Submits Daily Highlight Re Reactor Startup.Primary Sys Solid at 400 Psi & Missile Shield in Place
ML16341C071
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 12/07/1983
From: Schierling H
Office of Nuclear Reactor Regulation
To: Carter J, Case E, Harold Denton
NRC
References
NUDOCS 8312190103
Download: ML16341C071 (2)


Text

Docket Nos.:

50-275 and 50-323 MEMORANDUM FOR; H, Denton E,

Case J. Carter D. Eisehhut H. Thompson R. Vollmer R. Mattson T. Speis J.

Sniezek T. Ippolito T. Novak G. Lainas F. Miraglia G. Holohan 1983 DISTRIBUTION 0

C 0 7 "

'Document:-Control:(50-275/323)

L PDR I

NRC PDR PRC System LB83 Reading JLee HSchierling BBuckley GWKnighton A'ttorney, OELD FROM:

SUBJECT:

Hans Schierling, Project Manager Licensing Branch No, 3

Division of Licensing DAI'LY HIGHLIGHT Diablo Can on, Unit 1

~

~

1.

The primary system is "solid" at 400 psi, Reactor Coolant pumps have been operated on the 1-minute and 10-minute cycles.

2.

The missile shield is in place and remaining modification work has been started on the dome service crane, 3.

.The condenser hydrotest is complete, Several condenser tubes have leaks in the rolled joint on the tube sheet (tubes can be rerolled to stop leakage),

'1 4.

Testing of the control rod drives has been started (current test, coil current test and rod drop test],

The information is current as of December 6, 1983, 8312190103 831207 PDR ADQCK 05000275 P

PDR l~'//l'll>iv."IIlil "~>'Q<l bp) hcIlllu UCChfNHRg Hans. Schierling, Project Manager Licensing %ranch No.