Letter from Sherwin E Turk to the Atomic Safety and Licensing Board and Enclosed Integrated Inspection Report
ML16133A596
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 05/12/2016
From: Sherwin Turk
NRC/OGC
To: Kennedy M, Lawrence Mcdade, Richard Wardwell
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01, RAS 51110
Download: ML16133A596 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 May 12, 2016 Lawrence G. McDade, Chair Dr. Michael F. Kennedy Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Mail Stop: T-3 F23 Washington, D.C. 20555 Washington, D.C. 20555 Dr. Richard E. Wardwell Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Washington, D.C. 20555 In the Matter of ENTERGY NUCLEAR OPERATIONS, INC.

(Indian Point Nuclear Generating Unit Nos. 2 and 3)

Docket Nos. 50-247-LR/286-LR

Dear Administrative Judges:

The NRC Staff (Staff) has issued its quarterly integrated inspection report for Indian Point Units 2 and 3, entitled Indian Point Nuclear Generating - Integrated Inspection Report 05000247/2016001 and 05000286/2016001 (May 12, 2016) (available at ADAMS Accession No. ML16133A448). A copy of the inspection report is enclosed herewith.

The enclosed inspection report addresses NRC inspection activities at Indian Point Units 2 and 3 during the period of January 1 - March 31, 2016. The licensees performance of in-service inspections and its identification of issues involving the baffle-former bolts at Indian Point Unit 2 are discussed at pages 9-12 of the enclosed report. The Staff expects to present updated information concerning the baffle-former bolts in its quarterly inspection report for the period of April 1 - June 30, 2016, to be issued in August 2016.

Respectfully,

/Signed (electronically) by/

Sherwin E. Turk Counsel for NRC Staff

Enclosure:

As stated Cc w/Encl.: EIE Service List

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-247/286-LR

)

(Indian Point Nuclear Generating )

Units 2 and 3) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (as revised), I hereby certify that copies of the foregoing letter from Sherwin E. Turk to the Atomic Safety and Licensing Board, dated May 12, 2016, along with the enclosed Indian Point Nuclear Generating - Integrated Inspection Report 05000247/

2016001 and 05000286/2016001 dated May 12, 2016, have been served upon the Electronic Information Exchange (the NRCs E-Filing System), in the above-captioned proceeding, this 12th day of May, 2016.

/Signed (electronically) by/

Sherwin E. Turk Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 287-9194 E-mail: Sherwin.Turk@nrc.gov

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 May 12, 2016 Lawrence G. McDade, Chair Dr. Michael F. Kennedy Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Mail Stop: T-3 F23 Washington, D.C. 20555 Washington, D.C. 20555 Dr. Richard E. Wardwell Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Washington, D.C. 20555 In the Matter of ENTERGY NUCLEAR OPERATIONS, INC.

(Indian Point Nuclear Generating Unit Nos. 2 and 3)

Docket Nos. 50-247-LR/286-LR

Dear Administrative Judges:

The NRC Staff (Staff) has issued its quarterly integrated inspection report for Indian Point Units 2 and 3, entitled Indian Point Nuclear Generating - Integrated Inspection Report 05000247/2016001 and 05000286/2016001 (May 12, 2016) (available at ADAMS Accession No. ML16133A448). A copy of the inspection report is enclosed herewith.

The enclosed inspection report addresses NRC inspection activities at Indian Point Units 2 and 3 during the period of January 1 - March 31, 2016. The licensees performance of in-service inspections and its identification of issues involving the baffle-former bolts at Indian Point Unit 2 are discussed at pages 9-12 of the enclosed report. The Staff expects to present updated information concerning the baffle-former bolts in its quarterly inspection report for the period of April 1 - June 30, 2016, to be issued in August 2016.

Respectfully,

/Signed (electronically) by/

Sherwin E. Turk Counsel for NRC Staff

Enclosure:

As stated Cc w/Encl.: EIE Service List

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-247/286-LR

)

(Indian Point Nuclear Generating )

Units 2 and 3) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (as revised), I hereby certify that copies of the foregoing letter from Sherwin E. Turk to the Atomic Safety and Licensing Board, dated May 12, 2016, along with the enclosed Indian Point Nuclear Generating - Integrated Inspection Report 05000247/

2016001 and 05000286/2016001 dated May 12, 2016, have been served upon the Electronic Information Exchange (the NRCs E-Filing System), in the above-captioned proceeding, this 12th day of May, 2016.

/Signed (electronically) by/

Sherwin E. Turk Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 287-9194 E-mail: Sherwin.Turk@nrc.gov