Letter Sequence Other |
---|
|
|
MONTHYEARML16039A1212016-02-18018 February 2016 Corrections to Amendment No. 201 Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program Based on Technical Specification Task Force (TSTF) Change TSTF-425 Project stage: Other 2016-02-18
[Table View] |
Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23158A1332023-06-0808 June 2023 Notice of Enforcement Discretion (NOED) for Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000) Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/ Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink ML23130A1032023-05-17017 May 2023 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23114A1172023-05-0101 May 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23115A4152023-04-25025 April 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22325A2992023-02-24024 February 2023 Audit Plan in Support of Review of License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML23200A2162023-01-20020 January 2023 Outline Submittal Letter 2024-02-05
[Table view] Category:Technical Specifications
MONTHYEARML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) NRC-23-0055, NRR E-mail Capture - (External Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-00552023-08-16016 August 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-0055 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) ML21335A2802022-04-0707 April 2022 Issuance of Amendment No. 222 Regarding Revision of Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Several Editorial Changes ML22032A1572022-01-19019 January 2022 Technical Requirements Manual - Vol. 1 Revision 130 Dated 01/19/2022 ML21251A1602021-08-17017 August 2021 Technical Requirements Manual - Vol 1 - (Revision 127 Dated 08/17/2021) ML21053A2022021-02-0101 February 2021 Technical Requirements Manual, Vol 1 - Revision 124 Dated 02/01/2021 ML20233A8382020-10-0505 October 2020 Issuance of Amendment No. 216 - Revision to Technical Specification in Response to GE Energy-Nuclear's 10 CFR Part 21 Safety Communication SC05-03 ML18165A2022018-09-13013 September 2018 Issuance of Amendment Regarding the Adoption of TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities ML16270A5312016-12-15015 December 2016 Fermi, Unit 2, Preoperational Test, Startup Tests and Other Items ML16069A0062016-04-20020 April 2016 Issuance of Amendment Technical Specifications to Adopt Technical Specifications Task Force - 523, Generic Letter 2008-01, Managing Gas Accumulation ML16054A6372016-04-0505 April 2016 Issuance of Amendment to Revise License Amendment Request to Revise Technical Specification Section 3.5.1, Emergency Core Cooling System - Operating Report ML16039A1212016-02-18018 February 2016 Corrections to Amendment No. 201 Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program Based on Technical Specification Task Force (TSTF) Change TSTF-425 ML15233A0842015-09-29029 September 2015 Issuance of Amendment License Amendment Request to Revise the Emergency Action Level Scheme for the Fermi Emergency Plan ML15155B4162015-07-14014 July 2015 Ferm, Uniti 2 - Issuance of Amendment Revise Technical Specifications by Relocating Surveillance Frequencies to Licensee Control in Accordance with Technical Specification Task Force Traveler 425, Revision 3 ML15096A0432015-05-0707 May 2015 Issuance of Amendment Cyber Security Plan Implementation Schedule (Tac No. MF4366) NRC-14-0049, Supplement to License Amendment Request to Revise Technical Specification Surveillance Requirements for Direct Current Batteries2014-06-19019 June 2014 Supplement to License Amendment Request to Revise Technical Specification Surveillance Requirements for Direct Current Batteries ML13364A1312014-02-10010 February 2014 Issuance of Amendment Measurement Uncertainty Recapture Power Uprate ML13346B0672014-02-0404 February 2014 Issuance of Amendment Relocation of Pressure and Temperature Curves to a Pressure Temperature Limits Report ML13112A1422013-05-13013 May 2013 Issuance of Amendment to Revise Technical Specifications to Adopt TSTF-522, Using Consolidated Line Item Improvement Process NRC-13-0004, License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate2013-02-0707 February 2013 License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate NRC-13-0001, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-423, Revision 1, Technical Specifications End States, NEDC-32988-A, Using the Consolidated Line Item Improvement Process2013-01-11011 January 2013 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-423, Revision 1, Technical Specifications End States, NEDC-32988-A, Using the Consolidated Line Item Improvement Process NRC-12-0037, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report2012-12-21021 December 2012 Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report NRC-12-0037, Fermi 2, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report2012-12-21021 December 2012 Fermi 2, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report NRC-12-0071, Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item Improvement Process2012-11-13013 November 2012 Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Using the Consolidated Line Item Improvement Process NRC-12-0005, Proposed License Amendment to Revise the Residual Heat Removal Suppression Pool Cooling Flow Rate in Technical Specification Surveillance Requirement 3.6.2.3.22012-01-10010 January 2012 Proposed License Amendment to Revise the Residual Heat Removal Suppression Pool Cooling Flow Rate in Technical Specification Surveillance Requirement 3.6.2.3.2 NRC-12-0004, Proposed License Amendment to Modify Technical Specification Surveillance Requirements for Safety Relief Valves2012-01-10010 January 2012 Proposed License Amendment to Modify Technical Specification Surveillance Requirements for Safety Relief Valves NRC-11-0049, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration.2011-12-20020 December 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration. NRC-11-0030, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control.2011-08-12012 August 2011 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control. NRC-11-0013, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation.2011-04-0808 April 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation. ML1013408512010-05-14014 May 2010 Revised Clean TS Pages NRC-10-0003, Proposed License Amendment to Revise the Core Spray Flow Requirement of Technical Specification Surveillance Tests SR 3.5.1.8 and SR 3.5.2.62010-01-0404 January 2010 Proposed License Amendment to Revise the Core Spray Flow Requirement of Technical Specification Surveillance Tests SR 3.5.1.8 and SR 3.5.2.6 NRC-09-0022, Proposed License Amendment to Revise the Degraded Voltage Function Requirements of Technical Specification Table 3.3.8.1-1 to Reflect Undervoltage Backfit Modification2009-06-10010 June 2009 Proposed License Amendment to Revise the Degraded Voltage Function Requirements of Technical Specification Table 3.3.8.1-1 to Reflect Undervoltage Backfit Modification NRC-08-0061, Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification2008-09-12012 September 2008 Proposed License Amendment to Remove Statements Related to Nuclear Power Plant Staff Working Hours in Technical Specification ML0812808342008-06-25025 June 2008 Tech Spec Pages for Amendment 180 Delete the Note Associated with the Performance of Channel Calibration for Primary Containment High Range Radiation Monitor in Technical Specification 3.3.3.1 Surveillance Requirements ML0807900262008-03-17017 March 2008 Issuance of Amendment Technical Specification Change to Emergency Diesel Generator Surveillance Requirements NRC-08-0001, Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency and a Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process2008-01-15015 January 2008 Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency and a Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process ML0721404442007-08-0101 August 2007 Tech Spec Pages for Amendment Consolidated Line Item Improvement Process (Cllip) for Technical Specification Change (TSTF-427) to Add Limiting Condition for Operation (LCO) 30.9 Regarding the Unavailability of Barriers ML0721407632007-08-0101 August 2007 Technical Specification 3.8.1 Extension of the Completion Time for an Inoperable Diesel Generator Amendment ML0715002322007-04-12012 April 2007 Technical Specifications, Application for Technical Specification Change TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for the Diesel Fuel Oil Testing Programs Using the Consolidated Line Item Improvement Process NRC-07-0012, Proposed License Amendment to Revise the Minimum Emergency Diesel Generator Voltage in Technical Specification 3.8.1 Surveillance Requirements2007-03-19019 March 2007 Proposed License Amendment to Revise the Minimum Emergency Diesel Generator Voltage in Technical Specification 3.8.1 Surveillance Requirements NRC-07-0001, Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 Regarding the Unavailability of Barriers Using the Consolidated Line Item Improvement Process2007-01-26026 January 2007 Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 Regarding the Unavailability of Barriers Using the Consolidated Line Item Improvement Process ML0622004402006-08-0707 August 2006 Technical Specifications, Changes to Address Issues Related to an Inconsistency That Was Inadvertently Introduced During Conversion to Improved TSs When 1 Per Room Replaced 2 as the Required Channels Per Trip System NRC-06-0044, Response to Request for Additional Information for Revision to License Amendment Request to Revise Technical Specification 3.3.6.1, Primary Containment Isolation Instrumentation2006-07-12012 July 2006 Response to Request for Additional Information for Revision to License Amendment Request to Revise Technical Specification 3.3.6.1, Primary Containment Isolation Instrumentation NRC-06-0040, Proposed License Amendment Request to Extend the Completion Time for Technical Specification 3.8.1 for an Inoperable Emergency Diesel Generator2006-07-12012 July 2006 Proposed License Amendment Request to Extend the Completion Time for Technical Specification 3.8.1 for an Inoperable Emergency Diesel Generator ML0604800392006-02-15015 February 2006 Tech Spec Pages for Amendment 172 Regarding Consolidated Line Item Improvement for Snubbers ML0603704972006-02-0606 February 2006 Tech Spec Pages for Amendment 171 Allowed Outage Time Extension for Emergency Diesel Generator 12 for One Specific Incident 2023-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 18, 2016 Mr. Paul Fessler Senior Vice President and Chief Nuclear Officer DTE Electric Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, Ml 48166
SUBJECT:
FERMI 2 - CORRECTIONS TO AMENDMENT NO. 201 REGARDING RELOCATION OF SPECIFIC SURVILLANCE FREQUENCIES TO A LICENSEE-CONTROLLED PROGRAM BASED ON TECHNICAL SPECIFICATION TASK FORCE CHANGE TSTF-425 (CAC NO. MF7296)
Dear Mr. Fessler:
On July 14, 2015, the U.S. Nuclear Regulatory Commission (NRC) issued License Amendment No. 201 to Renewed Facility Operating License No. NPF-43 for the Fermi 2 facility (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15155B416). This amendment consisted of changes to the technical specifications (TSs) and Renewed Facility Operating License in response to your application dated September 16, 2014 (ADAMS Accession No. ML14259A564), as supplemented by letter dated April 17, 2015 (ADAMS Accession No. ML15107A407). The amendment modified the TSs by relocating specific surveillance frequencies to a licensee-controlled program based on TS Task Force (TSTF)
Change TSTF-425.
On January 29, 2016, the NRC staff identified an error in the TSs for Fermi 2. Upon further review, it was determined some of the clean pages prepared to support issuance of the amendment contained format and typographical errors; therefore, additional TS pages needed to be corrected. The NRC has reviewed the corrected TS pages attached and determined that they are consistent with the proposed TS markups included in the application dated September 16, 2014, and the errors were inadvertently introduced in License Amendment No. 201, dated July 14, 2015. The specific corrections are described below.
- 1. TS page 3.2-4-the heading "3.2.3 LINEAR HEAT GENERATION RATE (LHGR)" was corrected from "3.2.1."
- 2. TS page 3.3 the words "FUNCTIONAL TEST" in SR 3.3.1.1.5 were capitalized.
- 3. TS pages 3.5-7 and 3.6-21-SRs3.5.1.13 and 3.6.1.6.1 should state, " ... valve is capable of being opened" instead of, " ... valve opens when manually actuated." The change to the SRs were approved by License Amendment No. 190 issued in letter dated December 21, 2012 (ADAMS Accession No. ML12321A234).
- 4. TS page 3.6 SR 3.6.2.3 should state. "Verify each required RHR pump develops a flow rate~ 9,250 gpm through the associated heat exchanger while operating in the suppression pool cooling mode." The change from 10,000 gpm to 9,250 gpm was
P. Fessler approved by License Amendment No. 191 issued in letter dated December 21, 2012 (ADAMS Accession No. ML12333A327).
- 5. TS page 3.6 SR 3.6.4.3.1 should state, " ... 15 continuous minutes" instead of" 10 continuous hours." The change to this SR was approved by License Amendment No. 192 issued in letter dated May 13, 2013 (ADAMS Accession No. ML13112A142).
- 6. TS page 3.10 SR 3.10.5.5 should state, "Verify no other CORE ALTERATIONS are in progress." The addition of the word "other" was approved by License Amendment No. 134 issued in letter dated September 30, 1999 (ADAMS Legacy Accession No. 99102201218).
- 7. TS pages 3.1-17, 3.1-19, 3.6-32, 3. 7 spaces were added to properly align the text in the REQUIRED ACTION or CONDITION columns.
The NRC staff concludes that the errors were introduced during preparation of the license amendment and are entirely editorial in nature. The proposed correction does not change any of the conclusions in the safety evaluation associated with the amendment and does not affect the associated notice to the public. Enclosed are the corrected TS pages for License Amendment No. 201 for the Fermi 2 facility. Please replace the affected pages in the Fermi 2 TSs with the enclosed pages.
If you have any questions regarding this matter, please call me at (301) 415-1530.
Sincerely, 3_)'\A~~-
Jennivine K. Rankin, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Corrected Pages to License Amendment No. 201 cc w/encl: Distribution via Listserv
ENCLOSURE FERMI 2 DOCKET NO. 50-341 CORRECTED PAGES TO LICENSE AMENDMENT NO. 201 TECHNICAL SPECIFICATIONS PAGE 3.1-17 PAGE 3.1-19 PAGE 3.2-4 PAGE 3.3-5 PAGE 3.5-7 PAGE 3.6-21 PAGE 3.6-32 PAGE 3.6-34 PAGE 3.6-50 PAGE 3.7-2 PAGE 3.10-15
Control Rod Scram Accumulators 3.1.5 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
- c. One or more control C.l Verify all control Immediately upon rod scram accumulators rods associated with discovery of inoperable with inoperable charging water reactor steam dome accumulators are header pressure pressure < 900 psig. fully inserted. < 940 psig AND C.2 Declare the 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> associated control rod inoperable.
D. Required Action and D.l --------NOTE ---------
associated Completion Not applicable if all Time of Required inoperable control Action B.l or C.l not rod scram met. accumulators are associated with fully inserted control rods .
Place the reactor Immediately mode switch in the shutdown position.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3 .1. 5.1 Verify each control rod scram accumulator In accordance pressure is ~ 940 psig. with the Surveillance Frequency Control Program FERMI - UNIT 2 3.1-17 Amendment No. ~. 201
Rod Pattern Control 3.1.6 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME B. Nine or more OPERABLE B.1 -- -- ----NOTE ------ ---
control rods not in Rod worth minimizer compliance with the (RWM) may be bypassed prescribed withdrawal as a11 owed by sequence. LCO 3 . 3 . 2. 1.
Suspend withdrawal of Immediately control rods.
AND B.2 Place the reactor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> mode switch in the shutdown position.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3 .1.6.1 Verify all OPERABLE control rods comply In accordance with the prescribed withdrawal sequence. with the Surveillance Frequency Control Program FERMI - UNIT 2 3.1-19 Amendment No. !J4, 201
LHGR 3.2.3 3.2 POWER DISTRIBUTION LIMITS 3.2.3 LINEAR HEAT GENERATION RATE (LHGR)
LCO 3.2.3 All LHGRs shall be less than or equal to the limits specified in the COLR.
APPLICABILITY: THERMAL POWER ~ 25% RTP.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Any LHGR not within A.1 Restore LHGR(s) to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> limits. within limits.
B. Required Action and B.l Reduce THERMAL POWER 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> associated Completion to< 25% RTP.
Time not met.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.2.3.1 Verify all LHGRs are less than or equal Once within to the limits specified in the COLR. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
~ 25% RPT AND In accordance with the Surveillance Frequency Control Program FERMI - UNIT 2 3.2-4 Amendment No. ~. 201
RPS Instrumentation 3.3.1.1 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3 . 3 . 1. 1. 5 Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program SR 3. 3. 1. 1. 6 Verify the source range monitor (SRM) and Prior to fully intermediate range monitor (!RM) channels withdrawing overlap. SRMs from the core SR 3. 3. 1. 1. 7 --- ---------------NOTE ------------- -----
Only required to be met during entry into MODE 2 from MODE 1.
Verify the IRM and APRM channels overlap. In accordance with the Surveillance Frequency Control Program SR 3 . 3. 1. 1. 8 Calibrate the local power range monitors. In accordance with the Surveillance Frequency Control Program SR 3 . 3. 1. 1. 9 Perform CHANNEL FUNCTIONAL TEST. In accordance with the Surveillance Frequency Control Program (continued)
FERMI - UNIT 2 3.3-5 Amendment No.-+/-J4. 201
ECCS-Operati ng 3.5.1 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3 . 5 . 1 . 11 - - - - - -- - - - - - - -- - - - - NOTE --------------------
Vessel injection/spray may be excluded.
Verify each ECCS injection/spray subsystem In accordance actuates on an actual or simulated with the automatic initiation signal. Surveillance Frequency Control Program SR 3 . 5. 1. 12 -------------------NOTE - ----------- --------
Valve actuation may be excluded.
Verify the ADS actuates on an actual or In accordance simulated automatic initiation signal. with the Surveillance Frequency Control Program SR 3.5.1.13 Verify each ADS valve is capable of being In accordance opened. with the Surveillance Frequency Control Program SR 3 . 5 .1 .14 ------- ------------NOTE - --- ------ --- -------
ECCS instrumentation response times are not required to be measured.
Verify ECCS RESPONSE TIME is within limits. In accordance with the Surveillance Frequency Control Program FERMI - UNIT 2 3.5-7 Amendment No. ~ ~. 201
LLS Valves 3.6.1.6 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3. 6 . 1. 6 . 1 Verify each LLS valve is capable of being In accordance opened. with the Surveillance Frequency Control Program SR 3 .6 . 1. 6 .2 ---- ---- ----------NOTE -------------- -----
Valve actuation may be excluded.
Verify the LLS System actuates on an In accordance actual or simulated automatic initiation with the signal. Surveillance Frequency Control Program FERMI - UNIT 2 3.6-21 Amendment No. l.J4 +/-9-0, 201
Suppression Pool Water Level 3.6.2.2 3.6 CONTAINMENT SYSTEMS 3.6.2.2 Suppression Pool Water Level LCO 3.6.2.2 Suppression pool water level shall be~ -2 inches and s +2 inches.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Suppression pool water A.1 Restore suppression 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> level not within pool water level to limits. within limits.
B. Required Action and B.l Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. -AND B.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.2.2.1 Verify suppression pool water level is In accordance within limits. with the Surveillance Frequency Control Program FERMI - UNIT 2 3.6-32 Amendment No. +/-J4, 201
RHR Suppression Pool Cooling 3.6.2.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.2.3.1 Verify each RHR suppression pool cooling In accordance subsystem manual. power operated. and with the automatic valve in the flow path that is Surveillance not locked. sealed, or otherwise secured Frequency in position is in the correct position or Control Program can be aligned to the correct position.
SR 3.6.2.3.2 Verify each required RHR pump develops a In accordance flow rate ~ 9,250 gpm through the with the associated heat exchanger while operating Inservice in the suppression pool cooling mode. Testing Program FERMI - UNIT 2 3.6-34 Amendment No. !J4. +/-9-+/-, 201
SGT System 3.6.4.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.4.3.1 Operate each SGT subsystem for ~ 15 In accordance continuous minutes with heaters with the operating. Surveillance Frequency Control Program SR 3.6.4.3.2 Perform required SGT filter testing in In accordance accordance with the Ventilation Filter with the VFTP Testing Program (VFTP).
SR 3.6.4.3.3 Verify each SGT subsystem actuates on an In accordance actual or simulated initiation signal. with the Surveillance Frequency Control Program SR 3.6.4.3.4 Verify each SGT filter cooler bypass In accordance damper can be opened and the fan started. with the Surveillance Frequency Control Program FERMI - UNIT 2 3.6-50 Amendment No. ~. ~. 201
RHRSW System 3.7.1 ACTIONS (continued)
CONDITION REQUIRED ACT! ON COMPLETION TIME D. Required Action and D.l -- ------NOTE ----- ----
associated Completion LCD 3.0.4.a is not Time of Condition A, applicable when B, or C not met. entering MODE 3.
Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> E. Both RHRSW subsystems E.l -- -- ----NOTE ------ ---
inoperable for reasons Enter applicable other than Conditions and Condition B. Required Actions of LCD 3.4.8 for RHR shutdown cooling made inoperable by RHRSW System .
Restore one RHRSW 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> subsystem to OPERABLE status.
F. Required Action and F.1 Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition E AND not met.
F.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3 .7 .1.1 Verify each RHRSW manual, power operated. In accordance and automatic valve in the flow path, that with the is not locked, sealed, or otherwise secured Surveillance in position, is in the correct position or Frequency can be aligned to the correct position. Control Program FERMI - UNIT 2 3.7-2 Amendment No. ~ +/-94, 201
Single CRD Removal-Refueling 3.10.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.10.5.1 Verify all control rods. other than the In accordance control rod withdrawn for the removal of with the the associated CRD. are fully inserted. Surveillance Frequency Control Program SR 3.10.5.2 Verify all control rods. other than the In accordance control rod withdrawn for the removal of with the the associated CRD. in a five by five array Surveillance centered on the control rod withdrawn for Frequency the removal of the associated CRD. are Control Program disarmed.
SR 3.10.5.3 Verify a control rod withdrawal block is In accordance inserted. with the Surveillance Frequency Control Program SR 3.10.5.4 Perform SR 3.1.1.1. According to SR 3.1.1.1 SR 3.10.5.5 Verify no other CORE ALTERATIONS are in In accordance progress. with the Surveillance Frequency Control Program FERMI
- UNIT 2 3.10-15 Amendment No. +/-J4, 201
ML12333A327).
- 5. TS page 3.6 SR 3.6.4.3.1 should state, " ... 15 continuous minutes" instead of "10 continuous hours." The change to this SR was approved by License Amendment No.
192 issued in letter dated May 13, 2013 (ADAMS Accession No. ML13112A142).
- 6. TS page 3.10 SR 3.10.5.5 should state, "Verify no other CORE ALTERATIONS are in progress." The addition of the word "other was approved by License Amendment No. 134 issued in letter dated September 30, 1999 (ADAMS Legacy Accession No. 9910220121B).
- 7. TS pages 3.1-17, 3.1-19, 3.6-32, 3.7 spaces were added to properly align the text in the REQUIRED ACTION or CONDITION columns.
The NRC staff concludes that the errors were introduced during preparation of the license amendment and is entirely editorial in nature. The proposed correction does not change any of the conclusions in the safety evaluation associated with the amendment and does not affect the associated notice to the public. Enclosed are the corrected TS pages for License Amendment No. 201 for the Fermi 2 facility. Please replace the affected pages in the Fermi 2 TSs with the enclosed pages.
If you have any questions regarding this matter, please call me at (301) 415-1530.
Sincerely, IRA/
Jennivine K. Rankin, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Corrected Pages to License Amendment No. 201 cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsRgn3MailCenter Resource LPL3-1 R/F RidsNrrLAMHenderson Resource RidsNrrPMFermi Resource RecordsAmend Resource RidsNrrDorlLpl3-1 Resource RidsAcrsAcnm_MailCTR Resource ADAMS Accession No.: ML16039A121 OFFICE DORL/LPLI 11-1 /PM DORL/LPLlll-1/LA DORL/LPLI 11-1 /BC DORL/LPLlll-1/PM NAME JRankin MHenderson DWrona JRankin DATE 2/10/2016 2/10/2016 2/18/2016 2/18/2016