ML16029A351

From kanterella
Jump to navigation Jump to search
Summary of January 19, 2016, Pre-Submittal Meeting with Tennessee Valley Authority Regarding Technical Specifications for Sequoyah Nuclear Plant, Units 1 and 2
ML16029A351
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/05/2016
From: Andrew Hon
Plant Licensing Branch II
To:
Tennessee Valley Authority
Hon A, NRR/DORL/LPL1-2
References
Download: ML16029A351 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001

-February 5, 2016 LICENSEE: Tennessee Valley Authority FACILITY: Sequoyah Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF JANUARY 19, 2016, PRE-SUBMITTAL MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING TECHNICAL SPECIFICATIONS FOR SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 On January 19, 2016, a Category 1 public meeting by telephone was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.

The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System at Accession No. ML16007A184. A list of attendees is enclosed.

The purpose of this meeting was to discuss a proposal submittal by TVA after a similar license amendment request (LAR) was withdrawn on October 22, 2015. This LAR is to allow 7-day completion time (CT) to restore one train of the essential raw cooling water (ERCW) to OPERABLE status to facilitate the shutdown board maintenance under certain restrictions.

The current 72-hour CT would require a dual unit shutdown if the ERCW is not restored in 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. TVA requests that the NRC staff expedite the review of this reduced scope submittal to support the fall outage in November 2016.

Using ML16029A063, TVA presented its approach and expected changes to the technical specifications (TSs) and responded to the clarification question from the NRC staff. Significant points are summarized as follows:

  • The sole purpose of this LAR is to enable TVA to perform the deferred shutdown board cleaning beginning in the upcoming Unit 2 fall outage without the unnecessary dual unit shutdown. If additional operational flexibility is desired, TVA may submit a separate LAR to expand the scope in a future date.
  • Since the NRC staff cannot credit information contained in the prior submittal that has been.

withdrawn, TVA needs to ensure that this submittal is self-contained, including the responses to the applicable request for additional information from the previous submittal.

  • The added restrictions for the 7-day CT will be consistent with Electrical Power Systems, Section 3.8.9 of the TSs recently approved by the NRC as part of the improved TSs conversion.
  • TVA plans to submit this LAR by mid-February of 2016.

No regulatory decisions were made at this meeting. No members of the public called in to listen or provide comments to the staff after the business portion of the meeting. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-8480 or Andrew.Hon@nrc.gov.

Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328

Enclosures:

List of Attendees cc w/enclosure: Distribution via Listserv

LIST OF ATTENDEES JANUARY 19, 2016, PRE-SUBMITTAL MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING PROPOSED TECHNICAL SPECIFICATION CHANGES SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 Tennessee Valley Authority Tom Hess Ed Craig Paul Parashak Ed Schrull Mike McBrearty U.S. Nuclear Regulatory Commission Andy Hon

  • Greg Casto Matt Hamm Vijay Goel Nick Hobbs None Enclosure

No regulatory decisions were made at this meeting. No members of the public called in to listen or provide comments to the staff after the business portion of the meeting. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-8480 or Andrew.Hon@nrc.gov.

/RA/

Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328

Enclosures:

List of Attendees cc w/enclosure: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDssSbpb Resource LWheeler, NRR RidsRgn2MailCenter Resource RidsNrrDssStsb Resource MHamm, NRR RidsNrrLABClayton Resource RidsNrrPMSequoyah Resource VGoel, NRR RidsNrrDorllpl2-2 Resource RidsNrrLABClayton Resource TWertz, NRR RidsNrrDssSrxb Resource LPL2-2 R/F CRosales-Cooper, OEDO RidsACRS_MailCTR Resource NHobbs, NRR ADAMS Accession No.: ML16029A351 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC DORL/LPL2-2/PM NAME BClayton BBeasley AH on AH on (LRonewicz)

DATE 02/03/16 02/03/16 02/05/16 / 02/05/16 OFFICIAL RECORD COPY

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001

-February 5, 2016 LICENSEE: Tennessee Valley Authority FACILITY: Sequoyah Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF JANUARY 19, 2016, PRE-SUBMITTAL MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING TECHNICAL SPECIFICATIONS FOR SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 On January 19, 2016, a Category 1 public meeting by telephone was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.

The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System at Accession No. ML16007A184. A list of attendees is enclosed.

The purpose of this meeting was to discuss a proposal submittal by TVA after a similar license amendment request (LAR) was withdrawn on October 22, 2015. This LAR is to allow 7-day completion time (CT) to restore one train of the essential raw cooling water (ERCW) to OPERABLE status to facilitate the shutdown board maintenance under certain restrictions.

The current 72-hour CT would require a dual unit shutdown if the ERCW is not restored in 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. TVA requests that the NRC staff expedite the review of this reduced scope submittal to support the fall outage in November 2016.

Using ML16029A063, TVA presented its approach and expected changes to the technical specifications (TSs) and responded to the clarification question from the NRC staff. Significant points are summarized as follows:

  • The sole purpose of this LAR is to enable TVA to perform the deferred shutdown board cleaning beginning in the upcoming Unit 2 fall outage without the unnecessary dual unit shutdown. If additional operational flexibility is desired, TVA may submit a separate LAR to expand the scope in a future date.
  • Since the NRC staff cannot credit information contained in the prior submittal that has been.

withdrawn, TVA needs to ensure that this submittal is self-contained, including the responses to the applicable request for additional information from the previous submittal.

  • The added restrictions for the 7-day CT will be consistent with Electrical Power Systems, Section 3.8.9 of the TSs recently approved by the NRC as part of the improved TSs conversion.
  • TVA plans to submit this LAR by mid-February of 2016.

No regulatory decisions were made at this meeting. No members of the public called in to listen or provide comments to the staff after the business portion of the meeting. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-8480 or Andrew.Hon@nrc.gov.

Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328

Enclosures:

List of Attendees cc w/enclosure: Distribution via Listserv

LIST OF ATTENDEES JANUARY 19, 2016, PRE-SUBMITTAL MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING PROPOSED TECHNICAL SPECIFICATION CHANGES SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 Tennessee Valley Authority Tom Hess Ed Craig Paul Parashak Ed Schrull Mike McBrearty U.S. Nuclear Regulatory Commission Andy Hon

  • Greg Casto Matt Hamm Vijay Goel Nick Hobbs None Enclosure

No regulatory decisions were made at this meeting. No members of the public called in to listen or provide comments to the staff after the business portion of the meeting. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-8480 or Andrew.Hon@nrc.gov.

/RA/

Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328

Enclosures:

List of Attendees cc w/enclosure: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDssSbpb Resource LWheeler, NRR RidsRgn2MailCenter Resource RidsNrrDssStsb Resource MHamm, NRR RidsNrrLABClayton Resource RidsNrrPMSequoyah Resource VGoel, NRR RidsNrrDorllpl2-2 Resource RidsNrrLABClayton Resource TWertz, NRR RidsNrrDssSrxb Resource LPL2-2 R/F CRosales-Cooper, OEDO RidsACRS_MailCTR Resource NHobbs, NRR ADAMS Accession No.: ML16029A351 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC DORL/LPL2-2/PM NAME BClayton BBeasley AH on AH on (LRonewicz)