ML16342A113
| ML16342A113 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 05/13/1993 |
| From: | Brewer R, Coblentz L, Reese J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML16342A114 | List: |
| References | |
| 50-275-93-11, 50-323-93-11, NUDOCS 9306010230 | |
| Download: ML16342A113 (36) | |
See also: IR 05000275/1993011
Text
U. S.
NUCLEAR REGULATORY CONHISSION
REGION V
EA Number:
Report:
Licenses:
Licensee:
Facility:
Inspection Location:
Onsite Inspection:
93-107
50-275/93-11
and 50-323/93-11
and
Pacific
Gas
and Electric Company
(PGKE)
77 Beale Street
San Francisco,
94106
Diablo Canyon
Power Plant
(DCPP), Units
1 and
2
San Luis Obispo Country, California
April 5 9,
1993
In-Office Inspection:
April 12 - 28,
1993
Inspected
by:
Brew r,
Ra sat>on
Spec>a
>st
s- iz- ps
ate
S>gne
Approved by:
~Summa':
entz,
Sens r
sat>on
pecia est
me
.
Reese,
i
h
Faci ities Radiological Protection
Branc
5 -/5- r9
ate
sgne
s-8-B
ate
~gne
Areas
Ins ected:
Routine,
unannounced
inspection of a followup item
(regarding
the post-accident
sampling
system)
and occupational
exposure
controls.
Inspection
Procedures
83750,
83729,
84750,
and
92701
were used.
Results:
The licensee's
programs for controlling occupational
exposure,
in
the aspects
reviewed,
were adequate
in meeting the licensee's
safety
objectives.
One violation was identified, regarding four instances
of failure
to implement required controls for entry into posted
In addition, three
apparent violations were noted relating to aspects
of the
licensee's
post-accident
sampling
system:
(1) the licensee failed to
implement
and maintain
a program (per Technical Specification 6.8.4) that
ensured
the capability to obtain
and analyze reactor coolant
samples
for
dissolved
under accident conditions;
(2) the licensee
discontinued
procedures,
training,
and calibration of the
SENTRY gas
chromatograph
for
dissolved reactor coolant
hydrogen analysis,
and failed to perform
a written
safety analysis
(per
10 CFR 50.59) of this change;
and
(3) the licensee failed
to implement
and maintain
a program (per-Technical
Specification 6.8.4) that
ensured
the capability to obtain
and analyze
samples of radioiodines
and
particulates
in plant gaseous effluents
under accident conditions.
93060i 0230 9305i 3
ADOCK 05000275
0
DETAILS
Persons
Contacted
Licensee
Baxter,
Chemistry Instructor
Boots, Director, Chemistry
Bosseloo,
Instrumentation
and Control
(I&C) Lea
Project Engineering
Group
Carlsen,
Engineer,
Regulatory
Compliance
Ehrhardt,
Engineer,
Radiation Protection
(RP)
Fong,
Engineer,
Gardner,
Senior Engineer,
Chemistry
Gray, Director,
(RPH)
Grebel,
Supervisor,
Regulatory Compliance
Helman,
ALARA Engineer
Hess, Assistant Onsite Project Engineer
Irving, General
Foreman,
Hiklush, Hanager,
Operations
Services
Holden, Director,
Houlin, Assistant to Vice President
Mosher,
Engineer,
guality Assurance
(gA)
Rising, Auditor, gA
Snyder,
Senior Chemistry Instructor
Somerville,
Senior Engineer,
Taylor, Senior Engineer
Thierry, Senior
Engineer,
Regulatory Compliance
Wessel,
Engineer,
Chemistry
- p
- tJ
- F
d Engineer,
Onsite
- tE.
- S
H.,
tJ.
- R
T-.
C.
- R
- T
- tD.
+J
- T
- H
- W.
- R.
H.
tA.
- tR.
- tE
HRC
F.
Gee,
Resident
Inspector
H. Hiller, Senior Resident
Inspector
(t) Denotes
those individuals who participated in the teleconference
calls
on April 29 and 30,
1993.
Occu ational
Ex osure
83750
83729
(*) Denotes
those individuals who attended
the exit meeting
on April 9,
1993.
The inspector
met
and held discussions
with additional
members of
.the licensee's
staff during the onsite inspection.
At the time of the inspection,
Unit 2 was in
a refueling outage
(2R5).
The inspectors
examined this program area
by performing tours
and
independent
surveys of the facility, observing work in progress,
reviewing procedures
and records,
and interviewing cognizant personnel.
Observations
were
made regarding radiological posting
and labeli'ng,
surveys
and monitoring,
and control of posted
a.
Radiolo ical Postin
and Labelin
While conducting tours of the Auxiliary Building, Containment
Building, and various other areas within the licensee's
Protected
Area (PA), the inspectors
observed
and verified the licensee's
radiological posting
and labeling.
For those
areas
observed,
radioactive material labels,
as well as postings for radiation,
high
radiation,
and radioactive materials
areas,
were visible, accurate,
and current.
b.
Surve
s
and Monitorin
The inspectors
examined the licensee's
surveys,
survey logs,
and
instrument
issue logs.
In addition,
one inspector
accompanied
a
contract
RP technician
(RPT)
on
a routine survey of the Unit I PA,
Warehouse
A, and the
I&C instrument calibration facility.
The following licensee
procedures
were reviewed in assessing
the
licensee's
program implementation:
~
RCS-7,
"Radiation Control Standard - Surveys,"
Revision
6
~
RCP D-500, "Radiation
and Contamination
Surveys,"
Revision
9
~
RCP D-501, "Issue
and Return of Radiation Protection
Equipment," Revision I
~
RCP D-510, "Radiation
and Contamination
Survey Program,"
Revision
5
The inspectors
made specific observations
related to survey
practices,
worker usage of portal monitors
and friskers,
records of
surveys
and supervisory
review of survey information, instrument
availability,
and .adherence
to procedural
requirements.
il
(I)
Surve
Practices
Upon review of survey logs
and instrument
issue logs, the
inspectors
noted that surveys
were being performed
and
documented
thoroughly.
Routine surveys
were being performed at
the required frequency.
Observation of surveys
and discussions
with workers revealed that
RP personnel
had
a thorough
under standing of the survey program,
instrument
requirements
and limitations, techniques
for taking
and counting
smears,
and
ALARA practices.
The licensee's
routine survey practices
v.'ere
found to be .adequate
for monitoring and posting radiation
and
high radiation
areas
and were consistent with 10 CFR 20.201,
"Surveys."
While the inspector
was
accompanying
an
RPT on
a routine survey
of the Unit I PA,
a discrete radioactive particle ("hot
3
particle" ) was found on the asphalt
between
the north gate of
the 115'adiological
Controlled Area
(RCA) Backyard
and
Warehouse
A.
Readings with a count-rate
meter were in excess
of 50,000 corrected
counts per minute at 1/2 inch from the
particle.
The licensee
successfully
removed the particle from
the asphalt,
performed
a spectral
analysis,
and disposed of the
particle appropriately.
Additional
RPTs were sent to perform
a
more thorough survey of the area.
No other particles
were
found.
(2)
Worker Usa
e of Portal Monitors and Friskers
The inspectors
observed
worker usage of portal monitors
and
friskers at the 85'uxiliary Building and the 140'ontainment
Building access
control points.
The inspectors
noted that
workers'ontamination
monitoring practices
were adequate.
(3)
(4)
(5)
Records of Surve
s
and
Su ervisor
Review of Surve
Information
The inspectors
found the licensee's
maintenance
of survey
records to be acceptable.
Licensee
super visory review of
survey results
was performed efficiently, and survey data
and
information was disseminated
in a timely manner for use in work
planning
and radiation dose control.
Instrument Availabilit
The availability of RP instrumentation
was observed
at the
85'uxiliary
Building instrument
room.
The inspectors
noted that
few E-140 friskers
and telescoping
survey instruments
were
available for use.
The
RP Foreman
on shift indicated that the
majority of instruments
were in the Containment Building for
the outage.
The
RP Engineer responsible for coordinating
instrument calibration
and maintenance
with I&C stated that the
timeliness of instrument calibration
and maintenance still
needed
improvement,
but had improved over previous
outages.
All instruments
observed
by the inspectors
had current
calibration
and performance
test, stickers.
The inspectors
noted that Procedure
RCP D-500, "Radiation
and
Contamination Surveys," listed
an E-520
as
an available
instrument for use,
but cross-checks
against
the instrument
inventory revealed that the licensee
did not possess
any E-520
instruments.
An equivalent instrument,
an ASP-1 audible
response
with a Geiger-queller
probe,
was available in the-
licensee's
instrument inventory.
Adherence
to Procedural
Reouirements
The inspectors
reviewed survey practices for procedural
adherence.
Several
items'were
noted:
4
(a)
Review of survey logs for the period of January
1993
through Harch
1993 indicated. that routine surveys
were
performed at the frequencies
required
by Procedure
D-510, "Radiation
and Contamination
Survey Program."
(b)
Surveys
were thoroughly documented
as required
by
Procedure
RCP D-510, "Radiation
and Contamination
Survey
Program."
(c)
Other survey practices
observed
(e.g.
smear techniques,
instrument use;
preparation for surveys)
were performed
as
required
by Procedure
RCP D-500, "Radiation
and
Contamination Surveys."
Control of Posted
Hi
h Radiation Areas
Technical Specification (TS) 6.12. 1 requires that high
radiation areas
in which the intensity of accessible
whole body
radiation is greater
than
100 millirem per hour (mrem/hr) but
less
than or equal to 1000 millirem per hour {mrem/hr) at 18
inches shall
be barricaded
and conspicuously
posted
as
a high
radiation area.
Any individual or individuals permitted to
enter
such
an area
must have either:
(1)
a radiation
dose rate
survey meter,
or (2)
an alarming dosimeter
and prior knowledge
of the area
do'se rates,
or (3) accompaniment
by an individual
q'ualified in RP procedures
who carries .a survey meter,
provides
positive control over activities in the area,
and performs
'eriodic
radiation surveys.
The inspectors
reviewed four instances
in which workers
had
entered
posted
(HRAs) without meeting
TS
requirements for HRA controls.
The instances,
and the
licensee's
corrective actions for each
case,
were
as follows:
{1)
On October
2,
1992, during the Unit
1
1R5 outage,
a
contract worker entered
the refueling bridge posted
HRA to
look at
a reactor vessel
in-service inspection tool.
The
worker did not have either
a survey meter,
an alarming
dose rate meter,
or coverage
by an
RPT.
In addition, the
worker had not been briefed
on radiation levels present
in
the
BRA.
The worker was observed
by
a deconner,
who
called
an
RPT,
who in turn instructed the worker to exit
the
HRA.
As corrective action for this problem,
the worker's
access
authorizagion
was suspended,
and the worker was
subsequently
terminated.
In addition, worker training on
this incident was given prior to the Unit 2 2R5 outage.
(2)
On October
26,
1992, during the Unit
1
1R5 outage,
two
contractor carpenters
entered
a posted
HRA on the
140- oot
elevation of 'the Unit
1 Containment.
A nearby
PPT
'bserved
these entries,
noted the workers'ack of
monitoring devices,
and promptly removed the workers from
the
HRA.
As correc'tive action for this problem,
both workers'CA
access
authorizations
were temporarily placed
on hold,
and
the event
was discussed
with their supervision.
Subsequent
training on the event
(and
on TS requirements
for HRA entries)
was given to the entire crew on October
27,
1992.
(3)
On Harch 15,
1993, during the Unit 2 2R5 outage,
three
contractors
were observed
by a quality control inspector
.to be working without proper radiation monitoring in the
posted
HRA adjacent to reactor
coolant
pump
(RCP) 2-2.
The workers subsequently
stated that they had 'entered
the
area
by climbing. through
a narrow gap in the floor
grating,
and
had not
known that they were entering the
HRA.
In investigating this problem,
the. licensee
noted that the
workers
had received
a pre-job briefing on radi ation
hazards
by the
RPTs at the 115-foot elevation of
Containment;
however,
the workers
had not informed the
RPTs of the full scope of the job,
and therefore
had not
been briefed
on the radiation levels present
in the
beneath
the floor grating.
As corrective action, the
workers were counselled.
(4)
On March 22,
1993, during the Unit 2
2R5 outage,
two
contractor wor'kers were found without proper monitoring
inside the pressurizer
shed
posted
HRA on the 160-foot
elevation of the Unit 2 Containment.
The workers
had
checked
in with the access'ontrol
RPT,
who had forgotten
to issue
them alarming dosimeters.
As corrective action,
both the access
control
RPT and the
workers were counselled.
During discussions
with the inspectors,
the
RP Director (RPll)
noted that the percentage
of error evidenced
by these four
instances
was relatively small in proportion to the number of
properly monitored
HRA entries during outage periods.
The
RPH
noted,
in addition, that in each
case
subsequent
surveys
and
evaluations
had -concluded that the workers
had not actually
entered
those portions of the respective
HRAs in which the dose
field exceeded
100 millirem per'hour.
The inspectors
acknowledged
these
statements,
but observed
that,
by entering the posted
HRA, the workers
had in each
case
circumvented
the final
HRA control (i.e., the posted
sign
and
barricade)
and gained
access
to the high dose fields.
The
6
inspectors
also observed that the licensee's
corrective actions
thus far had not been effective in preventing recurr ence of
this problem.
The inspectors
concluded that the failure to
adhere to
HRA entry controls, in the four instances
noted
above,
constituted
a violation of TS
6'2 F 1 (50-275/93,-11-01)
In response
to the inspectors'bservations,
the
RPH stated
that, in an effort to prevent additional
improper
HRA entries,
additional controls were being evaluated.
These controls under
evaluation included:
(1) increased
emphasis
on
HRA controls
during general
employee training; (2) posting additional,
even
more conspicuous
HRA signs;
(3) using different
HRA barricades;
(4) "tightening" the
HRA boundaries (i.e., restricting the
boundaries
to the immediate
area of the high dose fields);
and
(5) inclusion of more conspicuous
markings
on radiation work
permits to remind workers of HRA monitoring requirements
prior
to beginning
a job.
With the exceptions
noted,
the licensee's
programs for controlling
occupational
exposure
appeared
effective in the areas
observed.
One
violation of NRC requirements
was identified.
3.
Post-Accident-Sam lin
84750
92701
V
This issue
was previously discussed
in
NRC Inspection
Report 50-275/93-04
and 50-323/93-04,
and was identified as Unresolved
Item 50-323/93-04-01
~
On the basis of the following discussion,
the unresolved
item is
considered
closed.
The inspectors'eview
of this area
was to determine
whether the
licensee's
program for obtaining post-accident
samples of reactor coolant
and plant gaseous
effluents
met the requirements
of TS 6.8.4.e
and the
commitments to NUREG-0737
as given in the Updated Final Safety Analysis
Report,
Chapter
9 '.2.2,
and historical
correspondence
between Pacific
Gas
and Electric Company
(PGSE)
and the
NRC.
In conducting this review,
the inspectors
reviewed applicable
licensee
procedures,
calculations,
maintenance
records,
and'elevant
historical correspondence,
and
discussed
the p'ost-accident
sampling
system
(PASS) history and
performance with various
members of the Chemistry Department
and licensee
management.
Discrepancies
were noted regarding
two aspects
of the licensee's
program:
(1) sampling
and analysis of dissolved
hydrogen in reactor
coolant;
and
(2) sampling
and analysis of radioiodines
and particulates
in plant gaseous
effluents.
Samolin
and Anal sis of Dissolved
H droaen
{1)
Requirements.
Criteria
and
Commitments
TS 6.8.4 requires
the licensee,
in part, to establish,
implement.
c.nd
ma ntain
a program l".hich will ensul e t,1e
capability to obtain
and analyze reactor coolant under accident
conditions.
The program must include (1) training of
personnel,
(2) procedures
for sampling
and analysis,
and (3)
provisions for maintenance
of sampling
and analysis. equipment.
r
UFSAR Section 9.3.2.2,
"Post-LOCA Sampling System," further
describes
the licensee's
methods of implementing this program,
including the system capability for quantifying dissolved
hydrogen in reactor
coolant.
The
UFSAR commitment states
that
all sampling
and analyses,
"as required
by NUREG-0737
(November
1980),"
can
be done within a 3-hour period.
(November 1980), "Clarification of THI Action Plan
Requirements,"
Section II.B.3, provides criteria for
postaccident
sampling capability.
These criteria include:
(a)
The capability of providing, within 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> of deciding to
take
a sample,
quantification of either hydrogen
gases
or
total dissolved
gases
in the reactor coolant;
(b)
The capability of performing backup grab samples for any
parameter
using inline monitoring;
and
(c)
Use of the dose limits of General
Design Criteria
(GDC) .19
of 10 CFR. 50, Appendix A (i.e.,
extremities)
as the design basis for any individual
performing postaccident
sampling
and analysis.
PG&E Letter DCL-85-047, dated
February
1,
1985,
committed to
having the Diablo Canyon Unit 2 SENTRY
criticality.
Enclosure
1 to this letter stated that the
SENTRY
PASS was "the permanent
system for providing post accident
sampling capability,"
and reiterated
PG&E's commitment to
meeting the criteria of NUREG-0737,Section II.B.3.
Finally,
10 CFR 50.59 requires,
in part, that the licensee
'hall
maintain records of changes
to the facility or procedures
described
in the
UFSAR, including
a written safety evaluation
that provides the basis for determining that the change
does
not involve an unreviewed safety question.
'I
Back round
The
SENTRY
PASS method of quantifying dissolved
hydrogen in
reactor coolant consisted of a shielded off-line system,
A
small, pressur'ized
sample of reactor coolant liquid was
,isolated within the system
and evacuated'o
a gas
bomb.
The
offgas
was routed through
a shielded
gas
chromatograph
(GC) to
obtain
a hydrogen concentration
readout.
After several
years of using the
SENTRY
PASS,
the licensee
developed
a concern
regarding moisture carryover from the
8
liquid sample through the gas
bomb and into the
SENTRY GC.
With routine use of the system (for training and operational
checks),
the carried-over moisture periodically wetted
down the
GC columns,
rendering the
GC inoperable until the columns could
be replaced.
Since the
SENTRY
GC was also
used for analyzing
dissolved
oxygen in the reactor coolant
and hydrogen in the
containment
atmosphere,
this matter
was of additional
concern.
~h
As an improvement to the system,
the licensee
decided to add
in-line reactor coolant hydrogen monitors.
These monitors,
called exosensors,
were designed with a gas-permeable
membrane.
Hydrogen passing
through'the
membrane
reacted with a sulfuric
acid solution,
and this reaction
was measured
to quantify the
hydrogen concentration.
The licensee's
evaluation of adding the exosensors,
performed
in accordance
with 10 CFR 50.59,
was completed in December
1987 'he evaluation stated that the
SENTRY
GC would continue
to be maintained
as
an alternate
method of analysis.
The
evaluation
concluded that the
VFSAR analysis
was unaffected
by
this change (i.e.,
by adding the exosensors).
The Unit 2 exosensor
was installed
and plant-accepted
on
December
8,
1989,
and the Unit
1 exosensor
was installed
and
plant-accepted
on January
15,
1990.
After more than
a year of
observing
exosensor
performance
in both units, operation of the
exosensors
was
added to the
PASS emergency
procedures
on March
27,
1991.
Due to continued
problems with moisture carryover in the
SENTRY
GC, the licensee
discontinued
use of the
GC for dissolved
reactor coolant hydrogen analysis (for both Units
1
and 2).
On
August 18,
1992, this method of analysis
was removed
from the
PASS emergency
procedures,
and training in this method
was
discontinued for PASS operators.
Comparisons of SENTRY
GC
reactor coolant hydrogen to normal reactor coolant hydrogen
samples,
formerly used to determine calibration of the
SENTRY
GC method,
were
no longer performed after this date.
NRC Evaluation
As previously noted in
NRC Inspection
Report 50-275/93-04
and
50-323/93-04,
the Unit 2 exosensor
performed
much more poorly
than the Unit
1 exosensor.
From August
1,
1992, to the time of
the onsite inspection,
the licensee
had considered
the Unit 2
exosensor
to be inoperable
during the following periods:
0
Peri od
August 24,
1992 - October 15,. 1992
November 6,
1992,
December
10,
1992
December 31,
1992 - February
12,
1993
February
25,
1993
April 9,
1993
T~otal
Da
s
53
35
44
44
During the
same period,
the Unit
1 exosensor
was only
inoperable for brief periods of routine maintenance.
The inspector
noted the following deficiencies related to the
licensee's
PASS capabilities for reactor coolant dissolved
hydrogen:
(a)
By invalidating the procedures,
training,
and calibration
for the
SENTRY
GC method of analysis,
this method
no
longer met the program requirements
of TS 6.8.4.
Despite
this fact, the
SENTRY
GC method
was still listed
as
an
alternate
method of analysis
under Equipment Control
Guideline
(ECG) 11.1,
"Post Accident Sampling System."
(b)
Other alternate
methods
given in
ECG ll.1 included normal
laboratory analysis of liquid grab samples
obtained
from
the
PASS sample lines or normal reactor coolant
sample
lines.
Using these
methods,
however,
the licensee
was
unable to perform sampling
and analysis within the design
basis
dose criteria of GDC 19 under accident conditions
(as outlined by NUREG-0737 criteria).
(c)
As
a result, for both Units
1
and 2, inline monitoring of
reactor coolant dissolved
was not supplemented
by
backup grab sampling capability,
as outlined by NUREG-0737
criteria.
(d)
During the periods of exosensor
inoperability in Unit 2,
no method of sampling
and analyzing reactor coolant
dissolved
under accident conditions
met the
criteria of NUREG-0737.
(e)
The licensee's
decision to discontinue
the procedures,
training,
and calibration of the
SENTRY
GC for reactor
coolant dissolved
hydrogen analysis
was not within the
scope of the
10 CFR 50.59 evaluation
performed in December
1987.
The licensee
had not performed
any additional
evaluation of this change'to
the
PASS capability.
(5)
Licensee
Evaluation
and Corrective Action
The inspectors
noted that enclosures
to the licensee's
Februart',
1985,
commitment letter had listed liquid grab samples
(drawn from either the
PASS lines or normal reactor coolant
sample lines)
as alternate
methods of meeting
10
P
criteria.
In discussions
with the inspectors,
the licensee
stated that
PGFE
had never performed evaluations
to demonstrate
that these alternate
methods
could. meet the design basis
dose
criteria of GDC-19.
The licensee
had incorrectly assumed
that
normal laboratory analysis of liquid grab samples
were always
an available alternative to the exosensor
or SENTRY GC.
During an April 14,
1993,
conference call, the licensee
discussed
proposed
corrective actions with members of NRC
Region
V management.
On April 15, the licensee
submitted
PGEE
Letter
DCL-93-089, which committed to the following corrective
actions:
(a)
The
SENTRY
GC method of quantifying reactor coolant
dissolved
hydrogen would be upgraded
by adding
a liquid
coalescing filter to reduce moisture carryover
and extend
thermal conductivity detector life.
This upgrade
would be
completed in Units
1
and
2 by April 21,
1993.
The letter
noted that the
SENTRY
GC method
was considered
a remote
{b)
The licensee
had already revised applicable
procedures
to
include the
SENTRY
GC method of quantifying reactor
coolant dissolved
In addition, calibration
and
interim training for this method would be completed
by
April 21,
1993.
Training of all
PASS assigned shift
chemistry
and
RP technicians
would be completed
by Hay 15,
1993.
(c)
The Unit 2 exosensor
would be returned to operable status
prior to restart of Unit 2.
During an April 21,
1993,
conference call, the licensee
stated
that the design
change installing coalescing filters in the
SENTRY
GC lines
had
been
completed
in both units.
In addition,
the licensee
stated that interim training and calibration
had
been completed,
and that the Unit 2 exosensor
had
been repaired
and declared
Finally, the licensee
stated that
calibration of the exosensor
would be verified against
normal
laboratory analysis of reactor coolant
upon restart of Unit 2.
{6)
Conclusion
The inspectors
determined that the licensee
had failed to
implement
and maintain
a program that ensured.
the capabilities
for sampling
and analysis
required
by TS 6.8.4,
'in the
following aspects:
(a)
At the time of discontinuing the procedures,
training,
"no
calibration for the
SENTRY
GC method of quantifying
reactor coolant dissolved
the licensee
had
removed grab samplino capability
as
a bacl:up to inline
11
monitoring.
{b)
During the periods of Unit 2 .exosensor
inoperability,
no
alternate
method
was available capable of quantifying
reactor
coolant dissolved
under the specified
.
accident conditions without exceeding
GDC-19 dose
criteria.
The inspectors
concluded that these failures constituted
an
apparent violation of TS 6.8.4 {50-323/93-11-02).
. The.
inspectors
concluded,
further, that the failure to perform
a
written safety evaluation of the effects of invalidating the
SENTRY
GC method of quantifying reactor coolant dissolved
hydrogen constituted
an apparent violation of 10 CFR 50.59 (50-
523/93-11-03).
In an effort to establish
the overall safety
consequence
of
these deficiencies,
the inspectors, noted that normal laboratory
analysis of reactor coolant dissolved
hydrogen while meeting
GOC-19 dose criteria was possible
under
some accident
conditions,
and that the conditions outlined in NUREG-0737
represented
worst-case
accident conditions.
The inspectors
also noted,
however, that the licensee's
PASS equipment control
'uidelines
and surveillance test procedures
did not establish
the severity of the accident for which these
"alternate
methods" could be used.
In addition, the inspectors
reviewed portions of the licensee's
emergency
plan
and discussed
the use of the reactor coolant
dissolved
hydrogen analysis with applicable
members of the
licensee's
emergency
organization.
The inspectors
noted that
this analysis
was not used
as
a primary means of assessing
core
damage
under accident conditions.
Rather, it was considered
supplemental
information used
in verification and long-term
analysis of core conditions.
b.
Sam lin
and
Anal sis of Radioiodines
a'nd Particulates
in Plant
Gaseous
Effluents
Re uirements
Criteria
and Commitments
TS 6.8.4 requires
the licensee,
in part, to establish,
implement,
and maintain
a program which will ensure
the
capability to obtain
and analyze
samples of radioiodines
and
particulates
in plant gaseous
effluents under accident
conditions.
The program must include (1) training of
personnel,
(2) procedures
for sampling
and analysis,
and
(3)
provisions for maintenance
of sampling
and analysis
equipment.
UFSAR Section
11.4 further describes
the licensee's
methods cf
implementing this program,
including
a basic description of i'...,
use
and functions of the midrange plant vent iodine monitor
12
{RE-32) and high-range plant vent iodine sampler
(RX-40).
In a letter to=the
NRC dated April 15,
1982,
PG&E committed to
meeting the criteria of NUREG-0737,Section II.F. 1, Attachment
2 for the gaseous
iodine and particulate
sampling
system in
Diablo Canyon Unit 1.
In a letter to the
NRC dated July 21,
1982,
PG&E reiterated this commitment,
and stated that RX-40
had
been
made operational
as of July 8,
1982.
(November 1980), "Clarification of THI Action Plan
Requirements,"
Section II.F. 1, Attachment 2, provides criteria
for the licensee's
post-accident capability of quantifying
radioiodines
and particulates
in plant effluents.
These
criteria include:
(a)
Concentration of 100 uCi/cc of gaseous
radioiodines
and
particulates,
deposited
on the sampling media;
(b)
30 minutes of sampling time;
(c)
An. average
gamma energy of 0.5 NeV;
and
{d)
Design of the sampling
system
such that plant personnel
could remove
samples,
replace
sampling media,
and
transport the
samples
to the onsite analysis facility with
radiation exposures
not in excess
of the
GDC-19 dose
criteria.
In addition,Section II.B.2 of NUREG-0737 provides the source
term to be used in reviewing plant shielding design
and in
determining the accessibility of vital. areas
during post-
accident operations.
(2)
~Back round
As originally installed,
the licensee
had several
monitors
and/or samplers
capable of quantifying plant vent radioiodines
and particulates
under various conditions:
(a)
RE-24, the normal
range monitor,
was located
on the
115'levation
of the Fuel Handling Building in the Plant Vent
Room.
RE-24 provided
a local readout
and alarm function,
as well
as
a remote
alarm in the Control
Room.
In
addition,
RE-24 was equipped with a particulate filter "nd
silver zeolite iodine cartridge that could
be
removed
and
analyzed
as
a grab sample.
The approximated
useful
range
of RE-24 was
from
1 E-7 microcuries
per cubic centimeter
(uCi/cc) to
1
E-4 uCi/cc.
(b)
RE-32, the midrange monitor,
was located adjacent to PE-2-'.
on the 115'levation of the Fuel Handling Building.
PE-
32 provided
remote monitorino, strip chart
'. ecorder,
-nc.'
13
alarm functions in the Control
Room,
and could be remotely
operated
and purged.
In addition,
RE-32 was equipped with
a particulate filter and silver zeolite iodine cartridge
that could
be removed
and analyzed
as
a grab sample.
The
approximated
useful
range of RE-32 was from 1.3 E-7 uCi/cc
to 3 E-3 uCi/cc.
(c)
RX-40, the high-range
sampler,
was located outside at the
85'levation against
the north wall of the Fuel Handling
Building.
RX-40 was provided with sampling functions only
(no monitoring or alarm functions),
and
was operated
remotely from the Control
Room.
A particulate filter and
silver zeolite iodine cartridge
was
housed
in a shielded
lead pig assembly,
which could be extracted
into
a larger,
lead-shielded
cart for transport to the Technical
Support
'enter
for analysis
as
under accident
conditions'.
The approximated
useful
range of RX-40 was
from
1 E-9 uCi/cc to
1
E+2 uCi/cc.
(3)
S stem Modifications
The licensee
was in the pro'cess of installing upgrades
in both
units for various process
and effluent radiation monitors.
As
part of this upgrade
program in Unit 1,
RE-24 had
been
removed,
and
a portable
RADECO pump assembly
had
been installed in the
former RE-24 sampler location.
This assembly
was provided with
a particulate filter and silver zeolite iodine cartridge for
periodic grab sampling.
In review of Unit
1 Control
Room logs,
the inspectors
noted
that the licensee
had taken both
RE-32
and
RX-40 out of service
for a 12-day period from February
26
March 9,
1993.
As part
of continued monitor upgrade
work, the monitors
had
been in
various conditions of inoperability during this time (e.g.,
clearances
hung with supply breakers
open,
leads lifted, heat
trace inoperable).
(4)
NRC Evaluation
'he
inspectors
noted that log entries
on February
26,
27,
and
28 gave
a list of monitors out of service
and then stated,
"Ho
alternate
sampling available for PASS" [referring to the plant
vent radioiodine/particulate
monitoring capability only].
Although subsequent
log entries
recorded
the
same monitors
as
being out of service
from February
26 - March 9,
no entries
regarding
PASS sampling capability were
made after the
February'8
entry.
p
The inspectors
asked
the chemistry engineer
responsible for
PASS what alternate
means
had
been provided for post-accident
sampling of plant vent radioiodines
and particulates
during th=
period in ouestion.
The chemistry engineer
stated that,
base
on discussions
between operations
and chemistry personnel,
the
licensee
had decided that the portable
RADECO pump temporarily
installed at the
RE-24 sampling lines provided
an acceptable
means of sampling under post-accident
conditions.
Based
on
that decision,
no log entry had been
made regarding
inoperability after February
28.
The inspectors
noted that licensee
Surveillance Test Procedure
{STP) G-14, "Operability Determination of Post Accident
Sampling Program," listed
RE-24
as
an alternate
post-accident
sampling point for plant vent radioiodines'nd particulates.
RE-24 was also listed
as
an alternate
sampling point in
Equipment Control Guideline
(ECG) 11. 1,
"Post Accident Sampling
System."
The inspectors
noted,
however,
the following
'concerns:
{a)
The grab sample cartridge at the
RE-24 location
had not
been provided with any shielding.
In addition, the
RADECO
pump temporarily attached
to RE-24 sampling lines required
local operation.
Under post-accident
conditions, this
would require prolonged
exposure
in a location
approximately
2 3 feet. from the plant vent.
(b)
Accessing
the
RE-24 sampling location
on the 115'uel
'andling Building would require passing
the filter banks
on the 115'allway.
Under post-accident
conditions,
these filter banks would become highly radioactive,
creating
a considerable
radiological
source
term in the
hallway.
(c)
Time and motion studies
had been
performed to ensure
the
capability to obtain
and analyze
a sample
from RX-40 under
accident conditions;
however,.no
such studies
had
been
performed for sampling
from RE-24.
(d)
Despite listing RE-24
as
an acceptable
alternate for RX-40
in the above
procedures,
the licensee
had never determined
that the
RE-24 design
allowed collecting
a sample
under
accident conditions within the
GDC-19 dose criteria, nor
was
such
a determination
made during the February
26 -,
Harch
9 period to justify dependence
on RE-24.
At the exit interview on April 9,
1993,
the inspectors
asked
the licensee
to perform
a dose calculation to determine whether
samples
could have justifiably been obtained
under specified
accident conditions using the temporary
RADECO pump at the
RE-
24 location.
(5)
Licensee
Evaluation
On April 13,
1993,
the licensee
provided the inspectors
~:ith
czlcuTation of source
term and resultant
dose entitled
l5
"Extemporaneous
Use of RE-24's 'Old'ample Line for Post
Accident Sampling in Connection with CAP E-2
5.
EP RB-12 in the
Event
RX-40 Is Not Operable."
This study accounted for
exposure
from (I) the sampling cartridge,
(2) the filter bank
hallway,
(3) outside
area
exposure,
and (4) plant vent exposure
while obtaining the sample.
The study concluded that
an
individual obtaining
and analyzing
such
a sample would receive
approximately 0.48
rem whole body dose
and 4.8 rem extremity
dose,
without the use of shielded
sampling or transport
casks.
Based
on the
above study, -the licensee
concluded that the use
of this proposed
sampling location would have provided
an
acceptable
means of obtaining
and analyzing radioiodines
and
particulates
in plant gaseous
effluents under accident
conditions.
(6)
Further
NRC Evaluation
and Conclusion
The inspectors
reviewed the licensee's
study,
and noted the
following concerns:
(a)
The licensee's
study had not -used the applicable
source
term provided in NUREG-0737,Section II.F.I, Attachment
2
(as committed in the April 15,
1982, letter), for
evaluating the dose from the, radioiodine cartridge
and
particulate filter.
Using the applicable
source
term from NUREG-0737,
the
inspectors
recalculated
the whole body dose from handling
the sampling cartridge for 90 seconds
to be approximately
25 rem.
(b)
The licensee's
study had not used
the analysis
methods of
NUREG-0737,Section II.B.2 for evaluating accessibility of
the Plant Vent
Room on the 115'levation of the Fuel
Handling Building during post-accident
operations.
(c)
Emergency
Procedure
(EP)
RB-12,
"Hid and High Range Plant
Vent Radiation Honitors,." Appendix I, Section 4.b,
stated
the following:
Should radioactivity levels of plant vent
effluents rise to the operating level of the
RE-
29 monitor, it would be virtually impossible to
detect radioiodines
in the presence
of the noble
gases.
Because of the high radiation levels
from the plant vent itself, personal
exposures
from entering the monitor area to obtain grab
samples
would be prohibitive.
For this reason,
a 'separate
iodine grab sampler
(RX-40) has,been
installed.
16
(d)
The inspectors
concluded that the licensee's
analysis
was
inadequate,
and that the licensee's
conclusion regarding
the adequacy of this sampling location
was in error.
In
subsequent
discussions
held on April 29,
1993,
the
licensee
acknowledged
the inspectors'bservations.
The
licensee
stated that
an additional possible
sampling
location would have
been from the
new RE-24
and
RE-24R
monitors,
which had not yet been declared fully
operational
at the time in question.
The inspectors
concluded that,
from February
26 to Harch 9,
1993, the licensee
had failed to implement
and maintain
a
program which ensured
the capability to obtain
and analyze
samples of radioiodines
and particulates
in the plant gaseous.
effluents under accident conditions, constituting
an apparent
violation of TS 6.8.4
(50-275/93-11-04).
Regarding the overall safety consequence
of these deficiencies,
the inspectors
noted that the Plant Vent
Room on the
115'levation
of the Fuel Handling Building would be accessible
while meeting
GDC-19 dose criteria under
some accident
conditions,
and that the conditions provided in NUREG-0737
represented
worst-case
accident conditions.
The inspectors
also noted,
however, that the licensee's
PASS equipment control
guidelines and'urveillance test procedures
did not establish
the severity of the accident for which this "alternate"
sampling location could be used.
In addition, the inspectors
noted that'Emergency
Procedure
(EP)
RB-9, "Calculation of Release
Rate,"
proposed
using the RX-40
sampling data
as
one input to
EP RB-11,
"Emergency Off-Site
Dose Calculations."
The inspectors
noted, further, that these
calculations of release
rate
and resultant off-site dose could
be used in establishing
protective action recommendations
under
certain accident conditions.
c.
Additional Observations
Related to
The inspectors
noted that the licensee
had incorrectly assumed
that
"alternate
methods" of post-accident
sampling,
when relied on, did
not need to meet
GDC-19 dose criteria.
As
a result,
the licensee
had not,
as
a rule,
conducted
time-and-motion studies for the
alternate
methods of any
PASS analysis listed in the equipment
control guideline
or surveillance test procedure.
The inspectors
noted that additional deficiencies
could result from dependence
on
these
unanalyzed
alternate
methods.
d.
~SUmmar
The inspectors
concluded that the licensee's
PASS program
require"'dditional
management
attention regarding the criteria to be met
v.'hen changes
were
made to the method. for'btaining
and analyzing
17
samples.
Three apparent
violations were identified.
4.
Exit Interview
The inspectors
met with members of licensee
management
at the conclusion
of the onsite portion of the inspection
on April 9,
1993.
On April 29
and 30, at the conclusion of the in-office portion of the inspection,
additional discussions
were held with the individuals noted in Section l.
0'