- En tergy Entergy Nuclear Operations, Inc.
John A. Dent, jr November 20, 2015 U.S. Nuclear Regulatory-Commission Attn:. Document Control Desk Washington, DC 20555
SUBJECT:
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 Final Safety Analysis Report Update Revision 30, Technical Specifications Bases Changes, 10 CFR 50.59(d) Report, and Regulatory Commitment Changes LETTER NUMBER:
2.15.072.
This letter submits Final Safety Analysis Report (FSAR) Revision 30 update pages for Pilgrim Nuclear Power Station. This update is submitted in accordance with 10 Code of Federal Regulations (CFR) 50.71(e) requirements and includes changes implemented during Fuel Cycle 20, ending with refueling outage 20 as contained in Attachments 1 and 2.
Additionally, Technical Specification Bases changes that were made are *provided in Attachment
- 3. There were no 10 CFR 50.59 Safety Evaluations performed during :Fuel Cycle 20. There were no Regulatory Commitment changes performed during Fuel Cycle 20.
There are no new regulatory commitments contained in this letter.
Should you have any questions concerning the content of this letter, please contact Mr. Everett (Chip) Perkins Jr. at (508) 830-8323.
I declare, under penalty of perjury that t~he foregoing is true and correct; executed on November 20, 2015.
Sincerely,
/.hn A. Dent, Jr, Uj
- .jieVice Preside~nt JAD/rrmb
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Letter Number: 2,15, 072 Page 2 of 2 : : :
Filing Instructions for FSAR Revision 30 Change-out pages (7 Pages)
FSAR Revision 30 Change-out pages (See Filing Instructions)
Technical Specification Bases Changes (6 Pages) cc: wICD of complete FSAR, w/o Attachments 1 and 2 Mr. Daniel H. Dorman Regional Administrator, Region I U.S. Nuclear Regulatory Commission, 2100 Renaissance Boulevard, Suite 100 King of Prussia, PA 19406-1415 Ms. Booma Venkataraman, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail StopO-8C2A Washington, DC 20555 NRC,Senior Resident Inspector Pilgrim Nuclear Power Station
- En tergy Entergy Nuclear Operations, Inc.
John A. Dent, jr November 20, 2015 U.S. Nuclear Regulatory-Commission Attn:. Document Control Desk Washington, DC 20555
SUBJECT:
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 Final Safety Analysis Report Update Revision 30, Technical Specifications Bases Changes, 10 CFR 50.59(d) Report, and Regulatory Commitment Changes LETTER NUMBER:
2.15.072.
This letter submits Final Safety Analysis Report (FSAR) Revision 30 update pages for Pilgrim Nuclear Power Station. This update is submitted in accordance with 10 Code of Federal Regulations (CFR) 50.71(e) requirements and includes changes implemented during Fuel Cycle 20, ending with refueling outage 20 as contained in Attachments 1 and 2.
Additionally, Technical Specification Bases changes that were made are *provided in Attachment
- 3. There were no 10 CFR 50.59 Safety Evaluations performed during :Fuel Cycle 20. There were no Regulatory Commitment changes performed during Fuel Cycle 20.
There are no new regulatory commitments contained in this letter.
Should you have any questions concerning the content of this letter, please contact Mr. Everett (Chip) Perkins Jr. at (508) 830-8323.
I declare, under penalty of perjury that t~he foregoing is true and correct; executed on November 20, 2015.
Sincerely,
/.hn A. Dent, Jr, Uj
- .jieVice Preside~nt JAD/rrmb
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Letter Number: 2,15, 072 Page 2 of 2 : : :
Filing Instructions for FSAR Revision 30 Change-out pages (7 Pages)
FSAR Revision 30 Change-out pages (See Filing Instructions)
Technical Specification Bases Changes (6 Pages) cc: wICD of complete FSAR, w/o Attachments 1 and 2 Mr. Daniel H. Dorman Regional Administrator, Region I U.S. Nuclear Regulatory Commission, 2100 Renaissance Boulevard, Suite 100 King of Prussia, PA 19406-1415 Ms. Booma Venkataraman, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail StopO-8C2A Washington, DC 20555 NRC,Senior Resident Inspector Pilgrim Nuclear Power Station