UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 31, 2016 Mr. Bryan C. Hanson President and Chief Nuclear Officer Exelon Generation Company, LLC R. E. Ginna Nuclear Power Plant 4300 Winfield Rd Warrenville, IL 60555

SUBJECT:

R. E. GINNA NUCLEAR POWER PLANT - BRANCH CHIEF REASSIGNMENT FOR PLANT LICENSING BRANCH 1-1

Dear Mr. Hanson,

This letter is to inform you that effective October 31, 2016, through December 3, 2016, the following Senior Project Managers (Sr. PMs) have been assigned as the U.S. Nuclear Regulatory Commission's Acting Chief for Plant Licensing Branch 1-1, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation, and have licensing oversight responsibility for R. E. Ginna Nuclear Power Plant.

Dates Sr. PM Actin Chief Email Address Office Phone Oct. 31 to Nov. 6, 2016 Brenda L. Mozafari 301 415-2020 Nov. 7 to Nov. 13, 2016 Dou las V. Pickett 301 415-1364 Nov 14 to Nov. 20, 2016 Brenda L. Mozafari 301 415-2020 Nov. 21 to Nov. 27, 2016 Richard V. Guzman 301 415-1030 Nov. 28 to Dec. 3, 2016 Dou las V. Pickett 301 415-1364 These Sr. PMs assume all supervisory duties previously held by Mr. Travis L. Tate, as Chief, Plant Licensing Branch 1-1.

Sincerely, George A. Wilson, Jr., Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244 cc: Distribution via Listserv

ML16302A019 OFFICE NRR/LPLl-1/LA NRR/LPLl-1/BC (A) NRR/DORL/DD NAME KGoldstein Pickett GWilson DATE 10/28/16 10/28/16 10/31/16