1 NRR-PMDAPEm Resource From:
Regner, Lisa Sent:
Thursday, January 21, 2016 2:04 PM To:
Wayne Harrison Cc:
Michael Murray; Sterling, Lance (lsterling@STPEGS.COM)
Subject:
NRC DRAFT GSI-191 Audit Plan - week of 2/22 Attachments:
DRAFT Audit Plan - QA's Simualtions.docx
- Wayne, Here is a draft of our audit plan for the week of 2/22/16. We are on schedule to get you T-H questions the first week of February.
- Thanks, Lisa
Hearing Identifier:
NRR_PMDA Email Number:
2736 Mail Envelope Properties (Lisa.Regner@nrc.gov20160121140400)
Subject:
NRC DRAFT GSI-191 Audit Plan - week of 2/22 Sent Date:
1/21/2016 2:04:08 PM Received Date:
1/21/2016 2:04:00 PM From:
Regner, Lisa Created By:
Lisa.Regner@nrc.gov Recipients:
"Michael Murray" <mpmurray@STpegs.com>
Tracking Status: None "Sterling, Lance (lsterling@STPEGS.COM)" <lsterling@STPEGS.COM>
Tracking Status: None "Wayne Harrison" <awharrison@STPEGS.COM>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 161 1/21/2016 2:04:00 PM DRAFT Audit Plan - QA's Simualtions.docx 25474 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Audit of South Texas Projects Simulations Used to Support Closure of GSI-191 BACKGROUND By letter dated August 20, 2015 (Reference 1), STP provided Supplement 2 to Risk-Informed Approach for addressing Generic Safety Issues 191. This is the latest from a significant number of references which describe STPs approach and their use of RELAP5-3D.
The NRC staff has proposed to conduct a regulatory audit at this point in the review process in an effort to increase the efficiency of the NRC staffs review. The scope of this audit is to review the recent simulations STP has performed in support of the GSI-191 licensing action request and to discuss the NRCs draft Requests for Additional Information sent by email on January 14, 2016 (ADAMS Accession No. xxxx).
The NRC staff has performed a review of the submitted information and expects the audit to increase their level of knowledge and understanding. The regulatory audit will be held in accordance with NRR procedure as described in LIC-111 Regulatory Audits.
REGULATORY AUDIT SCOPE This audit will focus on STPs simulations of long term core cooling following a loss of coolant accident (LOCA). Specifically, the NRC staff will review the following analysis:
Small break LOCA - cold leg Small break LOCA - hot leg Medium break LOCA - hot leg Large break LOCA - hot leg Additionally, the NRC staff will review the steps taken by STP to perform this analysis under the QA program. Thus, STP should make available any documentation which describes their QA process and/or demonstrates how the RELAP5-3D simulations were performed under STPs QA program.
The NRC staff would like STP to make available the appropriate engineer(s) with knowledge of the RELAP5-3D evaluation model and analysis to address any questions from the NRC staff.
These questions will likely include the following topics:
the progression of the event, the phenomena occurring during the LOCA, how the phenomena has been modeled, how the QA program verifies the input decks TEAM AND REVIEW ASSIGNMENTS
Lisa Regner - Audit Lead, STP Project Manager, Licensing Joshua Kaizer - Technical Lead, Nuclear Performance and Code Review Branch Reed Anzalone - Technical Support, Nuclear Performance and Code Review Branch Steve Bajorek - Technical Support, Office of Research LOGISTICS Audit Dates: Tuesday February 23, 2016 - Thursday February 25, 2016 Per STPs request, the audit will take place at Texas A&M University. STP should provide a conference room for discussions, necessary documents, access to evaluation model outputs, and access to STP staff and/or contractors knowledgeable in the evaluation model, results, and QA program.
DELIVERABLES A regulatory audit summary is usually provided within 90 days of the completion of the audit.
REFERENCES
- 1. Powell, G.T, South Texas Project Nuclear Operating Company, letter to U.S. Nuclear Regulatory Commission, Supplement 2 to STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Address Generic Safety Issue (GSI)-191 and Respond to Generic Letter (GL) 2004-02 (TAC NOS.
MF2400 - MF2409)", NOC-AE-15003241, August 20, 2015, ADAMS Accession No. ML15246A126.
1 NRR-PMDAPEm Resource From:
Regner, Lisa Sent:
Thursday, January 21, 2016 2:04 PM To:
Wayne Harrison Cc:
Michael Murray; Sterling, Lance (lsterling@STPEGS.COM)
Subject:
NRC DRAFT GSI-191 Audit Plan - week of 2/22 Attachments:
DRAFT Audit Plan - QA's Simualtions.docx
- Wayne, Here is a draft of our audit plan for the week of 2/22/16. We are on schedule to get you T-H questions the first week of February.
- Thanks, Lisa
Hearing Identifier:
NRR_PMDA Email Number:
2736 Mail Envelope Properties (Lisa.Regner@nrc.gov20160121140400)
Subject:
NRC DRAFT GSI-191 Audit Plan - week of 2/22 Sent Date:
1/21/2016 2:04:08 PM Received Date:
1/21/2016 2:04:00 PM From:
Regner, Lisa Created By:
Lisa.Regner@nrc.gov Recipients:
"Michael Murray" <mpmurray@STpegs.com>
Tracking Status: None "Sterling, Lance (lsterling@STPEGS.COM)" <lsterling@STPEGS.COM>
Tracking Status: None "Wayne Harrison" <awharrison@STPEGS.COM>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 161 1/21/2016 2:04:00 PM DRAFT Audit Plan - QA's Simualtions.docx 25474 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Audit of South Texas Projects Simulations Used to Support Closure of GSI-191 BACKGROUND By letter dated August 20, 2015 (Reference 1), STP provided Supplement 2 to Risk-Informed Approach for addressing Generic Safety Issues 191. This is the latest from a significant number of references which describe STPs approach and their use of RELAP5-3D.
The NRC staff has proposed to conduct a regulatory audit at this point in the review process in an effort to increase the efficiency of the NRC staffs review. The scope of this audit is to review the recent simulations STP has performed in support of the GSI-191 licensing action request and to discuss the NRCs draft Requests for Additional Information sent by email on January 14, 2016 (ADAMS Accession No. xxxx).
The NRC staff has performed a review of the submitted information and expects the audit to increase their level of knowledge and understanding. The regulatory audit will be held in accordance with NRR procedure as described in LIC-111 Regulatory Audits.
REGULATORY AUDIT SCOPE This audit will focus on STPs simulations of long term core cooling following a loss of coolant accident (LOCA). Specifically, the NRC staff will review the following analysis:
Small break LOCA - cold leg Small break LOCA - hot leg Medium break LOCA - hot leg Large break LOCA - hot leg Additionally, the NRC staff will review the steps taken by STP to perform this analysis under the QA program. Thus, STP should make available any documentation which describes their QA process and/or demonstrates how the RELAP5-3D simulations were performed under STPs QA program.
The NRC staff would like STP to make available the appropriate engineer(s) with knowledge of the RELAP5-3D evaluation model and analysis to address any questions from the NRC staff.
These questions will likely include the following topics:
the progression of the event, the phenomena occurring during the LOCA, how the phenomena has been modeled, how the QA program verifies the input decks TEAM AND REVIEW ASSIGNMENTS
Lisa Regner - Audit Lead, STP Project Manager, Licensing Joshua Kaizer - Technical Lead, Nuclear Performance and Code Review Branch Reed Anzalone - Technical Support, Nuclear Performance and Code Review Branch Steve Bajorek - Technical Support, Office of Research LOGISTICS Audit Dates: Tuesday February 23, 2016 - Thursday February 25, 2016 Per STPs request, the audit will take place at Texas A&M University. STP should provide a conference room for discussions, necessary documents, access to evaluation model outputs, and access to STP staff and/or contractors knowledgeable in the evaluation model, results, and QA program.
DELIVERABLES A regulatory audit summary is usually provided within 90 days of the completion of the audit.
REFERENCES
- 1. Powell, G.T, South Texas Project Nuclear Operating Company, letter to U.S. Nuclear Regulatory Commission, Supplement 2 to STP Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Address Generic Safety Issue (GSI)-191 and Respond to Generic Letter (GL) 2004-02 (TAC NOS.
MF2400 - MF2409)", NOC-AE-15003241, August 20, 2015, ADAMS Accession No. ML15246A126.