Forwards List of Open Issues for Which Util Submitted Info, But No SER Input Has Been Received.Encl 2 Identifies Issues for Which Util Must Provide Info & Expected Submittal Dates
ML16340B524
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/16/1981
From: Buckley R
Office of Nuclear Reactor Regulation
To: Tedesco R
Office of Nuclear Reactor Regulation
References
NUDOCS 8103230112
Download: ML16340B524 (12)


Text

MEMORANDUM FOR:

R. L. Tedesco, Assistant Director for Licensing, DL FROM:

THRU:

SUBJECT:

B.

C. Buckley, Project Manager, Licensing Branch,No. 3, DL F. J. Miraglia, Acting Chief, Licensing Branch No. 3, DL STATUS OF OUTSTANDING ISSUES ON DIABLO CANYON, UNITS 1

& 2 As requested by your March 11.

1981 memorandutt1, enclosure (1) delineates the issues for which information from PG&E has been submitted but no SER input have been received.

Enclosure (2) identifies those issues that PG&E must provide and the expected submittal dates from PG&E.

cc:

H. Denton D. Eisenhut Division Directors Bart Buckley, Project Manager Licensing Branch No.

3 Division of Licensing DISTRIBUTION

'ocket File 50-275/323 PDR LPDR NSIC TERA LB¹3 Files BBuckley FMirag 1 i a JLee

~82 ~32@ 0 Il~,

OFFICE)

SURNAME/

OATEP

...L BCBuckley: jb 3/IS/81

..J.B FJ 3/

L

~ ~ ~ ~

gila 1

~ ~ ~ ~ ~ ~ ~

0 ~ ~ ~ ~

~ ~

~ ~

NRC FORM 318 IIO/80)NRCM 0240 OFFICIAL RECORD COPY 9 USGPO; 19S~294124

~~e p

M8t ai @,,

~'

If If'

quan nac><s

~cN 0

":$4$llaj'g

+a**+

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 MAR 16 1S81 MEMORANDUM FOR:

R.

L. Tedesco, Assistant Director for Licensing, DL FROM:

THRU:

SUBJECT:

B.

C. Buckley, Project Manager, Licensing Branch No. 3, DL

~

~

. J. Miraglia, Acting Chief, Licensing Branch No. 3, DL STATUS OF OUTSTANDING ISSUES ON DIABLO CANYON, UNITS 1

5 2 As requested by your March ll, 1981 memorandum, enclosure (1) delineates the issues for which'information from PG&E has been submitted but no SER input have been received.

Enclosure (2) identifies those issues that PGLE must provide and the expected submittal dates. from PG8E.

cc:

H.

Denton D. Eisenhut Division Directors Bart Buckley, Project Manager Licensing Branch No.

'3 Division of Licensing

OPEH ISSUES -

I::FC;.:-:.-.TIO." H~S BEEl( SUBhITTEO BY PGKE Plant c...e:

."'.= lo Canyon, Units 1

and 2

Techr~".al i"".. -..

DL fol Full Power SSER):

3/17/81 Project Varacer:, Bart Bvckley Ex tens ion:

28355 Oate:

i'!arch 6, 1981 (5:00)

DIVi~iO.'i B4."CH OSI RSB RE V I E'h'ER Orr Fi tzpatri ck OPEH ISSUES II. Y,.3 Item 17 -

ECCS outages Item 25 Effect of Loss of AC power on Pump seals Item 30 -

SB LOCA Analysis Item 31 - Plant Specific.

Anal

~

II.E.3.1 Emerg.

Power Supply for Pressure Heaters STATUS COi:u~iE <TS Heed PTRB Review of Procedures-Heed OLB Review of Training AEB CSB CPB Lewis Pulsipher Huang III.A.2 Appendix E meteorology II.F.1 Items 2(d), 2(e), 2(f)

-II.E.4.2 Containment Isolation Dependability II.F.2 Instr. for detection of Inadequate Core Cooling S

5 DOE NEB Hemminger II.D.1 Safety 8 Relief Yalve Test.

A l

O."-"-!l ISSUES Ii:;".=... TIOll H" 5 BEEN SUBllITTED BY PGSE

'lan'"=-...
i"i -bio Canyon, Units 1 and 2

Techr -a 1 !n".~ "o DL or Full Po:;er SSER):

3/17/81 Project

>'lanacer:

Bart Bvckley Extension:

28355 Date:

".arch 6, 1981 (5:00)

DIVIS!G DE EPPO BRA'HACH EQB EPLB RE V!E'n'E R Ashe Tam OPEC ISSV"S II.B.2 Plant Shield>ng Equ>p.

Qual-Appendix f STATUS S

COi'O'E'i TS On schedule

- received draft SER DSI

-CSB RSB Pvlsipher Orr Heat Trans er Sump Debris

0

~ vr

('/

OPEN ISSUES -

IilFORI')ATION HAS NOT BEEN SUBi'iITTED BY PG&E Plant.::arne:

Diablo Canyon, Units 1

and 2

Technical ln ut to DL for Full Power SSER:

3/17/81 Project Hang er:

Bart Buckley Extension:

28355 Date:

Harch 6, 1981 (5:00)

DIVISION BRANCH REVIEWER OPEN ISSUES STATUS COSINE NTS DSI RSB Orr II.K.2 Item 13 - Thermal tlechanical Report Item 17 - Voiding in RCS Due in formally 3/13/81 Due in formally 3/13/81 EPPO ETSB CPB Orr Serbu Boegli Boegli Huang Talll

'I Item 19 - Benchmark Analysis SEQ.

AFW

,F]ow II.K.3 Item 1 -'uto PORV Isol Item 5

- Auto Trip of. RCPs II.B.2 Shielding Design II.B.3 Post Accident Sampling III.D.l.1 Outside Containment Leakage II.B.3 Post Accident Salllpling II.F.2 Instr. for detection of Inadequate Core Cooling Earthquake Letter A

A A

Due in formally 3/13/81 PG&E Submittal due 3/13/81 PG&E Submittal due 3/13/81 Draft due 3/13/81; Final on 3/16/81 Final due in 3/13/81 Due in 3/13/81 from PG&E Due 'in 3/13/81 from PG8E Phone call scheduled for 3/13/81 Due in from PG&E 3/13/81

I

~

~

l

~ $

OPEN ISSUES Ii'lFOR",ATION HAS NOT BEEN SUBMITTED BY PGFE Plan'"arne:

Diablo Canyon, Units 1 and 2

Techrical I'nout to DL for Full Power SSER):

3/17/81

~ Project Mana er:

Bart Buckley Extens i on:

28355 Da te:

Ma rch 6, 1981 (5: 00)

DIYISIOlI SRANCH

.DE

EOB QAB MTEB SEB HGEB CHES AMSS R EYI E 'n E R Ashe Spraul Halapatz

. Lipinski Fl iegel Harrison OPEN ISSUES Envir. Qual. of Class IE Eq.

Acceptability of QA-Ql list and reviews of 1/22/81

Response

to QA program GDC-51 Masonry Walls Breakwater structure damage Appendix R (Fire Protection)

Securi ty STATUS A

CO'RENTS Draft received 3/3 (Formal Submittal due 3/18)

Draft due in 3/16/81; Final due in+

3/18/81 PG8E Submittal due 3/13/81 Draft received 3/12/81; Final PGEE submittal due 3/13/81

'Due in 3/20/81 Phone call scheduled for 3/13/81-if phone call successful formal submittal will be in 3/16/81.

Submittal due 3/13/81

0

~ '

~

~

J