith 05/At99 KEBrockma 05 99 05/H99 05$

99 OFFICIALRECORD COPY BWHenderson CAHackne

L