Modification No. 001 to Task Order NRC-HQ-20-16-T-0006 Under Interagency Agreement No. NRC-HQ-25-14-D-0001
ML16273A544
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/27/2016
From: Sandra Nesmith
Acquisition Management Division
To: Madera G
Pacific Northwest National Laboratory
References
NRC-HQ-25-14-D-0001
Download: ML16273A544 (2)


Text

  • -Jf\ITERAGENCY AGREEMENT
r. IAANO.

IPA~E OF NRC-HQ-20-16-T-0006/MOOOl I 2

2. ORDER NO. 13. REQUISITION NO. 14. SOLICITATION NO.
5. EFFECTIVE DATE ,6. AWARD DATE 7. PERIOD OF PERFORMANCE 07/25/2016 07/25/2016 02/17/2016 TO 02/24/2017
8. SERVICING AGENCY 9. DELIVER TO PACIFIC NORTHWEST NAT LAB BERNARD GRENIER ALC: US NUCLEAR REGULATORY COMMISSION DUNS: +4: OFFICE OF NUCLEAR-REACTOR REGULATION us DEPARTMENT OF ENERGY 11555 ROCKVILLE PIKE PACIFIC NORTHWEST SITE OFFICE ROCKVILLE MD 20852 PO BOX 350 MS K9-42 RICHLAND WA 99352 POC Genice Madera TELEPHONE NO. 509-372-4010
10. REQUESTING AGENCY 11. INVOICE OFFICE ACQUISITION MANAGEMENT DIVISION US NUCLEAR REGULATORY COMMISSION ALC: 3100001 ONE WHITE FLINT NORTH DUNS: 040535809 +4:

US NUCLEAR REGULATORY COMMISSION 11555 ROCKVILLE PIKE ONE WHITE FLINT NORTH MAILSTOP 03-El7A 11555 ROCKVILLE PIKE ROCKVILLE MD 20852-2738 ROCKVILLE MD 20852-2738 POC Sandra Nesmith TELEPHONE NO. 301-415-6836

12. ISSUING OFFICE 13. LEGISLATIVE AUTHORITY

_ Energy Reorganization Act of 1974 US NRC - -HQ ACQUISITION MANAGEMENT DIVISION MAIL STOP TWFN-5E03 -

14. PROJECT ID WASHINGTON DC 20555-0001
15. PROJECT TITLE REVIEW OF THE TURKEY POINT NPP UNITS 3 AND 4 LICE!
16. ACCOUNTING DATA No funding obligated
17. 18. 19. 20. 21. 22.

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT Master IAA: NRCHQ2514D0001 Agreement No.: NRC-HQ-25-14-D-0001 Task Order No: NRC-HQ-20-16-T-0006 Task Order

Title:

Review of the Turkey Point NE P Units 3 and 4 License Amendment Request Pertaining to Risk-Informed Technical Specifications Task Force Initiative 4b, "Provic e Risk-Informed Extended Co~pletion Times," TSTF-: 05

SUMMARY

OF CHANGE:

Continued ...

23. PAYMENT PROVISIONS 124. TOTALAMOUNT

$0.00 26a. SIGN.Z OF~VERNMZ.R/l:NTATIVE (~;?STING) 25a. SIGNATURE OF GOVERNMENT REPRESENTATIVE (SERVICING)

..- '/A~ /r - , ,

  • _£/} /J/ / / _ 4

- 6 r 7~~

25b. NAME AND TITLE 125c. DATE 26b. c'eJ"rrfJ<XcfiNG OFFICER SANDRA R. NESMITH TEMPI BT~ *~ JJfJMfllJ11

IAANO PAGE NRC-HQ-20~16-T-0006/MOOOl 2 This modification provides a no-cost extension to the period of performance from 8/5/16 to 2/24/17 to allow additional time for completion of Task 3 and 4.

~ccordingly, the task order is modified as follows:

1. The period of performance has changed from 2/17/16 - 8/5/16 to 2/17/16 - 2/24/17.

Changes to the deliverable schedule are not needed since due dates were stated in time frames rather than actual dates in the SOW.