6/21/2016 - Seabrook Station Annual Assessment Meeting - NRC Presentation Slides (Assessment and ASR Update)
ML16176A054
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 06/21/2016
From:
NRC Region 1
To:
Bower F
References
MN 16-005
Download: ML16176A054 (10)


Text

ML16174A054 Seabrook Public Meeting - ASR Update Nuclear Regulatory Commission - Region I Hampton, NH June 21, 2016 1

NRC Staff

AGENDA

  • 2015 Safety Performance Overview
  • ASR Inspections
  • ASR License Amendment Request
  • Question and Answer Session
  • Closing Remarks 3

Seabrook 2015 Assessment Summary

  • Operated safely and in a manner that preserved the public health and safety and protected the environment
  • Licensee Response Column
  • 5,470 hours0.00544 days <br />0.131 hours <br />7.771164e-4 weeks <br />1.78835e-4 months <br /> of inspection and related activities.
  • All Green Performance Indicators
  • 2 Green Findings 4

NRC Inspections of Seabrook Structures Affected by ASR

  • NRC specialist inspections completed every six months
  • NRC issued a violation in 2016 for not evaluating ASR effects of bulk deformation in Containment Enclosure Building and Underground Equipment Vault Wall Cracks
  • Violation of very low safety significance because structural capability was maintained
  • Written response required due to repetitiveness
  • NRC will complete inspection to assess effectiveness of actions to prevent recurrence 5

License Renewal Status Update

  • Need reasonable assurance that ASR aging effects can be adequately managed
  • License renewal safety review is ongoing; regulatory decision on the application has not been finalized
  • Remaining schedule milestones, including 2nd ACRS Subcommittee meeting, are to be determined 6

License Renewal Status Update

  • ASR continues to be an Open Item, primarily due to building deformation and macro-cracking manifestations
  • Public meeting with NextEra at NRC HQ on April 28, 2016, discussed ASR open issues
  • NextEra intends to submit a revised ASR Monitoring AMP in August 2016 7

ASR License Amendment Request

  • Pre-application public meeting with NextEra held June 15, 2016.
  • NextEra stated it intends to submit an ASR license amendment request (LAR) in July 2016.
  • The LAR will request to revise Seabrooks design basis
  • Texas test data is intended to demonstrate that American Concrete Institute code acceptance criteria are met (within limits)f or ASR-affected structures.

8

NRC License Amendment Process Submit License Acceptance Review Request for Additional Amendment Request (LAR)

Information (RAI)

Publish Notice of Receipt of LAR in Federal Register Licensee Supplement in Pre-application Meeting *30-Day Comment Period on No Response to RAI June 15, 2016 Significant Hazards Consideration

  • 60-Day Period to Request a Hearing Complete Review of LAR on the LAR State Consultation Hearing Requests -

Follow 10 CFR Part 2 Issue Decision on LAR 9