Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] Category:License-Operator
MONTHYEARML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination ML22251A0192022-08-10010 August 2022 Form 5.1-1 Postexamination Check Sheet DC-Cook 2022 ML22251A0162022-08-10010 August 2022 Form 2.1-1 Examination Preparation Checklist DC-Cook 2022 ML22250A7202022-08-10010 August 2022 Form 1.3-1 Exam Security Agreement DC-Cook 2022 ML22251A0202022-08-0202 August 2022 Post Examination Submittal Letter DC-Cook 2022 ML22192A1192022-07-11011 July 2022 Operator Licensing Examination Approval ML22250A6912022-06-30030 June 2022 Form_2.3-4_Written_Exam_Quality_Checklist_DC-Cook_2022 ML22250A6902022-06-30030 June 2022 Form_2.3-2_Operating_Test_Quality_Checklist_DC-Cook_2022 ML22250A6652022-06-30030 June 2022 Form: 2.3-1 Examination Outline Quality Checklist DC-Cook - 2022 ML22250A6692022-06-30030 June 2022 Form 3.4.1 Events and Evolutions Checklist DC-Cook 2022 ML22250A6922022-05-12012 May 2022 Licensee_Iinitial_License_Exam_Submittal_Letter_DC-Cook_2022 AEP-NRC-2022-20, Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations2022-03-14014 March 2022 Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML22032A0392022-02-0101 February 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21347A5742021-12-29029 December 2021 Confirmation of Initial License Examination ML21110A5272021-04-19019 April 2021 GFE Results, March 2021 IR 05000315/20203012020-10-19019 October 2020 NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 ML20356A0912020-08-25025 August 2020 2020 DC Cook Ile Proposed Control Room and In-Plant Systems JPMs ML20356A0842020-08-25025 August 2020 2020 DC Cook Ile Simulator Scenario Quality Checklist ES-301-4 ML20356A1522020-08-25025 August 2020 2020 DC Cook Ile Written Exam Outlines ES-401-2 and ES-401-3 ML21006A2222020-08-25025 August 2020 2020 DC Cook Ile Operating Test Outline Submittal Letter ML20356A0332020-08-25025 August 2020 2020 DC Cook Ile Operating Test Competencies Checklist ES-301-6 ML20356A2592020-08-25025 August 2020 2020 DC Cook Ile As-Administered Control Room and In-Plant Systems JPMs ML21006A4402020-08-25025 August 2020 2020 DC Cook Ile Post Exam Package Submittal Letter and Comment Summary Rcvd 20200825 ML21006A4372020-08-25025 August 2020 2020 DC Cook Ile Exam Preparation Checklist ES-201-1 ML20356A0742020-08-25025 August 2020 2020 DC Cook Ile Operating Test Quality Checklist ES-301-3 ML21005A4312020-08-25025 August 2020 2020 DC Cook Ile As-Administered Simulator Scenarios ML21006A4292020-08-25025 August 2020 2020 DC Cook Ile Exam Security Checklists ES-201-3 ML20356A2652020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO and SRO Admin JPMs ML21006A4102020-08-25025 August 2020 2020 DC Cook Ile Operating Test Review Worksheet ES-301-7 ML20356A0802020-08-25025 August 2020 2020 DC Cook Ile Proposed Exam Submittal Letter ML21006A4412020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 RO ML20356A1602020-08-25025 August 2020 2020 DC Cook Ile Exam Outline Quality Checklist ES-201-2 ML20356A0862020-08-25025 August 2020 2020 DC Cook Ile Written Examination Quality Checklist ES-401-6 ML20356A1572020-08-25025 August 2020 2020 DC Cook Ile Transient and Event Checklists ES-301-5 ML20356A2572020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO SRO Written Examination ML20356A1012020-08-25025 August 2020 2020 DC Cook Ile Proposed Simulator Scenarios ML20356A1412020-08-25025 August 2020 2020 DC Cook Ile Operating Test JPM Outlines ES-301-1 and ES-301-2 ML20356A1492020-08-25025 August 2020 2020 DC Cook Ile Operating Test Scenario Outlines ES-D-1 ML20356A0992020-08-25025 August 2020 2020 DC Cook Ile Proposed Ro_Sro Written Examination ML21006A4182020-08-25025 August 2020 2020 DC Cook Ile Record of Rejected KAs ES-401-4 ML21006A4202020-08-25025 August 2020 2020 DC Cook Ile Written Exam Review Worksheet ES-401-9 ML20356A0952020-08-25025 August 2020 2020 DC Cook Ile Proposed RO and SRO Admin JPMs ML21006A4442020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 SRO ML20364A2132020-08-13013 August 2020 2018 Donald C. Cook Nuclear Power Plant Exam Administered Scenarios ML20210M4202020-07-29029 July 2020 Operator Licensing Examination Approval ML19353A0252019-12-18018 December 2019 Confirmation of Initial License Examination AEP-NRC-2019-26, Response to RIS 2019-022019-05-30030 May 2019 Response to RIS 2019-02 ML19106A0162019-04-15015 April 2019 GFE Results, March 2019 ML19045A3722019-02-12012 February 2019 March 2019 GFE Cover Letter Riii 2023-12-05
[Table view] Category:Other HQ and Regional Correspondence
MONTHYEARML16189A0862016-07-0606 July 2016 Ltr. 07/06/16 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Operator Licensing Examination Approval (Rdb) 2016-07-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 July 6, 2016 Mr. Joel Gebbie Senior VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
SUBJECT:
DONALD C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 OPERATOR LICENSING EXAMINATION APPROVAL
Dear Mr. Gebbie:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Donald C. Cook Nuclear Plant.
The U. S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications in connection with this examination and separately provided a list of approved applicants to Mr. Daniel Emery, Training Manager. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and you may administer the written examinations in accordance with Revision 10, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors, during the week of July 18, 2016. The NRC staff will administer the operating tests during the weeks of July 11, 2016 and July 18, 2016.
This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630-829-9834.
Please contact your Chief Examiner, Mr. Randal Baker at 630-829-9871, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
J. Gebbie In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 cc: Distribution via LISTSERV Daniel Emery, Training Manager
J. Gebbie In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 cc: Distribution via LISTSERV Daniel Emery, Training Manager DISTRIBUTION:
Jeremy Bowen RidsNrrDorlLpl3-1 Resource RidsNrrPMDCCook Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII M. Scheetz, NRR J. R. Kweiser, DRS ADAMS Accession Number ML16189A086 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS C RIII:DRS N RIII:DRS N RIII NAME JKweiser:cl RBaker: ROrlikowski:
DATE 07/06/16 07/06/16 07/06/16 OFFICIAL RECORD COPY