>Domininno Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 December 29, 2015 Attention: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Serial No.:
NL&OSITJS:
Docket Nos.:
License Nos.:
15-538 R0 5 0-3 36/42 3 50-338/339 50-280/281 DPR-65 NPF-49 DOMINION NUCLEAR CONNECTICUT. INC.
NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY DPR-32/3"*
MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 COMMITMENT TO MAINTAIN SEVERE ACCIDENT MANAGEMENT GUIDELINES 7
The Nuclear Energy Institute (NEI) Nuclear Strategic Issues Advisory Committee (NSIAC) recently approved an Industry Initiative to implement and maintain Severe Accident Management Guidelines (SAMGs).
This letter establishes commitments related to SAMGs for Millstone Power Station Units 2 and 3 (MPS2 and 3), North Anna Power Station Units 1 and 2 (NAPSI and 2), and Surry Power Station Units I and 2 (SPSI and 2).
These guidelines would be used by emergency response personnel during accident conditions that progress beyond the mitigation capabilities described in Emergency Operating Procedures (EOPs).
SAMG strategies are intended to arrest the progression of fuel damage, maintain the capability of the containment as long as possible, and minimize radiological releases.
The new SAMG commitments are listed in Attachment 1.
It is expected that NRC staff personnel will conduct periodic inspection of our SAMGs and performance deficiencies, if any, will be assessed using the Reactor Oversight Process.
We also understand that inspection activities will not extend to NRC review and approval of SAMG strategies, or the use of equipment described in the SAMGs.
If you have any questions, please contact Mr. Thomas Szymanski at 804-273-3065.
Sincerely, David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company,
Serial No.15-538 SAMG Commitments Page 2 of 3
Attachment:
- 1. List of Regulatory Commitments Associated with SAMGs for Millstone Power Station Units 2 and 3, North Anna Power Station Units 1 and 2, and Surry Power Station Units 1 and 2 Commitments made by this letter: See Attachment 1 cc:
U. S. Nuclear Regulatory Commission, Region I 2100 Renaissance Blvd.
Suite 100 King of Prussia, Pennsylvania 19406-2713 U. S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1 257 U. S. Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. R. V. Guzman NRC Senior Project Manager Millstone Units 2 and 3 U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton Gross NRC Project Manager Surry U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738
Serial No.15-538 SAMG Commitments Page 3 of 3 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station
Serial No.15-538 Docket Nos. 50-336,423,338,339,280,281 List of Reqiulatory Commitments Associated with SAMGs for Millstone Power Station Units 2 and 3. North Anna Power Station Units I and 2. and Surry Power Station Units I and 2 Dominion Nuclear Connecticut, Inc.
Virginia Electric and Power Company
Serial No.15-538 Docket Nos. 50-336,423,338,339,280,281 List of Regulatory Commitments The following table identifies those actions committed to by Millstone Power Station (MPS) Units 2 and 3, North Anna Power Station (NAPS) Units I and 2, and Surry Power Station (SPS) Units 1 and 2 in this document.
Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE (Check One)
SCHEDULED COMITMNT NE-CONTINUING COMPLETION DATE TIME ACTION COMPLIANCE MPS2 and 3, NAPS1 and 2, and SPSI and X
October 31, 2016 2 will consider the site SAMGs within plant configuration management processes in order to ensure that the SAMGs reflect changes to the facility over time.
MPS2 and 3, NAPS1I and 2, and SPSI and X
Within 2 refueling 2 will update the site SAMGs to future outages or 3 years revisions of the PWROG generic severe of the publication accident technical guidelines, and the date of the SAMGs will be integrated with other guidelines, emergency response guideline sets and whichever is greater symptom-based Emergency Operating Procedures, and validated, using the guidance in NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents.
>Domininno Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 December 29, 2015 Attention: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Serial No.:
NL&OSITJS:
Docket Nos.:
License Nos.:
15-538 R0 5 0-3 36/42 3 50-338/339 50-280/281 DPR-65 NPF-49 DOMINION NUCLEAR CONNECTICUT. INC.
NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY DPR-32/3"*
MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 COMMITMENT TO MAINTAIN SEVERE ACCIDENT MANAGEMENT GUIDELINES 7
The Nuclear Energy Institute (NEI) Nuclear Strategic Issues Advisory Committee (NSIAC) recently approved an Industry Initiative to implement and maintain Severe Accident Management Guidelines (SAMGs).
This letter establishes commitments related to SAMGs for Millstone Power Station Units 2 and 3 (MPS2 and 3), North Anna Power Station Units 1 and 2 (NAPSI and 2), and Surry Power Station Units I and 2 (SPSI and 2).
These guidelines would be used by emergency response personnel during accident conditions that progress beyond the mitigation capabilities described in Emergency Operating Procedures (EOPs).
SAMG strategies are intended to arrest the progression of fuel damage, maintain the capability of the containment as long as possible, and minimize radiological releases.
The new SAMG commitments are listed in Attachment 1.
It is expected that NRC staff personnel will conduct periodic inspection of our SAMGs and performance deficiencies, if any, will be assessed using the Reactor Oversight Process.
We also understand that inspection activities will not extend to NRC review and approval of SAMG strategies, or the use of equipment described in the SAMGs.
If you have any questions, please contact Mr. Thomas Szymanski at 804-273-3065.
Sincerely, David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company,
Serial No.15-538 SAMG Commitments Page 2 of 3
Attachment:
- 1. List of Regulatory Commitments Associated with SAMGs for Millstone Power Station Units 2 and 3, North Anna Power Station Units 1 and 2, and Surry Power Station Units 1 and 2 Commitments made by this letter: See Attachment 1 cc:
U. S. Nuclear Regulatory Commission, Region I 2100 Renaissance Blvd.
Suite 100 King of Prussia, Pennsylvania 19406-2713 U. S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1 257 U. S. Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. R. V. Guzman NRC Senior Project Manager Millstone Units 2 and 3 U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton Gross NRC Project Manager Surry U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738
Serial No.15-538 SAMG Commitments Page 3 of 3 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station
Serial No.15-538 Docket Nos. 50-336,423,338,339,280,281 List of Reqiulatory Commitments Associated with SAMGs for Millstone Power Station Units 2 and 3. North Anna Power Station Units I and 2. and Surry Power Station Units I and 2 Dominion Nuclear Connecticut, Inc.
Virginia Electric and Power Company
Serial No.15-538 Docket Nos. 50-336,423,338,339,280,281 List of Regulatory Commitments The following table identifies those actions committed to by Millstone Power Station (MPS) Units 2 and 3, North Anna Power Station (NAPS) Units I and 2, and Surry Power Station (SPS) Units 1 and 2 in this document.
Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE (Check One)
SCHEDULED COMITMNT NE-CONTINUING COMPLETION DATE TIME ACTION COMPLIANCE MPS2 and 3, NAPS1 and 2, and SPSI and X
October 31, 2016 2 will consider the site SAMGs within plant configuration management processes in order to ensure that the SAMGs reflect changes to the facility over time.
MPS2 and 3, NAPS1I and 2, and SPSI and X
Within 2 refueling 2 will update the site SAMGs to future outages or 3 years revisions of the PWROG generic severe of the publication accident technical guidelines, and the date of the SAMGs will be integrated with other guidelines, emergency response guideline sets and whichever is greater symptom-based Emergency Operating Procedures, and validated, using the guidance in NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents.