MONTHYEARIR 05000461/20230042024-02-0202 February 2024 Integrated Inspection Report 05000461/2023004 ML23361A1572024-01-24024 January 2024 Audit Plan in Support of Review of License Amendment Request Regarding Revision of Technical Specifications Related to Reactor Water Cleanup Isolation ML24004A0792024-01-18018 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0041 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000461/20234022023-12-27027 December 2023 Security Baseline Inspection Report 05000461/2023402 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 IR 05000461/20235012023-12-0505 December 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2023501 ML23284A2512023-11-22022 November 2023 Amendment No. 250 to Adopt TSTF-332 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000461/20230032023-11-0808 November 2023 Integrated Inspection Report 05000461/2023003 ML22300A2212023-11-0202 November 2023 Preliminary Decommissioning Cost Estimate and Fuel Management Plan RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000461/20234202023-08-29029 August 2023 Security Baseline Inspection Report 05000461/2023420 RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20230022023-08-0404 August 2023 Integrated Inspection Report 05000461/2023002 RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release ML23209A8102023-07-28028 July 2023 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23198A0152023-07-27027 July 2023 License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23200A2592023-07-24024 July 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting-Meeting Summary IR 05000461/20234012023-07-19019 July 2023 Cyber Security Inspection Report 05000461/2023401 ML23194A1662023-07-19019 July 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Partial Site Release ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release IR 05000461/20230102023-05-26026 May 2023 Triennial Fire Protection Inspection Report 05000461/2023010 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23143A3182023-05-23023 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 IR 05000461/20230012023-05-0404 May 2023 Integrated Inspection Report 05000461/2023001 ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air2023-03-0101 March 2023 Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air ML23031A2972023-03-0101 March 2023 Issuance of Amendment No. 248 Adoption of TSTF-269, Revision 2 RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23039A1852023-02-10010 February 2023 Integrated Inspection Report 05000461/2022004 07201046/2022001 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000461/20220112023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000461/2022011 RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing2023-01-13013 January 2023 Application to Adopt TSTF-332, ECCS Response Time Testing ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20224022022-12-0606 December 2022 Security Baseline Inspection Report 05000461/2022402 RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI 2024-02-02
[Table view] |
Text
November 28, 2016 Vanessa Quinn, Chief Radiological Emergency Preparedness Branch Technological Hazards Division Federal Emergency Management Agency - Area 8 400 C Street, South West Washington, DC 20024
SUBJECT:
LICENSE AMENDMENT REQUEST - PROPOSED CHANGES TO THE CLINTON POWER STATION EMERGENCY PLAN FOR PERMANENTLY DEFUELED CONDITION
Dear Ms. Quinn:
By letter dated August 11, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16229A278 - package), Exelon Generation Company LLC submitted a license amendment request to the Radiological Emergency Plan Annex for Clinton Power Station (CPS), proposing reductions in emergency response organization (ERO) staff to be implemented upon written certification to the U.S. Nuclear Regulatory Commission (NRC) under §50.82(a)(1)(i) and (ii) to Title 10 of the Code of Federal Regulations (10 CFR) of the permanent cessation of reactor operation and permanent removal of fuel from the reactor vessel. The proposed changes to the CPS Radiological Emergency Plan Annex would eliminate specific on-shift and augmented emergency response organization (ERO) staffing based on the permanently shutdown and defueled condition of the facility, which is commensurate with the reduced spectrum of credible accidents. These proposed changes are not associated with any requests for exemption to NRC regulations and must continue to meet the standards of 10 CFR 50.47, Emergency plans, and the requirements of Appendix E to 10 CFR Part 50, Emergency Planning and Preparedness for Production and Utilization Facilities.
Based on our on-going review, NRC staff has determined that the proposed changes to reduce ERO staffing commensurate with the permanently shutdown condition of the facility are limited to onsite ERO functions. As such, at this time NRC is not requesting FEMAs formal review of the potential impact of changes on the ability of States and local authorities to implement their FEMA-approved plans. NRCs determination is based on the following:
- The proposed reductions to on-shift staffing, ERO minimum staffing (60-minute responders), and ERO augmented staffing, as described in Sections 2.1 through 2.3 to Attachment 1 of Exelon Generations letter dated August 11, 2016, would not result in any reductions in the ERO minimum and augmented staffing levels at the Exelon Corporate Emergency Operations Facility (EOF) or Joint Information Center (JIC), nor change the location and activation timeliness requirements for these facilities, which serve as the primarily licensee interface with State and local response agencies and the public.
V. Quinn
- Section 5.3.4 (Assessment of Staff Changes on Off-Site Emergency Response Organizational Interfaces) to Attachment 1 of Exelon Generations letter dated August 11, 2016, describes that actions involving support or direct interface with the State of Illinois are not being revised and will continue to be performed by licensee ERO positions currently assigned. While Exelon Generation proposes to eliminate the TSC State/Local Communicator position, this position is currently listed as an ERO augmented (non-minimum staffing) position. Exelon Generation now proposes to transfer responsibility for event notifications directly from the Control Room to the EOF, which will still be required to be activated at an Alert or higher classification.
- Methods and timing, as well as content of messages, for the notification of designated State and local agencies for event declaration and protective action recommendations remain unchanged.
- Continued maintenance of licensee letters of agreement with various support organizations and local emergency response agencies, as listed in Appendix 2 of the proposed CPS Radiological Emergency Plan Annex.
- Exelon Generations engagement with the Illinois Emergency Management Agency (IEMA) and the primary affected county for CPS (DeWitt County) to discuss and familiarize these organizations with the proposed changes to the CPS Radiological Emergency Plan Annex. The NRC will continue to keep FEMA apprised of any correspondence received from the State of Illinois regarding discussion with Exelon Generation on the proposed CPS Radiological Emergency Plan Annex and associated emergency action level (EAL) scheme change.
This letter does not constitute NRC approval of proposed changes to the CPS Radiological Emergency Plan Annex, but rather to inform FEMA that at this time the NRC will not be requesting a formal FEMA review of the potential impact of changes on the ability of States and local authorities to implement their FEMA-approved plans. to Exelon Generations letter dated August 11, 2016, identifies a regulatory commitment that CPS will perform a drill, prior to implementation of the Post-Shutdown Emergency Plan, to confirm the ability of the post-shutdown ERO to perform the necessary functions of each emergency response facility and to utilize the post-shutdown procedures. The regulatory commitment further states:
The drill will involve a spent fuel pool event that tests the major elements of the licensees emergency plan and communications/coordination with offsite response organizations, including the Joint Information Center. State and local response organizations will be offered the opportunity to participate, and NRC and FEMA will be provided advance notice to observe drill activities.
This drill will provide the opportunity for FEMA to observe the continued adequacy of existing State and local radiological emergency plans under the existing FEMA drill/exercise process.
V. Quinn As always, if you have any questions regarding the specifics of the proposed changes to the Exelon Nuclear Clinton Radiological Emergency Plan and CPS Annex, or the NRC's evaluation of these proposed changes, please contact Richard Kinard at (301) 287-3768.
Sincerely,
/RA/
Joseph D. Anderson, Chief Reactor Licensing Branch Division of Preparedness and Response Office of Nuclear Security and Incident Response cc: J. King, FEMA HQ
V. Quinn The drill will involve a spent fuel pool event that tests the major elements of the licensees emergency plan and communications/coordination with offsite response organizations, including the Joint Information Center. State and local response organizations will be offered the opportunity to participate, and NRC and FEMA will be provided advance notice to observe drill activities.
This drill will provide the opportunity for FEMA to observe the continued adequacy of existing State and local radiological emergency plans under the existing FEMA drill/exercise process.
As always, if you have any questions regarding the specifics of the proposed changes to the CPS Radiological Emergency Plan Annex, or the NRC's evaluation of these proposed changes, please contact Richard Kinard at (301) 287-3768.
Sincerely,
/RA/
Joseph D. Anderson, Chief Reactor Licensing Branch Division of Preparedness and Response Office of Nuclear Security and Incident Response cc: J. King, FEMA HQ Distribution: