r,P 1
%0 AREcu oc
~
p0 Cy C0O ky*~W UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 Docket No. 50-275 JUL << i @84 MEMORANDUM FOR:
FROM:
SUBJECT:
Richard H. Vollmer, Director Division of Engineering Office of Nuclear Reactor Regulation James M. Taylor, Deputy Director Office of Inspection
& Enforcement EFFECTIVENESS OF QA PORTION OF THE DIABLO CANYON IDVP In your memorandum of June 25,
- 1984, you requested confirmation that, for the extent of the Reedy audit of the Diablo Canyon IDVP, the findings of the audit were not in conflict with Nr. Yin's findings.
Our assessment is that the
- RFR, Inc. audit results do not conflict with Yin's findings.
Based on your request and a telephone conversation on the afternoon of July 2
between Ted Sullivan of your staff and Jack Spraul of the
'QA Branch, we have reviewed the enclosures of your memo (particularly ITR-41) and Mr. Yin's findings as reported in his March 29, 1984 "Draft Investigation/Inspection Report,"
and his draft summary of findings of the same date.
A comparison is given in the enclosure to this memorandum.
The left column of the enclosure lists Mr. Yin's draft "Summary of Findings...."
dated MIarch 29, 1984.
The right column reflects similar findings of the RFR, Inc. audit taken from ITR 41, Appendix G, "Corrective Action Program Conditions and Pesolutions."
Me conclude that the Yin audits and the RFR, Inc. audits located some similar areas of concern.
For example, Nr. Yin's finding A indicates that he found inadequate indoctrination and training.
RFR, Inc. reports a similar concern based on a review of training records.
There are areas in the right column of the enclosure where specific findings of Nr. Yin are not, reflected in ITR-41.
There is, however, some correspondence in 7 of the 8 general areas of Nr. Yin's concerns.
In light of the sampling nature of the audit process, specific findings of Mr. Yin not being reflected in ITR-41 is not surprising.
If the roles were reversed (i.e., if the ITR-41 findings were listed and the correspondence of Mr. Yin's findings shown) similar comments would be observed.
- Thus, we conclude that the specific findings of the RFR, Inc. audit do not appear to be in conflict with Mr. Yin's findings.
Since Mr. Yin's audits (ll/83-3/84) were conducted about a year after the RFR, Inc. audits
( 10/82-3/83), this could reflect a lack of effective corrective action.
Any questions on the above should be addressed to Jack Spraul on X-24530.
84p7i70285 5pp 8PP7ii pDR pDOCI p
P
Enclosure:
As stated pi T mep N.
ylor, Deputy Director Offi'ce o Inspection and Enforcement
'I f
~",t 1
)
Hr. Yin's Findin s Corres or RFR Inc. Findings A.
There were inadequate rovisions in the program for personnel indoctrination and training.
The small bore pipe support engineers were not familiar with impor-tant elements in both the QA and techni-cal programs.
l.
In the area of general technical and QA training, the program permits personnel performing safety-related design work w/o training up to 30
~ days.
2.
Ho measures or program provisions establised to ensure adequate special training for the working staff on matters such as procedure revisions and problem trendings.
B.
QA program deficiencies and design nonconformances had not been identified and corrected promptly.
1.
Site design organization management was insensitive to staff concerns, and did not initiate timely correc-tive actions.
2.
Lack of project timely response to PGIE QA findings.
The delays were w/o justification.
3.
Lack of PGLE management attention to ensure timely responses to the audit findings.
4.
Bechtel audit finding corrective action scheduled completion dates were delayed without documented justification.
5.
Lack of PGIE audit finding correc-
.tive actions to identify the cause of the problem and the measures needed to prevent recurrence.
6.
Project corrective action only addressed specific problem areas identified in the PGSE audit find-ings and did not consider generic implication of the problems.
QA concurred with this apparently inadequate corrective action.
7.
Inadequate Bechtel QA verification of OPEG corrective actions prior to close-out of audit findings.
OPEG Personnel training continued to be inadequate.
8.
Lack of PGKE QA program measures to evaluate the effects of program efficiencies resulting in long delay of QA finding corrections prior to IDVP and CAP actions.
C.
Document control deficiencies were observed at the site design organizations.
1.
Engineers were using out-of-date procedures for performing calculations.
2.
Inter-office memorandums were issued in lieu of procedures that bypassed review and approval process.
3.
Site Quality Engineer and Support Group Leader maintained outdated listings of the latest work procedure.
A review o training records revealed that g
engineers who had been scheduled for training at least three times since Septamber 22, 1982 had not yet attended the training session.
Also, one of three Bechtel staff members had not been to a training session and the person-nel records were not complete for the three staff members.
Engineering non-conformance (Deficiency
- Reports, DR) do not appear to have been reviewed in a timely manner by QA; many DRs were observed to be past the close-out date.
No evidence of requests for extensions of close-out dates could be located.
(The time extensions are required to be initiated by the Engineering Cniefs).
Follow-up action had not yet been taken at the time of the audit.
A report for the first audit of DCP Site Engineering conducted by PGLE appeared not to have been issued within 30 days as required.
The manual of implementing Procedures, In-structions and Design Criteria Hemoranda (DCN) had instances of non-compliance with the requirements of EHP 5.2 for procedure prepara-tion, approval,
- issue, and control.
Fourteen examples cited.
Appendix J 6
K to DCH H-9 had been replaced by memos.
General corment - The date of effectivity, as listed in the Table of Contents, was not specified in or on the Procedure Cover Sheet.
The "Approved by" signature last entered did not always agree with the Table of Contents effectivity date.
4.
Design personnel was performing calculations without having ade-quately controlled procedures for extended periods of time.
Procedureal definition for small bore piping design packages had not yet been issued.
Eighteen receipt acknowledgment cards had not been returned.
These generic DCH's had not followed the consultant and safety review requirements of procedure 3.60h.
D.
There had been inadequate or lack of procedures for the design organizations.
Lack of provision to handle and resolve field initiated design questions and requests by the PGEE home office.
Procedural definition for small bore piping design packages had not yet been issued.
There was no documented statement identifying which designs were Iequired to have design verification by the Site Engineering Group.
Lack of prescription of the limited conditions where piping thermal stresses could be released by installation of gaps within rigid restraints.
Inadequate stress walkdown inspec-tion program to ensure freedom of interferences.
Procedures did not fully incorporate IEB 79-14 require-
- ments, and the acceptance criteria were relying on design piping movement predictions that were not always observed to be accurate.
Mays that support Joint loading can be reduced at structure connection were not prescribed.
Unacceptable pin )oint models were observed.
Lack of "Tolerance Clarification" procedural prescription on what could be "quickly fixed" at site without ma5or revision of the existing calculations.
Lack of sufficient references and engineering data for the site engineers to perform calculations that had resulted in personnel reliance on uncontrolled outside materials.
E.
Deficiencies observed that could have been the results of personnel not follow-ing the procedures.
Several instances noted where procedures were not followed.
For example:
The Signature Register had not been completed.
2.
Lack of S/B support calculation checks resulted in errors unrevealed.
"Preliminary" data identification and subsequent review of the calcu-lation against final data were not done.
No evidence could be found that the Chief responsible for the Piping Discipline had provided forrral DCCL approval at the time of the audit.
Personnel Training was not requested by the supervisors in a timely manner.
Stress walkdown inspections failed to identify all unintentional piping restraints.
F.
There had been design control deficien-cies identified during the program review and har dwape inspections.
Design criteria conflict in control of pipe support structural frequencies.
4-
2.
inadequate design evaluation of as-built deviations from design.
3.
Lack of program provisions to control preliminary design data provided through telephone, and to verify the calculation against subsequent final data when made avail able.
4.
There was no design consideration for synchronizing loading between closely spaced rigid/rigid re-
- straints, and rigid restraint/anchors.
5.
Snubbers were inoperab'le due to placing them in close proximity with rigid restraints and anchors.
Lack of ALARA considerations associ-ated with the use of snubbers.
Lack of documented design interface procedure for OPEG Piping Stress Group and Pipe Support Group.
Support field design change breakdown.
Quick acceptance and fixes of design deviations bypassed measures includ-ing prior caculations made, review, and approval.
There had been thou-sands of supports being "fixed" this way.
G.
inadequate licensee technical QA audits and surveillances to identify and correct the design control and program deficien-
-cies revealed during this inspection/investigation.
When a
QA audit item could not be evaluated due to a lack of project activities, followup of the item was not planned.
A management audit had not been conducted and had not been scheduled at the time of the audit.
2.
Lack of QA audit documentation of specific materials reviewed that leads to closing out of the audit findings.
4, Lack of QA documentation of materi-als reviewed during the conduct of the audit.
Lack of technical QA audits to independently verify that OPEG calculation inputs were checked to be in compliance with engineering procedures.
Auditor did not take the initiatives to investigate why there had not been any Discrepancy Reports issued by the site design group.
Relative to a document control audit, the auditor discovered that, since
- Navarch, 1983, the control of OPEG procedures was conducted at the PGSE and Bechtel, San Francisco offices.
There was no attempt made to revise the audit checklist to cover these activities.
The following conditions were found from auditing calculations:
l.,
Some signatures missing; 2.
Hot all pages numbered; 3.
Calculation indexes incomplete; 4.
References incomplete.
(The source of input data was not always shown);
and 5.
A list of items which establish "Prelimi-nary Status" was not inclu'ded.
Relative to the same document control audit, the checklist was modified to cover the subject OPEG activities, 10 months later the benefit of timely audit to ensure program compliance had been
H.
1nadequate PEAE and ~tel control of procured engineerin~vices.
1.
Lack of procedure to ensure effec-tive design interface between PGIE and Westinghouse.
2.
Lack of DCP control of procedures to be used by the contractors.
a.
Lack of measures to ensure that contractors had received required design criteria.
b.
Lack of justification on unrequired criteria and proce-dures being sent to the contractors.
Relative to DCP audit of contrac-tors, technical audits of lmprell, Cygna and Westinghouse had not been performed.
4.
Design procedures and instructions utilized by 1mprell, Cygna, and Westinghouse had not been reviewed and approved by the PGGE and Bechtel engineering and QA departments.
5.
PGSE did not perform QA program type audits of Westinghouse in 1983, when most of the CAP analytical work was carried out.
One suppl TERA, had been revie~ed and approved quired, but not yet audited to confirm t mplementation of the QA Program.
ANCO was only conditionally approved with follow-up action required.
A Corrective Action Request was outstanding regarding Quadrex.
6.
The PGSE QA program audit of West-
- inghouse, Ro.
- 20506, "Seismic Re-VerifIcation," conducted on Yiay 25-28, 1982. did not include a
review of piping analysis and pipe support calculation to ensure implementation of procedureal requirements.
7.
Relative to contractor internal
- audits, Cygna technical review for design analysis and calculation was questionable.
8.
Relative to contractor internal
- audits, the Westinghouse QA program type audit was considered to be inadequate and deficient.
9.
Relative to contractor internal
- audits, there had not been any technical audits conducted by Westinghouse.
DISTRIBUTION
~o QUAB Reading QASIP "
JSpraul Reading JSpraul JMilhoan RHeishman GTAnkrum JNGrace JNPartlow JMTaylor HDenton ECase RCDeYoung DEisenhut JNGrace JMartin EJSullivan, Jr.
AB:I E Q
B:E: I E DD/QA:IE Spraul J
lhoan GT krum JGPartlow 84/07/d 84 07/ap 84/
g 84/07/~ y D/QADIP: I E D
JNGrace J
ayl or 44+4~
/0 /
~r ~y
~
~
1 t ~
h V,
II v
A I I
l