MONTHYEARML15324A0142015-11-0606 November 2015 Steam Generator Tube Inspection Report for the Spring 2015 Refueling Outage Project stage: Request ML16069A1362016-03-18018 March 2016 Review of the Spring 2015 Steam Generator Tube Inservice Inspection Report Regarding Surry Power Station, Unit 1, Refueling Outage 26 Project stage: Approval 2015-11-06
[Table View] |
Similar Documents at Surry |
---|
Category:Letter
MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML24003A9022024-01-0303 January 2024 Stations, Units 1 and 2, Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - Editorial Correction IR 05000280/20233012023-12-28028 December 2023 NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23242A2292023-11-0707 November 2023 Issuance of Amendment Nos. 315 and 315, Regarding Emergency Procedure Relocation of the Technical Support Center ML23200A2622023-11-0202 November 2023 Issuance of Amendment Nos. 314 and 314, Regarding Technical Specification and Spent Fuel Pool Criticality Change IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23286A0372023-10-13013 October 2023 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J ML23285A0922023-10-12012 October 2023 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests ML23277A1172023-10-0303 October 2023 Operator Licensing Examination Approval 05000280/2023301 and 05000281/2023301 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 ML23244A0142023-08-30030 August 2023 Inservice Inspection Owner'S Activity Report IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) ML23226A1862023-08-10010 August 2023 Proposed License Amendment Request - Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML23220A1492023-08-0707 August 2023 Independent Spent Fuel Storage Installation - Submittal of Cask Registrations for Spent Fuel Storage ML23220A1482023-08-0707 August 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Response to Request for Additional Information IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23198A0322023-07-18018 July 2023 Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23173A0602023-07-11011 July 2023 Audit Summary for License Amendment Request Revision of the Emergency Plan to Support Relocation of the Technical Support Center ML23136B1392023-06-29029 June 2023 Issuance of Amendment No. 313 Administrative Changes to Subsequent Renewed Operating Licenses and Technical Specifications ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23152A0432023-06-22022 June 2023 Audit Plan License Amendment Requests to Change Emergency Plan Staff Augmentation Times ML23153A1732023-06-16016 June 2023 Correction to Amendment Nos. 346 & 286 Millstone, 294 & 277 North Anna, 311 & 311 Surry, and 225 Summer to Revise Technical Specifications to Adopt TSTF-554,Rev Reactor Coolant Leakage Requirement ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23151A6612023-05-31031 May 2023 ES-2.1-1, Surry 2023-301 Corporate Notification Letter (Revised) ML23167B0072023-05-31031 May 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Supplemental Information - LOCA Dose Calculation Summary ML23117A0952023-05-10010 May 2023 Audit Plan License Amendment Request to Support Relocation of the Technical Support Center ML23130A3742023-05-10010 May 2023 Request to Delay NRC Intial Licensing Examination 2024-02-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 18, 2016 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd.
Glenn Allen, VA 23060
SUBJECT:
SURRY POWER STATION - REVIEW OF THE SPRING 2015 STEAM GENERATOR TUBE INSERVICE INSPECTION REPORT REGARDING SURRY POWER STATION, UNIT 1 REFUELING OUTAGE 26 (TAC NO. MF7123)
Dear Mr. Heacock:
By letter dated November 6, 2015, Virginia Electric Power and Co. (the licensee), submitted information summarizing the results of the spring 2015 steam generator tube inservice inspections performed at Surry Power Station, Unit 1.
The NRC staff has completed its review of the report and concludes that the licensee provided the information required by their technical specifications and that no additional follow-up is required at this time.
If you have any questions regarding this matter, I may be reached at (301) 415-1438 or via e-mail at karen.cotton@nrc.gov.
&,~,~ ro~~c Karen Cotton, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-280
Enclosure:
As stated cc w/encl: Distribution via Listserv
SURRY POWER STATION, UNIT 1
SUMMARY
OF THE STAFF'S REVIEW OF THE SPRING 2015 STEAM GENERATOR TUBE INSERVICE INSPECTIONS FOR REFUELING OUTAGE 26 CAC NO. MF7123 DOCKET NUMBER 50-280 By letter dated November 6, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15324A014), Virginia Electric Power and Co. (the licensee),
submitted information summarizing the results of the spring 2015 steam generator (SG) tube inservice inspections performed at Surry Power Station, Unit 1.
The three replacement SGs at Surry, Unit 1, were installed in 1981. Westinghouse fabricated the replacement SGs and each SG contains 3,342 thermally treated Alloy 600 tubes. Each tube has a nominal outside diameter of 0.875 inches and a nominal wall thickness of 0.050 inches.
The tubes were hydraulically expanded at both ends for the full length of the tubesheet and are supported by a number of stainless steel tube support plates (TSPs). The Li-bends of the tubes installed in rows 1 through 8 were thermally stress relieved after bending.
The licensee provided the scope, extent, methods, and results of their steam generator tube inspections in the document referenced above. In addition, the licensee described corrective actions (e.g., tube plugging) taken in response to the inspection findings. The following observation is noted regarding to the licensee's 2015 inspections:
- The licensee did not detect any cracking during the 2015 inspections; however, one pit indication was identified. This pit indication was discussed in a prior U.S. Nuclear Regulatory Commission review (ADAMS Accession No. ML102580831).
During a conference call on January 19, 2016, the licensee provided additional information regarding the results of the spring 2015 inspections. The contents of the call are summarized below:
- All tubes in SG A and SG C were inspected with bobbin and array probes during the 2015 inspections.
- The four restrictions listed in Table 1 were described as follows:
o A dent between the fourth and fifth cold-leg TSPs at row 5, column 35 (R5C35) in SG A that limits the passage of a 0. 720-inch bobbin probe, but allows passage of a 0. 700-inch bobbin probe.
o A restriction is located at the U-bend tangent point in the tube located at R3C11 in SG A. Two additional restrictions are located at U-bend tangent points in the tubes located in R3C22 and R4C15 in SG C. The three U-bend tangent point restrictions would not allow passage of a 0.720-inch bobbin probe, but did allow passage of a 0.70-inch bobbin probe.
o There were no signs of tube degradation.
Based on a review of the information provided and discussions with the licensee, the NRC staff concludes that the licensee provided the information required by their technical specifications.
The SG tube inspections at Surry, Unit 1, appear to be consistent with the objective of detecting potential tube degradation and the inspection results appear to be consistent with industry operating experience at similarly designed and operated units.
Principal Contributor: A. Huynh, NRR
ML16069A136 OFFICE: DORL/LPL2-1 /PM DORL/LPL2-1 /LA DORL/LPL2-1 /BC DORL/LPL2-1 /PM NAME: KCotton SFigueroa MMarkley KCotton DATE: 03/17/16 03/10/16 03/18/16 03/18/16